{{#Wiki_filter:Serial No. 10-345 ATTACHMENT 3  
{{#Wiki_filter:Serial No. 10-345 ATTACHMENT 3 LICENSE AMENDMENT REQUEST 249: KEWAUNEE POWER STATION CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS (TAC NO. ME2139) -
 
SUPPLEMENT TO LICENSE AMENDMENT REQUEST - CLOSED REQUESTS FOR ADDITIONAL INFORMATION AND PROPOSED LICENSE CONDITIONS SUPPLEMENTAL INFORMATION FOR THE ENCLOSURE KEWAUNEE POWER STATION DOMINION ENERGY KEWAUNEE, INC.
LICENSE AMENDMENT REQUEST 249: KEWAUNEE POWER STATION CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS (TAC NO. ME2139) - SUPPLEMENT TO LICENSE AMENDMENT REQUEST - CLOSED REQUESTS FOR ADDITIONAL INFORMATION AND PROPOSED LICENSE CONDITIONS  
 
SUPPLEMENTAL INFORMATION FOR THE ENCLOSURE  
 
KEWAUNEE POWER STATION DOMINION ENERGY KEWAUNEE, INC.
 
Serial No. 10-345 Docket No. 50-305 Page 1 of 2 Kewaunee Conversion NRC Staff Reviewers (By Section)


Serial No. 10-345 Docket No. 50-305 Attachment 3 Page 1 of 2 Kewaunee Conversion NRC Staff Reviewers (By Section)
Chapter/
Chapter/
Section Title NRC Reviewer Initials 1.0 Use and Application Klett ALK 2.0 Safety Limits Klett ALK 3.0 LCO/SR Applicability Klett ALK  
Title               NRC Reviewer         Initials Section 1.0         Use and Application                 Klett               ALK 2.0         Safety Limits                       Klett               ALK 3.0         LCO/SR Applicability                 Klett               ALK 3.1         Reactivity Control Systems           Grover               RPG 3.2         Power Distribution Limits           Waig                 GMW 3.3         Instrumentation                     Bucholtz             KAB 3.4         Reactor Coolant System               Grover               PRG Emergency Core Cooling                                    MEH 3.5                                               Hamm Systems 3.6         Containment Systems                 Hamm                 MEH 3.7         Plant Systems                       Hamm                 MEH 3.8         Electrical Power Systems             Waig / Wolfgang     GMW / RW 3.9         Refueling Operations                 Grover               PRG 4.0         Design Features                     Klett               ALK 5.0         Administrative Controls             Cusumano             VGC To facilitate the review of DEKs LAR 249, a publicly available website was established to allow efficient issuance of and responses to NRC staff requests for additional information (RAIs) concerning the license amendment request. This website identifies each RAI using the NRC staff reviewers initials followed by a sequential number (e.g.,
 
ALK-001). The NRC staff reviewer closed the RAI upon an acceptable resolution.
===3.1 Reactivity===
Included in this Enclosure are the NRC staffs questions and DEKs responses to those questions associated with the attached Volumes. The following table lists those questions and responses included in this supplement.
Control Systems Grover RPG  
In the Enclosure, these questions and responses are arranged sequentially in the associated ITS Volume.
 
===3.2 Power===
Distribution Limits Waig GMW  
 
===3.3 Instrumentation===
Bucholtz KAB  
 
===3.4 Reactor===
Coolant System Grover PRG  
 
===3.5 Emergency===
Core Cooling Systems Hamm MEH 3.6 Containment Systems Hamm MEH 3.7 Plant Systems Hamm MEH  
 
===3.8 Electrical===
Power Systems Waig / Wolfgang GMW / RW 3.9 Refueling Operations Grover PRG 4.0 Design Features Klett ALK  
 
===5.0 Administrative===
Controls Cusumano VGC To facilitate the review of DEK's LAR 249, a publicly available website was established to allow efficient issuance of and responses to NRC staff requests for additional information (RAIs) concerning the license amendment request. This website identifies each RAI using the NRC staff reviewer's initials followed by a sequential number (e.g., ALK-001). The NRC staff reviewer closed the RAI upon an acceptable resolution. Included in this Enclosure are the NRC staff's questions and DEKs responses to those questions associated with the attached Volumes. The following table lists those questions and responses included in this supplement.  
 
In the Enclosure, these questions and responses are arranged sequentially in the associated ITS Volume.
 
Serial No. 10-345 Docket No. 50-305 Page 2 of 2 NRC Staff RAIs and DEK Responses Included in this Supplement Sequential Number ALK GMW KAB MEH RPG RW VGC 001        002        003        004        005      (a)  006        007        008        009        010    (b)  011        012        013        014        015        016                (a) This question requested a response by a separate letter. DEK responded by letter dated April 13, 2010 (reference 1)  (b) This question is open. The question is included but not DEKs response, which will be submitted in a future supplement.  


