ML100501614: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 02/18/2010 | | issue date = 02/18/2010 | ||
| title = Notification of Inspection (IR 05000483-10-003) and Request for Information | | title = Notification of Inspection (IR 05000483-10-003) and Request for Information | ||
| author name = Werner G | | author name = Werner G | ||
| author affiliation = NRC/RGN-IV/DRS/PSB-2 | | author affiliation = NRC/RGN-IV/DRS/PSB-2 | ||
| addressee name = Heflin A | | addressee name = Heflin A | ||
| addressee affiliation = AmerenUE | | addressee affiliation = AmerenUE | ||
| docket = 05000483 | | docket = 05000483 | ||
Line 14: | Line 14: | ||
| page count = 13 | | page count = 13 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000483/2010003]] | ||
=Text= | =Text= | ||
{{#Wiki_filter:February 18, 2010 | {{#Wiki_filter:UNITED STATES | ||
NUC LE AR RE G UL AT O RY C O M M I S S I O N | |||
Mr. Adam C. Heflin, Senior Vice | R E GI ON I V | ||
612 EAST LAMAR BLVD , SU I TE 400 | |||
AR LI N GTON , TEXAS 76011-4125 | |||
February 18, 2010 | |||
Mr. Adam C. Heflin, Senior Vice | |||
President and Chief Nuclear Officer | |||
AmerenUE | |||
P.O. Box 620 | |||
Fulton, MO 65251 | |||
SUBJECT: CALLAWAY NUCLEAR POWER PLANT - NOTIFICATION OF INSPECTION | |||
(NRC INSPECTION REPORT 050000483/2010003) AND REQUEST FOR | |||
INFORMATION | |||
Dear Mr. Heflin: | |||
From April 19 to April 23, 2010, reactor inspectors from the Nuclear Regulatory | |||
Commissions (NRC) Region IV office will perform the baseline inservice inspection at the | |||
Callaway Nuclear Power Plant, using NRC Inspection Procedure 71111.08, "Inservice | |||
Inspection Activities," and TI 2515/172, "Reactor Coolant System Dissimilar Metal Butt Welds." | |||
Experience has shown that this inspection is a resource intensive inspection both for the NRC | |||
inspectors and your staff. In order to minimize the impact to your onsite resources and to | |||
ensure a productive inspection, we have enclosed a request for documents needed for this | |||
inspection. These documents have been divided into two groups. The first group (Section A of | |||
the enclosure) identified information to be provided prior to the inspection to ensure that the | |||
inspectors are adequately prepared. The second group (Section B of the enclosure) identifies | |||
the information the inspectors will need upon arrival at the site. It is important that all of these | |||
documents are up to date and complete in order to minimize the number of additional | |||
documents requested during the preparation and/or the onsite portions of the inspection. | |||
We have discussed the schedule for these inspection activities with your staff and understand | |||
that our regulatory contact for this inspection will be Mr. Steve Petzel of your licensing | |||
organization. Our inspection dates are subject to change based on your updated schedule of | |||
outage activities. If there are any questions about this inspection or the material requested, | |||
please contact the lead inspector James Adams at (817) 860-8294 (James.Adams@nrc.gov) or | |||
Breck Henderson at (817) 276-6569 (Breck.Henderson@nrc.gov). | |||
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRCs document | |||
system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
AmerenUE -2- | |||
This letter does not contain new or amended information collection requirements subject to the | |||
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | |||
requirements were approved by the Office of Management and Budget, control number 3150- | |||
0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a | |||
request for information or an information collection requirement unless the requesting document | |||
displays a currently valid Office of Management and Budget control number. | |||
Sincerely, | |||
/RA/ | |||
Gregory E. Werner, Chief | |||
AmerenUE - 2 - | Plant Support Branch 2 | ||
Division of Reactor Safety | |||
request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. | Docket: 50-483 | ||
License: NPF-30 | |||
Enclosure: | |||
Inservice Inspection Document Request | |||
cc w/enclosure: | |||
Mr. Luke H. Graessle | |||
Director, Operations Support | |||
AmerenUE | |||
P.O. Box 620 | |||
Fulton, MO 65251 | |||
E. Hope Bradley | |||
Manager, Protective Services | |||
AmerenUE | |||
P.O. Box 620 | |||
Fulton, MO 65251 | |||
Mr. Scott Sandbothe, Manager | |||
Plant Support | |||
AmerenUE | |||
P.O. Box 620 | |||
Fulton, MO 65251 | |||
AmerenUE -3- | |||
R. E. Farnam | |||
Assistant Manager, Technical | |||
Training | |||
AmerenUE | |||
P.O. Box 620 | |||
Fulton, MO 65251 | |||
J. S. Geyer | |||
Radiation Protection Manager | |||
AmerenUE | |||
AmerenUE - 3 - | P.O. Box 620 | ||
Fulton, MO 65251 | |||
P.O. Box 620 Fulton, MO | John ONeill, Esq. | ||
Pillsbury Winthrop Shaw Pittman LLP | |||
AmerenUE P.O. Box 620 Fulton, MO | 2300 N. Street, N.W. | ||
Washington, DC 20037 | |||
Washington, DC | Missouri Public Service Commission | ||
P.O. Box 360 | |||
Jefferson City, MO 65102-0360 | |||
Dru Buntin | |||
Director of Government Affairs | |||
Department of Natural Resources | |||
P.O. Box 176 | |||
Jefferson City, MO 65102-0176 | |||
Mr. Rick A. Muench, President and | |||
Chief Executive officer | |||
Wolf Creek Nuclear Operating Corporation | |||
P.O. Box 411 | |||
Burlington, KS 66839 | |||
Kathleen Logan Smith, Executive Director and | |||
Kay Drey, Representative, Board of Directors | |||
Missouri Coalition for the Environment | |||
6267 Delmar Boulevard, Suite 2E | |||
St. Louis, MO 63130 | |||
Presiding Commissioner | |||
Callaway County Court House | |||
10 East Fifth Street | |||
Fulton, MO 65251 | |||
AmerenUE -4- | |||
Jefferson City, MO | Director, Missouri State Emergency | ||
Management Agency | |||
P.O. Box | P.O. Box 116 | ||
Jefferson City, MO 65102-0116 | |||
Missouri | Mr. Scott Clardy, Administrator | ||
Section for Disease Control | |||
Missouri Department of Health and | |||
Senior Services | |||
P.O. Box 570 | |||
Jefferson City, MO 65102-0570 | |||
Certrec Corporation | |||
4200 South Hulen, Suite 422 | |||
Fort Worth, TX 76109 | |||
