Line 3: Line 3:
| issue date = 10/14/2009
| issue date = 10/14/2009
| title = CG-2009-10-Simulator JPM C
| title = CG-2009-10-Simulator JPM C
| author name = Garchow S M
| author name = Garchow S
| author affiliation = NRC/RGN-IV/DRS/OB
| author affiliation = NRC/RGN-IV/DRS/OB
| addressee name =  
| addressee name =  
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:INSTRUCTIONAL COVER SHEET PROGRAM TITLE OPERATIONS TRAINING COURSE TITLE JOB PERFORMANCE MEASURE LESSON TITLE REACTOR FEED PUMP 'A' QUICK RESTART (SIM)
{{#Wiki_filter:INSTRUCTIONAL COVER SHEET PROGRAM TITLE           OPERATIONS TRAINING COURSE TITLE             JOB PERFORMANCE MEASURE LESSON TITLE             REACTOR FEED PUMP A QUICK RESTART (SIM)
LESSON LENGTH
LESSON LENGTH     .5 HRS   MAXIMUM STUDENTS       1 INSTRUCTIONAL MATERIALS INCLUDED Lesson Plan PQD Code                                                 Rev. No.
.5 HRS MAXIMUM STUDENTS 1 INSTRUCTIONAL MATERIALS INCLUDED Lesson Plan PQD Code   Rev. No. Simulator Guide PQD Code   Rev. No. JPM PQD Code LR000131 Rev. No.6 Exam PQD Code   Rev. No.
Simulator Guide PQD Code                                             Rev. No.
DIVISION TITLE Nuclear Training DEPARTMENT Operations Training PREPARED BY STAFF DATE 1995   REVISED BY Ron Hayden DATE 6/11/09       TECHNICAL REVIEW BY DATE INSTRUCTIONAL REVIEW BY DATE APPROVED BY DATE Operations Training Manager Verify materials current IAW SWP-TQS-01 prior to use.
JPM PQD Code                 LR000131                               Rev. No. 6 Exam PQD Code                                                       Rev. No.
LR000131 Rev. 6 Page 1 of 6 MINOR REVISION RECORD Minor Rev Number Description of Revision Affected Pages Entered By Effective Date Manager Approval                          JPM SETUP Simulator ICs; Malfunctions; Triggers; Overrides:
DIVISION TITLE   Nuclear Training DEPARTMENT       Operations Training PREPARED BY       STAFF                                                 DATE 1995 REVISED BY       Ron Hayden                                             DATE 6/11/09 TECHNICAL REVIEW BY                                                     DATE INSTRUCTIONAL REVIEW BY                                                 DATE APPROVED BY                                                             DATE Operations Training Manager Verify materials current IAW SWP-TQS-01 prior to use.
Post scram IC where both RFP's have tripped at 54.5" and current RPV level will allow the RFP to be  reset (LT +54.5")


MINOR REVISION RECORD Minor                    Description                      Affected      Entered  Effective  Manager Rev Number                of Revision                        Pages          By        Date    Approval JPM SETUP Simulator ICs; Malfunctions; Triggers; Overrides:
Post scram IC where both RFPs have tripped at 54.5 and current RPV level will allow the RFP to be reset (LT +54.5)
Special Setup Instructions:
Special Setup Instructions:
None JPM Instructions:
None JPM Instructions:
Verify Current Procedure against JPM and ensure procedure critical steps match if procedure is different revision than listed in JPM. If critical st eps have changed, the JPM should be revised.  
Verify Current Procedure against JPM and ensure procedure critical steps match if procedure is different revision than listed in JPM. If critical steps have changed, the JPM should be revised.
 
The evaluator and student shall use current procedure. The evaluator should mark off steps as they are completed, note comments, and transfer the comments to the Results of JPM page.
The evaluator and student shall use current procedure. The evaluator should mark off steps as they are completed, note comments, and transfer the comments to the "Results of JPM" page.
Tools/Equipment: None                                   Safety Items: None Task Number: RO-0371                                   Validation Time: 15 Minutes Prerequisite Training: None                             Time Critical: No PPM  
Tools/Equipment:
None Safety Items:
None Task Number:
RO-0371 Validation Time:
15 Minutes Prerequisite Training:
None Time Critical:
No PPM  