Attachment 3  
Serial No. 10-345 Docket No. 50-305 Attachment 3 Page 2 of 2 NRC Staff RAIs and DEK Responses Included in this Supplement Sequential ALK      GMW        KAB        MEH      RPG        RW        VGC Number 001              U 002              U 003              U 004              U 005              U                                        U (a) 006              U                              U        U 007              U                              U        U 008              U                              U        U 009              U                                        U 010              U                                        (b) 011              U 012              U                                                              U 013              U 014              U 015              U 016              U (a) This question requested a response by a separate letter. DEK responded by letter dated April 13, 2010 (reference 1)
(b) This question is open. The question is included but not DEKs response, which will be submitted in a future supplement. 


==Reference:==
==Reference:==
: 1. Letter from J Alan Price (DEK) to Document Control Desk (NRC), "License Amendment Request 249 (TAC NO. ME 02467) Conversion to Improved Technical Specifications Response to Request for Additional Information RE: TSTF-490," dated April 13, 2010 [ADAMS Accession No. ML101060517]}}
: 1. Letter from J Alan Price (DEK) to Document Control Desk (NRC), License Amendment Request 249 (TAC NO. ME02467) Conversion to Improved Technical Specifications Response to Request for Additional Information RE:
TSTF-490, dated April 13, 2010 [ADAMS Accession No. ML101060517]}}

Latest revision as of 17:25, 13 November 2019

Attachment 3, License Amendment Request 249: Kewaunee Power Station Conversion to Improved Technical Specifications (TAC No. ME2139) - Supplemental Information for the Enclosure
ML101890226
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 07/01/2010
From:
Dominion Energy Kewaunee
To:
Office of Nuclear Reactor Regulation
References
10-345, TAC ME2139
Download: ML101890226 (3)


Text

Serial No.10-345 ATTACHMENT 3 LICENSE AMENDMENT REQUEST 249: KEWAUNEE POWER STATION CONVERSION TO IMPROVED TECHNICAL SPECIFICATIONS (TAC NO. ME2139) -

SUPPLEMENT TO LICENSE AMENDMENT REQUEST - CLOSED REQUESTS FOR ADDITIONAL INFORMATION AND PROPOSED LICENSE CONDITIONS SUPPLEMENTAL INFORMATION FOR THE ENCLOSURE KEWAUNEE POWER STATION DOMINION ENERGY KEWAUNEE, INC.

Serial No.10-345 Docket No. 50-305 Attachment 3 Page 1 of 2 Kewaunee Conversion NRC Staff Reviewers (By Section)

Chapter/

Title NRC Reviewer Initials Section 1.0 Use and Application Klett ALK 2.0 Safety Limits Klett ALK 3.0 LCO/SR Applicability Klett ALK 3.1 Reactivity Control Systems Grover RPG 3.2 Power Distribution Limits Waig GMW 3.3 Instrumentation Bucholtz KAB 3.4 Reactor Coolant System Grover PRG Emergency Core Cooling MEH 3.5 Hamm Systems 3.6 Containment Systems Hamm MEH 3.7 Plant Systems Hamm MEH 3.8 Electrical Power Systems Waig / Wolfgang GMW / RW 3.9 Refueling Operations Grover PRG 4.0 Design Features Klett ALK 5.0 Administrative Controls Cusumano VGC To facilitate the review of DEKs LAR 249, a publicly available website was established to allow efficient issuance of and responses to NRC staff requests for additional information (RAIs) concerning the license amendment request. This website identifies each RAI using the NRC staff reviewers initials followed by a sequential number (e.g.,

ALK-001). The NRC staff reviewer closed the RAI upon an acceptable resolution.

Included in this Enclosure are the NRC staffs questions and DEKs responses to those questions associated with the attached Volumes. The following table lists those questions and responses included in this supplement.

In the Enclosure, these questions and responses are arranged sequentially in the associated ITS Volume.

Serial No.10-345 Docket No. 50-305 Attachment 3 Page 2 of 2 NRC Staff RAIs and DEK Responses Included in this Supplement Sequential ALK GMW KAB MEH RPG RW VGC Number 001 U 002 U 003 U 004 U 005 U U (a) 006 U U U 007 U U U 008 U U U 009 U U 010 U (b) 011 U 012 U U 013 U 014 U 015 U 016 U (a) This question requested a response by a separate letter. DEK responded by letter dated April 13, 2010 (reference 1)

(b) This question is open. The question is included but not DEKs response, which will be submitted in a future supplement.

Reference:

1. Letter from J Alan Price (DEK) to Document Control Desk (NRC), License Amendment Request 249 (TAC NO. ME02467) Conversion to Improved Technical Specifications Response to Request for Additional Information RE:

TSTF-490, dated April 13, 2010 [ADAMS Accession No. ML101060517]