Mr. Keith G. Henke, Planner II | |||
Division of Community and Public Health | |||
Office of Emergency Coordination | |||
Missouri Department of Health and | |||
Senior Services | |||
930 Wildwood Drive | |||
P.O. Box 570 | |||
Jefferson City, MO 65102 | |||
Chief, Technological Hazards Branch | |||
FEMA Region VII | |||
9221 Ward Parkway, Suite 300 | |||
Kansas City, MO 64114-3372 | |||
AmerenUE -5- | |||
Electronic distribution by RIV: | |||
Regional Administrator (Elmo.Collins@nrc.gov) | |||
Deputy Regional Administrator (Chuck.Casto@nrc.gov) | |||
DRP Director (Dwight.Chamberlain@nrc.gov) | |||
DRP Deputy Director (Anton.Vegel@nrc.gov) | |||
DRS Director (Roy.Caniano@nrc.gov) | |||
DRS Deputy Director (Troy.Pruett@nrc.gov) | |||
Senior Resident Inspector (David.Dumbacher@nrc.gov) | |||
AmerenUE - 5 - | Resident Inspector (Jeremy.Groom@nrc.gov) | ||
Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov) | |||
DRP Deputy Director (Anton.Vegel@nrc.gov) DRS Director (Roy.Caniano@nrc.gov) DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (David.Dumbacher@nrc.gov) Resident Inspector (Jeremy.Groom@nrc.gov) | Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov) | ||
Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov) Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov) Acting Senior Project Engineer, DRP/B (Peter.Jayroe@nrc.gov) | Acting Senior Project Engineer, DRP/B (Peter.Jayroe@nrc.gov) | ||
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) OEMail Resource | CWY Administrative Assistant (Dawn.Yancey@nrc.gov) | ||
Only inspection reports to the following: DRS/TSB STA (Dale.Powers@nrc.gov) OEDO RIV Coordinator (Leigh.Trocine@nrc.gov) | Public Affairs Officer (Victor.Dricks@nrc.gov) | ||
Public Affairs Officer (Lara.Uselding@nrc.gov) | |||
Project Manager (Mohan.Thadani@nrc.gov) | |||
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) | |||
/RA/ /RA//RA/ 2/17/10 2/17/10 2/18/10 | RITS Coordinator (Marisa.Herrera@nrc.gov) | ||
Regional Counsel (Karla.Fuller@nrc.gov) | |||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) | |||
OEMail Resource | |||
Only inspection reports to the following: | |||
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds" | DRS/TSB STA (Dale.Powers@nrc.gov) | ||
OEDO RIV Coordinator (Leigh.Trocine@nrc.gov) | |||
SUNSI Review Completed: ___Y___ ADAMS: 7 Yes No Initials: ____ | |||
specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure). | 7 Publicly Available Non-Publicly Available Sensitive 7 Non-Sensitive | ||
ML | |||
RI:EB1 RE:TSB C:PSB2 | |||
JAdams BHenderson GEWerner | |||
Informed (if applicable), and augmented ISI programs during the upcoming outage. | /RA/ /RA/ /RA/ | ||
2/17/10 2/17/10 2/18/10 | |||
ASME Section XI, IWX-2400 (Do not provide separately if other documentation requested contains this information) | OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax | ||
INSERVICE INSPECTION DOCUMENT REQUEST | |||
Inspection Dates: April 19 through April 23, 2010 | |||
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" | |||
TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds" | |||
Inspectors: James Adams, Reactor Inspector (Lead Inspector - ISI) | |||
Breck Henderson, Reactor Inspector | |||
A. Information Requested for the In-Office Preparation Week | |||
The following information should be sent to the Region IV office in hard copy or | |||
electronic format (ims.certrec.com or other electronic format is preferred over hard | |||
copy), in care of James Adams, by April 7, 2010, to facilitate the selection of specific | |||
items that will be reviewed during the onsite inspection week. The inspector will select | |||
specific items from the information requested below and then request from your staff | |||
additional documents needed during the onsite inspection week (Section B of this | |||
enclosure). We ask that the specific items selected from the lists be available and ready | |||
for review on the first day of inspection. *Please provide requested documentation | |||
electronically if possible. If requested documents are large and only hard copy formats | |||
are available, please inform the inspector(s), and provide subject documentation during | |||
the first day of the onsite inspection. If you have any questions regarding this | |||
information request, please call the inspector as soon as possible. | |||
A.1 ISI/Welding Programs and Schedule Information | |||
a) A detailed schedule (including preliminary dates) of: | |||
i) Nondestructive examinations (NDEs) planned for Class 1 & 2 systems | |||
and containment, performed as part of your ASME Section XI, Risk | |||
Informed (if applicable), and augmented ISI programs during the | |||
upcoming outage. | |||
Provide a status summary of the NDE inspection activities vs. the | |||
required inspection period percentages for this Interval by category per | |||
ASME Section XI, IWX-2400 (Do not provide separately if other | |||
documentation requested contains this information) | |||
ii) Reactor pressure vessel head (RPVH) examinations planned for the | |||
upcoming outage. | |||
iii) Examinations planned for Alloy 82/182/600 components that are not | |||
included in the Section XI scope. (If applicable) | |||
iv) Examinations planned as part of your Boric Acid Corrosion Control | |||
Program (Mode 3 walkdowns, bolted connection walkdowns, etc.) | |||
-1- Enclosure | |||
v) Welding activities that are scheduled to be completed during the | |||
upcoming outage (ASME Class 1, 2, or 3 structures, systems, or | |||
components (SSCs)). | |||
b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety | |||
Evaluations applicable to the examinations identified above. | |||
c) A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate, | |||
Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code | |||
Class 1 & 2 systems since the beginning of the last refueling outage. This should | |||
include the previous Section XI pressure test(s) conducted during start up and | |||
any evaluations associated with the results of the pressure tests. Also, include in | |||
the list the NDE reports with relevant conditions in the RPVH penetration nozzles | |||