==Reference:==
==Reference:==
SOP-RFW-RESTART-QC Rev. 2 Location: Simulator NUREG 1123 Ref:
SOP-RFW-RESTART-QC Rev. 2               Location: Simulator NUREG 1123 Ref: 259001A4.02 (3.9/3.7)                   Performance Method: Perform LR000131 Rev. 6 Page 1 of 6
259001A4.02 (3.9/3.7)
Performance Method:
Perform LR000131 Rev. 6 Page 2 of 6 JPM CHECKLIST PROCEDURE VALIDATION Procedure copies for evaluator and student, if procedure revision is different from that listed on JPM, critical tasks reverified. Evaluator copy may be used for marking step completion, and comments. INITIAL CONDITIONS: A reactor scram was inserted as part of a controlled shutdown. RPV level increased to GT 54.5" and both RFP's tripped. INITIATING CUE: You have been directed by the CRS to perform a quick restart of the "A" RFW Pump using SOP-RFT-RESTART-QC. Inform the CRS when the A RFW pump's speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM.
* Items are Critical Steps Comments Element Standard Sat/Unsat RECORD START TIME: __________
Step 2.1.1 If desired, then transfer RPV level control to RFW-FCV-10A/10B per SOP-RFW-FCV-QC concurrently with this procedure N/A  N/A Step 2.12 If performing this section following a reactor scram, then verify RFW-V-112A and RFW-V-112B have started to close Takes control switch for RFW-V-112A ands RFW-V-112B momentarily to the closed
 
position and observes dual light indication S / U
* Step 2.13 Verify MSIVs are open (H13-P601) Observes all MSIV red lights are lit and green lights are out on
 
P601 S / U Step 2.14 Verify at least two high level seal ins are reset (H13-
 
P603) Depresses at least two of the High Level Seal In P/B's on P603 S / U
* PROCEDURE NOTE: RFT-COMP-1 and RFT-COMP-2 are redundant units, either screen will allow operation of the Reactor Feed Turbine control system.
LR000131 Rev. 6 Page 3 of 6
* Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.15 Verify RFW-P-1A(B) in MDVP mode at 0% using RFT-COMP-1 or RFT-COMP-2 (Pump Control Screen) as follows (H13-
 
P840): a. Select MDVP
: b. Select YES
: c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B)
 
using RFT-COMP-1 or RFT-COMP-2 for 0%
output (Pump Control
 
Screen) (H13-P840) Verifies: a. Selects MDVP on either RFT-COMP-1 or RFT-COMP-2 b. Selects YES
: c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) using RFT-COMP-1 or RFT-COMP-2 for 0% output S / U  S / U  S / U Step 2.16 Hold the trip/reset switch to reset until RFW-P-1A(B)
HP and LP stop valves
 
indicate full open (H13-
 
P840) Places the Turbine Emergency Trip/Reset switch to the Reset position until the LP and HP Stop
 
valves red light is on and the green light is off, then release the Trip/Reset switch S / U
* PROCEDURE NOTE: If the Main Turbine is tripped, the RFP Turbine will not roll until Main Steam is admitted at approximately 60% GV position.
Step 2.17 Raise Turbine speed as follows: a. If the Main Turbine is not tripped--. Does not perform this step as MT is tripped S / U b. If the Main Turbine is tripped, then perform the
 
following:  Slowly raise RFW-P-1A(B) GV position using RFT-COMP-1 or RFT-COMP-2  Monitor RFW-P-1A(B) speed on RFT-COMP-1 or RFW-COMP-2 as GV position increases GT 60% GV position In MDVP, depresses increase pushbutton as necessary to raise GV position to GT 60% and then to increase turbine speed to raise GT 800 rpm S / U
* LR000131 Rev. 6 Page 4 of 6
* Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.18 Transfer RFW-P-1A(B) to MDEM using RFT-COMP-1 or RFT-COMP-2 as soon as practical (GT 800 rpm)
(Pump Control Screen) as


