=Text=
=Text=
{{#Wiki_filter:JAF-RPT-1 2-00015 Rev. 0 JAF SEISMIC WALKDOWN REPORT FOR RESOLUTION OF FUKUSHIMA NEAR-TERM TASK FORCE RECOMMENDATION 2.3 SEISMIC NOVEMBER 2012 BOOK 2 OF 3 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 283 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y-I N- UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class' 1- Motor Control Center Equipment Description Reactor building Motor Control Center Location:
{{#Wiki_filter:JAF-RPT-1 2-00015 Rev. 0 JAF SEISMIC WALKDOWN REPORT FOR RESOLUTION OF FUKUSHIMA NEAR-TERM TASK FORCE RECOMMENDATION 2.3 SEISMIC NOVEMBER 2012 BOOK 2 OF 3
Bldg. RB Floor El. 272' Room, Area Col 8, Line Y Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 283 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y-I N-   UN Seismic Walkdown Checklist (SWC)                     SWELl-456 Equipment ID No.         71BMCC-6                 Equip. Class' 1- Motor Control Center Equipment Description Reactor building Motor Control Center Location: Bldg. RB                   Floor El. 272'           Room, Area Col 8, Line Y Manufacturer, Model, Etc. (optional but recommended)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YO NE-]of the 50% of SWEL items requiring such verification)?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Anchorage
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?YE-] NE- UM N/AE--YE] NE:] UM N/A-Z YE-- NEJ UN N/A-1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 1. Is the anchorage configuration verification required (i.e., is the item one     YO NE-]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 284 of 573 ATTACHMENT 9.6 SEisMiC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YF-- NE] UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center 5. Is the anchorage configuration consistent with plant documentation?
of the 50% of SWEL items requiring such verification)?
YE] NEi U[ N/AE](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YE-] NE- UM N/AE--
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[- NEI U[potentially adverse seismic conditions?
: 3. Is the anchorage free of corrosion that is more than mild surface               YE] NE:] UM N/A-Z oxidation?
Interaction Effects 7. Are softtargets free from impact by nearby equipment or structures?
: 4. Is the anchorage free of visible cracks in the concrete near the               YE-- NEJ UN N/A-anchors?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NE: UE- N/A[E YO NEi UE N/AEF YE NEI UEi N/AE1 YE NEI U[:]
 
Attachment C EngiheiJrig Report No. JAF-RPT-12-00015 Rev. 0 Page 285 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YOI NE] U[Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor buildinQ Motor Control Center Other Adverse Conditions
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 284 of 573 ATTACHMENT 9.6                                                               SEisMiC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YF-- NE] UN Seismic Walkdown Checklist (SWC)               SWELl-456 Equipment ID No.       71BMCC-6               Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center
: 11. Have you looked for and found no other seismic conditions that could YZ NI- UI1 adversely affect the safety functions of the equipment?
: 5. Is the anchorage configuration consistent with plant documentation?         YE] NEi   U[   N/AE]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[- NEI U[
potentially adverse seismic conditions?
Interaction Effects
: 7. Are softtargets free from impact by nearby equipment or structures?         YE NE: UE- N/A[E
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YO NEi UE N/AEF and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YE NEI UEi N/AE1
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NEI U[:]
of potentially adverse seismic interaction effects?
 
Attachment C       EngiheiJrig Report No. JAF-RPT-12-00015 Rev. 0 Page 285 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YOI NE] U[
Seismic Walkdown Checklist (SWC)             SWELl-456 Equipment ID No. 71BMCC-6                 Equip. Class 1- Motor Control Center Equipment Description Reactor buildinQ Motor Control Center Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ NI- UI1 adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
L Evaluated by: A.G. Porch Date: 10/31/2012 C. Sawatzke 103/21 1013112012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 286 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0-- NEL U[Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center Photographs Note: 71BMCC-6 Front View Note: 71BMCC-6 Attached Lines Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 287 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YLI NO UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center EauiDment DescriDtion Reactor buildina Motor Control Center Note: 71BMCC-6 Side View Note: 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 288 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: Y[ NR U-Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class' 14 -Distribution Panels Equipment Description Relay Room Distribution Cabinet Location:
Evaluated by: A.G. Porch L                                                    Date: 10/31/2012 C. Sawatzke                                                             103/21 1013112012
Bldg. RR Floor El. 284.8 Room, Area Col. 10, Line F Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 286 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0-- NEL U[
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YN NEI of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)         SWELl-456 Equipment ID No. 71BMCC-6             Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center Photographs Note: 71BMCC-6 Front View                             Note: 71BMCC-6 Attached Lines
The anchorage configuration verification is required.2. Is the anchorage free of bent, broken, missing or loose hardware?
 
YE NZ U[I N/AE-The bottom right hand corner Unistrut Channel nut has failed. The resolution to this deficiency is to be tracked by CR-JAF-2012-07954
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 287 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5of 5 Status: YLI NO UN Seismic Walkdown Checklist (SWC)         SWELl-456 Equipment ID No. 71BMCC-6           Equip. Class 1- Motor Control Center EauiDment DescriDtion Reactorbuildina Motor Control Center Note: 71BMCC-6 Side View                             Note:
: 3. Is the anchorage free of corrosion that is more than mild surface YZ NEI UE- N/AE-oxidation?
0
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 288 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: Y[   NR U-Seismic Walkdown Checklist (SWC)                   SWELl-457 Equipment ID No.         71DC-A2                   Equip. Class' 14 - Distribution Panels Equipment Description Relay Room DistributionCabinet Location: Bldg. RR                   Floor El. 284.8         Room, Area Col. 10, Line F Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one     YN NEI of the 50% of SWEL items requiring such verification)?
The anchorageconfiguration verification is required.                                                       /
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YE NZ U[I N/AE-The bottom right hand corner Unistrut Channel nut has failed. The resolution to this deficiency is to be tracked by CR-JAF-2012-07954
: 3. Is the anchorage free of corrosion that is more than mild surface               YZ NEI   UE- N/AE-oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the YZ NEI UE- N/A[-]anchors?Anchorage is free of visible cracks in the concrete near the anchors./Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YZ NEI   UE- N/A[-]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 289 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NE] U-Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14 -Distribution Panels Equipment Description Relay Room Distribution Cabinet 5. Is the anchorage configuration consistent with plant documentation?
anchors?
YE] NEl uEr N/A[-1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage is free of visible cracks in the concrete near the anchors.
The anchorage configuration is consistent with the SEWS for 71DC-A2 (Rev. 0). The panel is anchored with four 3/8" bolts to a pair of unistrut channels, which are welded to a steel building column.6. Based on the above anchorage evaluations, is the anchorage free of YEl NE UI-I potentially adverse seismic conditions?
Enter the equipment class name from Appendix B: Classes of Equipment.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
 
The soft targets are free from impact by nearby equipments and structures.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 289 of 573 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NE] U-Seismic Walkdown Checklist (SWC)               SWELl-457 Equipment ID No.       71DC-A2                 Equip. Class 14 - Distribution Panels Equipment Description Relay Room DistributionCabinet
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 5. Is the anchorage configuration consistent with plant documentation?         YE] NEl uEr     N/A[-1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The overhead equipments and distribution systems are not likely to collapse onto the equipment.
The anchorageconfiguration is consistent with the SEWS for 71DC-A2 (Rev. 0). The panel is anchored with four 3/8" bolts to a pairof unistrut channels, which are welded to a steel building column.
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YEl NE UI-I potentially adverse seismic conditions?
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.YE NEI UE[ N/AE Y[ NE] UE- N/AEF Y] NEI UEi N/AEl YZ NEl UE1 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 290 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NE-l U-II Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14 -Distribution Panels Equipment Description Relay Room Distribution Cabinet Other Adverse Conditions
Interaction Effects
: 11. Have you looked for and found no other seismic conditions that could YM NE] U E-adversely affect the safety functions of the equipment?
: 7. Are soft targets free from impact by nearby equipment or structures?         YE NEI    UE[ N/AE The soft targets are free from impact by nearby equipments and structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NE] UE- N/AEF and masonry block walls not likely to collapse onto the equipment?
The overhead equipments and distributionsystems are not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y] NEI    UEi N/AEl The attachedlines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NEl UE1 of potentially adverse seismic interaction effects?
The equipment is free of potentiallyadverse seismic interactioneffects.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 290 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y]   NE-l U-II Seismic Walkdown Checklist (SWC)             SWELl-457 Equipment ID No.     71DC-A2               Equip. Class 14 - Distribution Panels Equipment Description Relay Room Distribution Cabinet Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YM NE]     UE-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Koberqa Z/;Date: 9/24/12 9/24/12.Pouria Pou-hobadi Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 291 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ ND- UD--Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14- Distribution Panels Equipment Description Relay Room Distribution Cabinet Photoaraghs efer to NUoe r-ufdiU UfIlNIsU1 lndfifIn IVUL, question 2.
Evaluated by: Donald Koberqa
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 292 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[-] NEl U[Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class' 3 Medium VoltaQe, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Location:
* Z/;                                 Date: 9/24/12 Pnllri* Pnmlrnhnh*di                                                      9/24/12.
Bldg. RB Floor El. 300 Room, Area Col 2 Line R Manufacturer, Model, Etc. (optional but recommended)
Pouria Pou-hobadi
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI NE of the 50% of SWEL items requiring such verification)?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 291 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ   ND- UD--
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is not visible for anchorage.
Seismic Walkdown Checklist (SWC)         SWELl-457 Equipment ID No. 71DC-A2             Equip. Class 14- DistributionPanels Equipment Description Relay Room DistributionCabinet Photoaraghs NUoe   r-ufdiU UfIlNIsU1 lndfifIn IVUL, efer to question 2.
: 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?YE NEI ULI N/AE1 YE: NE-- UN N/AF-E YE] NE: U[ N/AE' Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 292 of 573 ATTACHMENT       9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[-] NEl U[
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 293 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE] NE] UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Voltage, Metal clad Switch gear Equipment Description L 15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW 5. Is the anchorage configuration consistent with plant documentation?
Seismic Walkdown Checklist (SWC)                     SWELl- 462 Equipment ID No.         71DSC-11561               Equip. Class' 3 Medium VoltaQe, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Location: Bldg. RB                   Floor El. 300             Room, Area Col 2 Line R Manufacturer, Model, Etc. (optional but recommended)
YEI NE-] U[-E N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 6. Based on the above anchorage evaluations, is the anchorage free of YEr NEI UZ potentially adverse seismic conditions?
Anchorage
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NE of the 50% of SWEL items requiring such verification)?
No soft targets.8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YE NEI ULI N/AE1 The anchorage is not visible for anchorage.
8' lighting fixture would not likely to hit SWEL Item. If chain (1 of 2)break, SWEL is secured- no seismic concern.9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NEI U[E] N/AE-YN NE"] UE- N/AE-YE NEI' uE] N/AE Y[ NEI UE' Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 294 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YEl- Nil UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Volta-ge, Metal clad Switchgear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Other Adverse Conditions
: 3. Is the anchorage free of corrosion that is more than mild surface             YE:  NE-- UN N/AF-E oxidation?
: 11. Have you looked for and found no other seismic conditions that could YN N[] UI'I adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YE] NE: U[     N/AE anchors?
' Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 293 of 573 0 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE] NE] UN Seismic Walkdown Checklist (SWC)                   SWELl- 462 Equipment ID No.       71DSC-11561               Equip. Class 3 Medium Voltage, Metal clad Switchgear Equipment Description L 15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW
: 5. Is the anchorage configuration consistent with plant documentation?             YEI NE-] U[-E N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of               YEr   NEI UZ potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?           Y[    NEI U[E] N/AE-No soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,       YN NE"] UE- N/AE-and masonry block walls not likely to collapse onto the equipment?
8' lighting fixture would not likely to hit SWEL Item. If chain (1 of 2) break, SWEL is secured- no seismic concern.
: 9. Do attached lines have adequate flexibility to avoid damage?                   YE NEI'    uE] N/AE
: 10. Based on the above seismic interaction evaluations, is equipment free           Y[    NEI UE' of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 294 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YEl- Nil UN Seismic Walkdown Checklist (SWC)             SWELl- 462 Equipment ID No. 71DSC-11561             Equip. Class 3 Medium Volta-ge, Metal clad Switchgear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YN N[] UI'I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
LQ, ~Evaluated by: A. G, Porch Date: 11/01/2012 C. Sawatzke C.Saatk 1/0/21 1110112012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 295 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-I NEI UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Volta-ge, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Photoaraphs Note:Note:
Evaluated by: A. G, Porch LQ, ~                                              Date: 11/01/2012 C. Sawatzke   C.Saatk                                                   1/0/21 1110112012
71DSC-11561 Note: 71DSC-11561 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 296 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Yr-] NEI UH Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Voltage, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Note: 71DSC-11561 Note:
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 297 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YD NDI U[Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 711NV-3A Equip. Class, 16-Battery Chargers and Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Location:
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 295 of 573 ATTACHMENT 9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-I NEI       UN Seismic Walkdown Checklist (SWC)       SWELl- 462 Equipment ID No. 71DSC-11561       Equip. Class 3 Medium Volta-ge, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Photoaraphs Note:Note:                     71DSC-11561       Note: 71DSC-11561
Bldg. RB Floor El. 344.6' 'Room, Area RB 344.6, CoL5.5, Line P Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 296 of 573 ATTACHMENT   9.6                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Yr-] NEI UH Seismic Walkdown Checklist (SWC)       SWELl- 462 Equipment ID No. 71DSC-11561       Equip. Class 3 Medium Voltage, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Note: 71DSC-11561                                 Note:
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YZ NO of the 50% of SWEL items requiring such verification)?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 297 of 573 ATTACHMENT     9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YD NDI U[
Seismic Walkdown Checklist (SWC)                   SWELl-470 Equipment ID No.         711NV-3A                 Equip. Class, 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Location: Bldg. RB                 Floor El. 344.6'         'Room, Area RB 344.6, CoL5.5, Line P Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YZ NO of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YD NEI UN N/AD The expansion anchors and mounting bolts are free of bent, broken, missing or loose hardware.
YD NEI UN N/AD The expansion anchors and mounting bolts are free of bent, broken, missing or loose hardware.Panels need to be removed and anchorage of internal components needs to be checked.3. Is the anchorage free of corrosion that is more than mild surface YZ ND U[-D N/AD oxidation?
Panelsneed to be removed and anchorageof internalcomponents needs to be checked.
: 3. Is the anchorage free of corrosion that is more than mild surface             YZ ND U[-D     N/AD oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?There are hair line cracks in the grout on top of concrete foundation, and are deemed insignificant based on engineering judgment.YE. ND UD N/ADI'Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YE. ND UD N/ADI anchors?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 298 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YOI ND- UZ Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 71/NV-3A Equip. Class 16-Battery Chargers and Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter 5. Is the anchorage configuration consistent with plant documentation?
There are hairline cracks in the grout on top of concrete foundation, and are deemed insignificant based on engineeringjudgment.
YZ NOI U-I N/A[-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
'Enter the equipment class name from Appendix B: Classes of Equipment.
The 5/8", 3/4", and 1" Hilti Kwik Bolt 3 anchors and the 1/2" ASTM A449 mounting bolts are configured in accordance with the JAF-CALC 00042 calculation, Rev. 3 per EC-1 7239, DWG. No 1.26-2 and 1.26-102.6. Based on the above anchorage evaluations, is the anchorage free of YOI ND UN potentially adverse seismic conditions?
 
The external anchorage is free of potentially adverse seismic conditions.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 298 of 573 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YOI ND- UZ Seismic Walkdown Checklist (SWC)                 SWELl-470 Equipment ID No.     71/NV-3A                 Equip. Class 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter
Panels need to be removed and anchorage of internal components needs to be checked.Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 5. Is the anchorage configuration consistent with plant documentation?           YZ NOI   U-I N/A[-
Soft targets are free from impact from nearby equipment or structures.
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
The 5/8", 3/4", and 1" Hilti Kwik Bolt 3 anchors and the 1/2" ASTM A449 mounting bolts are configuredin accordance with the JAF-CALC         00042 calculation, Rev. 3 per EC-1 7239, DWG. No 1.26-2 and 1.26-102.
Light fixtures near the SWEL item need safety latches to prevent it from falling down during a seismic event. However the light fixtures will not damage the SWEL item.9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free ofpotentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YE ND UD N/AD YZ NO uD-I N/AD YE NDI UD N/ADl YE NEI U-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 299 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[-- NE] UZ Seismic Walkdown Checklist (SWC) SWELI-470 Equipment ID No. 71INV-3A Equip. Class 16-Battery Chargers and inverters Equipment Description LPCI MOV Indep Power SupplyA Inverter Other Adverse Conditions
: 6. Based on the above anchorage evaluations, is the anchorage free of           YOI ND UN potentially adverse seismic conditions?
: 11. Have you looked for and found no other seismic conditions that could YZ NEI UE-adversely affect the safety functions of the equipment?
The external anchorageis free of potentiallyadverse seismic conditions.
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
Panels need to be removed and anchorageof internal components needs to be checked.
No additional comments.Evaluated by: Harpreet Ghuman 1 .Yaroslav Losev Date: 09/30/2012 09/30/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 300 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YD-] Nn U]Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 71INV-3A Equip. Class 16-Battery Chargers and Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Photographs Note: Picture of equipment 71NV-3A.Note:
Interaction Effects
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 301 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[E NE! U[Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class' 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)Location:
: 7. Are soft targets free from impact by nearby equipment or structures?         YE ND UD N/AD Soft targets are free from impact from nearby equipment or structures.
Bldg. EG Floor El. 272 Room, Area Col 18.5 Line A1 Manufacturer, Model, Etc. (optional but recommended)
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NO uD-I N/AD and masonry block walls not likely to collapse onto the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Light fixtures near the SWEL item need safety latches to prevent it from falling down during a seismic event. However the light fixtures will not damage the SWEL item.
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[-) NO of the 50% of SWEL items requiring such verification)?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE NDI UD N/ADl The lines attached to the SWEL item have adequate flexibility to avoid damage.
Tha anchorage is not visible-Deferred.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NEI U-ofpotentially adverse seismic interaction effects?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Based on the above seismic interactionevaluations, the equipment is free of potentially adverse seismic interaction effects.
: 4. Is the'anchorage free of visible cracks in the concrete near the anchors?Y[:] N[-l] U N/AL]-Y[E] NEi UO N/A[:]Y[-! NE! UM N/A[-]I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 302 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NEI U[Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch-gear Distribution (Bus 12500)5. Is the anchorage configuration consistent with plant documentation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 299 of 573 0 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[-- NE] UZ Seismic Walkdown Checklist (SWC)             SWELI-470 Equipment ID No. 71INV-3A               Equip. Class 16-Battery Chargersand inverters Equipment Description LPCI MOV Indep Power SupplyA Inverter Other Adverse Conditions
YEI NEI UEi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 11. Have you looked for and found no other seismic conditions that could       YZ NEI   UE-adversely affect the safety functions of the equipment?
: 6. Based on the above anchorage evaluations, is the anchorage free of YE] NEl UZ potentially adverse seismic conditions?
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
No soft targets.8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based 6n the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NE UEi N/AEl YE NEl UEi N/AEl YE NEl U[E N/AE-YE NEI UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 303 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YWI NM. UN Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)Other Adverse Conditions
: 11. Have you looked for and found no other seismic'conditions that could YZ N[l U[-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: A Porch Date: 11/01/2012 C. Sawatzke 11/1/01 1110112012 Attachment C Engineerng Report No. JAF-RPT-12-00015 Rev. 0 Page 304 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YrI N[- UZ Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch -ear Distribution (Bus 12500)Photographs Note: 71L25 Note: 71L25 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 305 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[ NR- UL]Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class' 2 -Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switch-gear Distributioh BUS 12600 Location:
No additionalcomments.
Bldg. EB Floor El. 272 Room, Area C: 18.5, L: B Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: Harpreet Ghuman 1                      .                          Date: 09/30/2012 Yaroslav Losev                                                            09/30/2012
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the-SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist fordocumenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 300 of 573 ATTACHMENT  9.6                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YD-] Nn U]
Y[ NEI 2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Seismic Walkdown Checklist (SWC)      SWELl-470 Equipment ID No. 71INV-3A          Equip. Class 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Photographs Note: Picture of equipment 71NV-3A.                Note:
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 301 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[E  NE! U[
Seismic Walkdown Checklist (SWC)                    SWELl- 474 Equipment ID No.          71L25                    Equip. Class' 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)
Location: Bldg. EG                  Floor El. 272            Room, Area Col 18.5 Line A1 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    Y[-) NO of the 50% of SWEL items requiring such verification)?
Tha anchorageis not visible-Deferred.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              Y[:] N[-l] U  N/AL]-
: 3. Is the anchorage free of corrosion that is more than mild surface              Y[E] NEi UO N/A[:]
oxidation?
: 4. Is the'anchorage free of visible cracks in the concrete near the              Y[-! NE! UM N/A[-]
anchors?
I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 302 of 573 ATTACHMENT    9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NEI    U[
Seismic Walkdown Checklist (SWC)                SWELl- 474 Equipment ID No.      71L25                  Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch-gear Distribution (Bus 12500)
: 5. Is the anchorage configuration consistent with plant documentation?          YEI NEI UEi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of          YE] NEl UZ potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YE NE UEi N/AEl No soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,    YE NEl UEi N/AEl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                YE NEl U[E N/AE-
: 10. Based 6n the above seismic interaction evaluations, is equipment free        YE NEI UE-of potentially adverse seismic interaction effects?
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 303 of 573 ATTACHMENT 9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YWI  NM. UN Seismic Walkdown Checklist (SWC)              SWELl- 474 Equipment ID No. 71L25                    Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic'conditions that could    YZ N[l U[-
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Evaluated by: A Porch                                                           Date: 11/01/2012 C. Sawatzke                                                             11/1/01 1110112012
 
Attachment C       Engineerng Report No. JAF-RPT-12-00015 Rev. 0 Page 304 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YrI N[-     UZ Seismic Walkdown Checklist (SWC)         SWELl- 474 Equipment ID No. 71L25               Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch-ear Distribution (Bus 12500)
Photographs Note: 71L25                                         Note: 71L25 0
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 305 of 573 ATTACHMENT       9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[   NR- UL]
Seismic Walkdown Checklist (SWC)                     SWELl-475 Equipment ID No.         71L26                   Equip. Class' 2 - Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switch-gear DistributiohBUS 12600 Location: Bldg. EB                   Floor El. 272             Room, Area C: 18.5, L: B Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the-SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist fordocumenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[    NEI of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YN N--    U-I N/A--
Anchorage is free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface             YO NEI Ur-      N/AE-oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Anchorage is free of visible cracks in the concrete near the anchors.YN N-- U-I N/A--YO NEI Ur- N/AE-YE N[I u]Li N/A[-]1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YE N[I    u]Li N/A[-]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 306 of 573 O ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI U--Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2 -Low Voltage Switchgears and Breaker Panels Equipment Description 600V Switchpear Distribution BUS 12600 5. Is the anchorage configuration consistent with plant documentation?
anchors?
YE NIl UEI N/All (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage is free of visible cracks in the concrete near the anchors.
The anchorage configuration is consistent with the SEWS for 71L26 (Rev. 0). The plug welds were confirmed.
1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ NE-] UE]potentially adverse seismic conditions?
 
