MONTHYEARIR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 ML23115A3552023-03-0909 March 2023 10-CGS-2023-02 Post Exam Comments ML23115A3562023-03-0909 March 2023 11-CGS-2023-02 Public Forms IR 05000397/20213012021-04-21021 April 2021 NRC Exam Report 05000397/2021301 ML21113A0062021-03-0404 March 2021 CG-2021-02-FINAL Outlines ML21098A1702021-03-0404 March 2021 CG-2021-02-FINAL Written Examination ML21113A0002021-03-0404 March 2021 CG-2021-02-DRAFT Op Test Comments ML21113A0012021-03-0404 March 2021 CG-2021-02-DRAFT Op Test ML21113A0022021-03-0404 March 2021 CG-2021-02-DRAFT Outline Comments ML21098A1692021-03-0404 March 2021 CG-2021-02-FINAL Operating Test ML21098A1712021-03-0404 March 2021 CG-2021-02-Post Exam Submittal ML21113A0072021-03-0404 March 2021 CG-2021-02-Public Forms, Exam Assignment Tickler ML21113A0052021-03-0404 March 2021 CG-2021-02-DRAFT Written Exam ML21113A0042021-03-0404 March 2021 CG-2021-02-DRAFT Written Exam Comments ML21113A0032021-03-0404 March 2021 CG-2021-02-Draft Outlines ML20108F0522020-04-16016 April 2020 Notification of NRC Initial Operator Licensing Examination 05000397/2021301 ML19011A3712019-01-10010 January 2019 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2019 ML18145A2312018-05-29029 May 2018 Errata for Columbia Generating Station - Notification of NRC Initial Operator Licensing Examination 05000397/2019301 ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17081A5402017-03-0909 March 2017 4-COLUMBIA-2017-02 Draft Written Exam Comments ML17081A5352017-03-0909 March 2017 10-Columbia-2017-02 Post-Exam Comments ML17081A5422017-03-0909 March 2017 6-COLUMBIA-2017-02 Draft Operating Test Comments ML17081A5372017-03-0909 March 2017 1-COLUMBIA-2017-02 Draft Outlines ML17081A5332017-03-0909 March 2017 8-Columbia-2017-02 Final Written Exam ML17081A5342017-03-0909 March 2017 9-Columbia-2017-02 Final Operating Test ML17081A5392017-03-0909 March 2017 3-COLUMBIA-2017-02 Draft Written Exam ML17081A5412017-03-0909 March 2017 5-Columbia-2017-02 Draft Operating Test ML17100A3992017-03-0909 March 2017 11-COLUMBIA-2017-02 Public Forms ML17081A5432017-03-0909 March 2017 7-COLUMBIA-2017-02 Final Outlines ML17081A5382017-03-0909 March 2017 2-Columbia-2017-02 Draft Outline Comments ML17048A3562017-02-17017 February 2017 Generic Fundamentals Examination Results ML17094A5682017-02-16016 February 2017 NRC Initial Operator Licensing Examination Approval 05000397/2017301 ML17013A5482017-01-13013 January 2017 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2017 GO2-16-106, Voluntary Response to Regulatory Issue Summary 2016-092016-07-13013 July 2016 Voluntary Response to Regulatory Issue Summary 2016-09 ML15351A0282015-12-17017 December 2015 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2016 ML15273A3322015-09-30030 September 2015 Generic Fundamentals Examination Results Sept 2015 ML15167A1332015-05-13013 May 2015 2015-04 Post Exam Comments Analysis ML15167A1402015-05-0505 May 2015 2015-04 Draft Op Test ML15183A0512015-05-0505 May 2015 2015-04 Public Forms ML15167A1502015-05-0505 May 2015 2015-04 Final Outlines ML15167A1492015-05-0505 May 2015 2015-04 Draft Op Test Comments ML15167A1472015-05-0505 May 2015 2015-04 Draft Written Exam Comments ML15167A1452015-05-0505 May 2015 2015-04 - Draft Outline Comments ML15167A1442015-05-0505 May 2015 2015-04 Draft Outlines ML15167A1382015-05-0505 May 2015 2015-04 Draft Written Exams ML15167A1282015-05-0505 May 2015 2015-04 As-given Op Test Files ML15167A1272015-05-0505 May 2015 2015-04 Final Op Test ML15167A1232015-05-0505 May 2015 2015-04 Final Written Exams ML15111A0662015-04-21021 April 2015 Examination Approval 05000397/2015301 ML14345A3302014-12-11011 December 2014 Announcement of the Generic Fundamentals Section of the Written Operator Licensing Examinations for 2015 2024-02-14