which have been accepted for continued service. The list of NDE reports should | |||
include a brief description of the SSC where the relevant condition was identified. | |||
d) A list with a brief description (e.g., system, material, pipe size, weld number, and | |||
NDE performed) of the welds in Code Class 1 and 2 systems which have been | |||
fabricated due to component repair/replacement activities since the beginning of | |||
the last refueling outage, or are planned to be fabricated this refueling outage. | |||
e) If reactor vessel weld examinations required by the ASME Code are scheduled to | |||
occur during the upcoming outage, provide a detailed description of the welds to | |||
be examined and the extent of the planned examination. Please also provide | |||
reference numbers for applicable procedures that will be used to conduct these | |||
examinations. | |||
f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of | |||
Section XI of the ASME Code that have been identified since the beginning of the | |||
last refueling outage. | |||
g) A list of any temporary non-code repairs in service (e.g., pinhole leaks). | |||
h) Please provide copies of the most recent self assessments for the ISI, Welding, | |||
and Alloy 600 Programs. | |||
A.2 Reactor Pressure Vessel Head (RPVH) | A.2 Reactor Pressure Vessel Head (RPVH) | ||
a) Provide the detailed scope of the planned NDE of the reactor vessel head which | |||
applicable) | identifies the types of NDE methods to be used on each specific part of the | ||
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02 | |||
and NRC Order EA-03-009. Also, include examination scope expansion criteria | |||
and planned expansion sample sizes if relevant conditions are identified. (If | |||
applicable) | |||
b) A list of the standards and/or requirements that will be used to evaluate | |||
indications identified during NDE of the reactor vessel head (e.g., the specific | |||
-2- Enclosure | |||
industry or procedural standards which will be used to evaluate potential leakage | |||
and/or flaw indications). | |||
A.3 Boric Acid Corrosion Control Program (BACCP) | |||
the NRC regarding deviations from the STS. | a) Copy of the procedures that govern the scope, equipment and implementation of | ||
the inspections required to identify boric acid leakage and the procedures for | |||
boric acid leakage/corrosion evaluation. | |||
b) Please provide a list of leaks (including Code class of the components) that have | |||
been identified since the last refueling outage and associated corrective action | |||
documentation. If during the last cycle, the Unit was shutdown, please provide | |||
documentation of containment walkdown inspections performed as part of the | |||
programs. | BACCP. | ||
c) Please provide a copy of the most recent self-assessment performed for the | |||
BACCP. | |||
percentage of tubes to be examined. *Do not provide these documents separately if already included in other information requested. | A.4 Steam Generator Tube (SGT) Inspections | ||
a) A detailed schedule of: | |||
i) SGT inspection, data analyses, and repair activities for the upcoming | |||
outage. (If occurring) | |||
examinations should be available for review. | ii) SG secondary side inspection activities for the upcoming outage. (If | ||
occurring) | |||
b) Please provide a copy of your SG ISI Inspection Program and Plan. Please | |||
include a copy of the Operational Assessment from last outage and a copy of the | |||
following documents as they become available: | |||
i) Degradation Assessment | |||
ii) Condition Monitoring Assessment | |||
c) If you are planning on modifying your Technical Specifications such that they are | |||
boric acid, or errors in piping/SGT examinations. | consistent with TSTF-449, please provide copies of your correspondence with | ||
the NRC regarding deviations from the STS. | |||
d) Copy of SG history documentation given to vendors performing eddy current (ET) | |||
Snubbers and Supports Repair and Replacement Program Manager Licensing Contact Site Welding Engineer Boric Acid Corrosion Control Program | testing of the SGs during the upcoming outage. | ||
SG Inspection Activities (site lead and vendor contact) | e) Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy | ||
Current Technique Specification Sheets (ETSS). Additionally, please provide a | |||
copy of EPRI Appendix H ETSS Qualification Records. | |||
-3- Enclosure | |||
f) Identify and quantify any SGT leakage experienced during the previous operating | |||
cycle. Also provide documentation identifying which SG was leaking and | |||
corrective actions completed or planned for this condition (If applicable). | |||
g) Provide past history of the condition and issues pertaining to the secondary side | |||
of the steam generators (including items such as loose parts, fouling, top of tube | |||
sheet condition, crud removal amounts, etc.) | |||
h) Please provide copies of your most recent self assessments of the SG | |||
monitoring, loose parts monitoring, and secondary side water chemistry control | |||
programs. | |||
i) Please also indicate where the primary, secondary, and resolution analyses are | |||
scheduled to take place. | |||
j) Please provide a summary of the scope of the SGT examinations, including | |||
examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the | |||
percentage of tubes to be examined. *Do not provide these documents | |||
separately if already included in other information requested. | |||
A.5 Materials Reliability (MRP-139) Program Activities | |||
a) A list of, with verification, that the baseline inspections of all applicable Dissimilar | |||
Metal Butt Welds (DMBWs) have been completed or will be completed by | |||
December 31, 2010. | |||
b) Verification that baseline inspection of hot leg and cold leg temperature DMBWs | |||
have been included in the inspection program and that the schedules for the | |||
baseline inspections are consistent with the baseline schedules in MRP-139. | |||
c) A list and schedule (examination dates) of all DMBW examinations planned for | |||