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 306 of 573 O ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI U--
Seismic Walkdown Checklist (SWC)               SWELl-475 Equipment ID No.     71L26                   Equip. Class 2 - Low Voltage Switchgearsand Breaker Panels Equipment Description 600V Switchpear DistributionBUS 12600
: 5. Is the anchorage configuration consistent with plant documentation?         YE NIl UEI     N/All (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageconfigurationis consistent with the SEWS for 71L26 (Rev. 0). The plug welds were confirmed.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ NE-] UE]
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YN NEI    UE] N/A[-]
The soft targets are free from impact by nearby equipment and structure.
The soft targets are free from impact by nearby equipment and structure.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NE:] UE] N/AE1 and masonry block walls not likely to collapse onto the equipment?
Masonary block wall divides the East and West Electric bay.'Modifications were made to enhance the walls as part of IE Bulliten 80-11. (Ref. Calculation No. C012, "HCLPF for block walls EB-272-1,2")
Masonary block wall divides the East and West Electric bay.'
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
Modifications were made to enhance the walls as part of IE Bulliten 80-
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of adverse seismic interaction effect.YN NEI UE] N/A[-]Y[ NE:] UE] N/AE1 YM NEI U[] N/AE1 YE NEI U-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 307 of 573 ATTACHMENT 9.6 Sheet 3 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: Y[ NEI U--Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2- Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switchqear Distribution BUS 12600 Other Adverse Conditions
: 11. (Ref. CalculationNo. C012, "HCLPFfor block walls EB-272-1,2")
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI UE-adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YM NEI U[] N/AE1 The attached lines have adequateflexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NEI U-of potentially adverse seismic interaction effects?
The equipment is free of adverse seismic interactioneffect.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 307 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   NEI U--
Seismic Walkdown Checklist (SWC)             SWELl-475 Equipment ID No. 71L26                   Equip. Class 2- Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switchqear DistributionBUS 12600 Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEI UE-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Kobercq Date: 9/25/12 Pouria Pourqhobadi 9/25/12 9125112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 308 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ Nr"] U--Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2 -Low Voltafge Switch-gears and Breaker Panels Equipment Description 600V Switch-gear Distribution BUS 12600 Photographs Note: 71L26 Note: Bottom Comer Panel Open Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 309 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nr] U-Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2- Low Voltage Switch gears and Breaker Panels Eauipment Description 600V Switchqear Distribution BUS 12600 Note: Cabinet Base Plug Weld Note: 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 310 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YE NEI UE Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class' 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)Location:
Evaluated by: Donald Kobercq                                                   Date: 9/25/12 Pouria Pourqhobadi                                                       9/25/12 9125112
Bldg. RB Floor El. 272 Room, Area Co/ 1.5 Line W Manufacturer,;
 
Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 308 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ Nr"]     U--
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the'results of judgments and findings.
Seismic Walkdown Checklist (SWC)         SWELl-475 Equipment ID No. 71L26               Equip. Class 2 - Low Voltafge Switch-gears and Breaker Panels Equipment Description 600V Switch-gear DistributionBUS 12600 Photographs Note: 71L26                                         Note: Bottom Comer Panel Open
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE NZ of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Not Readily accessible.
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 309 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nr] U-Seismic Walkdown Checklist (SWC)         SWELl-475 Equipment ID No. 71L26             Equip. Class 2- Low Voltage Switch gears and Breaker Panels Eauipment Description 600V Switchqear DistributionBUS 12600 Note: Cabinet Base Plug Weld                       Note:
: 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
0
/4. Is the anchorage free of visible cracks in the concrete near the anchors?YFI NEI UZ N/AE-YE-- NE-, U[ N/AE-]YE1 NE: UZ N/AE-1 1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 311 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)5. Is the anchorage configuration consistent with plant documentation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 310 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YE NEI UE Seismic Walkdown Checklist (SWC)                   SWELl- 481 Equipment ID No.       71MCC-161                 Equip. Class' 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)
Y[E- NE- UE- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Location: Bldg. RB                 Floor El. 272             Room, Area Co/ 1.5 Line W Manufacturer,; Model, Etc. (optional but recommended)
: 6. Based on the above anchorage evaluations, is the anchorage free of YEl NEI UO potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the'results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
No soft targets.YE NE: UE- N/A[E 8. Are overhead equipment, distribution systems, ceiling tiles-and lighting, and masonry block walls not likely to collapse onto the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE NZ of the 50% of SWEL items requiring such verification)?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NEI U[-E N/AE-]YE NEJ UE: N/AEl Y[ NEI UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 312 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YIEI NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)Other Adverse Conditions
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YFI NEI  UZ N/AE-Not Readily accessible.
: 11. Have you looked for and found no other seismic conditions that could YZ NEI UMII adversely affect the safety functions of the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface             YE-- NE-, U[    N/AE-]
oxidation?
                                    /
: 4. Is the anchorage free of visible cracks in the concrete near the               YE1 NE: UZ N/AE-1 anchors?
1Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 311 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NEI   UN Seismic Walkdown Checklist (SWC)               SWELl- 481 Equipment ID No.       71MCC-161               Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)
: 5. Is the anchorage configuration consistent with plant documentation?         Y[E- NE- UE- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YEl NEI UO potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YE NE: UE- N/A[E No soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles-and lighting,   YE NEI    U[-E N/AE-]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YE NEJ UE: N/AEl
: 10. Based on the above seismic interaction evaluations, is equipment free       Y[    NEI UM of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 312 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YIEI NE] UZ Seismic Walkdown Checklist (SWC)             SWELl- 481 Equipment ID No. 71MCC-161               Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ NEI   UMII adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Area above 71MCC-161 is highly congested; cable trays, piping and conduits appear well supported.
Area above 71MCC-161 is highly congested; cable trays, piping and conduits appearwell supported.
Supports, hardware etc are intact.Evaluated by: A. Porch C. Sawatzke Date: 10/31/2012 10/31/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 313 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE]-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)Photographs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 314 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI- NEI UE Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Eauibment DescriDtion 600V Motor Control Center (Bus 116100)Note: 71MCC-161 Note:
Supports, hardware etc are intact.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 315 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YEI NE] UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class' I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)Location:
Evaluated by:       A. Porch                                                   Date: 10/31/2012 C. Sawatzke (,*.                                                        10/31/2012
Bldg. EB Floor El. 272 Room, Area Col. 18 Line A Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 313 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE]-- NE] UZ Seismic Walkdown Checklist (SWC)         SWELl- 481 Equipment ID No. 71MCC-161         Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Photographs
Y[-I NZ 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Y[-- NE] U[ N/AE]YO- NE] UE N/Ar-YO- NE] UL N/AE]' Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 314 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI- NEI UE Seismic Walkdown Checklist (SWC)         SWELl- 481 Equipment ID No. 71MCC-161           Equip. Class 1 Motor Control Center Eauibment DescriDtion 600V Motor Control Center (Bus 116100)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 316 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YDI NF- UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)5. Is the anchorage configuration consistent with plant documentation?
Note: 71MCC-161                                     Note:
YLI NR UI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
 
: 6. Based on the above anchorage evaluations, is the anchorage free of YEI NEI--U[potentially adverse seismic conditions?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 315 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YEI NE] UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252                         Equip. Class' I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Location: Bldg. EB                   Floor El. 272             Room, Area Col. 18 Line A Manufacturer, Model, Etc. (optional but recommended)
No soft targets.YEI NEI- UL- N/A[8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
9, Do attached lines have adequate flexibility to avoiddamage?
Anchorage
10, Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NEI ui- N/A[--YN NDI UD- N/ADl Y] N[:D U-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 317 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE] NEI UE Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)Other Adverse Conditions
: 1. Is the anchorage configuration verification required (i.e., is the item one     Y[-I NZ of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could YO NEI UEI adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               Y[-- NE] U[  N/AE]
: 3. Is the anchorage free of corrosion that is more than mild surface               YO- NE] UE N/Ar-oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the               YO- NE] UL N/AE]
anchors?
' Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 316 of 573 ATTACHMENT   9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YDI   NF-   UN Seismic Walkdown Checklist (SWC)               SWELl- 487 Equipment ID No.       71MCC-252               Equip. Class I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)
: 5. Is the anchorage configuration consistent with plant documentation?         YLI NR     UI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         YEI   NEI--U[
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YEI NEI- UL-   N/A[
No soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NEI ui-  N/A[--
and masonry block walls not likely to collapse onto the equipment?
9, Do attached lines have adequate flexibility to avoiddamage?                 YN NDI      UD- N/ADl 10, Based on the above seismic interaction evaluations, is equipment free       Y] N[:D  U-of potentially adverse seismic interaction effects?
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 317 of 573 ATTACHMENT 9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE] NEI    UE Seismic Walkdown Checklist (SWC)              SWELl- 487 Equipment ID No. 71MCC-252                Equip. Class  I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could    YO NEI      UEI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Evaluated by: A.Porch /                                                        Date: 11/1/2012.
C. Sawatzke ;____________                                                11/1/2012
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 318 of 573 ATTACHMENT 9.6                                                      SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252            Equip. Class 1 Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)
Photographs 0
Note: 71MCC-252                                      Note: 71MCC-252
 
Attachment C              Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 319 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[  NEI  UZ Seismic Walkdown Checklist (SWC)              SWEL 1- 489 Equipment ID No.      71MCC-254              Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)
Location: Bldg. EG              Floor El. 272          Room, Area      Col 23 line A1 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    YI-] NZ of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              Y[I NEI   UZ N/AD-
: 3. Is the anchorage free of corrosion that is more than mild surface              YDI NDI  U[  N/ADl oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the              YZ NDl UiD N/ADl anchors?
No cracks noted.
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 320 of 573 0 ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE] U[
Seismic Walkdown Checklist (SWC)                SWEL 1- 489 Equipment ID No.      71MCC-254              Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)
: 5. Is the anchorage configuration consistent with plant documentation?          Y[-] Nr--] ULJ N/An (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of          YEI NEI    UZ potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YN NEI U[I- N/A[-]
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,    YE NEl UJI N/A[-]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                Y[    ND-] UI- N/AD-
: 10. Based on the above seismic interaction evaluations, is equipment free        YE NEI Ur of potentially adverse seismic interaction effects?
 
Attachment C       Enigineerind Report No. JAF-RPT-1 2-00015 Rev. 0 Page 321 of 573 0 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YD- NEI- UZ Seismic Walkdown Checklist (SWC)               SWEL 1- 489 Equipment ID No. 71MCC-254                Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus '125400)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       YN N[:]U[_
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: A.Porch /C. Sawatzke ;____________
Evaluated by: R Casella     '1"- ( z*                                          Date: 10-31-12 A Porch     APorch                                                        10-31-12 10-31-12
Date: 11/1/2012.
 
11/1/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 318 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class 1 Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)Photographs 0 Note: 71MCC-252 Note: 71MCC-252 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 319 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[ NEI UZ Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)Location:
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 322 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI   NEI UN Seismic Walkdown Checklist (SWC)         SWEL 1- 489 Equipment ID No. 71MCC-254           Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center(Bus 125400)
Bldg. EG Floor El. 272 Room, Area Col 23 line A1 Manufacturer, Model, Etc. (optional but recommended)
Photographs Note: Conduit, duct, and cable tray above 71MCC-254 0
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YI-] NZ of the 50% of SWEL items requiring such verification)?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 323 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI NE   UE Seismic Walkdown Checklist (SWC)         SWEL 1- 489 Equipment ID No. 71MCC-254           Equip. Class Motor Control Centers and Wall-mounted Contactors Eauioment Descriotion 600V Motor Control Center (Bus 125400)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Note: Fillet welds at base of 71MCC-254             Note:
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?No cracks noted.Y[I NEI UZ N/AD-YDI NDI U[ N/ADl YZ NDl UiD N/ADl Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 320 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE] U[Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)5. Is the anchorage configuration consistent with plant documentation?
 
Y[-] Nr--] ULJ N/An (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C           Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 324 of 573 ATTACHMENT 9.6                                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NnL     Uni" Seismic Walkdown Checklist (SWC)                     SWELl-491 Equipment ID No.         71MCC-262                 Equip. Class' 1   - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)
: 6. Based on the above anchorage evaluations, is the anchorage free of YEI NEI UZ potentially adverse seismic conditions?
Location: Bldg. EB                   Floor El. 272             Room, Area Col. 18, Line B Manufacturer,-Model, Etc. (optional but recommended)
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Anchorage
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YN NEI U[I- N/A[-]YE NEl UJI N/A[-]Y[ ND-] UI- N/AD-YE NEI Ur Attachment C Enigineerind Report No. JAF-RPT-1 2-00015 Rev. 0 Page 321 of 573 0 ATTACHMENT 9.6 Sheet 3 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: YD- NEI- UZ Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus '125400)Other Adverse Conditions
: 1. Is the anchorage configuration verification required (i.e., is the item one       Y[    N[-]
: 11. Have you looked for and found no other seismic conditions that could adversely affect the safety functions of the equipment?
of the 50% of SWEL items requiring such verification)?
YN N[:]U[_Comments (Additional pages may be added as necessary)
The anchorageconfiguration verification is required.
Evaluated by: R Casella ' 1" -( Date: 10-31-12 A Porch 10-31-12 A Porch 10-31-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 322 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)Photographs Note: Conduit, duct, and cable tray above 71MCC-254 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 323 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI NE UE Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Eauioment Descriotion 600V Motor Control Center (Bus 125400)Note: Fillet welds at base of 71MCC-254 Note:
: 2. Is the anchorage free of bent, broken, missing or loose hardware?                 YNI   N[D U[-- N/A[D]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 324 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NnL Uni" Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class' 1 -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)Location:
Anchorage is free of bent, broken, missing or loos hardware.
Bldg. EB Floor El. 272 Room, Area Col. 18, Line B Manufacturer,-Model, Etc. (optional but recommended)
: 3. Is the anchorage free of corrosion that is more than mild surface                 YM ND-] ULI N/AD--
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
oxidation?
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Anchorage is free of corrosionthat is more than mild surface oxidation.
The anchorage configuration verification is required.2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage is free of bent, broken, missing or loos hardware.Y[ N[-]YNI N[D U[-- N/A[D]3. Is the anchorage free of corrosion that is more than mild surface oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the                   YE ND U[D] N/AD anchors?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of visible cracks in the concrete near the anchors.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Anchorage is free of visible cracks in the concrete near the anchors.YM ND-] ULI N/AD--YE ND U[D] N/AD' Enter the equipment class nirre from Appendix B: Classes of Equipment.
' Enter the equipment class nirre from Appendix B: Classes of Equipment.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 325 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ ND:] Ur-]Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class I -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)5. Is the anchorage configuration consistent with plant documentation?
 
Y[ NDI UE- N/AD1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 325 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   ND:] Ur-]
The anchorage configuration is consistent with SEWS for 71MCC-262.
Seismic Walkdown Checklist (SWC)                 SWELl-491 Equipment ID No.       71MCC-262               Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)
The 1/8" fillets 2" Long 20" center were field verified in accordance with DWG. No. 1.43-88.6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI UD-potentially adverse seismic conditions?.
: 5. Is the anchorage configuration consistent with plant documentation?         Y[   NDI UE- N/AD1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchorageconfiguration is consistentwith SEWS for 71MCC-262.
The 1/8" fillets 2" Long 20" center were field verified in accordancewith DWG. No. 1.43-88.
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[   NEI UD-potentially adverse seismic conditions?.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YN NDI    UD- N/A[D]
The soft targets are free from imact by nearby equipment and structures
The soft targets are free from imact by nearby equipment and structures
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ ND-- UD- N/AD-and masonry block walls not likely to collapse onto the equipment?
Masonary block wall divides the East and West Electric bay.Modifications were made to enhance the walls as part of IE Bulliten 80-11. (Ref. Calculation No. C012, "HCLPF for block walls EB-272-1,2")
Masonary block wall divides the East and West Electric bay.
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
Modifications were made to enhance the walls as part of IE Bulliten 80-
YN NDI UD- N/A[D]YZ ND-- UD- N/AD-YZ ND'- UD-- N/AD-10. Based on the above seismic interaction evaluations, is equipment free YIE NDI UD-I of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.
: 11. (Ref. CalculationNo. C012, "HCLPFfor block walls EB-272-1,2")
Attachm eht C Engihieei'hg Report No. JAF-RPT-12-00015 Rev. 0 Page 326 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ U-'Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class .1 -Motor Control Centers and Wall Mounted 7 Contractors Equipment Description 600V Motor Control Center (BUS 12600)Other Adverse Conditions
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ ND'-   UD-- N/AD-The attachedlines have adequate flexibility.
: 11. Have you looked for and found no other seismic conditions that could YE N[-I UrII adversely affect the safety functions of the equipment?
: 10. Based on the above seismic interaction evaluations, is equipment free       YIE NDI   UD-I of potentially adverse seismic interaction effects?
The equipment is free of potentially adverse seismic interactioneffects.
 
Attachm eht C       Engihieei'hg Report No. JAF-RPT-12-00015 Rev. 0 Page 326 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   NM* U-'
Seismic Walkdown Checklist (SWC)               SWELl-491 Equipment ID No. 71MCC-262               Equip. Class .1 - Motor Control Centers and Wall Mounted 7 Contractors Equipment Description 600V Motor Control Center (BUS 12600)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       YE N[-I UrII adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald
Evaluated by: Donald Kobergq*7d.            _       _       _     _         Date: 9/25/12 PouriaPourqhobadi                                                        9/25/12 9125112
_ _ _ _ Date: 9/25/12 Pouria Pourqhobadi 9/25/12 9125112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 327 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI U[-I Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class 1 -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)Photographs Note: 71MCC-262 Note: Base Welds Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 328 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YEI NE UN Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class' 1 -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)Location:
 
Bldg. EB Floor El. 272 Room, Area Col. 25.5, Line Al Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 327 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI     U[-I Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262             Equip. Class 1 - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Photographs Note: 71MCC-262                                     Note: Base Welds
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE NEI of the 50% of SWEL items requiring such verification)?
 
The anchorage configuration verification is required.2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 328 of 573 0 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YEI NE UN Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264                       Equip. Class' 1 - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?YEI NE UE N/AE[-YEr NE1 UN N/AE YEr NEI UN N/AEr-I Enter the equipment class name from Appendix B: Classes of Equipment.
Location: Bldg. EB                 Floor El. 272             Room, Area Col. 25.5, Line Al Manufacturer, Model, Etc. (optional but recommended)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 329 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE- N[] U]Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
YE NEI UZ N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
: 6. Based on the above anchorage evaluations, is the anchorage free of YE NEI UZ potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one     YE NEI of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchorageconfiguration verification is required.
The soft targets are free from imact by nearby equipment and structures YM NEI U[l N/AI-8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UE N/AE-and masonry block walls not likely to collapse onto the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YEI  NE UE N/AE[-
masonary block walls have been evaluated and enhanced according to DC# DI-96-011, Rev 0 as part IPEEE evaluations.
: 3. Is the anchorage free of corrosion that is more than mild surface               YEr  NE1 UN N/AE oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
: 4. Is the anchorage free of visible cracks in the concrete near the               YEr   NEI UN N/AEr-anchors?
YZ' NE UE N/AE 10. Based on the above seismic interaction evaluations, is equipment free YE NE UE-of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.
IEnter the equipment class name from Appendix B: Classes of Equipment.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 330 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y-- NEl] UZ Seismic Walkdown Checklist (SWC) S SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)Other Adverse Conditions
 
: 11. Have you looked for and found no other seismic conditions that could Y] N[-] U--adversely affect the safety functions of the equipment?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 329 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE- N[] U]
Seismic Walkdown Checklist (SWC)               SWELl-493 Equipment ID No.       71MCC-264             Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)
: 5. Is the anchorage configuration consistent with plant documentation?         YE NEI   UZ N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         YE NEI UZ potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YM NEI U[l N/AI-The soft targets are free from imact by nearby equipment and structures
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NEI   UE N/AE-and masonry block walls not likely to collapse onto the equipment?
masonary block walls have been evaluated and enhancedaccordingto DC# DI-96-011, Rev 0 as partIPEEE evaluations.
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ' NE UE N/AE The attachedlines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NE UE-of potentially adverse seismic interaction effects?
The equipment is free of potentially adverse seismic interactioneffects.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 330 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y-- NEl]   UZ Seismic Walkdown Checklist (SWC)             S SWELl-493 Equipment ID No. 71MCC-264               Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)
Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y] N[-] U--
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)-
Comments (Additional pages may be added as necessary)-
Evaluated by: Harptreet Ghuman Date: 9/25/12 Yaroslav Losev 9/25/12 9125112 ' '
Evaluated by: HarptreetGhuman                                                  Date: 9/25/12 Yaroslav Losev                                                           9/25/12 9125112   ' '
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 331 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI- NEI U]Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I -Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)Photographs Note: 71MCC-264 Note:
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 332 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[Z N7-" U7i Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2  
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 331 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI- NEI U]
'Equip. Class' 4- Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Location:
Seismic Walkdown Checklist (SWC)         SWELl-493 Equipment ID No. 71MCC-264           Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)
Bldg. CS Floor El. 272 Room, Area Col. 11. Line C Manufacturer, Model, Etc. (optional but recommended)
Photographs Note: 71MCC-264                                     Note:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[ NEi of the 50% of SWEL items requiring such verification)?  
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 332 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[Z N7-"   U7i Seismic Walkdown Checklist (SWC)                     SWELl-494 Equipment ID No.         71PT-71ACA2             'Equip. Class' 4- Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Location: Bldg. CS                   Floor El. 272             Room, Area Col. 11. Line C Manufacturer, Model, Etc. (optional but recommended)
-2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage is free of corrosion that is more than mild surface oxidation 4. Is the anchorage free of visible cracks in the concrete near the anchors?Anchorage is free of visible cracks in the concrete near the anchors.YN NEI u[-] N/AD--YN NE! U[] N/A[: YN NEI U'- N/Ar-1 Enter the equipment class name from Appendix B: Classes of Equipment.
Anchorage
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 333 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N-- U-Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 -Transformers Equipment Description Emerqency Distribution 15kVA Transformer 71MCC-253-OD3
: 1. Is the anchorage configuration verification required (i.e., is the item one     Y[   NEi of the 50% of SWEL items requiring such verification)?         -
: 5. Is the anchorage configuration consistent with plant documentation?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YN NEI    u[-] N/AD--
Y[D NI-] U[-I N/A[-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage is free of bent, broken, missing or loose hardware.
The anchorage configuration is consistent with SEWS for 71PT-71ACA2 (Rev. 0). The transformer is wall mounted with four Y2" shells.6. Based on the above anchorage evaluations, is the anchorage free of YO NEil U-I potentially adverse seismic conditions?
: 3. Is the anchorage free of corrosion that is more than mild surface               YN NE! U[] N/A[:
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation
: 4. Is the anchorage free of visible cracks in the concrete near the               YN NEI U'-      N/Ar-anchors?
Anchorage is free of visible cracks in the concrete near the anchors.
1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 333 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N--   U-Seismic Walkdown Checklist (SWC)               SWELl-494 Equipment ID No.       71PT-71ACA2             Equip. Class 4 - Transformers Equipment Description Emerqency Distribution 15kVA Transformer 71MCC-253-OD3
: 5. Is the anchorage configuration consistent with plant documentation?         Y[D NI-] U[-I N/A[-
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageconfigurationis consistent with SEWS for 71PT-71ACA2 (Rev. 0). The transformeris wall mounted with four Y2" shells.
: 6. Based on the above anchorage evaluations, is the anchorage free of         YO NEil U-I potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[D NEIl U[] N/AL]
The soft targets are free from impact by nearby equipments and structures.
The soft targets are free from impact by nearby equipments and structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    N[l U-  N/AL]
The overhead equipment and distribution systems are not likely to collapse onto the equipment.
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
The overhead equipment and distributionsystems are not likely to collapse onto the equipment.
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.Y[D NEIl U[] N/AL]Y[ N[l U- N/AL]YZ NEI] Ui N/AZl YZ NEI- UE]
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ NEI] Ui N/AZl The attachedlines have adequate flexibility.
Atta himedt C Engineeriihg Report No. JAF-RPT-12-00015 Rev. 0 Page 334 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEI UE-]Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 -Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Other Adverse Conditions
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NEI- UE]
: 11. Have you looked for and found no other seismic conditions that could YZ NLJ ULI adversely affect the safety functions of the equipment?
of potentially adverse seismic interaction effects?
The equipment is free of potentially adverse seismic interactioneffects.
 
Atta himedt C       Engineeriihg Report No. JAF-RPT-12-00015 Rev. 0 Page 334 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   NEI UE-]
Seismic Walkdown Checklist (SWC)             SWELl-494 Equipment ID No. 71PT-71ACA2             Equip. Class 4 - Transformers Equipment Description Emergency Distribution15kVA Transformer 71MCC-253-OD3 Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ   NLJ ULI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Kober Date: 9/25/12 Pouria Pourqhobadi/9/25/12 9125112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 335 of 573 S 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI-- U--Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 -Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Photographs Note: 71PT-71ACA2Transformer Note: 71PT-71ACA2Transformer Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page,336 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[ N[] UL'Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emerqencv Distribution 7.5 Kva Transformer Location:
Evaluated by: Donald Kober                                                     Date: 9/25/12 PouriaPourqhobadi/9/25/12                                               9125112
Bldg. EG Floor El. 272' Room, Area CoL 24 Line A Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 335 of 573 S ATTACHMENT   9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI-- U--
Additional space is provided at the end of this checklist for documenting other comments.-Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[-] NZ of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)         SWELl-494 Equipment ID No. 71PT-71ACA2         Equip. Class 4 - Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Photographs 0
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage has all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Note: 71PT-71ACA2Transformer                         Note: 71PT-71ACA2Transformer
There are no signs of any corrosion on the anchorage 4. Is the 'anchorage free of visible cracks in the concrete near the anchors?There are no cracks in the concrete near the anchorage Y[ NR] UE] N/AE]YN NEI UE] N/AE]YN NE] U[] N/AE]
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 337 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE No' U--Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emeraencv Distribution 7.5 Kva Transformer
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page,336 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[   N[] UL' Seismic Walkdown Checklist (SWC)               SWELl- 495 Equipment ID No.     71PT-71ACA4             Equip. Class 4-Transformers Equipment Description Emerqencv Distribution7.5 Kva Transformer Location: Bldg.     EG         Floor El.       272'     Room, Area         CoL 24 Line A Manufacturer, Model, Etc. (optional but recommended)
: 5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
YE- NEý UE- N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- Anchorage
: 6. Based on the above anchorage evaluations, is the anchorage free of YN NEI Ur-E potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[-] NZ of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[    NR] UE] N/AE]
Only soft target is anchored cable YE NE- UEI N/AE-]8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
The anchoragehas all necessary hardware
: 3. Is the anchorage free of corrosion that is more than mild surface               YN NEI UE] N/AE]
oxidation?
There are no signs of any corrosion on the anchorage
: 4. Is the 'anchorage free of visible cracks in the concrete near the               YN NE] U[] N/AE]
anchors?
There are no cracks in the concrete near the anchorage
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 337 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE No' U--
Seismic Walkdown Checklist (SWC)               SWELl- 495 Equipment ID No.     71PT-71ACA4             Equip. Class 4-Transformers Equipment Description Emeraencv Distribution7.5 Kva Transformer
: 5. Is the anchorage configuration consistent with plant documentation?         YE- NEý UE- N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YN NEI   Ur-E potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YE NE- UEI N/AE-]
Only soft target is anchored cable
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NEI UE] N/AE-and masonry block walls not likely to collapse onto the equipment?
All conduit located overhead is all well supported.
All conduit located overhead is all well supported.
: 9. Do attached lines have adequate flexibility to avoid damage?Only has attached conduit and armored cable. Both have adequate flexibility
: 9. Do attached lines have adequate flexibility to avoid damage?                 YN N[E] uEr    N/AEj Only has attached conduit and armored cable. Both have adequate flexibility
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YN NEI UE] N/AE-YN N[E] uEr N/AEj YE NE:] U-Attachment C.Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 338 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NM UM Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emergency Distribution 7.5 Kva Transformer Other Adverse Conditions
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NE:] U-of potentially adverse seismic interaction effects?
: 11. Have you looked for and found no other seismic conditions that could YE N[i ULI adversely affect the safety functions of the equipment?
 