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 ML23115A3552023-03-0909 March 2023 10-CGS-2023-02 Post Exam Comments ML23115A3562023-03-0909 March 2023 11-CGS-2023-02 Public Forms IR 05000397/20213012021-04-21021 April 2021 NRC Exam Report 05000397/2021301 ML21113A0062021-03-0404 March 2021 CG-2021-02-FINAL Outlines ML21098A1692021-03-0404 March 2021 CG-2021-02-FINAL Operating Test ML21098A1702021-03-0404 March 2021 CG-2021-02-FINAL Written Examination ML21098A1712021-03-0404 March 2021 CG-2021-02-Post Exam Submittal ML21113A0072021-03-0404 March 2021 CG-2021-02-Public Forms, Exam Assignment Tickler ML21113A0032021-03-0404 March 2021 CG-2021-02-Draft Outlines ML21113A0042021-03-0404 March 2021 CG-2021-02-DRAFT Written Exam Comments ML21113A0052021-03-0404 March 2021 CG-2021-02-DRAFT Written Exam ML21113A0002021-03-0404 March 2021 CG-2021-02-DRAFT Op Test Comments ML21113A0012021-03-0404 March 2021 CG-2021-02-DRAFT Op Test ML21113A0022021-03-0404 March 2021 CG-2021-02-DRAFT Outline Comments ML20108F0522020-04-16016 April 2020 Notification of NRC Initial Operator Licensing Examination 05000397/2021301 ML18145A2312018-05-29029 May 2018 Errata for Columbia Generating Station - Notification of NRC Initial Operator Licensing Examination 05000397/2019301 ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17081A5342017-03-0909 March 2017 9-Columbia-2017-02 Final Operating Test ML17100A3992017-03-0909 March 2017 11-COLUMBIA-2017-02 Public Forms ML17081A5352017-03-0909 March 2017 10-Columbia-2017-02 Post-Exam Comments ML17081A5422017-03-0909 March 2017 6-COLUMBIA-2017-02 Draft Operating Test Comments ML17081A5372017-03-0909 March 2017 1-COLUMBIA-2017-02 Draft Outlines ML17081A5402017-03-0909 March 2017 4-COLUMBIA-2017-02 Draft Written Exam Comments ML17081A5412017-03-0909 March 2017 5-Columbia-2017-02 Draft Operating Test ML17081A5432017-03-0909 March 2017 7-COLUMBIA-2017-02 Final Outlines ML17081A5332017-03-0909 March 2017 8-Columbia-2017-02 Final Written Exam ML17081A5392017-03-0909 March 2017 3-COLUMBIA-2017-02 Draft Written Exam ML17081A5382017-03-0909 March 2017 2-Columbia-2017-02 Draft Outline Comments ML17048A3562017-02-17017 February 2017 Generic Fundamentals Examination Results GO2-16-106, Voluntary Response to Regulatory Issue Summary 2016-092016-07-13013 July 2016 Voluntary Response to Regulatory Issue Summary 2016-09 ML15351A0282015-12-17017 December 2015 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2016 ML15273A3322015-09-30030 September 2015 Generic Fundamentals Examination Results Sept 2015 ML15167A1332015-05-13013 May 2015 2015-04 Post Exam Comments Analysis ML15183A0512015-05-0505 May 2015 2015-04 Public Forms ML15167A1502015-05-0505 May 2015 2015-04 Final Outlines ML15167A1492015-05-0505 May 2015 2015-04 Draft Op Test Comments ML15167A1472015-05-0505 May 2015 2015-04 Draft Written Exam Comments ML15167A1452015-05-0505 May 2015 2015-04 - Draft Outline Comments ML15167A1442015-05-0505 May 2015 2015-04 Draft Outlines ML15167A1402015-05-0505 May 2015 2015-04 Draft Op Test ML15167A1232015-05-0505 May 2015 2015-04 Final Written Exams ML15167A1272015-05-0505 May 2015 2015-04 Final Op Test ML15167A1282015-05-0505 May 2015 2015-04 As-given Op Test Files ML15167A1382015-05-0505 May 2015 2015-04 Draft Written Exams ML15111A0662015-04-21021 April 2015 Examination Approval 05000397/2015301 ML14345A3302014-12-11011 December 2014 Announcement of the Generic Fundamentals Section of the Written Operator Licensing Examinations for 2015 ML14163A4792014-05-29029 May 2014 Voluntary Response to Regulatory Issue Summary (RIS) 2014-05, Preparation and Scheduling of Operator Licensing Examinations ML13056A5202013-02-12012 February 2013 2013-02- Exam Performance Analysis ML13084A1092013-02-0808 February 2013 Generation Station-2013-02-Draft Operating Test Comments 2024-02-14