the upcoming refueling outage. If none are scheduled, then data from previous | |||
examinations should be available for review. | |||
d) A list and schedule for any welding to be performed on DMBWs in the upcoming | |||
outage. If no welding will be performed, then records of previous welding on | |||
DMBWs and postweld NDE documentation should be available for review. | |||
e) A list and schedule of any stress improvement (SI) activities planned for the | |||
upcoming refueling outage. If none are scheduled then have qualification reports | |||
for any SIs previously performed. | |||
f) Documentation and description of how the baseline and inservice inspection | |||
specifications in MRP-139 are satisfied at your facility. | |||
g) A list of weld locations controlled by MRP-139 which includes the MRP-139 weld | |||
category, pre-mitigation volumetric examination date, type of mitigation or stress | |||
-4- Enclosure | |||
improvement, post mitigation volumetric examination date, and plans for future | |||
MRP-139 required examinations. | |||
A.6 Additional information related to all ISI activities | |||
a) A list with a brief description of ISI, BACCP, and SGT inspection related issues | |||
(e.g., condition reports) entered into your corrective action program since the | |||
beginning of the last refueling outage. For example, a list based upon data base | |||
searches using key words related to piping or SG tube degradation such as: ISI, | |||
ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, | |||
boric acid, or errors in piping/SGT examinations. | |||
b) Please provide names and phone numbers for the following program leads: | |||
ISI contacts (Examination, planning) | |||
Containment Exams | |||
RPVH Exams | |||
Snubbers and Supports | |||
Repair and Replacement Program Manager | |||
Licensing Contact | |||
Site Welding Engineer | |||
Boric Acid Corrosion Control Program | |||
SG Inspection Activities (site lead and vendor contact) | |||
B. Information to be provided onsite to the inspector(s) at the entrance meeting (April 19, | |||
2010): | |||
B.1 ISI / Welding Programs and Schedule Information | B.1 ISI / Welding Programs and Schedule Information | ||
a) Updated schedules for ISI/NDE activities, including SGT inspections, planned | |||
welding activities, and schedule showing contingency repair plans, if available. | |||
b) For ASME Code Class 1 and 2 welds selected by the inspector from the lists | |||
ii) Weld configuration and system location iii) Applicable Code Edition and Addenda for weldment iv) Applicable Code Edition and Addenda for welding procedures v) Applicable weld procedures (WPS) used to fabricate the welds vi) Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii) Copies of mechanical test reports identified in the PQRs above | provided from section A of this enclosure, please provide copies of the following | ||
viii) Copies of the nonconformance reports for the selected welds (If applicable) ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed) | documentation for each subject weld: | ||
i) Weld data sheet (traveler) | |||
ii) Weld configuration and system location | |||
iii) Applicable Code Edition and Addenda for weldment | |||
iv) Applicable Code Edition and Addenda for welding procedures | |||
v) Applicable weld procedures (WPS) used to fabricate the welds | |||
examination procedures qualified in accordance with ASME Code, Section XI, Appendix VIII, provide documentation supporting the procedure qualification (e.g., the EPRI performance demonstration qualification summary sheets). | vi) Copies of procedure qualification records (PQRs) supporting the WPS | ||
personnel qualification records. | from B.1.b.v | ||
vii) Copies of mechanical test reports identified in the PQRs above | |||
viii) Copies of the nonconformance reports for the selected welds (If | |||
applicable) | |||
ix) Radiographs of the selected welds and access to equipment to allow | |||
viewing radiographs (If RT was performed) | |||
-5- Enclosure | |||
x) Copies of the preservice examination records for the selected welds. | |||
xi) Copies of welder performance qualifications records applicable to the | |||
selected welds, including documentation that welder maintained | |||
proficiency in the applicable welding processes specified in the WPS (at | |||
least six months prior to the date of subject work) | |||
xii) Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable | |||
c) For the ISI related corrective action issues selected by the inspector(s) from | |||
section A of this enclosure, provide a copy of the corrective actions and | |||
supporting documentation. | |||
d) For the NDE reports with relevant conditions on Code Class 1 & 2 systems | |||
selected by the inspector from section A above, provide a copy of the | |||
examination records, examiner qualification records, and associated corrective | |||
action documents. | |||
e) A copy of (or ready access to) most current revision of the ISI Program Manual | |||
and Plan for the current Interval. | |||
f) For the NDEs selected by the inspector from section A of this enclosure, provide | |||
a copy of the NDE procedures used to perform the examinations (including | |||
calibration and flaw characterization/sizing procedures). For ultrasonic | |||
examination procedures qualified in accordance with ASME Code, Section XI, | |||
Appendix VIII, provide documentation supporting the procedure qualification | |||
(e.g., the EPRI performance demonstration qualification summary sheets). Also, | |||
include qualification documentation of the specific equipment to be used (e.g., | |||
ultrasonic unit, cables, and transducers including serial numbers) and NDE | |||
personnel qualification records. | |||
B.2 Reactor Pressure Vessel Head (RPVH) | |||
a) Provide the NDE personnel qualification records for the examiners who will | |||
perform examinations of the RPVH. | |||
b) Provide drawings showing the following: (If a visual examination is planned for | |||
the upcoming refueling outage) | |||
i) RPVH and CRDM nozzle configurations | |||
ii) RPVH insulation configuration | |||