Attachment C     .Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 338 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NM UM Seismic Walkdown Checklist (SWC)               SWELl- 495 Equipment ID No. 71PT-71ACA4             Equip. Class 4-Transformers Equipment Description Emergency Distribution7.5 Kva Transformer Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       YE N[i   ULI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: R. Casella/A.G. Porch/Date: 10-26-12 10-26-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 339 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NO Ul--Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emergency Distribution 7.5 Kva Transformer Photographs 0
Evaluated by: R. Casella/                                                       Date: 10-26-12 A.G. Porch/                                                              10-26-12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 340 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NR] UE]Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description EmerQency Distribution 7.5 Kva Transformer 0 Note: 71PT-71ACA4 anchorage Note: 71PT-71ACA4 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 341 of 573 AT'rACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ N] U"I Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class' 04-Transformers Equipment Description Uninterruptable Bus 37.5KVA Transformer 71MCC-252-OD2 Location:
 
Bldg. RB Floor El. 272' Room, Area RB South East, Col. 14, Line A Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 339 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NO Ul--
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC)         SWELl- 495 Equipment ID No. 71PT-71ACA4         Equip. Class 4-Transformers Equipment Description Emergency Distribution 7.5 Kva Transformer Photographs 0
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 340 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NR] UE]
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Only three anchors actually penetrate through the block wall and are fastened to the back side with a plate and an L2x2 structural angle.This is acceptable since the SEWS evaluation addressed this anchorage configuration and found that it was acceptable.
Seismic Walkdown Checklist (SWC)         SWELl- 495 Equipment ID No. 71PT-71ACA4         Equip. Class 4-Transformers Equipment Description EmerQency Distribution 7.5 Kva Transformer 0
: 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Note: 71PT-71ACA4 anchorage                           Note: 71PT-71ACA4
Anchorage is free of corrosion that is more than mild surface oxidation.
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The transformer unit is anchored to a block wall. There are no visible cracks on the wall.YZ NEI YN N[:] UL- N/A[--YZ NR ULI N/ADl Y[ ND1 U[- N/Ar-D I Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 341 of 573 AT'rACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ N] U"I Seismic Walkdown Checklist (SWC)                     SWELl-498 Equipment ID No.         71PT-71ACUPS             Equip. Class' 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Location: Bldg. RB                   Floor El. 272'           Room, Area RB South East, Col. 14, Line A Manufacturer, Model, Etc. (optional but recommended)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 342 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[K NEI UiD Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description Uninterruptable Bus 37.5KVA Transformer 71MCC-252-OD2
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 5. -1s the anchorage configuration consistent with plant documentation?
Anchorage
YZ NO UEij] N/AE1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 1. Is the anchorage configuration verification required (i.e., is the item one   YZ NEI of the 50% of SWEL items requiring such verification)?
Four (4), 1/2" anchors attach the transformer to the wall. Only three out of four anchors penetrate through the wall and are fastened on the back of the wall by structural members and a steel plate. Only three anchors are utilized in the analysis.
The item is one of the 50% of SWEL items requiringanchorage configuration verification.
The 4, 1/2" anchors are configured in accordance with the SEWS document for equipment 71PT-71ACUPS, Rev. 0.6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[E ULI potentially adverse seismic conditions?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YN N[:] UL- N/A[--
Only three anchors actually penetrate through the block wall and are fastened to the back side with a plate and an L2x2 structuralangle.
This is acceptable since the SEWS evaluation addressedthis anchorageconfiguration and found that it was acceptable.
: 3. Is the anchorage free of corrosion that is more than mild surface             YZ NR ULI N/ADl oxidation?
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    ND1 U[-    N/Ar-D anchors?
The transformerunit is anchoredto a block wall. There are no visible cracks on the wall.
I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 342 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[K NEI   UiD Seismic Walkdown Checklist (SWC)                 SWELl-498 Equipment ID No.       71PT-71ACUPS           Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2
: 5. -1s the anchorage configuration consistent with plant documentation?           YZ NO UEij] N/AE1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Four (4), 1/2" anchors attach the transformerto the wall. Only three out of four anchorspenetrate through the wall and are fastened on the back of the wall by structuralmembers and a steel plate. Only three anchors are utilized in the analysis. The 4, 1/2" anchors are configured in accordancewith the SEWS document for equipment 71PT-71ACUPS, Rev. 0.
: 6. Based on the above anchorage evaluations, is the anchorage free of             Y[   N[E ULI potentially adverse seismic conditions?
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Interaction Effects
There are no soft targets on the equipment.
: 7. Are soft targets free from impact by nearby equipment or structures?           YEI  N[:- U[-] N/An There are no soft targets on the equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     YE, NEI ULI N/AE1 and masonry block walls not likely to collapse onto the equipment?
The masonry block walls were evaluated in calculation C012, "HCLPF for Block Walls EB-272-1, 2" under project USI A-46/IPEEE Seismic Evaluation Project, and were found to be acceptable.
The masonry block walls were evaluated in calculation C012, "HCLPF for Block Walls EB-272-1, 2" underproject USI A-46/IPEEE Seismic Evaluation Project,and were found to be acceptable. The overhead equipment, distributionsystems, ceiling tiles and lighting not likely to collapse onto the equipment.
The overhead equipment, distribution systems, ceiling tiles and lighting not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?                   YE NEI    UEI N/AE-The lines attachedto the SWEL item have adequate flexibility to avoid damage.
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YEI N[:- U[-] N/An YE, NE I ULI N/AE1 YE NEI UEI N/AE-YE NE- u0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 343 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEi Ul-'Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description Uninterruptable Bus 37.5KVA Transformer 71MCC-252-OD2 Other Adverse Conditions
: 10. Based on the above seismic interaction evaluations, is equipment free         YE NE- u0 of potentially adverse seismic interaction effects?
: 11. Have you looked for and found no other seismic conditions that could YN N[I- ULI adversely affect the safety functions of the equipment?
Based on the above seismic interactionevaluations, the equipment is free of potentially adverse seismic interaction effects.
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
 
No additional comments.Evaluated by: Harpreet Ghuman Yaroslav Losev.Date: 09/28/2012 09/28/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 344 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NR Ur-]Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description Uninterruptable Bus 37.5KVA Transformer 71MCC-252-OD2 Photographs Note: Picture of equipment 71PT-71ACUPS.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 343 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ     NEi Ul-'
Note: Picture of the anchorage attachment to the wall on the back side.
Seismic Walkdown Checklist (SWC)             SWELl-498 Equipment ID No. 71PT-71ACUPS           Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Other Adverse Conditions
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 345 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ ND U-II Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 -Battery Racks /Equipment Description 125 Volt Station Battery A Location:
: 11. Have you looked for and found no other seismic conditions that could     YN N[I- ULI adversely affect the safety functions of the equipment?
Bldg. BR Floor El. 272 Room, Area Col 12 Line E Manufacturer, Model, Etc. (optional but recommended)
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Comments (Additional pages may be added as necessary)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YO NEI-of the 50% of SWEL items requiring such verification)?
No additionalcomments.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage has all necessary hardware 3. Js the anchorage free of corrosion that is more than mild surface oxidation?
Evaluated by: Harpreet Ghuman
Minor paint chipping was found at specific locations.
* Date: 09/28/2012 Yaroslav Losev.                                                          09/28/2012
This is not a structural concern 4. Is the anchorage free of visible cracks in the concrete near the anchors?The concrete is free of cracking in the areas near the anchorage Y[ NEI U[1 N/AI[I YO N[-] uJ-I N/AD-1 YZ NDI ul- N/AD Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 346 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ- NE-I U'Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 -Battery Racks Equipment Description 125 Vo/t Station Battery A 5. Is the anchorage configuration consistent with plant documentation?
 
YE N'-Z U-- N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.20-3, 1.20-8, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free,of YO N] UMi potentially adverse seismic conditions?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 344 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   NR   Ur-]
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Seismic Walkdown Checklist (SWC)         SWELl-498 Equipment ID No. 71PT-71ACUPS         Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Photographs Note: Pictureof equipment 71PT-71ACUPS.             Note: Picture of the anchorage attachment to the wall on the back side.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
 
: 9. Do attached lines have adequate flexibility to avoid damage?Flexible conduit connections to station batteries have adequate flexibility.
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 345 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ ND     U-II Seismic Walkdown Checklist (SWC)               SWELl- 501 Equipment ID No.     71SB-1                 Equip. Class_15 - Battery Racks                             /
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NEl UZ1 N/A[-YE NEI UE] N/A[--YN Nih u-] N/AZ1 YZ NZI U[-
Equipment Description 125 Volt Station Battery A Location: Bldg. BR             Floor El. 272           Room, Area Col 12 Line E Manufacturer, Model, Etc. (optional but recommended)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 347 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI U--Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15-Battery Racks Equipment Description 125 Volt Station Battery A Other Adverse Conditions
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 11. Have you looked for and found no other seismic conditions that could YZ NI-- UI-I adversely affect the safety functions of the equipment?
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YO NEI-of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[    NEI  U[1 N/AI[I The anchorage has all necessary hardware
: 3. Js the anchorage free of corrosion that is more than mild surface             YO N[-] uJ-I N/AD-1 oxidation?
Minor paint chipping was found at specific locations. This is not a structural concern
: 4. Is the anchorage free of visible cracks in the concrete near the               YZ NDI    ul-  N/AD anchors?
The concrete is free of cracking in the areas near the anchorage
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 346 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ- NE-I U' Seismic Walkdown Checklist (SWC)                 SWELl- 501 Equipment ID No.       71SB-1                 Equip. Class_15 - Battery Racks Equipment Description 125 Vo/t Station Battery A
: 5. Is the anchorage configuration consistent with plant documentation?         YE N'-Z U-- N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
(Ref. 1.20-3, 1.20-8, associated SEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free,of           YO N] UMi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YE NEl UZ1 N/A[-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NEI    UE] N/A[--
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YN Nih u-] N/AZ1 Flexible conduit connections to station batteries have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free         YZ NZI    U[-
of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 347 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI   U--
Seismic Walkdown Checklist (SWC)             SWELl- 501 Equipment ID No. 71SB-1                 Equip. Class_15- Battery Racks Equipment Description 125 Volt Station Battery A Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ   NI-- UI-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
C ~&Evaluated by: Rick Casella Date: 10/30/12 Al Porch 10/30/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 348 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI Ur-]Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 -Battery Racks Equipment Description 125 Volt Station BatteryA PhotoaraDhs Note: 71SB-1 Note: 71SB-1 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 349 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YN NEI- UF Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 -Battery Racks EauiDment DescriDtion 125 Volt Station Batterv A Note: 71SB-1 anchorage Note: 71SB-1 anchorage 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 350 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEI UF]Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class' 15-Batter-i Racks Equipment Description 125 Volt Station Battery B Location:
Evaluated by: Rick Casella C ~&                                Date: 10/30/12 Al Porch                                                                 10/30/12
Bldg. BR Floor El. 272' Room, Area BR3. Col. 12, Line F Manufacturer, Model, Etc., (optional but recommended)
 
Instructionsfor Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the-following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 348 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI     Ur-]
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YM NE]of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)           SWELl- 501 Equipment ID No. 71SB-1               Equip. Class_15 - Battery Racks Equipment Description 125 Volt Station BatteryA PhotoaraDhs Note: 71SB-1                                         Note: 71SB-1
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 349 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YN NEI- UF Seismic Walkdown Checklist (SWC)           SWELl- 501 Equipment ID No. 71SB-1                 Equip. Class_15 - Battery Racks EauiDment DescriDtion 125 Volt Station Batterv A Note: 71SB-1 anchorage                                 Note: 71SB-1 anchorage 0
YN NEI ULI N/AL]The seventy two (72), 1/2" diameter expansion anchors are free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface Y[ NEI U[--] N/AL-oxidation?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 350 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEI UF]
Seismic Walkdown Checklist (SWC)                     SWELl-502 Equipment ID No.         71SB-2                   Equip. Class' 15-Batter-i Racks Equipment Description 125 Volt Station Battery B Location: Bldg. BR                   Floor El. 272'           Room, Area BR3. Col. 12, Line F Manufacturer, Model, Etc., (optional but recommended)
Instructionsfor Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the-following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one     YM NE]
of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiringanchorage configuration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YN NEI ULI N/AL]
The seventy two (72), 1/2" diameter expansion anchors are free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface               Y[   NEI U[--] N/AL-oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the YE NIl U[] N/AL-]anchors?There are no visible cracks in the concrete near the anchors.'Enter the equipment class bname from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YE NIl U[] N/AL-]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 351 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI] ULJ Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B 5. Is the anchorage configuration consistent with plant documentation?
anchors?
YN NEI U-I N/A[-](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
There are no visible cracks in the concrete near the anchors.
The frames of the racks are spaced at 27" on center. There are two racks mounted to each other (back to back) at the center location.
'Enter the equipment class bname from Appendix B: Classes of Equipment.
The racks on the sides are by themselves.
 
The 72, 1/2" expansion anchors (18 for the side racks, and 36 for the center rack) are configured in accordance with the EC36608 and drawing 1.20-3.6. Based on the above anchorage evaluations, is the anchorage free of YE NE-- UEi potentially adverse seismic conditions?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 351 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI] ULJ Seismic Walkdown Checklist (SWC)               SWELl-502 Equipment ID No.       71SB-2                 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
: 5. Is the anchorage configuration consistent with plant documentation?         YN NEI U-I N/A[-]
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The frames of the racks are spaced at 27" on center. There are two racks mounted to each other (back to back) at the center location. The racks on the sides are by themselves. The 72, 1/2" expansion anchors (18 for the side racks, and 36 for the center rack) are configured in accordance with the EC36608 and drawing 1.20-3.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE   NE-- UEi potentially adverse seismic conditions?
Based on the above anchorageevaluations, the anchorageis free of potentiallyadverse seismic conditions.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YZ N-- u[--1 N/A --
There are no soft targets on the equipment.
There are no soft targets on the equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NE: UE- N/AZ-and masonry block walls not likely to collapse onto the equipment?
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YZ N-- u[--1 N/A --YZ NE: UE- N/AZ-YZ NEI U[-] N/AZ!YZ NEI UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 352 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NrI- U-'Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Other Adverse Conditions
: 9. Do attached lines have adequate flexibility to avoid damage?                 YZ NEI U[-] N/AZ!
: 11. Have you looked for and found no other seismic conditions that could Y; N[I- UI-adversely affect the safety functions of the equipment?
The lines attached to the SWEL item have adequate flexibility to avoid damage.
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NEI UE-of potentially adverse seismic interaction effects?
No additional comments.Evaluated by: Harpreet Ghuman Yaroslav Losev Date: 09/30/2012 09/30/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 353 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N- UF-Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Photoqraphs Note: Picture of equipment 71SB-2.Note:
Based on the above seismic interactionevaluations, the equipment is free of potentiallyadverse seismic interactioneffects.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 354 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEIl U[]Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Location:
 
Bldg. BR Floor El. 282 Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 352 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NrI-     U-'
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC)             SWELl-502 Equipment ID No.     71SB-2                 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Other Adverse Conditions
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI NO of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could       Y;   N[I- UI-adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Visible anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free~of corrosion that is more than mild surface oxidation?
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
Visible anchorage is free of corrosion.
Comments (Additional pages may be added as necessary)
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?No cracks.YO NEIl U-] N/A-]Y[ NEI U[E] N/AL]Y[ NEI UiE N/A[-I Attachment C Engineering Report No, JAF-RPT-12-00015 Rev. 0 Page 355 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NM ULI Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlinq Unit 5. Is the anchorage configuration consistent with plant documentation?
No additionalcomments.
YEI N[-] UD N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Evaluated by: HarpreetGhuman                                                      Date: 09/30/2012 Yaroslav Losev                                                              09/30/2012
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ Ni-i U-I potentially adverse seismic conditions?
 
Interaction Effects.7. Are soft targets free from impact by nearby equipment or structures?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 353 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N-     UF-Seismic Walkdown Checklist (SWC)           SWELl-502 Equipment ID No. 71SB-2                 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Photoqraphs Note: Picture of equipment 71SB-2.                     Note:
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
 
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE N[-] uM N/AD-YE NEi UE1 N/AE-YE NEl UD1 N/AD-]YE N[E UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 356 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI U[-]SeismicWalkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Other Adverse Conditions
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 354 of 573 ATTACHMENT     9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEIl U[]
: 11. Have you looked for and found no other seismic conditions that could YZ NEI U-I adversely affect the safety functions of the equipment?
Seismic Walkdown Checklist (SWC)               SWELl- 508 Equipment ID No.     72AHU-30A               Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Location: Bldg. BR             Floor El. 282           Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NO of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YO NEIl    U-] N/A-]
Visible anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free~of corrosion that is more than mild surface             Y[    NEI U[E] N/AL]
oxidation?
Visible anchorageis free of corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[   NEI UiE N/A[-I anchors?
No cracks.
 
Attachment C         Engineering Report No, JAF-RPT-12-00015 Rev. 0 Page 355 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NM ULI Seismic Walkdown Checklist (SWC)               SWELl- 508 Equipment ID No.     72AHU-30A               Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlinq Unit
: 5. Is the anchorage configuration consistent with plant documentation?         YEI N[-] UD N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         YZ Ni-i U-I potentially adverse seismic conditions?
Interaction Effects
    .7. Are soft targets free from impact by nearby equipment or structures?       YE N[-] uM N/AD-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NEi    UE1 N/AE-and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YE NEl UD1 N/AD-]
: 10. Based on the above seismic interaction evaluations, is equipment free       YE N[E UM of potentially adverse seismic interaction effects?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 356 of 573 ATTACHMENT   9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI       U[-]
SeismicWalkdown Checklist (SWC)               SWELl- 508 Equipment ID No. 72AHU-30A               Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could         YZ NEI U-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Missing mounting screws on door of unit 2 missing screws on west hinged door 1 missing screw on east hinged door All screws missing on bottom row of door panel The existing screws will keep the door secured. This condition will not create any credible adverse seismic interaction.
Missing mounting screws on door of unit 2 missing screws on west hinged door 1 missing screw on east hinged door All screws missing on bottom row of door panel The existing screws will keep the door secured. This condition will not create any credible adverse seismic interaction.
Although only a portion of the anchorage was visible, the existing SEWS for 72AHU-30A shows significant anchorage margin.Evaluated by: R. Casella C Date: 10-30-12 I A. Porch 10-30-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 357 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YS NOl UR Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlingq Unit Photographs Note: 72AHU-30A Note: 72AHU-30A Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 358 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE]- ULI Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Location:
Although only a portion of the anchorage was visible, the existing SEWS for 72AHU-30A shows significantanchoragemargin.
Bldg. BR Floor El. 282 Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: R. Casella                   *C                                     Date: 10-30-12 I
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
A. Porch                                                                   10-30-12
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
YN N[I: 2. Is the anchorage free of bent, broken, missing or loose hardware?3/8" anchor bolts to floor (4 locations-4 bolts per location) are slightly skewed. This condition was noted and accepted in the SEWS A-46 evaluation.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 357 of 573 ATTACHMENT   9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YS NOl   UR Seismic Walkdown Checklist (SWC)         SWELl- 508 Equipment ID No. 72AHU-30A             Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlingq Unit Photographs Note: 72AHU-30A                                       Note: 72AHU-30A
: 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
The bolting shows signs of minor surface oxidation.
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 358 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE]- ULI Seismic Walkdown Checklist (SWC)               SWELl- 516 Equipment ID No.     72FN-31A               Equip. Class Fans Equipment Description Battery Room A Recirc Fan Location: Bldg. BR               Floor El. 282           Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)
This is not a structural concern 4. Is the anchorage free of visible cracks in the concrete near the anchors?The concrete nearby the anchorage has no cracking Y[ N[:] U[] N/A[-]YO NIEJ UEI N/AEJ YOI NO~ U[:] N/AEL]
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 359 of 573 I ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ NEI U-]Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan 5. Is the anchorage configuration consistent with plant documentation?
Anchorage
Y[ N[I UI- N/A[-](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 1. Is the anchorage configuration verification required (i.e., is the item one   YN N[I:
The anchorage is consistent with A-46 SEWS for 72FN-31A.6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Ur-1 potentially adverse seismic conditions?
of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[    N[:] U[] N/A[-]
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
3/8" anchor bolts to floor (4 locations-4 bolts per location) are slightly skewed. This condition was noted and accepted in the SEWS A-46 evaluation.
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YN N[] ULI N/A-1 YN NEI ULI N/A[:]YS NW- UW- N/A~l YN NEI UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 360 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NE] UM Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Other Adverse Conditions
: 3. Is the anchorage free of corrosion that is more than mild surface               YO NIEJ UEI    N/AEJ oxidation?
: 11. Have you looked for and found no other seismic conditions that could Y[ NEJ UEi adversely affect the safety functions of the equipment?
The bolting shows signs of minor surface oxidation. This is not a structural concern
: 4. Is the anchorage free of visible cracks in the concrete near the               YOI NO~ U[:] N/AEL]
anchors?
The concrete nearby the anchorage has no cracking
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 I                                                                                                      Rev. 0 Page 359 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ   NEI U-]
Seismic Walkdown Checklist (SWC)                 SWELl- 516 Equipment ID No.       72FN-31A               Equip. Class Fans Equipment Description Battery Room A Recirc Fan
: 5. Is the anchorage configuration consistent with plant documentation?         Y[   N[I   UI- N/A[-]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageis consistent with A-46 SEWS for 72FN-31A.
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y[   NEI Ur-1 potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YN N[] ULI N/A-1
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NEI ULI N/A[:]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YS NW- UW- N/A~l
: 10. Based on the above seismic interaction evaluations, is equipment free       YN NEI    UM of potentially adverse seismic interaction effects?
 
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 360 of 573 0 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ   NE] UM Seismic Walkdown Checklist (SWC)               SWELl- 516 Equipment ID No. 72FN-31A                 Equip. Class Fans Equipment Description Battery Room A Recirc Fan Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEJ UEi adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: R Casella .Date: 10-30-12 A Porch 10 12...10-30-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 361 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE N-] Ur-I Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Photographs 0 Note: 72FN-31A Note: 72FN-31A anchorage Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 362 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N-- Ur-Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans EauiDment DescriDtion Batten/ Room A Recirc Fan Note: 72FN-31A anchorage of fan assembly to vibration isolator and to floor Note: 0 Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 363 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YO NEI Un Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09-Fans Equipment Description Battery Room A Exhaust Fan Location:
Evaluated by: R Casella       *                          .                     Date: 10-30-12 10-30-12...
Bldg. BR Floor El. 282 Room, Area 12, E Manufacturer, Model, Etc. (optional but recommended)
A Porch                                                                  10-30-12
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 361 of 573 ATTACHMENT 9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE N-]     Ur-I Seismic Walkdown Checklist (SWC)         SWELl- 516 Equipment ID No. 72FN-31A           Equip. Class Fans Equipment Description Battery Room A Recirc Fan Photographs 0
Y[ NE 2. Is the anchorage free of bent, broken, missing or loose hardware?East Hat -SW & NE bolts slightly skewed but have contact with hat flange. SE & NE bolts have less than full thread encasement
Note: 72FN-31A                                     Note: 72FN-31A anchorage
(<Threads below full encasement).
 
Blot size is 3/8 inch. Each hat secure to floor with bolts. These issues judged to not be a seismic concern.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 362 of 573 ATTACHMENT   9.6                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N-- Ur-Seismic Walkdown Checklist (SWC)         SWELl- 516 Equipment ID No. 72FN-31A           Equip. Class Fans EauiDment DescriDtion Batten/ Room A Recirc Fan Note: 72FN-31A anchorage of fan assembly           Note:
The bolting shows signs of minor surface oxidation.
to vibration isolatorand to floor 0
The oxidation is not a seismic concern 4. Is the anchorage free of visible cracks in the concrete near the anchors?No cracking was present YEI NM U[E N/AE-]YN NEI UE1 N/AE1 YE NEl U[E- N/AE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 364 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ Nr- U-Seismic Walkdown Checklist (SWC) SWELl-518 Equipment ID No. 72FN-46A Equip. Class_09 -Fans-Equipment Description Battery Room A Exhaust Fan 5. Is the anchorage configuration consistent with plant documentation?
 