[Table view] |
Text
INSTRUCTIONAL COVER SHEET PROGRAM TITLE OPERATIONS TRAINING COURSE TITLE JOB PERFORMANCE MEASURE LESSON TITLE REACTOR FEED PUMP A QUICK RESTART (SIM)
LESSON LENGTH .5 HRS MAXIMUM STUDENTS 1 INSTRUCTIONAL MATERIALS INCLUDED Lesson Plan PQD Code Rev. No.
Simulator Guide PQD Code Rev. No.
JPM PQD Code LR000131 Rev. No. 6 Exam PQD Code Rev. No.
DIVISION TITLE Nuclear Training DEPARTMENT Operations Training PREPARED BY STAFF DATE 1995 REVISED BY Ron Hayden DATE 6/11/09 TECHNICAL REVIEW BY DATE INSTRUCTIONAL REVIEW BY DATE APPROVED BY DATE Operations Training Manager Verify materials current IAW SWP-TQS-01 prior to use.
MINOR REVISION RECORD Minor Description Affected Entered Effective Manager Rev Number of Revision Pages By Date Approval JPM SETUP Simulator ICs; Malfunctions; Triggers; Overrides:
Post scram IC where both RFPs have tripped at 54.5 and current RPV level will allow the RFP to be reset (LT +54.5)
Special Setup Instructions:
None JPM Instructions:
Verify Current Procedure against JPM and ensure procedure critical steps match if procedure is different revision than listed in JPM. If critical steps have changed, the JPM should be revised.
The evaluator and student shall use current procedure. The evaluator should mark off steps as they are completed, note comments, and transfer the comments to the Results of JPM page.
Tools/Equipment: None Safety Items: None Task Number: RO-0371 Validation Time: 15 Minutes Prerequisite Training: None Time Critical: No PPM
Reference:
SOP-RFW-RESTART-QC Rev. 2 Location: Simulator NUREG 1123 Ref: 259001A4.02 (3.9/3.7) Performance Method: Perform LR000131 Rev. 6 Page 1 of 6
JPM CHECKLIST PROCEDURE Procedure copies for evaluator and student, if procedure revision is different from VALIDATION that listed on JPM, critical tasks reverified. Evaluator copy may be used for marking step completion, and comments.
INITIAL A reactor scram was inserted as part of a controlled shutdown. RPV level increased CONDITIONS: to GT 54.5 and both RFPs tripped.
INITIATING CUE: You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC. Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM.
- Items are Critical Steps Comments Element Standard Sat/Unsat RECORD START TIME: __________
Step 2.1.1 If desired, then transfer RPV level control to RFW- N/A N/A FCV-10A/10B per SOP-RFW-FCV-QC concurrently with this procedure Step 2.12 If performing this section Takes control switch for RFW-V- S/U*
following a reactor scram, 112A ands RFW-V-112B then verify RFW-V-112A momentarily to the closed and RFW-V-112B have position and observes dual light started to close indication Step 2.13 Verify MSIVs are open Observes all MSIV red lights are S/U (H13-P601) lit and green lights are out on P601 Step 2.14 Verify at least two high Depresses at least two of the S/U*
level seal ins are reset (H13- High Level Seal In P/Bs on P603 P603)
PROCEDURE NOTE: RFT-COMP-1 and RFT-COMP-2 are redundant units, either screen will allow operation of the Reactor Feed Turbine control system.