The drawings listed above should include fabrication drawings for the nozzle attachment | |||
welds as applicable. | |||
c) Copy of NDE reports from the last RPVH examination. | |||
d) Copy of evaluation or calculation demonstrating that the scope of the visual | |||
examination of the upper head will meet the 95 percent minimum coverage | |||
-6- Enclosure | |||
required by NRC Order EA-03-009 (If a visual examination is planned for the | |||
upcoming refueling outage). | |||
e) Provide a copy of the procedures that will be used to identify the source of any | |||
boric acid deposits identified on the RPVH. If no explicit procedures exist which | |||
govern this activity, provide a description of the process to be followed including | |||
personnel responsibilities and expectations. | |||
f) Provide a copy of the updated calculation of effective degradation years (EDY) | |||
for the RPVH susceptibility ranking. | |||
g) Provide a copy of the vendor qualification report(s) that demonstrates the | |||
detection capability of the NDE equipment used for the RPVH examinations. | |||
Also, identify any changes in equipment configurations used for the RPVH | |||
examinations which differ from that used in the vendor qualification report(s). | |||
B.3 Boric Acid Corrosion Control Program (BACCP) | |||
a) Please provide boric acid walkdown inspection results, an updated list of boric | |||
acid leaks identified so far this outage, associated corrective action | |||
documentation, and the overall status of planned boric acid inspections. | |||
b) Please provide any engineering evaluations completed for boric acid leaks | |||
identified since the end of the last refueling outage. Please include a status of | |||
corrective actions to repair and/or clean these boric acid leaks. Please identify | |||
specifically which known leaks, if any, have remained in service or will remain in | |||
service as active leaks. | |||
B.4 Steam Generator Tube (SGT) Inspections | |||
a) Copies of the Examination Technique Specification Sheets (ETSS) and | |||
associated justification for any revisions. | |||
b) Copy of the guidance to be followed if a loose part or foreign material is identified | |||
in the SGs. | |||
c) Please provide a copy of the ET procedures used to perform the SGT | |||
inspections (specifically calibration and flaw characterization/sizing procedures, | |||
etc.). Also include documentation for the specific equipment to be used. | |||
d) Please provide copies of your responses to NRC and industry operating | |||
experience communications such as Generic Letters, Information Notices, etc. | |||
(as applicable to SGT inspections) *Do not provide these documents separately if | |||
already included in other information requested such as the degradation | |||
assessment. | |||
e) List of corrective action documents generated by the vendor and/or site with | |||
respect to SG inspection activities. | |||
-7- Enclosure | |||
B.5 Codes and Standards | |||
a) Ready access to (i.e., copies provided to the inspector(s) for use during the | |||
inspection at the onsite inspection location, or room number and location where | |||
available): | |||
i) Applicable Editions of the ASME Code (Sections V, IX and XI) for the | |||
inservice inspection program and the repair/replacement program. | |||
ii) EPRI and industry standards referenced in the procedures used to | |||
perform the SGT eddy current examination. | |||
Inspector Contact Information: | |||
James Adams Breck Henderson | |||
Reactor Inspector Reactor Inspector | |||
817-860-8294 817-276-6569 | |||
James.Adams@nrc.gov Breck.Henderson@nrc.gov | |||
Mailing Address: | |||
US NRC Region IV | |||
Attn: James Adams | |||
612 E. Lamar Blvd, Suite 400 | |||
Arlington, TX 76011-4125 | |||
-8- Enclosure | |||
available): | |||
ii) | |||
Reactor Inspector | |||
US NRC Region IV Attn: | |||
}} | }} |
Latest revision as of 22:41, 13 November 2019
ML100501614 | |
Person / Time | |
---|---|
Site: | Callaway |
Issue date: | 02/18/2010 |
From: | Greg Werner NRC/RGN-IV/DRS/PSB-2 |
To: | Heflin A AmerenUE |
References | |
IR-10-003 | |
Download: ML100501614 (13) | |
See also: IR 05000483/2010003
Text
UNITED STATES
NUC LE AR RE G UL AT O RY C O M M I S S I O N
R E GI ON I V
612 EAST LAMAR BLVD , SU I TE 400
AR LI N GTON , TEXAS 76011-4125
February 18, 2010
Mr. Adam C. Heflin, Senior Vice
President and Chief Nuclear Officer
AmerenUE
P.O. Box 620
Fulton, MO 65251
SUBJECT: CALLAWAY NUCLEAR POWER PLANT - NOTIFICATION OF INSPECTION
(NRC INSPECTION REPORT 050000483/2010003) AND REQUEST FOR
INFORMATION
Dear Mr. Heflin:
From April 19 to April 23, 2010, reactor inspectors from the Nuclear Regulatory
Commissions (NRC) Region IV office will perform the baseline inservice inspection at the
Callaway Nuclear Power Plant, using NRC Inspection Procedure 71111.08, "Inservice
Inspection Activities," and TI 2515/172, "Reactor Coolant System Dissimilar Metal Butt Welds."
Experience has shown that this inspection is a resource intensive inspection both for the NRC
inspectors and your staff. In order to minimize the impact to your onsite resources and to
ensure a productive inspection, we have enclosed a request for documents needed for this
inspection. These documents have been divided into two groups. The first group (Section A of
the enclosure) identified information to be provided prior to the inspection to ensure that the
inspectors are adequately prepared. The second group (Section B of the enclosure) identifies
the information the inspectors will need upon arrival at the site. It is important that all of these
documents are up to date and complete in order to minimize the number of additional
documents requested during the preparation and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Mr. Steve Petzel of your licensing
organization. Our inspection dates are subject to change based on your updated schedule of
outage activities. If there are any questions about this inspection or the material requested,
please contact the lead inspector James Adams at (817) 860-8294 (James.Adams@nrc.gov) or
Breck Henderson at (817) 276-6569 (Breck.Henderson@nrc.gov).