YZ N[-- U[I- N/AI--(Note: This question only applies if the item is one of the 50% for which anchorage configuration verification is required.)
Attachment C             Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 363 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YO NEI Un Seismic Walkdown Checklist (SWC)               SWELl- 518 Equipment ID No.     72FN-46A               Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Location: Bldg. BR               Floor El. 282     Room, Area     12, E Manufacturer, Model, Etc. (optional but recommended)
Y2 inch bolts at connection between fan/motor s/zid and vibration damper (1.79-474, SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of YE NEIl U-I potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[    NE of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YEI NM U[E N/AE-]
East Hat - SW & NE bolts slightly skewed but have contact with hat flange. SE & NE bolts have less than full threadencasement
(<Threadsbelow full encasement). Blot size is 3/8 inch. Each hat secure to floor with bolts. These issues judged to not be a seismic concern.
: 3. Is the anchorage free of corrosion that is more than mild surface             YN NEI UE1 N/AE1 oxidation?
The bolting shows signs of minor surface oxidation. The oxidation is not a seismic concern
: 4. Is the anchorage free of visible cracks in the concrete near the               YE NEl U[E- N/AE-anchors?
No cracking was present
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 364 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ   Nr- U-Seismic Walkdown Checklist (SWC)               SWELl-518 Equipment ID No.       72FN-46A               Equip. Class_09 - Fans-Equipment Description Battery Room A Exhaust Fan
: 5. Is the anchorage configuration consistent with plant documentation?         YZ N[-- U[I- N/AI--
(Note: This question only applies if the item is one of the 50% for which anchorage configuration verification is required.)
Y2 inch bolts at connection between fan/motor s/zid and vibration damper (1.79-474, SEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE NEIl U-I potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YEI N[E UE-- N/A[
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YO NEIl UEI N/AEl and masonry block walls not likely to collapse onto the equipment?
Flex conduit has adequate flexibility.
Flex conduit has adequate flexibility.
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YEI N[E UE-- N/A[YO NEIl UEI N/AEl YZ Nl UEl N/AFl YN N[-] U-1 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 365 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE N1 UI--Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09-Fans Equipment Description Battery Room A Exhaust Fan Other Adverse Conditions
: 9. Do attached lines have adequate flexibility to avoid damage?                 YZ Nl UEl N/AFl
: 11. Have you looked for and found no other seismic conditions that could YM NEI UD-adversely affect the safety functions of the equipment?
: 10. Based on the above seismic interaction evaluations, is equipment free       YN N[-] U-1 of potentially adverse seismic interaction effects?
 
Attachment C    Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 365 of 573 ATTACHMENT 9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE N1    UI--
Seismic Walkdown Checklist (SWC)                SWELl- 518 Equipment ID No.          72FN-46A            Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could    YM    NEI UD-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary) cUUL-uy L. va  I VU(*L*
k Y4 VIt,Lfl&#xfd;    11                                                  Date: 10/30/12
                                &62JI ~
Al Porch                                                              10130112
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 366 of 573 0 ATTACHMENT 9.6                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y[   NEI  U-I Seismic Walkdown Checklist (SWC)        SWELl- 518 Equipment ID No. 72FN-46A            Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Photographs 0
Note: 72FN-46A anchorage
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 367 of 573 ATTACHMENT  9.6                                                      SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[ NR" Ur-]
Seismic Walkdown Checklist (SWC)        SWELl- 518 Equipment ID No. 72FN-46A            Equip. Class_09 - Fans EauiDment DescriDtion Battery I Room A Exhaust Fan Note: 72FN-46A showing vibration isolators          Note: 72FN-46A showing one anchorto floor installed at a slight skew 0
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 368 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE' UM-Seismic Walkdown Checklist (SWC)                    SWELl-519 Equipment ID No.        72FN-46B                Equip. Class' 09-Fans Equipment Description Battery Room B Exhaust Fan Location: Bldg. BR                  Floor El. 282'            Room, Area BR4, Col. 12, Line F Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    YO Nl of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiring anchorage configurationverification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              YO NO ul-I N/A--
One anchoris missing on the North East corner of the skid; however, this is already documented in the SEWS evaluation and was found to be acceptable. One anchoris loose on the North West corner of the skid.The resolution to this deficiency is tracked through CR-JAF-2012-06538
: 3. Is the anchorage free of corrosion that is more than mild surface              YZ NEIrUI-- N/A[]
oxidation?
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the                YE Nil UiL N/A[-l anchors?
There are no visible cracks in the concrete near the SWEL item.
Enter the equipment class name from Appendix B: Classes of Equipment.
 
Atiachm ent C        Erigineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 369 of 573 ATTACHMENT 9.6                                                                SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YN   ND Ut]
Seismic Walkdown Checklist (SWC)                SWELl-519 Equipment ID No.        72FN-46B              Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan
: 5. Is the anchorage configuration consistent with plant documentation?            YE Nt] Ut] N/At]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The 8, 1/4" expansion anchorsare configured in accordancewith the SEWS document for 72FN-46A ,which has the same configuration as 72FN-46B, except for one missing bolt, which was evaluate in SEWS to be OK).
: 6. Based on the above anchorage evaluations, is the anchorage free of            YtI  NZ UEi potentially adverse seismic conditions?
Based on.the above anchorage evaluations,the anchorageis not free of potentiallyadverse seismic conditions. See item 2.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?          Y] NEI .Ut] N/At]
Soft targets are free from impact by nearby equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NtI        Uti N/At]
and masonry block walls not likely to collapse onto the equipment?
The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?                  Y[   NtI  Ut] N/At]
The lines attached to the SWEL item have adequateflexibility to avoid damage.
: 10. Based on the above seismic interaction evaluations, is equipment free        Y[    NEI U-1 of potentially adverse seismic interaction effects?
Based on the above seismic interaction evaluations,the equipment is free of potentially adverse seismic interactioneffects.
 
Attachrmient C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 370 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[    NEI  UI-I Seismic Walkdown Checklist (SWC)             SWELl-519 Equipment ID No.     72FN-46B              Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       YS N[-] U["]
adversely affect the safety functions of the equipment?
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
L. I cUUL-uy k VIt,Lfl&#xfd; 11 Date: 10/30/12 va Y 4&62JI ~Al Porch 10130112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 366 of 573 0 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09-Fans Equipment Description Battery Room A Exhaust Fan Photographs Note: 72FN-46A anchorage Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 367 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[ NR" Ur-]Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09 -Fans EauiDment DescriDtion Battery Room A Exhaust Fan I Note: 72FN-46A showing vibration isolators Note: 72FN-46A showing one anchor to floor installed at a slight skew 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 368 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE' UM-Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class' 09-Fans Equipment Description Battery Room B Exhaust Fan Location:
No additionalcomments.
Bldg. BR Floor El. 282' Room, Area BR4, Col. 12, Line F Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: HarpreetGhumanbI          *jAA.                                    Date: 09/30/2012 Yaroslav Losev                                                            09/30/2012
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 371 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI     UL-Seismic Walkdown Checklist (SWC)       SWELl-519 Equipment ID No. 72FN-46B            Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Photographs 0
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
Note: Picture of equipment 72FN-46B.                Note: Picture showing the missing anchoron the skid for the SWEL item.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?One anchor is missing on the North East corner of the skid; however, this is already documented in the SEWS evaluation and was found to be acceptable.
 
One anchor is loose on the North West corner of the skid. The resolution to this deficiency is tracked through CR-JAF-2012-06538 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C   Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 372 of 573 ATTACHMENT 9.6                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NI'-    UI-]
Anchorage is free of corrosion that is more than mild surface oxidation.
Seismic Walkdown Checklist (SWC)       SWELl-519 Equipment ID No. 72FN-46B            Equip. Class 09-Fans Eauipment Description Battery Room B Exhaust Fan Note: Picture showing the loose anchoron            Note:
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?There are no visible cracks in the concrete near the SWEL item.YO Nl YO NO ul-I N/A--YZ NEIr UI-- N/A[]YE Nil UiL N/A[-l Enter the equipment class name from Appendix B: Classes of Equipment.
the skid for the SWEL item.
Atiachm ent C Erigineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 369 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YN ND Ut]Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan 5. Is the anchorage configuration consistent with plant documentation?
 
YE Nt] Ut] N/At](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 373 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI    U-I Seismic Walkdown Checklist (SWC)                     SWELl-522 Equipment ID No.         72HV-7A                  Equip. Class, 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Location: Bldg. BR                   Floor El. 272'           Room, Area BR5, Col. 11.5, Line C Manufacturer, Model, Etc. (optional but recommended)
The 8, 1/4" expansion anchors are configured in accordance with the SEWS document for 72FN-46A ,which has the same configuration as 72FN-46B, except for one missing bolt, which was evaluate in SEWS to be OK).6. Based on the above anchorage evaluations, is the anchorage free of YtI NZ UEi potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Based on. the above anchorage evaluations, the anchorage is not free of potentially adverse seismic conditions.
Anchorage
See item 2.Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 1. Is the anchorage configuration verification required (i.e., is the item one     YE:] NZ of the 50% of SWEL items requiring such verification)?
Soft targets are free from impact by nearby equipment.
The item is not one of the 50% of SWEL items requiringanchorage configuration verification.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 2. Is the anchorage free of bent, broken, missing or-loose hardware?               YZ ND1 U[-I N/AD-The equipment is stitch welded in four (4) locations and the welds are intact and do not appeardamaged.
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 3. Is the anchorage free of corrosion that is more than mild surface               Y[    N[-' UD- N/Ar-oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.Y] NEI .Ut] N/At]YE NtI Uti N/At]Y[ NtI Ut] N/At]Y[ NEI U-1 Attachrmient C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 370 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NEI UI-I Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Other Adverse Conditions
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 11. Have you looked for and found no other seismic conditions that could YS N[-] U["]adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    Nr-- U-I N/A[]
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
anchors?
No additional comments.Evaluated by: Harpreet GhumanbI Yaroslav Losev Date: 09/30/2012 09/30/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 371 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI UL-Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Photographs 0 Note: Picture of equipment 72FN-46B.Note: Picture showing the missing anchor on the skid for the SWEL item.
There are no visible cracks in the concrete near the SWEL item.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 372 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NI'- UI-]Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Eauipment Description Battery Room B Exhaust Fan Note: Picture showing the loose anchor on the skid for the SWEL item.Note:
I Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 373 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI U-I Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class, 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Location:
 
Bldg. BR Floor El. 272' Room, Area BR5, Col. 11.5, Line C Manufacturer, Model, Etc. (optional but recommended)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 374 of 573 0 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[  NEI UM Seismic Walkdown Checklist (SWC)               SWELl-522 Equipment ID No.       72HV-7A                Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
: 5. Is the anchorage configuration consistent with plant documentation?         YEI NEI U[-] N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE:] NZ of the 50% of SWEL items requiring such verification)?
Item is not one of the 50% for which an anchorageconfiguration verification is required.
The item is not one of the 50% of SWEL items requiring anchorage configuration verification.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YN NEi    UiE potentially adverse seismic conditions?
: 2. Is the anchorage free of bent, broken, missing or-loose hardware?
Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.
YZ ND1 U[-I N/AD-The equipment is stitch welded in four (4) locations and the welds are intact and do not appear damaged.3. Is the anchorage free of corrosion that is more than mild surface Y[ N[-' UD- N/Ar-oxidation?
Interaction Effects
Anchorage is free of corrosion that is more than mild surface oxidation.
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    NEI UEi N/AEl Soft targets are free from impact by nearbyequipment.
: 4. Is the anchorage free of visible cracks in the concrete near the Y[ Nr-- U-I N/A[]anchors?There are no visible cracks in the concrete near the SWEL item.I Enter the equipment class name from Appendix B: Classes of Equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NEI UEi N/AE[
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 374 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI UM Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel 5. Is the anchorage configuration consistent with plant documentation?
and masonry block walls not likely to collapse onto the equipment?
YEI NEI U[-] N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Safety latches for the overheadlight fixtures should be installed. There is a masonry block wall near the equipment; however, the wall was evaluated under IPEEEeffort to reinforce the block walls underJAF-RPT-MISC-0221 1, Section 3.1.4.1, page 3-44, Table 3.1.4.1.
Item is not one of the 50% for which an anchorage configuration verification is required.6. Based on the above anchorage evaluations, is the anchorage free of YN NEi UiE potentially adverse seismic conditions?
There is a 1" gap between cable tray I TCO77R and the SWEL item; however, based on engineeringjudgment this is a sufficient amount of space during a seismic event to where there will be no interaction between SWEL equipment and raceway.
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
: 9. Do attached lines have adequate flexibility to avoid damage?                YE NEI uE1 N/AEl The lines attached to the SWEL item have adequateflexibility to avoid damage.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 10. Based on the above seismic interaction evaluations, is equipment free        YE N[l UEl of potentially adverse seismic interaction effects?
Soft targets are free from impact by nearbyequipment.
Based on the above seismic interaction evaluations,the equipment is free of potentially adverse seismic interaction effects.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
 
Safety latches for the overhead light fixtures should be installed.
Attachmen t C        Engin:eering Report No. JAF-RPT-12-00015 Rev. 0 Page 375 of 573 0 ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N[II    URI Seismic Walkdown Checklist (SWC)             SWELI-522 Equipment ID No.     72HV-7A                Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Other Adverse Conditions
There is a masonry block wall near the equipment; however, the wall was evaluated under IPEEE effort to reinforce the block walls under JAF-RPT-MISC-0221 1, Section 3.1.4.1, page 3-44, Table 3.1.4.1.There is a 1" gap between cable tray I TCO77R and the SWEL item;however, based on engineering judgment this is a sufficient amount of space during a seismic event to where there will be no interaction between SWEL equipment and raceway.9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.Y[ NEI UEi N/AEl YE NEI UEi N/AE[YE NEI uE1 N/AEl YE N[l UEl Attachmen t C Engin:eering Report No. JAF-RPT-12-00015 Rev. 0 Page 375 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N[II URI Seismic Walkdown Checklist (SWC) SWELI-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could         YZ NEI    UI--
: 11. Have you looked for and found no other seismic conditions that could YZ NEI UI--adversely affect the safety functions of the equipment?
adversely affect the safety functions of the equipment?
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
No additional comments.Evaluated by: Harpreet Ghuman Yaroslav Losev Date: 09/30/2012 09/30/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 376 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEZ UF--j Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Photographs Note: Picture of equipment 72HV-7A.Note: Picture showing the 1"gap between the cable tray ITCO77R and the SWEL item.
Comments (Additional pages may be added as necessary)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 377 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NE]I UF7 Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergency Diesel Generator A Vent Supply Fan Location:
No additionalcomments.
Bldg. EG Floor El. 272', Room, Area Col. 24 Line Al Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: Harpreet Ghuman                                                      Date: 09/30/2012 Yaroslav Losev                                                              09/30/2012
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 376 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEZ UF--j Seismic Walkdown Checklist (SWC)         SWELl-522 Equipment ID No. 72HV-7A              Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Photographs Note: Picture of equipment 72HV-7A.                   Note: Picture showing the 1"gap between the cable tray ITCO77R and the SWEL item.
Y[-7--NM 2. Is the anchorage free of bent, broken, missing or loose hardware?Ability to discern condition of anchorage was difficult based on distance to anchorage from our location.
 
Based on what we could see, anchorage was free of bent, broken or missing hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 377 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NE]I UF7 Seismic Walkdown Checklist (SWC)               SWELl- 555 Equipment ID No.     92FN-IA                Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan Location: Bldg.       EG        Floor El. 272',    Room, Area            Col. 24 Line Al Manufacturer, Model, Etc. (optional but recommended)
No corrosion was evident, based on limited view from floor.4. Is the anchorage free of visible cracks in the concrete near the anchors?The component is connected to steel. There is no concrete.YE NEI UL] N/A[-'Y[9 NEI UL-E N/A[]YEL N[l U[-] N/AN EN-DC-168 REV 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 378 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE ND UEI Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergencv Diesel Generator A Vent Supplv Fan 5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Y[-- NE] UE- N/AS (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
: 6. Based on the above anchorage evaluations, is the anchorage free of YE NEi ULi potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one    Y[-7--NM of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              YE NEI UL] N/A[-'
There are no soft targets on this equipment.
Ability to discern condition of anchoragewas difficult based on distance to anchorage from our location. Based on what we could see, anchoragewas free of bent, broken or missing hardware.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface              Y[9 NEI UL-E N/A[]
: 9. Do attached lines have adequate flexibility to avoid damage?No attached lines 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YEi NEI UE] N/AN YE NEI UEi N/AE]YE] NE] U--] N/A[YE N[] UE]
oxidation?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 379 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI U-]Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. Q2FN-1A Equip. Class 9- Fans Equipment Description Emergency Diesel Generator A Vent Supply Fan Other Adverse Conditions
No corrosion was evident, based on limited view from floor.
: 11. Have you looked for and found no other seismic conditions that could YE NEI U[I adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the                YEL N[l U[-] N/AN anchors?
The component is connected to steel. There is no concrete.
EN-DC-168 REV 0
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 378 of 573 ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE ND    UEI Seismic Walkdown Checklist (SWC)                SWELl- 555 Equipment ID No.      92FN-IA                Equip. Class 9- Fans Equipment Description Emergencv Diesel GeneratorA Vent Supplv Fan
: 5. Is the anchorage configuration consistent with plant documentation?          Y[-- NE] UE- N/AS (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE NEi    ULi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YEi NEI UE] N/AN There are no soft targets on this equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,  YE NEI     UEi N/AE]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                YE] NE] U--] N/A[
No attachedlines
: 10. Based on the above seismic interaction evaluations, is equipment free        YE N[] UE]
of potentially adverse seismic interaction effects?
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 379 of 573 ATTACHMENT 9.6                                                          SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI    U-]
Seismic Walkdown Checklist (SWC)              SWELl- 555 Equipment ID No. Q2FN-1A                  Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could    YE NEI    U[I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Evaluated by: A.G. Porch /                                                    Date: 10/26/12 R. Casella I                                                            10/26/12
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 380 of 573 ATTACHMENT 9.6                                                    SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI    UL-I Seismic Walkdown Checklist (SWC)        SWELl- 555 Equipment ID No. 92FN-IA              Equip. Class 9- Fans Equipment Description Emergzency Diesel GeneratorA Vent Supply Fan Photographs Note: 92FN-IA                                        Note: 92FN-IA 0
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 381 of 573 ATTACHMENT  9.6                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NEI    U-Seismic Walkdown Checklist (SWC)        SWELl- 555 Equipment ID No. 92FN-1A            Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan
 
Attachment C            Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 382 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[   NRI  URl Seismic Walkdown Checklist (SWC)              SWELl- 577 Equipment ID No.       92RTD-IOIA            Equip. Class 19- Temperature Sensor Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector Location: Bldg.       EG        Floor El. 300      Room, Area          Col. 23 Line A2, AZ Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    Y[-1 NO of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              YE NEI UE1 N/A--
Ability to discern condition of anchorage was difficult based on distance to anchoragefrom our location. Based on what we could see-to the ceiling mounted component, it appearedto be secured to the flange of the roof steel.
: 3. Is the anchorage free of corrosion that is more than mild surface              YZ N[I] ULI N/A[-]
oxidation?
Ability to discern condition of anchorage was difficult based on distance to anchoragefrom our location. Based on what we could see to the ceiling mounted component, it appearedto be secured to the flange of the roof steel.
: 4. Is the anchorage free of visible cracks in the concrete near the               YI- ND- UD- N/AO anchors?
There is no concrete. The component is mounted to steel beam flange.
EN-DC-168 REV 0
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 383 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NR Ur Seismic Walkdown Checklist (SWC)               SWELl- 577 Equipment ID No.       92RTD-1OIA              Equip. Class 19 - Temperature Sensor.
Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector
: 5. Is the anchorage configuration consistent with plant documentation?          Y-] NF] U-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ NEI UI-potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact-by nearby equipment or structures?        YZ N[-] U-1 N/AE-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,    YLI N[: U[I N/Az and masonry block walls not likely to collapse onto the equipment?
Attached to overhead roof steel beam, there are no visible objects to fall on the SWEL item.
: 9. Do attached lines have adequate flexibility to avoid damage?                Y[W NEI UEII N/AZ
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NE] Ur-of potentially adverse seismic interaction effects?
EN-DC-168 REV 0
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 384 of 573 ATTACHMENT 9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status:  YZ NEI] U-I!
Seismic Walkdown Checklist (SWC)              SWELl- 577 Equipment ID No. 92RTD-1O1A              Equip. Class 19 - Temperature Sensor Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector Other Adverse Conditions
: 11. Have you looked for~and found no other seismic conditions that could     YZ    NEi UrI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: A.G. Porch /R. Casella I Date: 10/26/12 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 380 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI UL-I Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergzency Diesel Generator A Vent Supply Fan Photographs Note: 92FN-IA Note: 92FN-IA 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 381 of 573 ATTACHMENT 9.6 Sheet 5 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: YZ NEI U-Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-1A Equip. Class 9- Fans Equipment Description Emergency Diesel Generator A Vent Supply Fan Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 382 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NRI URl Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-IOIA Equip. Class 19- Temperature Sensor Equipment Description Emergency Diesel Generator Room A South Side Resist Temperature Detector Location:
(see photo)
Bldg. EG Floor El. 300 Room, Area Col. 23 Line A2, AZ Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: A.G. Porch         ,                                               Date: 10/26/12 R. Casella /                                                             10/26/12 EN-DC-1 68 REV 0
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 385 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N[:] UFW Seismic Walkdown Checklist (SWC)       SWELl- 577 Equipment ID No. 92RTD-101A         Equip. Class 19 - Temperature Sensor Equipment Description Emerqency Diesel GeneratorRoom A South Side Resist Temperature Detector Photographs Note:   92RTD-IOIA                                 Note: 92RTD-IOIA EN-DC-168 REV 0
Y[-1 NO 2. Is the anchorage free of bent, broken, missing or loose hardware?Ability to discern condition of anchorage was difficult based on distance to anchorage from our location.
 