LR000131 Rev. 6 Page 2 of 6
- Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.15 Verify RFW-P-1A(B) in Verifies:
MDVP mode at 0% using a. Selects MDVP on either RFT- S/U RFT-COMP-1 or RFT- COMP-1 or RFT-COMP-2 COMP-2 (Pump Control
- b. Selects YES S/U Screen) as follows (H13-P840): c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) S/U
- a. Select MDVP using RFT-COMP-1 or
- b. Select YES RFT-COMP-2 for 0% output
- c. If required, then DEPRESS the DOWN arrow for RFW-P-1A(B) using RFT-COMP-1 or RFT-COMP-2 for 0%
output (Pump Control Screen) (H13-P840)
Step 2.16 Hold the trip/reset switch to Places the Turbine Emergency reset until RFW-P-1A(B) Trip/Reset switch to the Reset HP and LP stop valves position until the LP and HP Stop S/U*
indicate full open (H13- valves red light is on and the P840) green light is off, then release the Trip/Reset switch PROCEDURE NOTE: If the Main Turbine is tripped, the RFP Turbine will not roll until Main Steam is admitted at approximately 60% GV position.
Step 2.17 Raise Turbine speed as Does not perform this step as MT follows: is tripped S/U
- a. If the Main Turbine is not tripped.
- b. If the Main Turbine is In MDVP, depresses increase tripped, then perform the pushbutton as necessary to raise S/U*
following: GV position to GT 60% and then
- Slowly raise RFW-P- to increase turbine speed to raise 1A(B) GV position GT 800 rpm using RFT-COMP-1 or RFT-COMP-2
- Monitor RFW-P-1A(B) speed on RFT-COMP-1 or RFW-COMP-2 as GV position increases GT 60% GV position LR000131 Rev. 6 Page 3 of 6
- Items are Critical Steps Comments Element Standard Sat/Unsat Step 2.18 Transfer RFW-P-1A(B) to With speed GT 800 rpm, MDEM using RFT-COMP- transfers RFW-P-1A to MDEM 1 or RFT-COMP-2 as soon by:
as practical (GT 800 rpm) a. depressing the MDEM (Pump Control Screen) as S/U*
pushbutton follows (H13-P840):
- b. depresses Yes pushbutton S/U*
- a. Select MDEM
- b. Select Yes Termination Criteria: Student informs CRS that A RFW pumps speed is GT 800 rpm and the speed controller has been transferred to MDEM RECORD TERMINATION TIME: _________
Transfer to Results of JPM page the following information: Procedures validated prior to use; Comments from marked up evaluators procedure copy; Unsatisfactory critical tasks; Total JPM time; Marked Up procedure and remaining JPM pages may be discarded.
LR000131 Rev. 6 Page 4 of 6
RESULTS OF JPM:
REACTOR FEED PUMP QUICK RESTART Examinee (Please Print): ______________________________________________
Evaluator (Please Print): ______________________________________________
Task Standard: RFP A is running with rpm is GT 800 and the controller is in MDEM Overall Evaluation Exam Code SAT / UNSAT (Circle One)
Verified Procedure #/Rev. Used for Validation/Critical JPM Completion JPM Time Time 15 Minutes / NA COMMENTS:
Evaluator's Signature: Date:
LR000131 Rev. 6 Page 5 of 6
STUDENT JPM INFORMATION CARD Initial Conditions:
A reactor scram was inserted as part of a controlled shutdown RPV level increased to GT 54.5 and both RFPs tripped Cue:
You have been directed by the CRS to perform a quick restart of the A RFW Pump using SOP-RFT-RESTART-QC Inform the CRS when the A RFW pumps speed is GT 800 rpm and RFW-P-1A has been transferred to MDEM LR000131 Rev. 6 Page 6 of 6