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
AmerenUE -2-
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a
request for information or an information collection requirement unless the requesting document
displays a currently valid Office of Management and Budget control number.
Sincerely,
/RA/
Gregory E. Werner, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket: 50-483
License: NPF-30
Enclosure:
Inservice Inspection Document Request
cc w/enclosure:
Mr. Luke H. Graessle
Director, Operations Support
AmerenUE
P.O. Box 620
Fulton, MO 65251
E. Hope Bradley
Manager, Protective Services
AmerenUE
P.O. Box 620
Fulton, MO 65251
Mr. Scott Sandbothe, Manager
Plant Support
AmerenUE
P.O. Box 620
Fulton, MO 65251
AmerenUE -3-
R. E. Farnam
Assistant Manager, Technical
Training
AmerenUE
P.O. Box 620
Fulton, MO 65251
J. S. Geyer
Radiation Protection Manager
AmerenUE
P.O. Box 620
Fulton, MO 65251
John ONeill, Esq.
Pillsbury Winthrop Shaw Pittman LLP
2300 N. Street, N.W.
Washington, DC 20037
Missouri Public Service Commission
P.O. Box 360
Jefferson City, MO 65102-0360
Dru Buntin
Director of Government Affairs
Department of Natural Resources
P.O. Box 176
Jefferson City, MO 65102-0176
Mr. Rick A. Muench, President and
Chief Executive officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
Kathleen Logan Smith, Executive Director and
Kay Drey, Representative, Board of Directors
Missouri Coalition for the Environment
6267 Delmar Boulevard, Suite 2E
St. Louis, MO 63130
Presiding Commissioner
Callaway County Court House
10 East Fifth Street
Fulton, MO 65251
AmerenUE -4-
Director, Missouri State Emergency
Management Agency
P.O. Box 116
Jefferson City, MO 65102-0116
Mr. Scott Clardy, Administrator
Section for Disease Control
Missouri Department of Health and
Senior Services
P.O. Box 570
Jefferson City, MO 65102-0570
Certrec Corporation
4200 South Hulen, Suite 422
Fort Worth, TX 76109
Mr. Keith G. Henke, Planner II
Division of Community and Public Health
Office of Emergency Coordination
Missouri Department of Health and
Senior Services
930 Wildwood Drive
P.O. Box 570
Jefferson City, MO 65102
Chief, Technological Hazards Branch
FEMA Region VII
9221 Ward Parkway, Suite 300
Kansas City, MO 64114-3372
AmerenUE -5-
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (David.Dumbacher@nrc.gov)
Resident Inspector (Jeremy.Groom@nrc.gov)
Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov)
Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov)
Acting Senior Project Engineer, DRP/B (Peter.Jayroe@nrc.gov)
CWY Administrative Assistant (Dawn.Yancey@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Mohan.Thadani@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
Only inspection reports to the following:
DRS/TSB STA (Dale.Powers@nrc.gov)
OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)
SUNSI Review Completed: ___Y___ ADAMS: 7 Yes No Initials: ____
7 Publicly Available Non-Publicly Available Sensitive 7 Non-Sensitive
RI:EB1 RE:TSB C:PSB2
JAdams BHenderson GEWerner
/RA/ /RA/ /RA/
2/17/10 2/17/10 2/18/10
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
INSERVICE INSPECTION DOCUMENT REQUEST
Inspection Dates: April 19 through April 23, 2010
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities"
TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds"
Inspectors: James Adams, Reactor Inspector (Lead Inspector - ISI)
Breck Henderson, Reactor Inspector
A. Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or
electronic format (ims.certrec.com or other electronic format is preferred over hard
copy), in care of James Adams, by April 7, 2010, to facilitate the selection of specific
items that will be reviewed during the onsite inspection week. The inspector will select
specific items from the information requested below and then request from your staff
additional documents needed during the onsite inspection week (Section B of this
enclosure). We ask that the specific items selected from the lists be available and ready
for review on the first day of inspection. *Please provide requested documentation
electronically if possible. If requested documents are large and only hard copy formats
are available, please inform the inspector(s), and provide subject documentation during
the first day of the onsite inspection. If you have any questions regarding this
information request, please call the inspector as soon as possible.
A.1 ISI/Welding Programs and Schedule Information
a) A detailed schedule (including preliminary dates) of:
i) Nondestructive examinations (NDEs) planned for Class 1 & 2 systems
and containment, performed as part of your ASME Section XI, Risk
Informed (if applicable), and augmented ISI programs during the
upcoming outage.
Provide a status summary of the NDE inspection activities vs. the
required inspection period percentages for this Interval by category per
ASME Section XI, IWX-2400 (Do not provide separately if other
documentation requested contains this information)
ii) Reactor pressure vessel head (RPVH) examinations planned for the
upcoming outage.
iii) Examinations planned for Alloy 82/182/600 components that are not
included in the Section XI scope. (If applicable)
iv) Examinations planned as part of your Boric Acid Corrosion Control
Program (Mode 3 walkdowns, bolted connection walkdowns, etc.)