Based on what we could see-to the ceiling mounted component, it appeared to be secured to the flange of the roof steel.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 386 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE]     U-1 Seismic Walkdown Checklist (SWC)                   SWELl-578 Equipment ID No.       92RTD-1O1B               Equip. Class' 19 - Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Location: Bldg. EG                 Floor El. 272             Room, Area C: 27, L:A2 Manufacturer, Model, Etc. (optional but recommended)
Ability to discern condition of anchorage was difficult based on distance to anchorage from our location.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Based on what we could see to the ceiling mounted component, it appeared to be secured to the flange of the roof steel.4. Is the anchorage free of visible cracks in the concrete near the anchors?There is no concrete.
Anchorage
The component is mounted to steel beam flange.YE NEI UE1 N/A--YZ N[I] ULI N/A[-]YI- ND- UD- N/AO EN-DC-168 REV 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 383 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NR Ur Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-1OIA Equip. Class 19 -Temperature Sensor.Equipment Description Emergency Diesel Generator Room A South Side Resist Temperature Detector 5. Is the anchorage configuration consistent with plant documentation?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NM of the 50% of SWEL items requiring such verification)?
Y-] NF] U-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YN N[i UiEl N/AD-The unit is at high elevation. No close visual inspection is possible.
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI UI-potentially adverse seismic conditions?
Based on review of drawings, and weight of the equipment, the anchorage was determined to be adequate
N/A Interaction Effects 7. Are soft targets free from impact-by nearby equipment or structures?
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[    NEI Ui[E N/A[:
YZ N[-] U-1 N/AE-8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YLI N[: U[I N/Az and masonry block walls not likely to collapse onto the equipment?
oxidation?
Attached to overhead roof steel beam, there are no visible objects to fall on the SWEL item.9. Do attached lines have adequate flexibility to avoid damage?Y[W NEI UEII N/AZ 10. Based on the above seismic interaction evaluations, is equipment free YZ NE] Ur-of potentially adverse seismic interaction effects?EN-DC-168 REV 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 384 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI] U-I!Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-1O1A Equip. Class 19 -Temperature Sensor Equipment Description Emergency Diesel Generator Room A South Side Resist Temperature Detector Other Adverse Conditions
The unit is at high elevation. No close visual inspection is possible
: 11. Have you looked for~and found no other seismic conditions that could YZ NEi UrI adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    N[Il U[-- N/Ar-Z anchors?
Comments (Additional pages may be added as necessary)(see photo)Evaluated by: A.G. Porch , Date: 10/26/12 R. Casella / 10/26/12 EN-DC-1 68 REV 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 385 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N[:] UFW Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-101A Equip. Class 19 -Temperature Sensor Equipment Description Emerqency Diesel Generator Room A South Side Resist Temperature Detector Photographs Note: 92RTD-IOIA Note: 92RTD-IOIA EN-DC-168 REV 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 386 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE] U-1 Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-1O1B Equip. Class' 19 -Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Location:
The unit is at high elevation. No close visual inspection is possible
Bldg. EG Floor El. 272 Room, Area C: 27, L:A2 Manufacturer, Model, Etc. (optional but recommended)
'Enter the equipment class name from Appendix B: Classes of Equipment.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Afttchmient C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 387 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NrIi U--
YEI NM 2. Is the anchorage free of bent, broken, missing or loose hardware?The unit is at high elevation.
Seismic Walkdown Checklist (SWC)               SWELl-578 Equipment ID No.- 92RTD-IOIB                   Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector
No close visual inspection is possible.Based on review of drawings, and weight of the equipment, the anchorage was determined to be adequate 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
: 5. Is the anchorage configuration consistent with plant documentation?         Y[I NEI   U[- N/A[
The unit is at high elevation.
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
No close visual inspection is possible 4. Is the anchorage free of visible cracks in the concrete near the anchors?The unit is at high elevation.
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y] Nil U[I potentially adverse seismic conditions?
No close visual inspection is possible YN N[i UiEl N/AD-Y[ NEI Ui[E N/A[: Y[ N[Il U[-- N/Ar-Z'Enter the equipment class name from Appendix B: Classes of Equipment.
The anchorageis free of any potentiallyadverse seismic condition.
Afttchmient C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 387 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NrIi U--Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No.- 92RTD-IOIB Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector 5. Is the anchorage configuration consistent with plant documentation?
Interaction Effects
Y[I NEI U[- N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 7. Are soft targets free from impact by nearby equipment or structures?       YZ NEI   ULI N/AEl The soft targets are free from impact by nearbyequipment and structures.
: 6. Based on the above anchorage evaluations, is the anchorage free of Y] Nil U[I potentially adverse seismic conditions?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NEI UEI N/AEZ and masonry block walls not likely to collapse onto the equipment?
The anchorage is free of any potentially adverse seismic condition.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
YZ NEI ULI N/AEl The soft targets are free from impact by nearby equipment and structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NEI UEI N/AEZ and masonry block walls not likely to collapse onto the equipment?
Unit is mounted on a masonry block wall. The block walls have been evaluated and enhanced in accordance with DC# D1-96-011, RevO as part of IPEEE evaluations.
Unit is mounted on a masonry block wall. The block walls have been evaluated and enhanced in accordance with DC# D1-96-011, RevO as part of IPEEE evaluations.
: 9. Do attached lines have adequate flexibility to avoid damage? YZ NE U[- N/A-Attached lines have adequate flexibility.
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ NE     U[- N/A-Attached lines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free Y; N[il UI&#xfd;of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.
: 10. Based on the above seismic interaction evaluations, is equipment free       Y; N[il UI&#xfd; of potentially adverse seismic interaction effects?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 388 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEl UI Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-IO1B Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Other Adverse Conditions
The equipment is free of potentiallyadverse seismic interaction effects.
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI U[-I adversely affect the safety functions of the equipment?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 388 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEl   UI Seismic Walkdown Checklist (SWC)             SWELl-578 Equipment ID No. 92RTD-IO1B               Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEI U[-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Pouria Pour hobadi Donald Kobera Date: 9/21/12 9/21/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 389 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NE] UFi-Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-101B Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Photographs Note :_92R TD-101B Temperature sensor installed on concrete block.Note:
Evaluated by: Pouria Pour hobadi                                               Date: 9/21/12 Donald Kobera                                                            9/21/12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 390 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE Nr- U[I Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-Al Equip. Class 12-Air Comoressors Equipment Description Emergency Diesel Generator A Air Start Compressor Al Location:
 
Bldg. EG Floor El. 272' Room, Area Col. 24 Line A2 Manufacturer, Model, Etc. (optional but recommended)
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 389 of 573 ATTACHMENT 9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NE] UFi-Seismic Walkdown Checklist (SWC)       SWELl-578 Equipment ID No. 92RTD-101B         Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Photographs Note :_92R TD-101B Temperature sensor installed     Note:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
on concrete block.
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YN Nil of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage contains all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 390 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE Nr-     U[I Seismic Walkdown Checklist (SWC)               SWELl- 581 Equipment ID No. 93AC-Al                 Equip. Class 12-Air Comoressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl Location: Bldg.       EG       Floor El.     272'     Room, Area           Col. 24 Line A2 Manufacturer, Model, Etc. (optional but recommended)
The anchorage has a small amount of paint chipping that is not a structural concern 4. Is the anchorage free of visible cracks in the concrete near the anchors?There are no cracks in the concrete around the anchorage YN N[i U[I N/AE--YE NE UE N/AR YO NEJ UL[ N/AR Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 391 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI UD Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1I.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Equip. Class 12-Air Compressors Equipment Description Emergency Diesel Generator A Air Start Compressor Al 5. Is the anchorage configuration consistent with plant documentation?
Anchorage
YE NE:] ULI N/AFi (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.12-2, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of YE N[I U-]potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one     YN Nil of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YN N[i    U[I N/AE--
Soft targets = 1/4" tubing (cu) see photo; Cable trays, conduit and 2" diameter air piping well supported (Note tubing in tube track -secure -SAT). No soft target issues -SAT.8, Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Anchorage contains all necessary hardware
Lighting, masonry wall, cable trays -all SAT.9. Do attached lines have adequate flexibility to avoid damage?Flex conduit and air hose (air start system ref.. 93RV-101A)  
: 3. Is the anchorage free of corrosion that is more than mild surface               YE NE UE N/AR oxidation?
-all SAT.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YN N-] U[] N/A[]Y] NE] U[] N/AEr YE NE] ULI N/AE]YZ N[-] UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 392 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NE]U UF-1 Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-Al Equip. Class 12-Air Compressors Equipment Description Emergency Diesel Generator A Air Start Compressor Al Other Adverse Conditions
The anchorage has a small amount of paint chipping that is not a structural concern
: 11. Have you looked for and found no other seismic conditions that could YN N--] U-I adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YO NEJ UL[    N/AR anchors?
All SAT.Comments (Additional pages may be added as necessary)
There are no cracks in the concrete around the anchorage
Some cracks running E-W along masonry wall near concrete pad (see photo) -not an issue (i.e.shrinkage/settlement cracks). Not considered adverse to anchorage system.Evaluated by: R. Casella /Date: 10/26/12 A.G. Porch /10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 393 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NF-- UI-Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1 Equip. Class 12-Air Compressors Equipment Description Emergency Diesel Generator A Air Start Compressor A I Photographs Note: 93AC-A1 end AC-Al including anchorage on east Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 394 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1 Equip. Class 12-Air Compressors Equipment Description Emergency Diesel Generator A Air Start Compressor A 1 Status: YZ NEIr u[]0 Note: 93A C-A I anchorage 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 395 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ Nn U[j Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emergency Diesel Generator A Air Start Receiver Al Location:
 
Bldg. EG Floor El. 272' Room, Area 24, A2 Manufacturer, Model, Etc. (optional but recommended)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 391 of 573 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI UD Seismic Walkdown Checklist (SWC)               SWELl- 581 Equipment ID No.       93AC-A1I.               Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
: 5. Is the anchorage configuration consistent with plant documentation?           YE NE:] ULI N/AFi (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YO NEI of the 50% of SWEL items requiring such verification)?
(Ref. 1.12-2, associated SEWS document)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage contains all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE N[I U-]
Mild surface oxidation and paint chipping was observed -no structural concerns 4. Is the anchorage free of visible cracks in the concrete near the anchors?Settlement crack in slab along masonry block wall approximately 4" South of wall. Not an issue based on load on anchor -OK.Hairline crack (very light) -SAT.Welds -leg to base plate and tank -SAT YZ NE: UE- N/A[E-YZ NE: UEl N/A-YEI NO U[-- N/AE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 396 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-Al Equip. Class 21 Equipment Description Emergency Diesel Generator A Air Start Receiver Al 5. Is the anchorage configuration consistent with plant documentation?
potentially adverse seismic conditions?
YN NEI UE- N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1./12-43, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI UIE]potentially adverse seismic conditions?
Interaction Effects
Interaction Effects 7. Are soft targetsfree from impact by nearby equipment or structures?
: 7. Are soft targets free from impact by nearby equipment or structures?         YN N-] U[] N/A[]
93EDG-701A (3/4" drain valve -air receiver drain valve) only soft target-free from seismic effects (ppg above is well supported)
Soft targets = 1/4" tubing (cu) see photo; Cable trays, conduit and 2" diameter air piping well supported (Note tubing in tube track - secure -
-SAT 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
SAT). No soft target issues - SAT.
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NEI U[I N/AZl Y[ NEI ULi N/AZl Y[ NEI ULi N/AZ-YZ NEI U[-
8, Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y] NE] U[] N/AEr and masonry block walls not likely to collapse onto the equipment?
Attachrmient C Engirdering Report No. JAF-RPT-12-00015 Rev. 0 Page 397 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI U0-Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 *Equip. Class 21 Equipment Description Emergency Diesel Generator A Air Start Receiver Al Other Adverse Conditions
Lighting, masonry wall, cable trays - all SAT.
: 11. Have you looked for and found no other seismic conditions that could YO NEI UE-adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE NE] ULI    N/AE]
Flex conduit and air hose (air start system ref.. 93RV-101A) - all SAT.
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ N[-] UM of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 392 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   NE]UUF-1 Seismic Walkdown Checklist (SWC)             SWELl- 581 Equipment ID No. 93AC-Al                 Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YN N--] U-I adversely affect the safety functions of the equipment?
All SAT.
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Other air tanks are typical of 93AR-A1 Evaluated by: R. Casella I A.G. Porch Date: 10/26/122 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 398 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEi UI-]Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emergencv Diesel Generator A Air Start Receiver A 1 Photographs Note: 93AR-Alincluding support legs (note -3rd support leg in rear cannot be seen in this photo)
Some cracks running E-W along masonry wall near concrete pad (see photo) - not an issue (i.e.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 399 of 573 ATTACHMENT 9.6 Sheet 5 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: YE NO ULI Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emerqency Diesel Generator A Air Start Receiver A l Note: 93AR-A I anchorage to floor at 2 of the 3 legs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 400 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NDI U[-]Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class' 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Location:
shrinkage/settlement cracks). Not considered adverse to anchorage system.
Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26.5 Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: R. Casella /                                                      Date: 10/26/12 A.G. Porch /                                                             10/26/12
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 393 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NF--    UI-Seismic Walkdown Checklist (SWC)       SWELl- 581 Equipment ID No. 93AC-A1             Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorA I Photographs Note: 93AC-A1                                                AC-Al including anchorage on east end
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The three (3), 3/8" expansion anchors are free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?  
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 394 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NEIru[]
)Anchorage is free of corrosion that is more than mild surface oxidation.
Seismic Walkdown Checklist (SWC)       SWELl- 581 Equipment ID No. 93AC-A1             Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorA 1 0
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?There are concrete hairline cracks within the vicinity of the anchors but they do not pass through the center of any of the anchors. Therefore, based on engineering judgment there will be no significant reduction in the anchor strength due to these cracks and is deemed acceptable.
Note: 93A C-A I anchorage 0
YjN NEI YO ND-] ULI N/AD1 YN NEI U-] N/AD-YN NDI UD1 N/ADl 1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 401 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YN NEI ULI Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 5. Is the anchorage configuration consistent with plant documentation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 395 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ Nn U[j Seismic Walkdown Checklist (SWC)               SWELl- 582 Equipment ID No. 93AR-A1                  Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al Location: Bldg.     EG         Floor El. 272'     Room, Area           24, A2 Manufacturer, Model, Etc. (optional but recommended)
YE NEi U[iI N/A[-](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
The configuration of the three (3), 3/8" expansion anchors are consistent with the SEWS documentation for equipment 93AR-Al (same as 93AR-B2).6. Based on the above anchorage evaluations, is the anchorage free of YO NE] UiE potentially adverse seismic conditions?
Anchorage
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
: 1. Is the anchorage configuration verification required (i.e., is the item one   YO NEI of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YZ NE: UE- N/A[E-Anchorage contains all necessary hardware
The soft targets are free from impact by nearby equipment or structures.
: 3. Is the anchorage free of corrosion that is more than mild surface               YZ NE: UEl N/A-oxidation?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Mild surface oxidation and paint chipping was observed - no structural concerns
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YEI NO U[-- N/AE-anchors?
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YO NE]I UiE N/AL]Y[ NE] Ul] N/AL-]Y[ NEI UE] N/AL]YE NE] uIE]
Settlement crack in slab along masonry block wall approximately 4" South of wall. Not an issue based on load on anchor - OK.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 402 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N'-' U--Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Other Adverse Conditions
Hairline crack (very light) - SAT.
: 11. Have you looked for and found no other seismic conditions that could YZ NEI- U[]adversely affect the safety functions of the equipment?
Welds - leg to base plate and tank - SAT
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
 
No additional comments.Evaluated by: Harpreet Ghuman IW.Yaroslav Losev--S Date: 09/21/2012 09/21/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 403 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NR-] ULI Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 21-Tanks and Heat Exchangers Equipment Description EDG B Air Start Receiver B2 Photographs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 404 of 573 S ATTACHMENT 9.6 Sheet I of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: YI-- NEI UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 -Instrument and Control Panels Equipment Description EDG A Engine Control Panel Location:
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 396 of 573 ATTACHMENT      9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[  NEI U-I Seismic Walkdown Checklist (SWC)                 SWELl- 582 Equipment ID No.       93AR-Al                Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al
Bldg. EG Floor El. 272 Room, Area 24, GI Manufacturer, Model, Etc. (optional but recommended)
: 5. Is the anchorage configuration consistent with plant documentation?         YN NEI      UE- N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
(Ref. 1./12-43, associated SEWS document)
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ NEI    UIE]
YED N[:]2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
potentially adverse seismic conditions?
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Y[I NEI U[I N/AE]YE-] NE] ULI N/AE]-Y[E] NE] UN N/A[-]
Interaction Effects
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 405 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 -Instrument and Control Panels Equipment Description EDG A Engine Control Panel 5. Is the anchorage configuration consistent with plant documentation?
: 7. Are soft targetsfree from impact by nearby equipment or structures?         Y[   NEI U[I N/AZl 93EDG-701A (3/4" drain valve - air receiver drain valve) only soft target
YI- NEI US N/AZl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
        - free from seismic effects (ppg above is well supported) - SAT
: 6. Based on the above anchorage evaluations, is the anchorage free of YEI NEi US potentially adverse seismic conditions?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NEI  ULi N/AZl and masonry block walls not likely to collapse onto the equipment?
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y[    NEI ULi N/AZ-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NEI U[-
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YS NEI UE] N/A[-YS NEI uEr N/A[Z YZ NEI] UE] N/A YZ NEI UE]
of potentially adverse seismic interaction effects?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 406 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI] U Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 -Instrument and Control Panels Equipment Description EDG A Engine Control Panel Other Adverse Conditions
 
: 11. Have you looked for and found no other seismic conditions that could YE NE] UE]adversely affect the safety functions of the equipment?
Attachrmient C     Engirdering Report No. JAF-RPT-12-00015 Rev. 0 Page 397 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI   U0-Seismic Walkdown Checklist (SWC)               SWELl- 582 Equipment ID No. 93AR-A1                  *Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YO NEI    UE-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Conduit (rigid) is supported by unistrut vertical/
Other air tanks are typical of 93AR-A1 Evaluated by: R. Casella   I                                                  Date: 10/26/122 A.G. Porch                                                              10/26/12
laterally (via knee brace); There is approximately 5 feet of flex conduit at inter with top of panel. Therefore any seismic loads below rigid conduit support will be dissipated by flex.C 42 Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 407 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-'LI NE] UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 -Instrument and Control Panels Equipment Description EDG A EnQine Control Panel Photographs 0 of panel ix conduit rising off top Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 408 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YLI Nil UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 -Instrument and Control Panels Equipment Description EDG A Engine Control Panel 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 409 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI Ur-D Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class' 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Location:
 
Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26, Line A3 Manufacturer, Model, Etc. (optional but recommended)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 398 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEi    UI-]
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC)       SWELl- 582 Equipment ID No. 93AR-A1            Equip. Class 21 Equipment Description Emergencv Diesel GeneratorA Air Start Receiver A 1 Photographs Note: 93AR-Alincluding support legs (note -
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE Ni: of the 50% of SWEL items requiring such verification)?
3rd support leg in rearcannot be seen in this photo)
The item is one of the 50% of SWEL items requiring anchorage configuration verification.
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The four (4) 3/4" expansion anchors are free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 399 of 573 ATTACHMENT   9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NO ULI Seismic Walkdown Checklist (SWC)       SWELl- 582 Equipment ID No. 93AR-A1            Equip. Class 21 Equipment Description Emerqency Diesel GeneratorA Air Start Receiver A l Note: 93AR-A I anchorage to floor at 2 of the 3 legs
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 400 of 573 0 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NDI    U[-]
Seismic Walkdown Checklist (SWC)                     SWELl-594 Equipment ID No.         93AR-B2                  Equip. Class' 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Location: Bldg. EG                   Floor El. 272'           Room, Area EG Room B, Col. 26.5 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YjN NEI of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiringanchorage configuration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YO ND-] ULI N/AD1 The three (3), 3/8" expansion anchors are free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface             YN NEI U-] N/AD-oxidation?                                                           )
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The anchors are free of visible cracks in the concrete.YM NIl UL N/A-]YE NrI U[IE] N/A[--YE Nil U[- N/A[--I Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YN NDI    UD1 N/ADl anchors?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 410 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NF1 UF-Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel 5. Is the anchorage configuration consistent with plant documentation?
There are concrete hairline cracks within the vicinity of the anchors but they do not pass through the center of any of the anchors. Therefore, based on engineeringjudgment there will be no significantreduction in the anchorstrength due to these cracks and is deemed acceptable.
YZ NEI UI- N/AE-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
1 Enter the equipment class name from Appendix B: Classes of Equipment.
The configuration of the four (4), 3/4" expansion anchors is consistent with the SEWS documentation for equipment 93ECP-A (same as 93ECP-B).6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Uil potentially adverse seismic conditions?
 
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 401 of 573 ATrACHMENT    9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YN NEI      ULI Seismic Walkdown Checklist (SWC)               SWELl-594 Equipment ID No.       93AR-B2                Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 5. Is the anchorage configuration consistent with plant documentation?         YE NEi      U[iI N/A[-]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The configuration of the three (3), 3/8" expansion anchors are consistent with the SEWS documentation for equipment 93AR-Al (same as 93AR-B2).
: 6. Based on the above anchorage evaluations, is the anchorage free of           YO NE]    UiE potentially adverse seismic conditions?
Based on the above anchorageevaluations, the anchorageis free of potentially adverse seismic conditions.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YO NE]I UiE    N/AL]
The soft targets are free from impact by nearby equipment or structures.
The soft targets are free from impact by nearby equipment or structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[      NE]  Ul]  N/AL-]
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.Y] NEI UE- N/AZl YN NEl UZ-- N/A--YN NE UEi N/AZ YN NO UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 411 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEIl ULI Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Other Adverse Conditions
The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 11. Have you looked for and found no other seismic conditions that could Y[-] NO UF-Z adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y[    NEI  UE] N/AL]
Top of the Control Panel is unsupported.
The lines attached to the SWEL item have adequate flexibility to avoid damage.
The SWES evaluation determined that the panel is acceptable without these anchors;however the same evaluation does not include the load transferred from the overhead conduits attached to the panel. These conduits drop approximately 10 ft vertically into the panel without any lateral support to minimize the interaction load to the panel. Based on engineering judgment, during a seismic event a significant lateral load from the conduits will contribute to the moment arm transferred to the base anchors which potentially could result in failure of the anchors and overturn the panel. The resolution to this deficiency is tracked through LB-01.Comments (Additional pages may be added as necessary)
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NE] uIE]
No additional comments.Evaluated by: Harpreet Ghuman " .Yaroslav Losev Date: 09/21/2012 09/21/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 412 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YNI NEIr ULI Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Photographs Note: Picture of equipment 93ECP-B. Note: the conduits attached at the top of the panel are the ones that extend approximately 10' vertically.
of potentially adverse seismic interaction effects?
Note: Picture showing that the control panel is not attached/supported at the top.
Based on the above seismic interaction evaluations, the equipment is free of potentiallyadverse seismic interactioneffects.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 413 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Yo] NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Location:
 
Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 402 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N'-' U--
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC)             SWELl-594 Equipment ID No.     93AR-B2                Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Other Adverse Conditions
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could       YZ NEI- U[]
YE] NE 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
adversely affect the safety functions of the equipment?
Y[E] Nr] ULI N/A[-]Y[E] NE] UN N/AE-]4. Is the anchorage free of visible cracks in the concrete near the anchors?Y[E] NE] UN N/AE]
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0, Page 414 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NEI UE Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel 5. Is the anchorage configuration consistent with plant documentation?
Comments (Additional pages may be added as necessary)
YE] N[-1 UI- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
No additionalcomments.
: 6. Based on the above anchorage evaluations, is the anchorage free of YEI NE UM potentially adverse seismic conditions?
Evaluated by: HarpreetGhuman      IW.                                            Date: 09/21/2012 Yaroslav Losev--S                                                        09/21/2012
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
 
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 403 of 573 ATTACHMENT  9.6                                                    SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NR-] ULI Seismic Walkdown Checklist (SWC)        SWELl-594 Equipment ID No. 93AR-B2              Equip. Class 21-Tanks and Heat Exchangers Equipment Description EDG B Air Start Receiver B2 Photographs
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YZ NE-I UE1 N/AEl Y[D NM UEl N/AEl YO NEl UE N/A[E]YN NEl U[E]
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 415 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YF-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Other Adverse Conditions
Attachment C              Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 404 of 573 S ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YI-- NEI  UN Seismic Walkdown Checklist (SWC)               SWELl- 624 Equipment ID No.     93ECP-A                Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel Location: Bldg. EG              Floor El. 272          Room, Area 24, GI Manufacturer, Model, Etc. (optional but recommended)
: 11. Have you looked for and found no other seismic conditions that could Y[D N[i Uil adversely affect the safety functions of the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    YED N[:]
of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              Y[I NEI  U[I N/AE]
: 3. Is the anchorage free of corrosion that is more than mild surface              YE-] NE] ULI N/AE]-
oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[E] NE] UN N/A[-]
anchors?
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 405 of 573 0 ATTACHMENT    9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y-- NE] UZ Seismic Walkdown Checklist (SWC)              SWELl- 624 Equipment ID No.     93ECP-A                Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel
: 5. Is the anchorage configuration consistent with plant documentation?        YI- NEI    US N/AZl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YEI NEi  US potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YS NEI UE] N/A[-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,    YS NEI    uEr N/A[Z and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                YZ NEI] UE] N/A
: 10. Based on the above seismic interaction evaluations, is equipment free        YZ NEI UE]
of potentially adverse seismic interaction effects?
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 406 of 573 0 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI] U Seismic Walkdown Checklist (SWC)                 SWELl- 624 Equipment ID No.     93ECP-A                   Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could          YE NE] UE]
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Conduit (rigid)is supportedby unistrut vertical/ laterally (via knee brace); There is approximately5 feet of flex conduit at inter with top of panel. Therefore any seismic loads below rigid conduit support will be dissipatedby flex.
Evaluated by: Rick Casella C          42                        Date: 10/29/12 Al Porch                                                                      10129112
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 407 of 573 ATTACHMENT 9.6                                                    SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-'LI NE]    UN Seismic Walkdown Checklist (SWC)        SWELl- 624 Equipment ID No. 93ECP-A            Equip. Class_20 - Instrumentand Control Panels Equipment Description EDG A EnQine Control Panel Photographs 0
ix conduit rising off top of panel
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 408 of 573 ATTACHMENT 9.6                                                    SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YLI Nil UN Seismic Walkdown Checklist (SWC)        SWELl- 624 Equipment ID No. 93ECP-A            Equip. Class_20 - Instrumentand Control Panels Equipment Description EDG A Engine Control Panel 0
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 409 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI Ur-D Seismic Walkdown Checklist (SWC)                    SWELl-625 Equipment ID No.        93ECP-B                  Equip. Class' 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Location: Bldg. EG                  Floor El. 272'            Room, Area EG Room B, Col. 26, Line A3 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    YE Ni:
of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiringanchorage configuration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              YM NIl UL      N/A-]
The four (4) 3/4" expansion anchors are free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface              YE NrI U[IE] N/A[--
oxidation?
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the                YE Nil U[-    N/A[--
anchors?
The anchors are free of visible cracks in the concrete.
I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 410 of 573 ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[  NF1 UF-Seismic Walkdown Checklist (SWC)                SWELl-625 Equipment ID No.      93ECP-B                Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel
: 5. Is the anchorage configuration consistent with plant documentation?          YZ NEI UI-    N/AE-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The configurationof the four (4), 3/4" expansion anchors is consistent with the SEWS documentation for equipment 93ECP-A (same as 93ECP-B).
: 6. Based on the above anchorage evaluations, is the anchorage free of          Y[    NEI  Uil potentially adverse seismic conditions?
Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        Y] NEI UE- N/AZl The soft targets are free from impact by nearby equipment or structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,  YN NEl UZ-- N/A--
and masonry block walls not likely to collapse onto the equipment?
The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?                YN NE UEi N/AZ The lines attachedto the SWEL item have adequate flexibility to avoid damage.
: 10. Based on the above seismic interaction evaluations, is equipment free        YN NO UE-of potentially adverse seismic interaction effects?
Based on the above seismic interaction evaluations, the equipment is free of potentiallyadverse seismic interaction effects.
 
