| title = Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
| title = Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
| author name = Heacock D A
| author name = Heacock D
| author affiliation = Virginia Electric & Power Co (VEPCO)
| author affiliation = Virginia Electric & Power Co (VEPCO)
| addressee name =  
| addressee name =  
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 10 CFR 2.202 EA-12-051 October 25, 2012 Attention:
{{#Wiki_filter:VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA   23261               10 CFR 2.202 EA-12-051 October 25, 2012 Attention: Document Control Desk                                   Serial No.:   12-166A U.S. Nuclear Regulatory Commission                                 NL&OS/MAE:   RO Washington, D.C. 20555-0001                                       Docket Nos.: 50-338/339 License Nos.: NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS I AND 2 INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051)
Document Control Desk Serial No.: 12-166A U.S. Nuclear Regulatory Commission NL&OS/MAE:
RO Washington, D.C. 20555-0001 Docket Nos.: 50-338/339 License Nos.: NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS I AND 2 INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051)


==References:==
==References:==
: 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12073A202)
: 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12073A202)
: 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)
: 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)
On March 12, 2012, the Nuclear Regulatory Commission
On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Virginia Electric and Power Company (Dominion). Reference 1 was immediately effective and directs Dominion to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.
("NRC" or "Commission")
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012.
issued an order (Reference
The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms Dominion has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the spent fuel storage pool as described in of Reference 1.
: 1) to Virginia Electric and Power Company (Dominion).
Major activities completed during this reporting period:
Reference 1 was immediately effective and directs Dominion to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance.
    " Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
The final interim staff guidance (Reference
* Requests for Information (RFI) were issued to spent fuel pool instrumentation (SFPI) suppliers.
: 2) was issued August 29, 2012.The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference
    " Responses to the RFIs have been reviewed and potential equipment has been identified.
: 2. This report confirms Dominion has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the spent fuel storage pool as described in Attachment 2 of Reference 1.Major activities completed during this reporting period: " Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.* Requests for Information (RFI) were issued to spent fuel pool instrumentation (SFPI)suppliers." Responses to the RFIs have been reviewed and potential equipment has been identified." Procurement specifications, requesting bids from SFPI suppliers that offer this equipment, are being prepared.Planned activities for the next six months: " Development and submittal of the overall integrated plan.* Issuance of site-specific procurement specifications.
    " Procurement specifications, requesting bids from SFPI suppliers that offer this equipment, are being prepared.
AON* Selection of equipment and a supplier(s).
Planned activities for the next six months:
I'l ..¢-
    " Development and submittal of the overall integrated plan.
Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 2 of 4" Preparation, review, and approval of conforming specifications.
* Issuance of site-specific procurement specifications.                                         AON
* Issuance of purchase orders for SFPI.* Initiation of the design change process.Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
* Selection of equipment and a supplier(s).
0 None at this time.Project milestones schedule through completion of installation and testing: " A project milestones schedule will be provided with the overall integrated plan.* Implementation of the order will be completed for North Anna Unit 1 prior to startup from Refueling Outage (RFO) 24 (Spring 2015).* Implementation of the order will be completed for North Anna Unit 2 prior to startup from Refueling Outage (RFO) 23 (Fall 2014).If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.Sincerely, David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Commitments made by this letter: No New Regulatory Commitments COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by David A. Heacock who is President and Chief Nuclear Officer of Virginia Electric and Power Company.He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.Acknowledged before me thisq?5 day of , 2012.My Commission Expire _- , pp~~ aaa ~Notary Publid 4 VICKI L. HULL (SEAL) Notary Public Commonwealth of Virginia 140542 My Commission Expires May 31. 2014 Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 3 of 4 cc:' Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission, Region I1 Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 Ms. Lisa M. Regner U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 011 F1 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Blake A. Purnell U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 012 D20 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Steven R. Jones U. S. Nuclear Regulatory Commission One White Flint North Mail Stop.O10 Al 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 4 of 4 Mr. J. E. Reasor, Jr, Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.Glen Allen, Virginia 23060}}
I'l             .     .¢-
 
Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 2 of 4
    " Preparation, review, and approval of conforming specifications.
* Issuance of purchase orders for SFPI.
* Initiation of the design change process.
Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
0 None at this time.
Project milestones schedule through completion of installation and testing:
    " A project milestones schedule will be provided with the overall integrated plan.
* Implementation of the order will be completed for North Anna Unit 1 prior to startup from Refueling Outage (RFO) 24 (Spring 2015).
* Implementation of the order will be completed for North Anna Unit 2 prior to startup from Refueling Outage (RFO) 23 (Fall 2014).
Ifyou have any questions, please contact Ms. Margaret Earle at (804) 273-2768.
Sincerely, David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Commitments made by this letter: No New Regulatory Commitments COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by David A. Heacock who is President and Chief Nuclear Officer of Virginia Electric and Power Company.
He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.
Acknowledged before me thisq?5 day of                 ,*'i2d__,, , 2012.
My Commission Expire             _-       ,
                                                      ~Notary                    Publid 4
pp~~ aaa VICKI L. HULL (SEAL)                   Notary Public Commonwealth of Virginia 140542 My Commission Expires May 31. 2014
 
Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 3 of 4 cc:' Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission, Region I1 Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 Ms. Lisa M. Regner U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 011 F1 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Blake A. Purnell U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 012 D20 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Steven R. Jones U. S. Nuclear Regulatory Commission One White Flint North Mail Stop.O10 Al 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station
 
Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 4 of 4 Mr. J. E. Reasor, Jr, Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.
Glen Allen, Virginia 23060}}

Latest revision as of 21:38, 11 November 2019

Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
ML12307A037
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 10/25/2012
From: Heacock D
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
12-166A, EA-12-051
Download: ML12307A037 (4)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 10 CFR 2.202 EA-12-051 October 25, 2012 Attention: Document Control Desk Serial No.: 12-166A U.S. Nuclear Regulatory Commission NL&OS/MAE: RO Washington, D.C. 20555-0001 Docket Nos.: 50-338/339 License Nos.: NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS I AND 2 INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051)

References:

1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12073A202)
2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)

On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Virginia Electric and Power Company (Dominion). Reference 1 was immediately effective and directs Dominion to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012.

The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms Dominion has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the spent fuel storage pool as described in of Reference 1.

Major activities completed during this reporting period:

" Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.

" Responses to the RFIs have been reviewed and potential equipment has been identified.

" Procurement specifications, requesting bids from SFPI suppliers that offer this equipment, are being prepared.

Planned activities for the next six months:

" Development and submittal of the overall integrated plan.

  • Issuance of site-specific procurement specifications. AON
  • Selection of equipment and a supplier(s).

I'l . .¢-

Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 2 of 4

" Preparation, review, and approval of conforming specifications.

  • Issuance of purchase orders for SFPI.
  • Initiation of the design change process.

Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:

0 None at this time.

Project milestones schedule through completion of installation and testing:

" A project milestones schedule will be provided with the overall integrated plan.

  • Implementation of the order will be completed for North Anna Unit 1 prior to startup from Refueling Outage (RFO) 24 (Spring 2015).
  • Implementation of the order will be completed for North Anna Unit 2 prior to startup from Refueling Outage (RFO) 23 (Fall 2014).

Ifyou have any questions, please contact Ms. Margaret Earle at (804) 273-2768.

Sincerely, David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Commitments made by this letter: No New Regulatory Commitments COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by David A. Heacock who is President and Chief Nuclear Officer of Virginia Electric and Power Company.

He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me thisq?5 day of ,*'i2d__,, , 2012.

My Commission Expire _- ,

~Notary Publid 4

pp~~ aaa VICKI L. HULL (SEAL) Notary Public Commonwealth of Virginia 140542 My Commission Expires May 31. 2014

Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 3 of 4 cc:' Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission, Region I1 Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 Ms. Lisa M. Regner U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 011 F1 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Blake A. Purnell U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 012 D20 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Steven R. Jones U. S. Nuclear Regulatory Commission One White Flint North Mail Stop.O10 Al 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station

Serial No. 12-166A 60-Day Response to Order EA-12-051 Docket Nos. 50-338/339 Page 4 of 4 Mr. J. E. Reasor, Jr, Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.

Glen Allen, Virginia 23060