-1- Enclosure
v) Welding activities that are scheduled to be completed during the
upcoming outage (ASME Class 1, 2, or 3 structures, systems, or
components (SSCs)).
b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety
Evaluations applicable to the examinations identified above.
c) A list of NDE reports (ultrasonic, radiography, magnetic particle, dye penetrate,
Visual VT-1, VT-2, and VT-3), which have identified relevant conditions on Code
Class 1 & 2 systems since the beginning of the last refueling outage. This should
include the previousSection XI pressure test(s) conducted during start up and
any evaluations associated with the results of the pressure tests. Also, include in
the list the NDE reports with relevant conditions in the RPVH penetration nozzles
which have been accepted for continued service. The list of NDE reports should
include a brief description of the SSC where the relevant condition was identified.
d) A list with a brief description (e.g., system, material, pipe size, weld number, and
NDE performed) of the welds in Code Class 1 and 2 systems which have been
fabricated due to component repair/replacement activities since the beginning of
the last refueling outage, or are planned to be fabricated this refueling outage.
e) If reactor vessel weld examinations required by the ASME Code are scheduled to
occur during the upcoming outage, provide a detailed description of the welds to
be examined and the extent of the planned examination. Please also provide
reference numbers for applicable procedures that will be used to conduct these
examinations.
f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of
Section XI of the ASME Code that have been identified since the beginning of the
last refueling outage.
g) A list of any temporary non-code repairs in service (e.g., pinhole leaks).
h) Please provide copies of the most recent self assessments for the ISI, Welding,
and Alloy 600 Programs.
A.2 Reactor Pressure Vessel Head (RPVH)
a) Provide the detailed scope of the planned NDE of the reactor vessel head which
identifies the types of NDE methods to be used on each specific part of the
vessel head to fulfill commitments made in response to NRC Bulletin 2002-02
and NRC Order EA-03-009. Also, include examination scope expansion criteria
and planned expansion sample sizes if relevant conditions are identified. (If
applicable)
b) A list of the standards and/or requirements that will be used to evaluate
indications identified during NDE of the reactor vessel head (e.g., the specific
-2- Enclosure
industry or procedural standards which will be used to evaluate potential leakage
and/or flaw indications).
A.3 Boric Acid Corrosion Control Program (BACCP)
a) Copy of the procedures that govern the scope, equipment and implementation of
the inspections required to identify boric acid leakage and the procedures for
boric acid leakage/corrosion evaluation.
b) Please provide a list of leaks (including Code class of the components) that have
been identified since the last refueling outage and associated corrective action
documentation. If during the last cycle, the Unit was shutdown, please provide
documentation of containment walkdown inspections performed as part of the
BACCP.
c) Please provide a copy of the most recent self-assessment performed for the
BACCP.
A.4 Steam Generator Tube (SGT) Inspections
a) A detailed schedule of:
i) SGT inspection, data analyses, and repair activities for the upcoming
outage. (If occurring)
ii) SG secondary side inspection activities for the upcoming outage. (If
occurring)
b) Please provide a copy of your SG ISI Inspection Program and Plan. Please
include a copy of the Operational Assessment from last outage and a copy of the
following documents as they become available:
i) Degradation Assessment
ii) Condition Monitoring Assessment
c) If you are planning on modifying your Technical Specifications such that they are
consistent with TSTF-449, please provide copies of your correspondence with
the NRC regarding deviations from the STS.
d) Copy of SG history documentation given to vendors performing eddy current (ET)
testing of the SGs during the upcoming outage.
e) Copy of SG Eddy Current Data Analyst Guidelines and Site Validated Eddy
Current Technique Specification Sheets (ETSS). Additionally, please provide a
copy of EPRI Appendix H ETSS Qualification Records.
-3- Enclosure
f) Identify and quantify any SGT leakage experienced during the previous operating
cycle. Also provide documentation identifying which SG was leaking and
corrective actions completed or planned for this condition (If applicable).
g) Provide past history of the condition and issues pertaining to the secondary side
of the steam generators (including items such as loose parts, fouling, top of tube
sheet condition, crud removal amounts, etc.)
h) Please provide copies of your most recent self assessments of the SG
monitoring, loose parts monitoring, and secondary side water chemistry control
programs.
i) Please also indicate where the primary, secondary, and resolution analyses are
scheduled to take place.
j) Please provide a summary of the scope of the SGT examinations, including
examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the
percentage of tubes to be examined. *Do not provide these documents
separately if already included in other information requested.
A.5 Materials Reliability (MRP-139) Program Activities
a) A list of, with verification, that the baseline inspections of all applicable Dissimilar
Metal Butt Welds (DMBWs) have been completed or will be completed by
December 31, 2010.
b) Verification that baseline inspection of hot leg and cold leg temperature DMBWs
have been included in the inspection program and that the schedules for the
baseline inspections are consistent with the baseline schedules in MRP-139.
c) A list and schedule (examination dates) of all DMBW examinations planned for
the upcoming refueling outage. If none are scheduled, then data from previous
examinations should be available for review.
d) A list and schedule for any welding to be performed on DMBWs in the upcoming
outage. If no welding will be performed, then records of previous welding on
DMBWs and postweld NDE documentation should be available for review.
e) A list and schedule of any stress improvement (SI) activities planned for the
upcoming refueling outage. If none are scheduled then have qualification reports
for any SIs previously performed.
f) Documentation and description of how the baseline and inservice inspection
specifications in MRP-139 are satisfied at your facility.
g) A list of weld locations controlled by MRP-139 which includes the MRP-139 weld
category, pre-mitigation volumetric examination date, type of mitigation or stress
-4- Enclosure
improvement, post mitigation volumetric examination date, and plans for future
MRP-139 required examinations.