Attachment C            Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 411 of 573 ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[    NEIl  ULI Seismic Walkdown Checklist (SWC)                SWELl-625 Equipment ID No. 93ECP-B                  Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could        Y[-] NO  UF-Z adversely affect the safety functions of the equipment?
Top of the Control Panel is unsupported. The SWES evaluation determined that the panel is acceptable without these anchors; however the same evaluation does not include the load transferred from the overhead conduits attached to the panel. These conduits drop approximately 10 ft vertically into the panel without any lateralsupport to minimize the interactionload to the panel. Based on engineering judgment, during a seismic event a significant lateralload from the conduits will contribute to the moment arm transferredto the base anchors which potentiallycould result in failure of the anchorsand overturn the panel. The resolution to this deficiency is tracked through LB-01.
Comments (Additional pages may be added as necessary)
No additionalcomments.
Evaluated by: HarpreetGhuman "                        .                            Date: 09/21/2012 Yaroslav Losev                                                            09/21/2012
 
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 412 of 573 ATTACHMENT 9.6                                                            SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YNI    NEIr  ULI Seismic Walkdown Checklist (SWC)              SWELl-625 Equipment ID No. 93ECP-B                  Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Photographs Note: Picture of equipment 93ECP-B. Note: the            Note: Picture showing that the control panel is conduits attached at the top of the panel are the        not attached/supportedat the top.
ones that extend approximately 10' vertically.
 
Attachment C              Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 413 of 573 ATTACHMENT 9.6                                                                  SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Yo] NE] UZ Seismic Walkdown Checklist (SWC)              SWELl- 628 Equipment ID No.      93ECSP-A                Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Location: Bldg. EG              Floor El. 272          Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one    YE] NE of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?              Y[E] Nr] ULI N/A[-]
: 3. Is the anchorage free of corrosion that is more than mild surface              Y[E] NE] UN N/AE-]
oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the                Y[E] NE] UN N/AE]
anchors?
 
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0, Page 414 of 573 0
ATTACHMENT 9.6                                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI  NEI UE Seismic Walkdown Checklist (SWC)                SWELl- 628 Equipment ID No.      93ECSP-A                Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel
: 5. Is the anchorage configuration consistent with plant documentation?        YE] N[-1 UI- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of          YEI NE UM potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YZ NE-I UE1 N/AEl
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,  Y[D NM UEl N/AEl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                YO NEl UE N/A[E]
: 10. Based on the above seismic interaction evaluations, is equipment free      YN NEl U[E]
of potentially adverse seismic interaction effects?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 415 of 573 0 ATTACHMENT   9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YF-- NE] UZ Seismic Walkdown Checklist (SWC)               SWELl- 628 Equipment ID No. 93ECSP-A                 Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       Y[D N[i   Uil adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Need support detail FC~4.Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10129112 -Al Porch 10/29/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 416 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI- NEl U[Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Photographs
Need support detail Evaluated by: Rick Casella FC~4.                                              Date: 10/29/12 Al Porch                                                                   10129112 10/29/12 -
&#xfd;g anchorage Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 417 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEr- NR- UO Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Note: 93ECSP-A anchorage M-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 418 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ N[E U[Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class' 20 -Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Location:
Al Porch
Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 416 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI- NEl U[
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YZ NE of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl- 628 Equipment ID No. 93ECSP-A           Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Photographs
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The four (4) 3/8" Hilti anchors are free of bent, broken, missing or loose hardware.Panels need to be removed and anchorage of internal components needs to be checked.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
                                                                                &#xfd;g anchorage
The anchorage is free of corrosion that is more than mild surface oxidation.
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The anchorage is free of visible cracks in the concrete near the anchors.YE]I NEI UN N/AZ-YZ NEI uE- N/AZ-Y[ NE-] UE] N/AZ!Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 417 of 573 ATrACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEr- NR- UO Seismic Walkdown Checklist (SWC)       SWELl- 628 Equipment ID No. 93ECSP-A           Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Note: 93ECSP-A anchorage                                                                     M-
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 419 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NE] UFL Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20 -Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel 5. Is the anchorage configuration consistent with plant documentation?
 
Y[ NEL UI- N/ALl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 418 of 573 ATTACHMENT     9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ N[E U[
The configuration of the four (4), 3/8" Hilti Anchors is consistent with SEWS for 93 ECSP-A Rev 0, which is identical to ECSP-B.6. Based on the above anchorage evaluations, is the anchorage free of YI- NEI ULI potentially adverse seismic conditions?
Seismic Walkdown Checklist (SWC)                   SWELl-629 Equipment ID No.       93ECSP-B                   Equip. Class' 20 - Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Location: Bldg. EG                 Floor El. 272             Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
Panels need to be removed and anchorage of internal components needs to be checked.Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Anchorage
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YZ NEL ULE N/A[L Y[ N[L U[L N/AL-Y[ NEL UL[] N/ALE Y[ N[-]7LIu Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 420 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI U-'Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Other Adverse Conditions
: 1. Is the anchorage configuration verification required (i.e., is the item one     YZ NE of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could YEE N[i UMI adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YE]I NEI  UN N/AZ-The four (4) 3/8" Hilti anchorsare free of bent, broken, missing or loose hardware.
Panels need to be removed and anchorage of internal components needs to be checked.
: 3. Is the anchorage free of corrosion that is more than mild surface               YZ NEI uE- N/AZ-oxidation?
The anchorageis free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    NE-] UE] N/AZ!
anchors?
The anchorageis free of visible cracks in the concrete nearthe anchors.
Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 419 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   NE] UFL Seismic Walkdown Checklist (SWC)               SWELl-629 Equipment ID No.       93ECSP-B               Equip. Class 20 - Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel
: 5. Is the anchorage configuration consistent with plant documentation?           Y[   NEL UI- N/ALl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The configurationof the four (4), 3/8" Hilti Anchors is consistentwith SEWS for 93 ECSP-A Rev 0, which is identicalto ECSP-B.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YI- NEI ULI potentially adverse seismic conditions?
Panels need to be removed and anchorage of internal components needs to be checked.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YZ NEL ULE    N/A[L
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    N[L U[L N/AL-and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y[    NEL UL[] N/ALE
: 10. Based on the above seismic interaction evaluations, is equipment free       Y[    N[-]7LIu of potentially adverse seismic interaction effects?
 
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 420 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI U-'
Seismic Walkdown Checklist (SWC)               SWELl-629 Equipment ID No. 93ECSP-B                 Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YEE N[i   UMI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Harpreet Ghuman -M-.--: Date: 9/21/12 Yaroslav Losev 9121112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 421 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YN N[-E ULI-Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Photographs Note: 93ECSP-B Engine Control Sub Panel Note:
Evaluated by: Harpreet Ghuman           -M-.--:                                 Date: 9/21/12 Yaroslav Losev                                                           9121112
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 422 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YN NEI UF]Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Enqine Generators Equipment Description Emergency Diesel Generator C Location:
 
Bldg. EG Floor El. 272' Room, Area Col. 24 line A4, AZ Manufacturer, Model, Etc. (optional but recommended)
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 421 of 573 ATTACHMENT 9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YN N[-E   ULI-Seismic Walkdown Checklist (SWC)       SWELl-629 Equipment ID No. 93ECSP-B           Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Photographs Note: 93ECSP-B Engine Control Sub Panel           Note:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic.Walkdown of an item of equipment on the SWEL. The space below each of the following questions.
 
may be used to record the results of judgments and findings.
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 422 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YN NEI UF]
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)               SWELl- 634 Equipment ID No.     93EDG-C                 Equip. Class Enqine Generators Equipment Description Emergency Diesel GeneratorC Location: Bldg.       EG       Floor El. 272'     Room, Area             Col. 24 line A4, AZ Manufacturer, Model, Etc. (optional but recommended)
YO NEI 2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage contains all necessary hardware YO N[-- UI- N/A[-3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic.Walkdown of an item of equipment on the SWEL. The space below each of the following questions. may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
The anchorage is free of any corrosion 4. Is the anchorage free of visible cracks in the concrete near the anchors?Hairline cracks in grout at various bolt locations (previously addressed at 93EDG-D and documented in CR-JAF-2012-06090)
Anchorage
YO NEI- uE N/AZJ YEI NO UE- N/A-,
: 1. Is the anchorage configuration verification required (i.e., is the item one     YO NEI of the 50% of SWEL items requiring such verification)?
Attachment C
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YO N[--   UI- N/A[-
Report No. JAF-RPT-12-00015 Rev. 0 Page 423 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] Ur[7 Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description EmerQency Diesel Generator C 5. Is the anchorage configuration consistent with plant documentation?
Anchorage contains all necessary hardware
YZ NEI U-I N/AFZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.12-95, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of YN NEil UII potentially adverse seismic conditions?
: 3. Is the anchorage free of corrosion that is more than mild surface               YO NEI-    uE N/AZJ oxidation?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchorage is free of any corrosion
Numerous soft targets on EDG. No credible seismic impacts 8. Are' overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YEI NO UE- N/A-,
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NEI u- N/A[--YO NEI uE- N/AEl YE NEI UE- N/A[E YE N[l UEI Atta6ficihht C IEngineering Report No. JAF-RPT-12-00015 Rev. 0 Page 424 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NEI UD--Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description Emeraencv Diesel Generator C Other Adverse Conditions
anchors?
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI UE]adversely affect the safety functions of the equipment?
Hairline cracks in grout at various bolt locations (previously addressed at 93EDG-D and documented in CR-JAF-2012-06090)
 
Attachment C         Engireerin*    Report No. JAF-RPT-12-00015 Rev. 0 Page 423 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NE] Ur[7 Seismic Walkdown Checklist (SWC)               SWELl- 634 Equipment ID No.       93EDG-C                 Equip. Class Engine Generators Equipment Description EmerQency Diesel GeneratorC
: 5. Is the anchorage configuration consistent with plant documentation?           YZ NEI U-I N/AFZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
(Ref. 1.12-95, associated SEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YN NEil UII potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         Y[    NEI  u-  N/A[--
Numerous soft targets on EDG. No credible seismic impacts
: 8. Are' overhead equipment, distribution systems, ceiling tiles and lighting,   YO NEI    uE- N/AEl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE NEI UE- N/A[E
: 10. Based on the above seismic interaction evaluations, is equipment free         YE N[l UEI of potentially adverse seismic interaction effects?
 
Atta6ficihht C     IEngineering Report No. JAF-RPT-12-00015 Rev. 0 Page 424 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NEI   UD--
Seismic Walkdown Checklist (SWC)             SWELl- 634 Equipment ID No. 93EDG-C                 Equip. Class Engine Generators Equipment Description Emeraencv Diesel GeneratorC Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEI UE]
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: R. Casella Date: 10/26/12 A.G. Porch/I1/61 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 425 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI ULI Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description EmerQency Diesel Generator C Photographs Note: 93EDG-C Note: 93EDG-C Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 426 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N-- Ui Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators EauiDment DescriDtion Emeraencv Diesel Generator C Note: 93EDG-C Note:
Evaluated by: R. Casella                                                         Date: 10/26/12 A.G. Porch/I1/61                                                         10/26/12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 427 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UE-I Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel Generator D Location:
 
Bldg. EG Floor El. 272 Room, Area Col. 26.5 Manufacturer, Model, Etc. (optional but recommended) , EMD Engine Portec Gen Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an' item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 425 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI   ULI Seismic Walkdown Checklist (SWC)       SWELl- 634 Equipment ID No. 93EDG-C             Equip. Class Engine Generators Equipment Description EmerQency Diesel GeneratorC Photographs Note: 93EDG-C                                       Note: 93EDG-C
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
YE NEil 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 426 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N--   Ui Seismic Walkdown Checklist (SWC)       SWELl- 634 Equipment ID No. 93EDG-C             Equip. Class Engine Generators EauiDment DescriDtion Emeraencv Diesel GeneratorC Note: 93EDG-C                                       Note:
Mild surface corrosion on the bolts. No impact on seismic adequacy.4. Is the anchorage free of visible cracks in the concrete near the anchors?Anchors on north side'of unit -Hairline crack in grout adjacent to the 3 rd anchor from the Northeast corner. Crack continues on concrete at base of unit. Hairline crack 4" S of 5t anchor from northeast.
 
Both the 7 th and, 8 th bolts have hair line cracks at the bolts in the grout.Anchors on south side of unit -Additional hair line cracks similar to north side.The above condition is addressed in CR-JAF-2012-06345.
Attachment C           Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 427 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UE-I Seismic Walkdown Checklist (SWC)                 SWELl-635 Equipment ID No.       93EDG-D                 Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Location: Bldg. EG                 Floor El. 272           Room, Area Col. 26.5 Manufacturer, Model, Etc. (optional but recommended)           , EMD Engine Portec Gen Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an' item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
As discussed in the response to CA #1, the existing condition is acceptable with no adverse seismic effects.YO Nil UEi N/A[-YE Nil UI[I N/A[-L YZ N['] U-] N/AE' Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 428 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] U-I I Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No., 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel Generator D 5. Is the anchorage configuration consistent with plant documentation?
Anchorage
YN N[E U'-J N/A[l (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE  NEil of the 50% of SWEL items requiring such verification)?
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ N[-] UEI potentially adverse seismic conditions?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YO Nil UEi N/A[-
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchorageis free of bent, broken, missing or loose hardware.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface               YE Nil UI[I N/A[-L oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YEJ NE .UN N/AEl Y ] N[-I UE1 N/AEl Y ] N['- UE N/AE[YE NEI UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 429 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ N[II&#xfd; UI-Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel Generator D Other Adverse Conditions
Mild surface corrosion on the bolts. No impact on seismic adequacy.
: 11. Have you looked for and found no other seismic conditions that could YZ NEI UI-adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YZ N['] U-] N/AE' anchors?
Support for 2" air line has 2 bolts on each side that are either flush with the nuts or less than full thread engagement.
Anchors on north side'of unit - Hairline crack in grout adjacent to the 3 rd anchor from the Northeast corner. Crack continues on concrete at base of unit. Hairline crack 4" S of 5t anchor from northeast. Both the 7 th and, 8 th bolts have hair line cracks at the bolts in the grout.
This condition was addressed in CR-JAF-2012-06345.
Anchors on south side of unit - Additional hair line cracks similar to north side.
There is no adverse seismic impact resulting from this condition.
The above condition is addressed in CR-JAF-2012-06345. As discussed in the response to CA #1, the existing condition is acceptable with no adverse seismic effects.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 428 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NE] U-II Seismic Walkdown Checklist (SWC)               SWELl-635 Equipment ID No., 93EDG-D                     Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD
: 5. Is the anchorage configuration consistent with plant documentation?         YN N[E U'-J N/A[l (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ N[-] UEI potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YEJ NE .UN N/AEl
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y ] N[-I UE1 N/AEl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y ] N['-  UE N/AE[
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NEI UE-of potentially adverse seismic interaction effects?
 
Attachment C           Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 429 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   N[II&#xfd; UI-Seismic Walkdown Checklist (SWC)               SWELl-635 Equipment ID No.     93EDG-D                 Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could           YZ NEI     UI-adversely affect the safety functions of the equipment?
Support for 2" air line has 2 bolts on each side that are either flush with the nuts or less than full thread engagement. This condition was addressed in CR-JAF-2012-06345. There is no adverse seismic impact resulting from this condition.
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Hair line crack from support of south air start line. Vertical side less pronounced.
Hair line crack from support of south air start line. Vertical side less pronounced. This item is addressed in CR-JAF-2012-06345. This does not constitute an adverse seismic condition.
This item is addressed in CR-JAF-2012-06345.
Evaluated by: Rick Casella                                                           Date: 9-27-12 Alan Porch                                                                   9-27-12
This does not constitute an adverse seismic condition.
 
Evaluated by: Rick Casella Date: 9-27-12 Alan Porch 9-27-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 430 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NnI- UL-1 Seismic Walkdown Checklist (SWC) SWELl -635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel Generator D Photographs Note: 93EDG-D Note: 93EDG-D Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 431 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nn-] U--Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Eauipment Description Emerqencv Diesel Generator D Note: 93EDG-D crack in grout in proximity of anchor bolt Note: 93EDG Anchor Bolt (8 on each side of Unit)0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 432 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YO-- NEI[ U[Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Generator Control Panel Location:
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 430 of 573 ATTACHMENT 9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NnI-   UL-1 Seismic Walkdown Checklist (SWC)       SWELl -635 Equipment ID No. 93EDG-D             Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Photographs Note: 93EDG-D                                       Note: 93EDG-D
Bldg. EG Floor El. 272 Room, Area 24, A1 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 431 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nn-] U--
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl-635 Equipment ID No. 93EDG-D             Equip. Class Engine Generator Eauipment Description Emerqencv Diesel GeneratorD Note: 93EDG-D crack in grout in proximity of       Note: 93EDG Anchor Bolt (8 on each side of anchorbolt                                          Unit) 0
YEl-- NO 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Y[-D N[-] U[ N/ADI YEI NDI U[ N/AD-YD7 NDI U[ N/AD-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 433 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE] UI Seismic Walkdown Checklist (SWC) SWELl -636 Equipment ID No. 93EGP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Generator Control Panel 5. Is the anchorage configuration consistent with plant documentation?.
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 432 of 573 ATTACHMENT   9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YO-- NEI[ U[
YOI Nil ULi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Seismic Walkdown Checklist (SWC)               SWELl-636 Equipment ID No.     93EGP-A                 Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Location: Bldg. EG             Floor El. 272           Room, Area 24, A1 Manufacturer, Model, Etc. (optional but recommended)
: 6. Based on the above anchorage evaluations, is the anchorage free of YLI NOi U[potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEl-- NO of the 50% of SWEL items requiring such verification)?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NlO UI[ N/All YO NO] U[] N/A-l!YE NEI Ui] N/Al]YE NE! Ui See Comments.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[-D N[-] U[    N/ADI
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 434 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE UN Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Generator Control Panel Other Adverse Conditions, 11. Have you looked for and found no other seismic conditions that could Yg NE] UE&#xfd;adversely affect the safety functions of the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface             YEI  NDI  U[  N/AD-oxidation?
: 4. Is the anchorage free of visible cracks in the concrete near the               YD7 NDI   U[   N/AD-anchors?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 433 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE]   UI Seismic Walkdown Checklist (SWC)               SWELl -636 Equipment ID No.       93EGP-A                 Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel
: 5. Is the anchorage configuration consistent with plant documentation?.       YOI Nil ULi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         YLI NOi U[
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YE NlO UI[    N/All
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YO NO] U[] N/A-l!
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YE NEI Ui] N/Al]
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NE! Ui of potentially adverse seismic interaction effects?
See Comments.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 434 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE UN Seismic Walkdown Checklist (SWC)               SWELl-636 Equipment ID No. 93EGP-A                   Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Other Adverse Conditions,
: 11. Have you looked for and found no other seismic conditions that could         Yg NE]     UE&#xfd; adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Question 10: In a seismic event, if light fixture was decoupled from I of its 2 supporting chains, out-of-plane swinging motion (i.e. toward 93EGO-A) would be limited and will not contact the panel. No adverse seismic interaction.
Question 10: In a seismic event, if light fixture was decoupled from I of its 2 supporting chains, out-of-plane swinging motion (i.e. toward 93EGO-A) would be limited and will not contact the panel. No adverse seismic interaction.
gc~Evaluated by: Rick Casella Date: 10/29/12 LCII K%-~~&Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 435 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE] NE] U[Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Generator Control Panel Photographs Note: 93EGP-A Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 436 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YR-7 NEO U[Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 -Instrument and Control Panels Equipment Description EDG A Generator Control Panel Note: Conduit off top of 93EGP-A Note:
gc~
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 437 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NEI U[I Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class' 20 -Instrumentation and Control Panels Equipment Description Emergency Diesel Generator B Control Panel Location:
Evaluated by: Rick Casella                                                           Date: 10/29/12 Al Porch LCII         K%-~~&                                             10129112
Bldg. EG- Floor El. 272 Room, Area Col. 26, Line A1 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 435 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE] NE]   U[
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl-636 Equipment ID No. 93EGP-A           Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Photographs Note: 93EGP-A
Y[ NEI 2. Is the anchorage free of bent, broken, missing or loose hardware?External anchorage is free of bent, broken, missing or loose hardware.Panels need to be removed and anchorage of internal components needs to be checked.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
Anchorage is free of corrosion that is more than mild surface oxidation.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 436 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YR-7 NEO U[
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Anchorage is free of visible cracks in the concrete near the anchors.YEI NE-] UN N/AE]YE NE] uEl N/AE]Y[ N] UI-E] N/AE-1 Enter the equipment class'name from Appendix B: Classes of Equipment.
Seismic Walkdown Checklist (SWC)       SWELl-636 Equipment ID No. 93EGP-A           Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Note: Conduit off top of 93EGP-A                   Note:
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 438 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ NRI- UII Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20 -Instrumentation and Control Panels Equipment Description EmerQencv Diesel Generator B Control Panel 5. Is the anchorage configuration consistent with. plant documentation?
 
YN Nil UI-- N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 437 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NEI   U[I Seismic Walkdown Checklist (SWC)                     SWELl-637 Equipment ID No.         93EGP-B                   Equip. Class' 20 - Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorB Control Panel Location: Bldg. EG-                 Floor El. 272             Room, Area Col. 26, Line A1 Manufacturer, Model, Etc. (optional but recommended)
The anchorage configuration is consistent with the SEWS for 93EGP-B (Rev. 0). The front welding consists of six 1" x 1/8" fillets, the back welding consists of six 1" seam welds plus one 2" corner weld.6. Based on the above anchorage evaluations, is the anchorage free of YN NEIl UEl potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one     Y[    NEI of the 50% of SWEL items requiring such verification)?
Cable from tray I TC456B is overhanging the tray. Will not damage the cabinet in a seismic event 9. Do attached lines have adequate flexibility to avoid damage?YZ NOl U- N/AL YE Nil] U[- N/A[]YZ NO U[I- N/A[-10. Based on the above seismic interaction evaluations, is equipment free YN NE] ULi of potentially adverse seismic interaction effects?)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YEI  NE-] UN N/AE]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 439 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST'FORM Sheet 3 of 5 Status: YZ NE] ULI Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergencv Diesel Generator B Control Panel Other Adverse Conditions
External anchorageis free of bent, broken, missing or loose hardware.
: 11. Have you looked for and found no other seismic conditions that could Y[ NE-1 UE-adversely affect the safety functions of the equipment?
Panels need to be removed and anchorageof internalcomponents needs to be checked.
: 3. Is the anchorage free of corrosion that is more than mild surface               YE NE] uEl    N/AE]
oxidation?
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    N] UI-E] N/AE-anchors?
Anchorage is free of visible cracks in the concrete near the anchors.
1 Enter the equipment class'name from Appendix B: Classes of Equipment.
 