follows (H13-P840):
JPM CHECKLIST PROCEDURE        Procedure copies for evaluator and student, if procedure revision is different from VALIDATION        that listed on JPM, critical tasks reverified. Evaluator copy may be used for marking step completion, and comments.
INITIAL          A reactor scram was inserted as part of a controlled shutdown. RPV level increased CONDITIONS:      to GT 54.5 and both RFPs tripped.
INITIATING CUE: You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC. Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM.
* Items are Critical Steps Comments                  Element                            Standard                  Sat/Unsat RECORD START TIME: __________
Step 2.1.1    If desired, then transfer RPV level control to RFW-                        N/A                        N/A FCV-10A/10B per SOP-RFW-FCV-QC concurrently with this procedure Step 2.12      If performing this section        Takes control switch for RFW-V-          S/U*
following a reactor scram,        112A ands RFW-V-112B then verify RFW-V-112A            momentarily to the closed and RFW-V-112B have              position and observes dual light started to close                  indication Step 2.13      Verify MSIVs are open            Observes all MSIV red lights are          S/U (H13-P601)                        lit and green lights are out on P601 Step 2.14      Verify at least two high          Depresses at least two of the            S/U*
level seal ins are reset (H13- High Level Seal In P/Bs on P603 P603)
PROCEDURE NOTE: RFT-COMP-1 and RFT-COMP-2 are redundant units, either screen will allow operation of the Reactor Feed Turbine control system.
LR000131 Rev. 6 Page 2 of 6
* Items are Critical Steps Comments                  Element                          Standard                  Sat/Unsat Step 2.15      Verify RFW-P-1A(B) in          Verifies:
MDVP mode at 0% using          a. Selects MDVP on either RFT-            S/U RFT-COMP-1 or RFT-            COMP-1 or RFT-COMP-2 COMP-2 (Pump Control
: b. Selects YES                            S/U Screen) as follows (H13-P840):                        c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B)                S/U
: a. Select MDVP using RFT-COMP-1 or
: b. Select YES                  RFT-COMP-2 for 0% output
: c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) using RFT-COMP-1 or RFT-COMP-2 for 0%
output (Pump Control Screen) (H13-P840)
Step 2.16      Hold the trip/reset switch to  Places the Turbine Emergency reset until RFW-P-1A(B)        Trip/Reset switch to the Reset HP and LP stop valves          position until the LP and HP Stop        S/U*
indicate full open (H13-      valves red light is on and the P840)                          green light is off, then release the Trip/Reset switch PROCEDURE NOTE: If the Main Turbine is tripped, the RFP Turbine will not roll until Main Steam is admitted at approximately 60% GV position.
Step 2.17      Raise Turbine speed as        Does not perform this step as MT follows:                      is tripped                                S/U
: a. If the Main Turbine is not tripped.
: b. If the Main Turbine is      In MDVP, depresses increase tripped, then perform the      pushbutton as necessary to raise        S/U*
following:                    GV position to GT 60% and then
* Slowly raise RFW-P-        to increase turbine speed to raise 1A(B) GV position          GT 800 rpm using RFT-COMP-1 or RFT-COMP-2
* Monitor RFW-P-1A(B) speed on RFT-COMP-1 or RFW-COMP-2 as GV position increases GT 60% GV position LR000131 Rev. 6 Page 3 of 6
* Items are Critical Steps Comments                      Element                      Standard                Sat/Unsat Step 2.18          Transfer RFW-P-1A(B) to      With speed GT 800 rpm, MDEM using RFT-COMP-        transfers RFW-P-1A to MDEM 1 or RFT-COMP-2 as soon      by:
as practical (GT 800 rpm)    a. depressing the MDEM (Pump Control Screen) as                                          S/U*
pushbutton follows (H13-P840):
: b. depresses Yes pushbutton          S/U*
: a. Select MDEM
: a. Select MDEM
: b. Select Yes With speed GT 800 rpm, transfers RFW-P-1A to MDEM  
: b. Select Yes Termination Criteria: Student informs CRS that A RFW pumps speed is GT 800 rpm and the speed controller has been transferred to MDEM RECORD TERMINATION TIME: _________
Transfer to Results of JPM page the following information: Procedures validated prior to use; Comments from marked up evaluators procedure copy; Unsatisfactory critical tasks; Total JPM time; Marked Up procedure and remaining JPM pages may be discarded.
LR000131 Rev. 6 Page 4 of 6