A.6 Additional information related to all ISI activities
a) A list with a brief description of ISI, BACCP, and SGT inspection related issues
(e.g., condition reports) entered into your corrective action program since the
beginning of the last refueling outage. For example, a list based upon data base
searches using key words related to piping or SG tube degradation such as: ISI,
ASME Code,Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion,
boric acid, or errors in piping/SGT examinations.
b) Please provide names and phone numbers for the following program leads:
ISI contacts (Examination, planning)
Containment Exams
RPVH Exams
Snubbers and Supports
Repair and Replacement Program Manager
Licensing Contact
Site Welding Engineer
Boric Acid Corrosion Control Program
SG Inspection Activities (site lead and vendor contact)
B. Information to be provided onsite to the inspector(s) at the entrance meeting (April 19,
2010):
B.1 ISI / Welding Programs and Schedule Information
a) Updated schedules for ISI/NDE activities, including SGT inspections, planned
welding activities, and schedule showing contingency repair plans, if available.
b) For ASME Code Class 1 and 2 welds selected by the inspector from the lists
provided from section A of this enclosure, please provide copies of the following
documentation for each subject weld:
i) Weld data sheet (traveler)
ii) Weld configuration and system location
iii) Applicable Code Edition and Addenda for weldment
iv) Applicable Code Edition and Addenda for welding procedures
v) Applicable weld procedures (WPS) used to fabricate the welds
vi) Copies of procedure qualification records (PQRs) supporting the WPS
from B.1.b.v
vii) Copies of mechanical test reports identified in the PQRs above
viii) Copies of the nonconformance reports for the selected welds (If
applicable)
ix) Radiographs of the selected welds and access to equipment to allow
viewing radiographs (If RT was performed)
-5- Enclosure
x) Copies of the preservice examination records for the selected welds.
xi) Copies of welder performance qualifications records applicable to the
selected welds, including documentation that welder maintained
proficiency in the applicable welding processes specified in the WPS (at
least six months prior to the date of subject work)
xii) Copies of NDE personnel qualifications (VT, PT, UT, RT), as applicable
c) For the ISI related corrective action issues selected by the inspector(s) from
section A of this enclosure, provide a copy of the corrective actions and
supporting documentation.
d) For the NDE reports with relevant conditions on Code Class 1 & 2 systems
selected by the inspector from section A above, provide a copy of the
examination records, examiner qualification records, and associated corrective
action documents.
e) A copy of (or ready access to) most current revision of the ISI Program Manual
and Plan for the current Interval.
f) For the NDEs selected by the inspector from section A of this enclosure, provide
a copy of the NDE procedures used to perform the examinations (including
calibration and flaw characterization/sizing procedures). For ultrasonic
examination procedures qualified in accordance with ASME Code,Section XI,
Appendix VIII, provide documentation supporting the procedure qualification
(e.g., the EPRI performance demonstration qualification summary sheets). Also,
include qualification documentation of the specific equipment to be used (e.g.,
ultrasonic unit, cables, and transducers including serial numbers) and NDE
personnel qualification records.
B.2 Reactor Pressure Vessel Head (RPVH)
a) Provide the NDE personnel qualification records for the examiners who will
perform examinations of the RPVH.
b) Provide drawings showing the following: (If a visual examination is planned for
the upcoming refueling outage)
i) RPVH and CRDM nozzle configurations
ii) RPVH insulation configuration
The drawings listed above should include fabrication drawings for the nozzle attachment
welds as applicable.
c) Copy of NDE reports from the last RPVH examination.
d) Copy of evaluation or calculation demonstrating that the scope of the visual
examination of the upper head will meet the 95 percent minimum coverage
-6- Enclosure
required by NRC Order EA-03-009 (If a visual examination is planned for the
upcoming refueling outage).
e) Provide a copy of the procedures that will be used to identify the source of any
boric acid deposits identified on the RPVH. If no explicit procedures exist which
govern this activity, provide a description of the process to be followed including
personnel responsibilities and expectations.
f) Provide a copy of the updated calculation of effective degradation years (EDY)
for the RPVH susceptibility ranking.
g) Provide a copy of the vendor qualification report(s) that demonstrates the
detection capability of the NDE equipment used for the RPVH examinations.
Also, identify any changes in equipment configurations used for the RPVH
examinations which differ from that used in the vendor qualification report(s).
B.3 Boric Acid Corrosion Control Program (BACCP)
a) Please provide boric acid walkdown inspection results, an updated list of boric
acid leaks identified so far this outage, associated corrective action
documentation, and the overall status of planned boric acid inspections.
b) Please provide any engineering evaluations completed for boric acid leaks
identified since the end of the last refueling outage. Please include a status of
corrective actions to repair and/or clean these boric acid leaks. Please identify
specifically which known leaks, if any, have remained in service or will remain in
service as active leaks.
B.4 Steam Generator Tube (SGT) Inspections
a) Copies of the Examination Technique Specification Sheets (ETSS) and
associated justification for any revisions.
b) Copy of the guidance to be followed if a loose part or foreign material is identified
in the SGs.
c) Please provide a copy of the ET procedures used to perform the SGT
inspections (specifically calibration and flaw characterization/sizing procedures,
etc.). Also include documentation for the specific equipment to be used.
d) Please provide copies of your responses to NRC and industry operating
experience communications such as Generic Letters, Information Notices, etc.
(as applicable to SGT inspections) *Do not provide these documents separately if
already included in other information requested such as the degradation
assessment.
e) List of corrective action documents generated by the vendor and/or site with
respect to SG inspection activities.
-7- Enclosure
B.5 Codes and Standards
a) Ready access to (i.e., copies provided to the inspector(s) for use during the
inspection at the onsite inspection location, or room number and location where
available):
i) Applicable Editions of the ASME Code (Sections V, IX and XI) for the
inservice inspection program and the repair/replacement program.
ii) EPRI and industry standards referenced in the procedures used to
perform the SGT eddy current examination.
Inspector Contact Information:
James Adams Breck Henderson
Reactor Inspector Reactor Inspector
817-860-8294 817-276-6569
James.Adams@nrc.gov Breck.Henderson@nrc.gov
Mailing Address:
US NRC Region IV
Attn: James Adams
612 E. Lamar Blvd, Suite 400
Arlington, TX 76011-4125
-8- Enclosure