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 438 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ NRI-     UII Seismic Walkdown Checklist (SWC)               SWELl-637 Equipment ID No.       93EGP-B                 Equip. Class 20 - Instrumentation and Control Panels Equipment Description EmerQencv Diesel GeneratorB Control Panel
: 5. Is the anchorage configuration consistent with. plant documentation?           YN Nil UI-- N/A[
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageconfigurationis consistent with the SEWS for 93EGP-B (Rev. 0). The front welding consists of six 1" x 1/8" fillets, the back welding consists of six 1" seam welds plus one 2" corner weld.
: 6. Based on the above anchorage evaluations, is the anchorage free of             YN NEIl   UEl potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?           YZ NOl U-      N/AL
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     YE Nil] U[- N/A[]
and masonry block walls not likely to collapse onto the equipment?
Cable from tray I TC456B is overhanging the tray. Will not damage the cabinet in a seismic event
: 9. Do attached lines have adequate flexibility to avoid damage?                   YZ NO U[I-     N/A[-
: 10. Based on the above seismic interaction evaluations, is equipment free         YN NE] ULi of potentially adverse seismic interaction effects?
                                                                            )
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 439 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST'FORM Sheet 3 of 5 Status: YZ NE] ULI Seismic Walkdown Checklist (SWC)             SWELl-637 Equipment ID No. 93EGP-B                 Equip. Class 20- Instrumentationand Control Panels Equipment Description Emergencv Diesel GeneratorB Control Panel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NE-1 UE-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Koberq I Date: 9/27/12 Pouria Pourqhobadi 9/27/1 9127112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 440 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NFD Ur Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergency Diesel Generator B Control Panel Photographs 0 Note: 93EGP-B Panel 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 441 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF] U-J Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergencv Diesel Generator B Control Panel Note: 93EGP-B Panel base welds.Note:
Evaluated by: Donald Koberq                                           I       Date: 9/27/12 PouriaPourqhobadi                                                        9/27/1 9127112
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 442 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[ NE UN Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emerqencv Diesel Generator A and C Forced Paralleling Panel Location:
 
Bldg. EG Floor El. 272' Room, Area 24.5. A Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 440 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NFD   Ur Seismic Walkdown Checklist (SWC)       SWELl-637 Equipment ID No. 93EGP-B             Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorB Control Panel Photographs 0
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Note: 93EGP-B Panel 0
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[ N[-I of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 441 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF] U-J Seismic Walkdown Checklist (SWC)       SWELl-637 Equipment ID No. 93EGP-B             Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergencv Diesel GeneratorB Control Panel Note: 93EGP-B Panel base welds.                     Note:
Y[E] NEi ULI N/A[-D YE- NEl UN N/AEl 4. Is the anchorage free of visible cracks in the concrete near the anchors?YE: NEJ UN N/AE:
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 443 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEl UN Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel Generator A and C Forced Paralleling Panel 5. Is the anchorage configuration consistent with plant documentation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 442 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[ NE UN Seismic Walkdown Checklist (SWC)               SWELl- 640 Equipment ID No.     93FPAC                 Equip. Class Instrumentation and Control Panels Equipment Description Emerqencv Diesel GeneratorA and C ForcedParallelingPanel Location: Bldg.       EG       Floor El.     272'     Room, Area           24.5. A Manufacturer, Model, Etc. (optional but recommended)
Y[E NEI U[ N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 6. Based on the above anchorage evaluations, is the anchorage free of YE] NEI U[potentially adverse seismic conditions?
Anchorage
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[   N[-I of the 50% of SWEL items requiring such verification)?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[E] NEi ULI N/A[-D
and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface               YE- NEl UN N/AEl oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE] NEl UE- N/A[K YN'NE]UE1 N/AEl YE[ NEI UE- N/A2 YN NEI UE1 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 444 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Yr-D NEI U[Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel Generator A and C Forced Paralleling Panel Other Adverse Conditions
: 4. Is the anchorage free of visible cracks in the concrete near the               YE: NEJ UN N/AE:
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI Un adversely affect the safety functions of the equipment?
anchors?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 443 of 573 0 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEl UN Seismic Walkdown Checklist (SWC)               SWELl- 640 Equipment ID No.       93FPAC                 Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C Forced ParallelingPanel
: 5. Is the anchorage configuration consistent with plant documentation?         Y[E NEI     U[ N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE] NEI     U[
potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YE] NEl UE- N/A[K
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,. YN'NE]UE1 N/AEl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE[    NEI UE- N/A2
: 10. Based on the above seismic interaction evaluations, is equipment free       YN NEI UE1 of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 444 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Yr-D NEI U[
Seismic Walkdown Checklist (SWC)               SWELl- 640 Equipment ID No. 93FPAC                 Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C ForcedParallelingPanel Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       Y[   NEI Un adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Conduits 1 CK402RC and 1 CC421 RE off the top of 93FPAC 1st support is 3' 9" above top of box. This exceeds 3' spacing given in IS-E-05. Not a seismic concern low 'g' levels in EDG switchgear at Elevation 272.Evaluated by: R. Casella " A.G. Porch I Date: 10/26/12 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 445 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE[ NE- U[Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel Generator A and C Forced Paralleling Panel Photographs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 446 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[L- N-] UN Seismic Walkdown Checklist (SWC) SWELl -640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergiency Diesel Generator A and C Forced Paralleling Panel Note: 93FPAC Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 447 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y] NEI U[-Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 -Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Location:
Conduits 1CK402RC and 1CC421 RE off the top of 93FPAC 1st support is 3' 9" above top of box. This exceeds 3' spacing given in IS-E-05. Not a seismic concern low 'g' levels in EDG switchgear at Elevation 272.
Bldg. BR Floor El. 282 Room, Area 12, E Manufacturer, Model, Etc. (optional but recommended)
Evaluated by: R. Casella                   "                                     Date: 10/26/12 A.G. Porch I                                                              10/26/12
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 445 of 573 0 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE[ NE- U[
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Seismic Walkdown Checklist (SWC)       SWELl- 640 Equipment ID No. 93FPAC             Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C Forced ParallelingPanel Photographs
The anchorage is free of corrosion.
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?No concrete.YZ NEI UE]- N/AE1 YZ! NEI U-E] N/A[]Y-E] NEI UE] N/A[
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 446 of 573 ATTACHMENT   9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[L- N-] UN Seismic Walkdown Checklist (SWC)         SWELl - 640 Equipment ID No. 93FPAC               Equip. Class Instrumentation and Control Panels Equipment Description Emergiency Diesel GeneratorA and C Forced ParallelingPanel Note: 93FPAC
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 448 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ ND UMI Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 -Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator 5. Is the anchorage configuration consistent with plant documentation?
 
Yr-] NF-O U-I N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 447 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y] NEI     U[-
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ NI UEI potentially adverse seismic conditions?
Seismic Walkdown Checklist (SWC)               SWELl- 642 Equipment ID No.     93LI-102A               Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Location: Bldg. BR             Floor El. 282           Room, Area       12, E Manufacturer, Model, Etc. (optional but recommended)
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Anchorage
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NEI UD N/AD YO NOl U-I N/AEI YO ND- U[-' N/A[YO NO UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 449 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEil Ur-Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 -Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Other Adverse Conditions
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NZ of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could YE NEIl UL adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YZ NEI    UE]- N/AE1 The anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface               YZ! NEI  U-E] N/A[]
oxidation?
The anchorageis free of corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y-E] NEI UE] N/A[
anchors?
No concrete.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 448 of 573 ATTACHMENT   9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ ND UMI Seismic Walkdown Checklist (SWC)               SWELl- 642 Equipment ID No.       93LI-102A               Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator
: 5. Is the anchorage configuration consistent with plant documentation?         Yr-] NF-O U-I N/A[
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ NI     UEI potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    NEI UD N/AD
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YO NOl U-I N/AEI and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YO ND- U[-' N/A[
: 10. Based on the above seismic interaction evaluations, is equipment free       YO NO UM of potentially adverse seismic interaction effects?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 449 of 573 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEil   Ur-Seismic Walkdown Checklist (SWC)               SWELl- 642 Equipment ID No. 93LI-102A               Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       YE NEIl   UL adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Attached to South side SWEL item 93ECP-A (see photo)Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10/29/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 450 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ Nil U[-]Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 -Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Photographs Note: 93LI-102A (located on 93ECP-A)Note:
Attached to South side SWEL item 93ECP-A (see photo)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 451 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN Nil UI-J Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class' 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Location:
Evaluated by: Rick Casella                                                       Date: 10/29/12 Al Porch                                                                 10/29/12
Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 450 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   Nil U[-]
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)         SWELl- 642 Equipment ID No. 93LI-102A           Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Photographs Note: 93LI-102A (locatedon 93ECP-A)                 Note:
The evaluated item in this SWC is not part of the 50% of the SWEL items requiring anchorage configuration verification.
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The four (4) self-tapping screws are free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 451 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN Nil UI-J Seismic Walkdown Checklist (SWC)                   SWELl-643 Equipment ID No.         93LI-102B                 Equip. Class' 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Location: Bldg. EG                   Floor El. 272'           Room, Area EG Room B, Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEl- NE of the 50% of SWEL items requiring such verification)?
The evaluated item in this SWC is not partof the 50% of the SWEL items requiring anchorageconfiguration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[    NDI  Ur- N/A[-D The four (4) self-tapping screws are free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface             YN NEI    U[-I N/AD-oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Gage/Instrument is attached to a steel panel.YEl- NE Y[ NDI Ur- N/A[-D YN NEI U[-I N/AD-Y-I NEI U['] N/AE 1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y-I NEI U['] N/AE anchors?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 452 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N-- U-I Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator 5. Is the anchorage configuration consistent with plant documentation?
Gage/Instrumentis attached to a steel panel.
YI- NEI UI- N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)*
1 Enter the equipment class name from Appendix B: Classes of Equipment.
Item is not one of the 50% for which an anchorage configuration verification is required.6. Based on the above anchorage evaluations, is the anchorage free of YE NEi UI--potentially adverse seismic conditions?
 
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 452 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N-- U-I Seismic Walkdown Checklist (SWC)                 SWELl-643 Equipment ID No.       93LI-102B               Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 5. Is the anchorage configuration consistent with plant documentation?         YI- NEI UI- N/A[
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)*
Item is not one of the 50% for which an anchorage configuration verification is required.
: 6. Based on the above anchorage evaluations, is the anchorage free of         YE NEi     UI--
potentially adverse seismic conditions?
Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YZ N[il UiE N/AL]
The soft targets are free from impact by nearby equipment or structures.
The soft targets are free from impact by nearby equipment or structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NI-] UE] N/Al]
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YZ N[il UiE N/AL]YZ NI-] UE] N/Al]YE NEI UL] N/A-]YE NFL UiL Attachment C Etginee-ing Report No. JAF-RPT-12-00015 Rev. 0 Page 453 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI UDI Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Other Adverse Conditions
The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 11. Have you looked for and found no other seismic conditions that could YZ NEI U-I adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YE NEI UL] N/A-]
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
The lines attachedto the SWEL item have adequate flexibility to avoid damage.
No additional comments.Evaluated by: Harpreet Ghuman Date: 09/21/2012 V 0912112012 Yaroslaii Los~e V 0/121 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 454 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl UI'Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Photographs Note: Picture of equipment 93L0-102B.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NFL UiL of potentially adverse seismic interaction effects?
Note:
Based on the above seismic interaction evaluations,the equipment is free of potentiallyadverse seismic interaction effects.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 455 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NEil UI-Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Location:
 
Bldg. EG Floor El. 272 Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)
Attachment C        Etginee-ing Report No. JAF-RPT-12-00015 Rev. 0 Page 453 of 573 ATTACHMENT   9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI     UDI Seismic Walkdown Checklist (SWC)             SWELl-643 Equipment ID No. 93LI-102B               Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Other Adverse Conditions
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
: 11. Have you looked for and found no other seismic conditions that could       YZ   NEI U-I adversely affect the safety functions of the equipment?
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE- NE of the 50% of SWEL items requiring such verification)?
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Comments (Additional pages may be added as necessary)
The anchorage is free of corrosion.
No additionalcomments.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?No concrete.Y9 NR] U[I N/A[]Y[D NEi U[- N/AZ!YE] N[-] UE] N/A[
Evaluated by: HarpreetGhuman                                                    Date: 09/21/2012 V                               0912112012 0/121 Yaroslaii Los~e                         V
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 456 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y] NI]I UII Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler 5. Is the anchorage configuration consistent with plant documentation?
 
YEI-I NEI ULi N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 454 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl   UI' Seismic Walkdown Checklist (SWC)         SWELl-643 Equipment ID No. 93LI-102B           Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Photographs Note: Picture of equipment 93L0-102B.               Note:
: 6. Based on the above anchorage evaluations, is the anchorage free of YEE Nil ULi potentially adverse seismic conditions?
 
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?(See Photo)8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 455 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NEil UI-Seismic Walkdown Checklist (SWC)               SWELl- 646 Equipment ID No. 93LOE-1A                 Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Location: Bldg. EG             Floor El. 272           Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NEI U[i N/AEI YE NEI UDI N/ADl YEl NDi UiD N/AD-YE N[I Uil Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 457 of 573 ATTACHMENT 9.6 Sheet 3 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: Y[ NEI U-III Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Other Adverse Cond itions 11. Have you looked for and found no other seismic conditions that could adversely affect the safety functions of the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
YE NO UF Comments (Additional pages may be added as necessary)
Anchorage
Evaluated by: Rick Casella C2~(G~Date: 10/29/12 Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 458 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE Nn' U-Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Photographs Note: 93LOE-IA (large rectangular component in center of picture)Note: 93LOE-1A (long rectangular component at top)
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE- NE of the 50% of SWEL items requiring such verification)?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 459 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NI U-L Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Note: 93LOE-1A (it is the rectangular shaped component mounted on angle)Note:
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y9 NR] U[I N/A[]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0-Page 460 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NM U[--Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Classi 21 -Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Location:
The anchorageis free of bent, broken, missing or loose hardware.
Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[D NEi U[-    N/AZ!
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
oxidation?
Additional space is provided at the end of this checklist for documenting other comments;Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI No of the 50% of SWEL items requiring such verification)?
The anchorageis free of corrosion.
: 2. Is the anchorage free of bent, broken, missing or Ioosehardware?
: 4. Is the anchorage free of visible cracks in the concrete near the               YE] N[-] UE] N/A[
The anchorage is free of bent broken, missing, or loose hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
anchors?
The anchorage is free of corrosion.
No concrete.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Y[ NEI uEr N/AE-Y[ NE-1 UE:] N/AE-]YEI N[:E UE- N/A['Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 461 of 573 01 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U--Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-1B Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler 5. Is the anchorage configuration consistent with plant documentation?
Attachment C          Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 456 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y]   NI]I UII Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No.       93LOE-1A               Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler
YE-] N-] U-- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 5. Is the anchorage configuration consistent with plant documentation?         YEI-I NEI ULi N/A[
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEi U[]potentially adverse seismic conditions?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 6. Based on the above anchorage evaluations, is the anchorage free of           YEE Nil ULi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YE NEI U[i N/AEI (See Photo)
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NEI UDI    N/ADl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YEl NDi UiD N/AD-
: 10. Based on the above seismic interaction evaluations, is equipment free       YE N[I Uil of potentially adverse seismic interaction effects?
 
Attachment C      Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 457 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   NEI U-III Seismic Walkdown Checklist (SWC)             SWELl- 646 Equipment ID No. 93LOE-1A                 Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Other Adverse Cond itions
: 11. Have you looked for and found no other seismic conditions that could     YE NO UF adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Evaluated by: Rick Casella C2~(G~                               Date: 10/29/12 Al Porch                                                                 10129112
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 458 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE Nn' U-Seismic Walkdown Checklist (SWC)       SWELl- 646 Equipment ID No. 93LOE-1A           Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Photographs Note: 93LOE-IA (large rectangular                   Note: 93LOE-1A (long rectangularcomponent component in center of picture)                    at top)
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 459 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NI     U-L Seismic Walkdown Checklist (SWC)       SWELl- 646 Equipment ID No. 93LOE-1A           Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Note: 93LOE-1A (it is the rectangularshaped        Note:
component mounted on angle)
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0-Page 460 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NM U[--
Seismic Walkdown Checklist (SWC)                   SWELl-647 Equipment ID No.       93LOE-IB                 Equip. Classi 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Location: Bldg. EG                 Floor El. 272             Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments; Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI No of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or Ioosehardware?               Y[    NEI uEr  N/AE-The anchorageis free of bent broken, missing, or loose hardware
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[    NE-1 UE:] N/AE-]
oxidation?
The anchorageis free of corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the               YEI N[:E UE- N/A[
anchors?
'Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 461 of 573 01 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NEI   U--
Seismic Walkdown Checklist (SWC)               SWELl-647 Equipment ID No.     93LOE-1B                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler
: 5. Is the anchorage configuration consistent with plant documentation?         YE-] N-] U-- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[   NEi U[]
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YS NE] UE]- N/A[-
Soft targets in this SWEL item are gauges. They are free from any impact by nearby equipment.
Soft targets in this SWEL item are gauges. They are free from any impact by nearby equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NEI U[] N/AE-1 and masonry block walls not likely to collapse onto the equipment?
The north wall of the room, is a masonary block wall but it has been enhanced according to DC# D1-96-011, Rev 0 as part IPEEE evaluations.
The north wall of the room, is a masonary block wall but it has been enhanced accordingto DC# D1-96-011, Rev 0 as part IPEEE evaluations.
: 9. Do attached lines have adequate flexibility to avoid damage?The attached line have adequate flexibility.
: 9. Do attached lines have adequate flexibility to avoid damage?                 YN NEI    U[]  N/A[:]
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of any adverse seismic interaction.
The attached line have adequate flexibility.
YS NE] UE]- N/A[-YZ NEI U[] N/AE-1 YN NEI U[]N/A[:]YIE NEI UE]
: 10. Based on the above seismic interaction evaluations, is equipment free       YIE NEI UE]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev., 0 Page 462 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NE] U-]Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Other Adverse Conditions
of potentially adverse seismic interaction effects?
: 11. Have you looked for and found no other seismic conditions that could YN N[i ULI adversely affect the safety functions of the equipment?
The equipment is free of any adverse seismic interaction.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev., 0 Page 462 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NE] U-]
Seismic Walkdown Checklist (SWC)             SWELl-647 Equipment ID No. 93LOE-IB                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YN N[i     ULI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
I/Evaluated by: Pouria Pourcqhobadi Date: 9/21/12 Donald Koberci 9/2 1/1.9121112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 463 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0 Nr-] UL--Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-1B Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Photographs Note: 93LOE-1B EDG B Lube Oil Cooler Note: 93LOE-IB EDG B Lube Oil Cooler 0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 464 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF-] UL-]Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Note: 93LOE-1B EDG B Lube Oil Cooler Note:
I/
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 465 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NEI[ U-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-Cl Equip. Class Horizontal Pumps Equipment Description Emergency Diesel Generator C Fuel Oil Transfer Pump C1 Location:
Evaluated by: Pouria Pourcqhobadi                                               Date: 9/21/12 9/2 1/1 Donald Koberci                                                          .9121112
Bldg. EG Floor El. 272' Room, Area 24.5i A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 463 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0 Nr-] UL--
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[ Nil of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl-647 Equipment ID No. 93LOE-1B           Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Photographs Note: 93LOE-1B EDG B Lube Oil Cooler               Note: 93LOE-IB EDG B Lube Oil Cooler 0
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage contains all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
The anchorage has mild oxidation on its surface. There is no structural concern 4. Is the anchorage free of visible cracks in the concrete neat the anchors?There are no cracks in the concrete near the anchors YN NI-] UE[ N/A--YN NE] U[I] N/AL]YN NER U[] N/AE-]
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 464 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF-] UL-]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 466 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel Generator C Fuel Oil Transfer Pump C1 5. Is the anchorage configuration consistent with plant documentation?
Seismic Walkdown Checklist (SWC)       SWELl-647 Equipment ID No. 93LOE-IB           Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Note: 93LOE-1B EDG B Lube Oil Cooler               Note:
YE NFi ULi N/A-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.12-99, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of YE Nil ULi potentially adverse seismic conditions?
 
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 465 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NEI[ U-Seismic Walkdown Checklist (SWC)               SWELl- 658 Equipment ID No.     93P1-Cl                 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil TransferPump C1 Location: Bldg.       EG       Floor El. 272'     Room, Area           24.5i A4 Manufacturer, Model, Etc. (optional but recommended)
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
9, Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YN NEI- Ui- N/All]YN NEi U[-I N/AF]YE Nil UL] N/AZ!YN NEI U-I Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 467 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YN NEIl U-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel Generator C Fuel Oil Transfer Pump C1 Other Adverse Conditions
Anchorage
: 11. Have you looked for and found no other seismic conditions that could YN NEI UI--adversely affect the safety functions of the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[   Nil of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YN NI-]    UE[ N/A--
The anchorage contains all necessary hardware
: 3. Is the anchorage free of corrosion that is more than mild surface             YN NE] U[I] N/AL]
oxidation?
The anchorage has mild oxidation on its surface. There is no structural concern
: 4. Is the anchorage free of visible cracks in the concrete neat the               YN NER U[] N/AE-]
anchors?
There are no cracks in the concrete near the anchors
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 466 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NEI U-I Seismic Walkdown Checklist (SWC)               SWELl- 658 Equipment ID No.       93P1-C1                 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil Transfer Pump C1
: 5. Is the anchorage configuration consistent with plant documentation?         YE NFi   ULi N/A-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
(Ref. 1.12-99, associated SEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free of           YE Nil ULi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YN NEI- Ui- N/All]
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NEi U[-I N/AF]
and masonry block walls not likely to collapse onto the equipment?
9, Do attached lines have adequate flexibility to avoid damage?               YE Nil UL] N/AZ!
: 10. Based on the above seismic interaction evaluations, is equipment free       YN NEI    U-I of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 467 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YN NEIl U-Seismic Walkdown Checklist (SWC)             SWELl- 658 Equipment ID No. 93P1-C1                 Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel GeneratorC Fuel Oil TransferPump C1 Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YN NEI     UI--
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: R. Casella /Date: 10/26/12 A.G. Porch 1 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 468 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEIl UE]Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel Generator C Fuel Oil Transfer Pump C1 Photographs Note: 93P1-Co Note: 93PI-Cl Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 469 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEI UI-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel Generator C Fuel Oil Transfer PumD C1 Note: 93P1-C1 anchorage Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 470 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI] UrI-I Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-DI Equip. Class' 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Location:
Evaluated by: R. Casella /                                                     Date: 10/26/12 A.G. Porch                                                               10/26/12
Bldg. EG Floor El. 272' Room, Area EG Room D, Col. 26.5, Line A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 468 of 573 ATrACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEIl   UE]
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl- 658 Equipment ID No. 93P1-C1             Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil TransferPump C1 Photographs Note: 93P1-Co                                       Note: 93PI-Cl
The item is one of the 50% of SWEL items requiring anchorage* configuration verification.
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 469 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEI     UI-Seismic Walkdown Checklist (SWC)       SWELl- 658 Equipment ID No. 93P1-C1             Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel GeneratorC Fuel Oil Transfer PumD C1 Note: 93P1-C1 anchorage
Anchorage is free of corrosion that is more than mild surface oxidation.
 
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The anchorage is free of visible cracks in the concrete near the anchors.YE N[:]YN ND-I U-- N/AD-Y[ NDI UIE N/AD--Y[ NDl U-- N/ADl I Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 470 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI] UrI-I Seismic Walkdown Checklist (SWC)                     SWELl-660 Equipment ID No.         93P1-DI                 Equip. Class' 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Location: Bldg. EG                   Floor El. 272'           Room, Area EG Room D, Col. 26.5, Line A4 Manufacturer, Model, Etc. (optional but recommended)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 471 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ Nil U[]Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-D1 Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Y[ NEI USI N/AL](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
The configuration of the six (6), 1/2" Phillips studs is consistent with the SEWS documentation for equipment 93P1-A 1 (same as 93P1-D 1), Rev. 0 and drawing 1.12-99, Rev. 4.6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI U[-]potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE N[:]
of the 50% of SWEL items requiring such verification)?
The item is one of the 50% of SWEL items requiringanchorage
        *configuration verification.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YN ND-I U-- N/AD-The anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[    NDI UIE N/AD--
oxidation?
Anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[    NDl U-- N/ADl anchors?
The anchorageis free of visible cracks in the concrete near the anchors.
I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C           Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 471 of 573 0 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ Nil U[]
Seismic Walkdown Checklist (SWC)                 SWELl-660 Equipment ID No.       93P1-D1                 Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil TransferPump D1
: 5. Is the anchorage configuration consistent with plant documentation?           Y[   NEI USI N/AL]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The configurationof the six (6), 1/2" Phillips studs is consistent with the SEWS documentation for equipment 93P1-A 1 (same as 93P1-D1),
Rev. 0 and drawing 1.12-99, Rev. 4.
: 6. Based on the above anchorage evaluations, is the anchorage free of             YZ NEI U[-]
potentially adverse seismic conditions?
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Interaction Effects
There are no soft targets on the equipment.
: 7. Are soft targets free from impact by nearby equipment or structures?         YE- NE] UE] N/AO There are no soft targets on the equipment.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     Y[    NE] UE] N/AL]
The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?The lines attached to the SWEL item have adequate flexibility to avoid damage.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.YE- NE] UE] N/AO Y[ NE] UE] N/AL]YJ NE] UL] N/AL]YZ N[] UE Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 472 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NO UIT, Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-D1 Equip. Class 05-Horizontal Pump Equipment Description EDG 0 Fuel Oil Transfer Pump D1 Other Adverse Conditions
The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.
: 11. Have you looked for and found no other seismic conditions that could YN NEI ULI adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YJ    NE] UL] N/AL]
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.Comments (Additional pages may be added as necessary)
The lines attachedto the SWEL item have adequate flexibility to avoid damage.
No additional comments.Evaluated by: Harpreet Ghuman bM -Yaroslav Losev Date: 09/21/2012 09/21/2012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 473 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NII UII--Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-Dl Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Photographs Note: Picture of equipment 93P1-DI.Note:
: 10. Based on the above seismic interaction evaluations, is equipment free         YZ N[] UE of potentially adverse seismic interaction effects?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 474 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NR UR Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class 06 -Vertical Pumps Equipment Description EDG A Circulating Lube Oil Pump Location:
Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.
Bldg. EG Floor El. 272 Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 472 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NO       UIT, Seismic Walkdown Checklist (SWC)             SWELl-660 Equipment ID No. 93P1-D1                 Equip. Class 05-Horizontal Pump Equipment Description EDG 0 Fuel Oil TransferPump D1 Other Adverse Conditions
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[-I NM of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could     YN NEI   ULI adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?93P-2A (SWEL 1-662) is not anchored.
No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.
It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Comments (Additional pages may be added as necessary)
93P-2A (SWEL 1-662) is not anchored.
No additionalcomments.
It is connected to its motor which is bolted, but the pump is in-line with no anchorage.
Evaluated by: HarpreetGhuman    bM                 -                           Date: 09/21/2012 Yaroslav Losev                                                          09/21/2012
of its own.4. Is the anchorage free of visible cracks in the concrete near the anchors?No concrete.Y[I- Nil Ui] N/AM YEI NE] U[] WN/A Y[] NEI u-1 N/A0 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 475 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI UI-]Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 -Vertical Pumps_Equipment Description EDG A CirculatinQ Lube Oil Pump 5. Is the anchorage configuration consistent with plant documentation?
 
Y-I N[-] Ur- N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 473 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NII   UII--
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[] UE]potentially adverse seismic conditions?
Seismic Walkdown Checklist (SWC)         SWELl-660 Equipment ID No. 93P1-Dl             Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Photographs Note: Picture of equipment 93P1-DI.                 Note:
93P-2A (SWEL 1-662) is not anchored.
 