by: a. depressing the MDEM pushbutton b. depresses Yes pushbutton S / U
RESULTS OF JPM:
* S / U
REACTOR FEED PUMP QUICK RESTART Examinee (Please Print): ______________________________________________
* Termination Criteria: Student informs CRS that A RFW pumps speed is GT 800 rpm and the speed controller has been transferred to MDEM RECORD TERMINATION TIME: _________
Evaluator (Please Print): ______________________________________________
Transfer to "Results of JPM" page the following information:  Procedures validated prior to use; Comments from marked up evaluator's procedure copy; Unsatisfactory critical tasks; Total JPM time; Marked Up procedure and re maining JPM pages may be discarded.
Task Standard: RFP A is running with rpm is GT 800 and the controller is in MDEM Overall Evaluation                                   Exam Code SAT / UNSAT (Circle One)
LR000131 Rev. 6 Page 5 of 6  RESULTS OF JPM: REACTOR FEED PUMP QUICK RESTART Examinee (Please Print):
Verified Procedure #/Rev. Used for           Validation/Critical           JPM Completion JPM                                  Time                      Time 15 Minutes / NA COMMENTS:
______________________________________________
Evaluator's Signature:                                     Date:
Evaluator (Please Print):
LR000131 Rev. 6 Page 5 of 6
______________________________________________
Task Standard:
RFP "A" is running with rpm is GT 800 and the controller is in MDEM Overall Evaluation Exam Code SAT / UNSAT (Circle One)
Verified Procedure #/Rev. Used for JPM Validation/Critical Time JPM Completion Time 15 Minutes / NA COMMENTS:                                       Evaluator's Signature:
Date:
LR000131 Rev. 6 Page 6 of 6 STUDENT JPM INFORMATION CARD Initial Conditions:
A reactor scram was inserted as part of a controlled shutdown RPV level increased to GT 54.5" and both RFP's tripped


Cue: You have been directed by the CRS to perform a quick restart of the "A" RFW Pump using SOP-RFT-RESTART-QC Inform the CRS when the A RFW pump's speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM}}
STUDENT JPM INFORMATION CARD Initial Conditions:
A reactor scram was inserted as part of a controlled shutdown RPV level increased to GT 54.5 and both RFPs tripped Cue:
You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM LR000131 Rev. 6 Page 6 of 6}}

Latest revision as of 13:49, 13 November 2019

CG-2009-10-Simulator JPM C
ML102450183
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/14/2009
From: Garchow S
Operations Branch IV
To:
Energy Northwest
References
Download: ML102450183 (7)


Text

INSTRUCTIONAL COVER SHEET PROGRAM TITLE OPERATIONS TRAINING COURSE TITLE JOB PERFORMANCE MEASURE LESSON TITLE REACTOR FEED PUMP A QUICK RESTART (SIM)

LESSON LENGTH .5 HRS MAXIMUM STUDENTS 1 INSTRUCTIONAL MATERIALS INCLUDED Lesson Plan PQD Code Rev. No.

Simulator Guide PQD Code Rev. No.

JPM PQD Code LR000131 Rev. No. 6 Exam PQD Code Rev. No.

DIVISION TITLE Nuclear Training DEPARTMENT Operations Training PREPARED BY STAFF DATE 1995 REVISED BY Ron Hayden DATE 6/11/09 TECHNICAL REVIEW BY DATE INSTRUCTIONAL REVIEW BY DATE APPROVED BY DATE Operations Training Manager Verify materials current IAW SWP-TQS-01 prior to use.

MINOR REVISION RECORD Minor Description Affected Entered Effective Manager Rev Number of Revision Pages By Date Approval JPM SETUP Simulator ICs; Malfunctions; Triggers; Overrides:

Post scram IC where both RFPs have tripped at 54.5 and current RPV level will allow the RFP to be reset (LT +54.5)

Special Setup Instructions:

None JPM Instructions:

Verify Current Procedure against JPM and ensure procedure critical steps match if procedure is different revision than listed in JPM. If critical steps have changed, the JPM should be revised.

The evaluator and student shall use current procedure. The evaluator should mark off steps as they are completed, note comments, and transfer the comments to the Results of JPM page.

Tools/Equipment: None Safety Items: None Task Number: RO-0371 Validation Time: 15 Minutes Prerequisite Training: None Time Critical: No PPM

Reference:

SOP-RFW-RESTART-QC Rev. 2 Location: Simulator NUREG 1123 Ref: 259001A4.02 (3.9/3.7) Performance Method: Perform LR000131 Rev. 6 Page 1 of 6

JPM CHECKLIST PROCEDURE Procedure copies for evaluator and student, if procedure revision is different from VALIDATION that listed on JPM, critical tasks reverified. Evaluator copy may be used for marking step completion, and comments.

INITIAL A reactor scram was inserted as part of a controlled shutdown. RPV level increased CONDITIONS: to GT 54.5 and both RFPs tripped.

INITIATING CUE: You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC. Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM.

  • Items are Critical Steps Comments Element Standard Sat/Unsat RECORD START TIME: __________

Step 2.1.1 If desired, then transfer RPV level control to RFW- N/A N/A FCV-10A/10B per SOP-RFW-FCV-QC concurrently with this procedure Step 2.12 If performing this section Takes control switch for RFW-V- S/U*

following a reactor scram, 112A ands RFW-V-112B then verify RFW-V-112A momentarily to the closed and RFW-V-112B have position and observes dual light started to close indication Step 2.13 Verify MSIVs are open Observes all MSIV red lights are S/U (H13-P601) lit and green lights are out on P601 Step 2.14 Verify at least two high Depresses at least two of the S/U*

level seal ins are reset (H13- High Level Seal In P/Bs on P603 P603)

PROCEDURE NOTE: RFT-COMP-1 and RFT-COMP-2 are redundant units, either screen will allow operation of the Reactor Feed Turbine control system.

LR000131 Rev. 6 Page 2 of 6

  • Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.15 Verify RFW-P-1A(B) in Verifies:

MDVP mode at 0% using a. Selects MDVP on either RFT- S/U RFT-COMP-1 or RFT- COMP-1 or RFT-COMP-2 COMP-2 (Pump Control

b. Selects YES S/U Screen) as follows (H13-P840): c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) S/U
a. Select MDVP using RFT-COMP-1 or
b. Select YES RFT-COMP-2 for 0% output
c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) using RFT-COMP-1 or RFT-COMP-2 for 0%

output (Pump Control Screen) (H13-P840)

Step 2.16 Hold the trip/reset switch to Places the Turbine Emergency reset until RFW-P-1A(B) Trip/Reset switch to the Reset HP and LP stop valves position until the LP and HP Stop S/U*

indicate full open (H13- valves red light is on and the P840) green light is off, then release the Trip/Reset switch PROCEDURE NOTE: If the Main Turbine is tripped, the RFP Turbine will not roll until Main Steam is admitted at approximately 60% GV position.

Step 2.17 Raise Turbine speed as Does not perform this step as MT follows: is tripped S/U

a. If the Main Turbine is not tripped.
b. If the Main Turbine is In MDVP, depresses increase tripped, then perform the pushbutton as necessary to raise S/U*

following: GV position to GT 60% and then

  • Slowly raise RFW-P- to increase turbine speed to raise 1A(B) GV position GT 800 rpm using RFT-COMP-1 or RFT-COMP-2
  • Monitor RFW-P-1A(B) speed on RFT-COMP-1 or RFW-COMP-2 as GV position increases GT 60% GV position LR000131 Rev. 6 Page 3 of 6
  • Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.18 Transfer RFW-P-1A(B) to With speed GT 800 rpm, MDEM using RFT-COMP- transfers RFW-P-1A to MDEM 1 or RFT-COMP-2 as soon by:

as practical (GT 800 rpm) a. depressing the MDEM (Pump Control Screen) as S/U*

pushbutton follows (H13-P840):

b. depresses Yes pushbutton S/U*
a. Select MDEM
b. Select Yes Termination Criteria: Student informs CRS that A RFW pumps speed is GT 800 rpm and the speed controller has been transferred to MDEM RECORD TERMINATION TIME: _________

Transfer to Results of JPM page the following information: Procedures validated prior to use; Comments from marked up evaluators procedure copy; Unsatisfactory critical tasks; Total JPM time; Marked Up procedure and remaining JPM pages may be discarded.

LR000131 Rev. 6 Page 4 of 6

RESULTS OF JPM:

REACTOR FEED PUMP QUICK RESTART Examinee (Please Print): ______________________________________________

Evaluator (Please Print): ______________________________________________

Task Standard: RFP A is running with rpm is GT 800 and the controller is in MDEM Overall Evaluation Exam Code SAT / UNSAT (Circle One)

Verified Procedure #/Rev. Used for Validation/Critical JPM Completion JPM Time Time 15 Minutes / NA COMMENTS:

Evaluator's Signature: Date:

LR000131 Rev. 6 Page 5 of 6

STUDENT JPM INFORMATION CARD Initial Conditions:

A reactor scram was inserted as part of a controlled shutdown RPV level increased to GT 54.5 and both RFPs tripped Cue:

You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM LR000131 Rev. 6 Page 6 of 6