It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 474 of 573 0
Flex conduit off motor.8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NR UR Seismic Walkdown Checklist (SWC)               SWELl- 662 Equipment ID No.     93P-2A                 Equip. Class 06 - Vertical Pumps Equipment Description EDG A CirculatingLube Oil Pump Location: Bldg. EG             Floor El. 272           Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)
: 9. Do attached lines haveadequate flexibility to avoid damage?Y[ NE:] U[] N/A[]Y[ NE] UE] N/A[-]YE NEI UE] N/AR-10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 476 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NW- U[-Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 -Vertical Pumps._Equipment Description EDG A Circulating Lube Oil Pump Other Adverse Conditions
Anchorage
: 11. Have you looked for and found no other seismic conditions that could Y[ NWJ UM adversely affect the safety functions of the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[-I NM of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[I- Nil Ui] N/AM 93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.
: 3. Is the anchorage free of corrosion that is more than mild surface             YEI NE] U[] WN/A oxidation?
93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage.of its own.
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[] NEI u-1 N/A0 anchors?
No concrete.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 475 of 573 0 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NEI UI-]
Seismic Walkdown Checklist (SWC)                 SWELl- 662 Equipment ID No.       93P-2A                 Equip. Class_06 - Vertical Pumps_
Equipment Description EDG A CirculatinQ Lube Oil Pump
: 5. Is the anchorage configuration consistent with plant documentation?         Y-I N[-] Ur-   N/A[
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y[   N[] UE]
potentially adverse seismic conditions?
93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    NE:] U[] N/A[]
Flex conduit off motor.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NE] UE] N/A[-]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines haveadequate flexibility to avoid damage?                 YE NEI UE] N/AR-
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 476 of 573 0 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   NW- U[-
Seismic Walkdown Checklist (SWC)               SWELl- 662 Equipment ID No. 93P-2A                   Equip. Class_06 - Vertical Pumps._
Equipment Description EDG A Circulating Lube Oil Pump Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could       Y[   NWJ UM adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
See Photos C &#xa3;i426~~Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10/29/12 Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 477 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE ND1 U-I!Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 -Vertical Pumps Equipment Description EDG A Circulatinq Lube Oil Pump Photographs Note: 93P-2A Note: 93P-2A Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 478 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE ND-] U-Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 -Vertical Pumps.Equipment Description EDG A Circulatinq Lube Oil Pump 0 Note:
See Photos Evaluated by: Rick Casella C &#xa3;i426~~                           Date: 10/29/12 10/29/12 Al Porch Al Porch                                                          10129112
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 479 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE] UEI-Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class' 5- Horizontal Pump Equipment Description Emergencv Diesel Generator B Circulating Lube Oil Pump Location:
 
Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 477 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE ND1     U-I!
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A               Equip. Class_06 - Vertical Pumps Equipment Description EDG A Circulatinq Lube Oil Pump Photographs Note: 93P-2A                                         Note: 93P-2A
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Yr--] NZ of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 478 of 573 ATTACHMENT   9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE   ND-] U-Seismic Walkdown Checklist (SWC)         SWELl- 662 Equipment ID No. 93P-2A               Equip. Class_06 - Vertical Pumps.
The anchorage is free of corrosion.
Equipment Description EDG A CirculatinqLube Oil Pump 0
: 4. Is the anchorage free of Visible cracks in the concrete near the anchors?No concrete YZ NE]l U-E N/AZ-YZ NEI UE- N/AE" YEI NEI UE- N/AZ' Enter the equipment class name from Appendix B: Classes of Equipment.
Note:
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 480 of 573.ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status. Y[ NEI- UE Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- Horizontal Pump Equipment Description Emergency Diesel Generator B Circulating Lube Oil Pump 5. Is the anchorage configuration consistent with plant documentation?
 
YEI NEIl Url N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 479 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE] UEI-Seismic Walkdown Checklist (SWC)                     SWELl-663 Equipment ID No.         93P-2B                   Equip. Class' 5- HorizontalPump Equipment Description Emergencv Diesel GeneratorB CirculatingLube Oil Pump Location: Bldg. EG                   Floor El. 272             Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)
: 6. Based on the above anchorage evaluations, is the anchorage free of Y] NEIr UI-potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects.7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
The soft targets are free from impact by nearby equipment and structures.
: 1. Is the anchorage configuration verification required (i.e., is the item one     Yr--] NZ of the 50% of SWEL items requiring such verification)?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YZ NE]l U-E  N/AZ-The anchorageis free of bent, broken, missing or loose hardware.
The overhead equipment and distribution systems are not likely to collapse onto the equipment.
: 3. Is the anchorage free of corrosion that is more than mild surface               YZ NEI    UE- N/AE" oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
The anchorageis free of corrosion.
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.YEI NE] UEl N/AEl YO NE: u[-- N/AE-YO NEI UE N/A YE N[IUE1 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 481 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ N[] U[-/Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- Horizontal Pump Equipment Description Emergency Diesel Generator B Circulating Lube Oil Pump Other Adverse Conditions
: 4. Is the anchorage free of Visible cracks in the concrete near the               YEI NEI   UE- N/AZ anchors?
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI UI-adversely affect the safety functions of the equipment?
No concrete
' Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 480 of 573.
ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status. Y[   NEI- UE Seismic Walkdown Checklist (SWC)               SWELl-663 Equipment ID No.       93P-2B                 Equip. Class 5- HorizontalPump Equipment Description Emergency Diesel GeneratorB CirculatingLube Oil Pump
: 5. Is the anchorage configuration consistent with plant documentation?         YEI NEIl Url N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y] NEIr UI-potentially adverse seismic conditions?
Interaction Effects
    .7. Are soft targets free from impact by nearby equipment or structures?         YEI NE] UEl N/AEl The soft targets are free from impact by nearby equipment and structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YO NE: u[-- N/AE-and masonry block walls not likely to collapse onto the equipment?
The overhead equipment and distributionsystems are not likely to collapse onto the equipment.
: 9. Do attached lines have adequate flexibility to avoid damage?                 YO NEI    UE N/A The attachedlines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE N[IUE1 of potentially adverse seismic interaction effects?
The equipment is free of potentially adverse seismic interaction effects.
 
Attachment C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 481 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   N[] U[-/
Seismic Walkdown Checklist (SWC)               SWELl-663 Equipment ID No. 93P-2B                   Equip. Class 5- HorizontalPump Equipment Description Emergency Diesel GeneratorB CirculatingLube Oil Pump Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEI UI-adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Kober q Pouria Pourghobadi
Evaluated by: Donald Koberq                                                    Date: 9/21/12 Pouria Pourghobadi        ,                                            9/21/12
, Date: 9/21/12 9/21/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 482 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NEI ULI Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- Horizontal Pump Equipment Description Emergency Diesel Generator B Circulating Lube Oil Pump Photographs Note: 93P-2B Pump Note:
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 483 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NE] U[--Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 -Horizontal Pumps Equipment Description EDG A Fuel Oil Pump Location:
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 482 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   NEI ULI Seismic Walkdown Checklist (SWC)       SWELl-663 Equipment ID No. 93P-2B             Equip. Class 5- Horizontal Pump Equipment Description Emergency Diesel GeneratorB Circulating Lube Oil Pump Photographs Note: 93P-2B Pump                                   Note:
Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 483 of 573 ATTACHMENT     9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NE] U[--
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)               SWELl- 670 Equipment ID No.     93P-4A                 Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump Location: Bldg. EG             Floor El. 272           Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y-I NZ of the 50% of SWEL items requiring such verification)?
Dwg not available under 93P-3A (Not used for anchorage)
Dwg not available under 93P-3A (Not used for anchorage)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage was free of bent, broken, missing and loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YZ NEI    Uil N/AI-]
No corrosion was evident 4. Is the anchorage free of visible cracks in the concrete near the anchors?There is no concrete Y-I NZ YZ NEI Uil N/AI-]Y[ NEI U[:] N/AZ3 YEIl NE]i UE] N/AN Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 484 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ ND U0I Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 -Horizontal Pumps Equipment Description EDG A Fuel Oil Pump 5. Is the anchorage configuration consistent with plant documentation?
Anchorage was free of bent, broken, missing and loose hardware.
Yi-] Nr- ULI N/A[9 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[    NEI U[:] N/AZ3 oxidation?
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NDI U[]potentially adverse seismic conditions?
No corrosion was evident
: 4. Is the anchorage free of visible cracks in the concrete near the               YEIl NE]i UE] N/AN anchors?
There is no concrete
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 484 of 573 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   ND   U0I Seismic Walkdown Checklist (SWC)                 SWELl- 670 Equipment ID No.       93P-4A                 Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump
: 5. Is the anchorage configuration consistent with plant documentation?         Yi-] Nr-   ULI N/A[9 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y[     NDI U[]
potentially adverse seismic conditions?
Anchorage is free of potentially adverse seismic conditions.
Anchorage is free of potentially adverse seismic conditions.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Interaction Effects
Protected by superstructure above pump.8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?(See #7 above)9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ ND: UD- N/A[D]Y[ NDI uD- N/AD-]YZ ND- u[-] N/AD1 Y[ NEI U[-
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    ND: UD- N/A[D]
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 485 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NE ULI Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 -Horizontal Pumps Equipment Description EDG A Fuel Oil Pump Other Adverse Conditions
Protectedby superstructureabove pump.
: 11. Have you looked for and found no other seismic conditions that could YN NE:1 Ur-adversely affect the safety functions of the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   Y[    NDI uD- N/AD-]
Comments (Additional pages may be added as necessary)(Photos)Evaluated by: Rick Casella Date: 10/29/12 LC~, K~&Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 486 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NFI U-I Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 -Horizontal Pumps Equipment Description EDG A Fuel Oil Pump Photoaraphs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 487 of 573 ATTACHMENT 9.6 Sheet 5 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: YZ NFI] Ur-]Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 -Horizontal Pumps Eauipment DescriDtion EDG A Fuel Oil PumD Note: 93P-4A (could not get any closer picture of anchorage)
and masonry block walls not likely to collapse onto the equipment?
Note:
(See #7 above)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 488 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI UE]Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class' 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Location:
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ ND- u[-] N/AD1
Bldg. EG Floor El. 272 Room, Area C: 26.5. L: A4 Manufacturer, Model, Etc. (optional but recommended)
: 10. Based on the above seismic interaction evaluations, is equipment free       Y[    NEI U[-
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
of potentially adverse seismic interaction effects?
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
YO] NM 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 485 of 573 0 ATTACHMENT 9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[   NE ULI Seismic Walkdown Checklist (SWC)             SWELl- 670 Equipment ID No. 93P-4A                   Equip. Class 05 - Horizontal Pumps Equipment Description EDG A Fuel Oil Pump Other Adverse Conditions
The anchorage is free of corrosion.
: 11. Have you looked for and found no other seismic conditions that could     YN   NE:1 Ur-adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?No concrete.-
Comments (Additional pages may be added as necessary)
The equipment is mounted on the generator skid.YO N[-] Ur] N/A[-]Y[ NE] UE] N/AE]YE] N[E] UE] N/A]I Enter the equipment class name from Appendix B: Classes of Equipment.
(Photos)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 489 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI U[-]Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_2 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump 5. Is the anchorage configuration consistent with plant documentation?
Evaluated by: Rick Casella                                                       Date: 10/29/12 Al Porch LC~,         K~&                                             10129112
Y[-I NEI UE] N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
 
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NE] UiI potentially adverse seismic conditions?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 486 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NFI     U-I Seismic Walkdown Checklist (SWC)       SWELl- 670 Equipment ID No. 93P-4A             Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump Photoaraphs
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
 
8, Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 487 of 573 ATTACHMENT   9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NFI] Ur-]
9, Do attached lines have adequate flexibility to avoid damage?10. Based'on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YEi NE] UM] N/A[YE NEI UE] N/AE]YN NEI UE] N/AEI YM NEI u--2 Enter the equipment class name from Appendix B: Classes of Equipment.
Seismic Walkdown Checklist (SWC)       SWELl- 670 Equipment ID No. 93P-4A             Equip. Class 05 - Horizontal Pumps Eauipment DescriDtion EDG A Fuel Oil PumD Note: 93P-4A (could not get any closer picture     Note:
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 490 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NE] Un Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_3 5- Horizontal Pumps Equiipment Description EDG B Fuel Oil Pump Other Adverse Conditions
of anchorage)
: 11. Have you looked for and found no other seismic conditions that could YN NEI UI--adversely affect the safety functions of the equipment?
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 488 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI   UE]
Seismic Walkdown Checklist (SWC)                     SWELl-671 Equipment ID No.         93P-4B                   Equip. Class' 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Location: Bldg. EG                   Floor El. 272             Room, Area C: 26.5. L: A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one     YO] NM of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YO N[-] Ur] N/A[-]
The anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface               Y[    NE] UE] N/AE]
oxidation?
The anchorageis free of corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the               YE] N[E] UE] N/A]
anchors?
No concrete.-The equipment is mounted on the generatorskid.
I Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 489 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI   U[-]
Seismic Walkdown Checklist (SWC)                   SWELl-671 Equipment ID No.         93P-4B                   Equip. Class_2 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump
: 5. Is the anchorage configuration consistent with plant documentation?           Y[-I NEI   UE] N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of             Y[   NE] UiI potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YEi NE] UM] N/A[
8, Are overhead equipment, distribution systems, ceiling tiles and lighting,     YE NEI UE] N/AE]
and masonry block walls not likely to collapse onto the equipment?
9, Do attached lines have adequate flexibility to avoid damage?                 YN NEI UE] N/AEI
: 10. Based'on the above seismic interaction evaluations, is equipment free         YM NEI    u--
of potentially adverse seismic interaction effects?
2 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 490 of 573 ATTACHMENT       9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   NE] Un Seismic Walkdown Checklist (SWC)                   SWELl-671 Equipment ID No.         93P-4B                   Equip. Class_3 5- Horizontal Pumps Equiipment Description EDG B Fuel Oil Pump Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could         YN NEI UI--
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Pump missing equipment tag. The issue was brought to site personnel attention immediately.
Pump missing equipment tag. The issue was brought to site personnel attention immediately.
Evaluated by: Pouria Evaluated by: Pouria PourQhobadi Donald Kobera Date: 9/21/12 9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.
Evaluated by: Pouria Evaluated by: PouriaPourQhobadi                                                      Date: 9/21/12 Donald Kobera                                                              9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 491 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NR UM-1 Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_4 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Photographs Note: EDG B Fuel Oil Pump Note: 4 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 492 of 573 ATTACHMENT 9.6 Sheet I of 5 k SEISMIC WALKOOWN CHECKLIST FORM Status: Y[ NE] U-Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description EDG A Jacket Water Expansion Tank Location:
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 491 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NR UM-1 Seismic Walkdown Checklist (SWC)                   SWELl-671 Equipment ID No.         93P-4B                   Equip. Class_4 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Photographs Note: EDG B Fuel Oil Pump                                         Note:
Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
4 Enter the equipment class name from Appendix B: Classes of Equipment.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 492 of 573 ATTACHMENT 9.6                                                               k SEISMIC WALKOOWN CHECKLIST FORM Sheet I of 5 Status: Y[   NE] U-Seismic Walkdown Checklist (SWC)               SWELl- 674 Equipment ID No.     93TK-1A                 Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Jacket Water Expansion Tank Location: Bldg. EG             Floor El. 272           Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)
YE[ NO 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
No corrosion evident.4. Is the anchorage free of visible cracks in the concrete near the anchors?There is-no concrete.YM NEI UE- N/AE[YO NE: UE- N/AE[Y[E] NE:] UE- N/AM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 493 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NiI UI--1 Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-IA Equip. Class_21 -Tanks and Heat Exchangers Equipment Description
Anchorage
: 5. Is the anchorage configuration consistent with plant documentation?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE[  NO of the 50% of SWEL items requiring such verification)?
YEI N[il UZ1 N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YM NEI    UE- N/AE[
: 6. Based on the above anchorage evaluations, is the anchorage free of YN Nil UI potentially adverse seismic conditions?
The anchorage is free of bent, broken, missing or loose hardware.
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 3. Is the anchorage free of corrosion that is more than mild surface             YO NE: UE- N/AE[
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ N[il ULi N/A[-]YN NEI' UI1 N/AL]YZ N[] Ul] N/A--YN N[] U[]
No corrosion evident.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 494 of 573 ATTACHMENT 9.6 Sheet 3 of 5 SEISMIC WALKOOWN CHECKLIST FORM Status: YZ NEI. ULI Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip, Class_21 -Tanks and Heat Exchangers Equipment Description Other Adverse Conditions
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[E] NE:] UE- N/AM anchors?
: 11. Have you looked for and found no other seismic conditions that could adversely affect the safety functions of the equipment?
There is-no concrete.
YN N[-]UM Comments (Additional pages may be added as necessary)
 
Tank well supported; no interaction effects noted. Mounted on diesel skid / frame.P t e2 2~A-~L~Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 495 of 573 ATTACHMENT 9.6 Sheet 4 of 5 SEISMIC WALKDOWN CHECKLIST FORM Status: Y[ Nn- U-iJ Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description Photographs Note: 93TK-IA shown on EDG A unit Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 496 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEIr Ur]Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 -Tanks and Heat Exchangers Equipment Description Note: 93TK-IA underside Note:
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 493 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NiI     UI--1 Seismic Walkdown Checklist (SWC)               SWELl- 674 Equipment ID No.       93TK-IA                 Equip. Class_21 - Tanks and Heat Exchangers Equipment Description
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 497 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI URi--Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-1B Equip. Class' 21 -Tanks and Heat Exchanqers Equipment Description Emergency Diesel Generator B Jacket Water Expansion Tank Location:
: 5. Is the anchorage configuration consistent with plant documentation?         YEI N[il UZ1 N/A[
Bldg. EG Floor El.. 272 Room, Area Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
: 6. Based on the above anchorage evaluations, is the anchorage free of           YN Nil UI potentially adverse seismic conditions?
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YI-] NO of the 50% of SWEL items requiring such verification)?
N/A Interaction Effects
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    N[il ULi N/A[-]
The anchorage is free of corrosion that is more than mild surface oxidation.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NEI' UI1 N/AL]
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?YN NDI U[I N/AD-YE NDI U[: N/AD: YD'- NDl UDI N/A[IEnter the equipment class name from Appendix B: Classes of Equipment.
and masonry block walls not likely to collapse onto the equipment?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 498 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE ND UI&#xfd;Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-IB Equip. Class_2 21 -Tanks and Heat Exchangers Equipment Description Emerqencv Diesel Generator B Jacket Water Expansion Tank 5. Is the anchorage configuiration consistent with plant documentation?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YZ N[] Ul] N/A--
YLI NEI UE- N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 10. Based on the above seismic interaction evaluations, is equipment free       YN N[] U[]
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NI ULiD potentially adverse-seismic conditions?
of potentially adverse seismic interaction effects?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
 
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 494 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKOOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI. ULI Seismic Walkdown Checklist (SWC)             SWELl- 674 Equipment ID No. 93TK-1A                  Equip, Class_21 - Tanks and Heat Exchangers Equipment Description Other Adverse Conditions
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE NEI UE N/AE-YZ NEI UE- N/AAE7 Y[ NEI UE N/AAE-YO NE uEr 2 Enter the equipment class name from Appendix B: Classes of Equipment.
: 11. Have you looked for and found no other seismic conditions that could     YN N[-]UM adversely affect the safety functions of the equipment?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 499 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] U[D1 Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-IB Equip. Class_3 21 -Tanks and Heat Exchangers Equipment Description Emergencv Diesel Generator B Jacket Water Expansion Tank Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could Y[ NE-1 UF--adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Pouria Pourghobadi Donald Koberaq Date: 9/21/12 9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.
Tank well supported; no interactioneffects noted. Mounted on diesel skid / frame.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 500 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NZ- UI--Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-1B Equip. Class_4 21 -Tanks and Heat Exchangers Equipment Description Emergency Diesel Generator B Jacket Water Expansion Tank Photographs Note: 93TK-IB Front view Note: 93TK-IB Side view 4 Enter the equipment class name from Appendix B: Classes of Equipment.
Evaluated by: Rick Casella Pte2        2~A-~L~
Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 501 of 573 0 A.nrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y[ NEI Ur-Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Location:
Date: 10/29/12 Al Porch                                                                  10129112
Bldg. EG Floor El. 272 Room, Area 24,A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 495 of 573 ATTACHMENT  9.6                                              SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y[  Nn- U-iJ Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A        Equip. Class_21 - Tanks and Heat Exchangers Equipment Description Photographs Note: 93TK-IA shown on EDG A unit
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[, NEI of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?'Anchorage contains all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 496 of 573 ATTACHMENT 9.6                                                SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEIr Ur]
Anchorage contains no corrosion 4. Is the anchorage free of visible cracks in the concrete near the anchors?Hairline cracks ( @ x) at anchors primarily at top of concrete pedestal (refer to 93TK-7B and CR-JAF-2012-06090)
Seismic Walkdown Checklist (SWC)  SWELl- 674 Equipment ID No. 93TK-1A      Equip. Class_21 - Tanks and Heat Exchangers Equipment Description Note: 93TK-IA underside                      Note:
YZ N[: Ui- N/A[-D YZ ND U0iD N/ADl YDI NZ UDl N/AD-Aita6hment C Entgineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 502 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] Ufi Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 -Tank&#xfd; and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank 5. Is the anchorage configuration consistent with plant documentation?
 
Y[ NEI U-I N/A-](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.12-128, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of Y Z NEl UEi potentially adverse seismic conditions?
Attachment C        Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 497 of 573 ATTACHMENT 9.6                                                                    SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI URi--
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Seismic Walkdown Checklist (SWC)                    SWELl-675 Equipment ID No.        93TK-1B                  Equip. Class' 21 - Tanks and Heat Exchanqers Equipment Description Emergency Diesel GeneratorB Jacket Water Expansion Tank Location: Bldg. EG                  Floor El.. 272            Room, Area Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 9. Do attached lines have adequate flexibility to avoid damage?YZ NE] UE- N/AEl Y[ NEI ur- N/AZl Y[ NEI U[-] N/AZl 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
Anchorage
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 503 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE] U--Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Other Adverse Conditions
: 1. Is the anchorage configuration verification required (i.e., is the item one      YI-] NO of the 50% of SWEL items requiring such verification)?
: 11. Have you looked for and found no other seismic conditions that could YE N[:I U[-I adversely affect the safety functions of the equipment?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?                YN NDI    U[I N/AD-The anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface                YE NDI    U[: N/AD:
oxidation?
The anchorageis free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the                YD'- NDl UDI N/A[
anchors?
IEnter the equipment class name from Appendix  B: Classes of Equipment.
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 498 of 573 ATTACHMENT      9.6                                                          SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE ND UI&#xfd; Seismic Walkdown Checklist (SWC)                    SWELl-675 Equipment ID No.        93TK-IB                  Equip. Class_2 21 - Tanks and Heat Exchangers Equipment Description Emerqencv Diesel GeneratorB Jacket Water Expansion Tank
: 5. Is the anchorage configuiration consistent with plant documentation?          YLI NEI    UE- N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of            Y[    NI  ULiD potentially adverse-seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?        YE NEI    UE N/AE-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,    YZ NEI    UE- N/AAE7 and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                Y[    NEI  UE N/AAE-
: 10. Based on the above seismic interaction evaluations, is equipment free        YO NE uEr of potentially adverse seismic interaction effects?
2 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C      Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 499 of 573 ATTACHMENT 9.6                                                                SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] U[D1 Seismic Walkdown Checklist (SWC)                    SWELl-675 Equipment ID No.        93TK-IB                  Equip. Class_3 21 - Tanks and Heat Exchangers Equipment Description Emergencv Diesel GeneratorB Jacket Water Expansion Tank Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could          Y[  NE-1 UF--
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Evaluated by: PouriaPourghobadi                                                      Date: 9/21/12 Donald Koberaq                                                              9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 500 of 573 ATrACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NZ- UI--
Seismic Walkdown Checklist (SWC)                   SWELl-675 Equipment ID No.         93TK-1B                   Equip. Class_4 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorB Jacket Water Expansion Tank Photographs Note: 93TK-IB Front view                                           Note: 93TK-IB Side view 4 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C             Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 501 of 573 0 A.nrACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y[   NEI Ur-Seismic Walkdown Checklist (SWC)               SWELl- 682 Equipment ID No.     93TK-7A                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Location: Bldg. EG             Floor El. 272           Room, Area 24,A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[,   NEI of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YZ N[: Ui- N/A[-D
        'Anchorage contains all necessaryhardware
: 3. Is the anchorage free of corrosion that is more than mild surface             YZ ND U0iD N/ADl oxidation?
Anchorage contains no corrosion
: 4. Is the anchorage free of visible cracks in the concrete near the               YDI  NZ UDl N/AD-anchors?
Hairline cracks ( @ x) at anchorsprimarilyat top of concrete pedestal (refer to 93TK-7B and CR-JAF-2012-06090)
 
Aita6hment C         Entgineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 502 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   NE] Ufi Seismic Walkdown Checklist (SWC)               SWELl- 682 Equipment ID No.       93TK-7A                 Equip. Class 21 - Tank&#xfd; and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank
: 5. Is the anchorage configuration consistent with plant documentation?           Y[   NEI U-I N/A-]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
(Ref. 1.12-128, associatedSEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free of             Y Z NEl UEi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YZ NE] UE- N/AEl
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     Y[    NEI ur- N/AZl and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y[   NEI U[-] N/AZl
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 503 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE]   U--
Seismic Walkdown Checklist (SWC)             SWELl- 682 Equipment ID No. 93TK-7A                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YE N[:I U[-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
None C 3A2~&o~~~Evaluated by: Rick Casella Date: 10/29/12 I Al Porch 10129112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 504 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YN NEIl U[Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank PhotoaraDhs Note: 93TK-7A Note: 93TK-7A Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 505 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[ Nr-n Ur-]Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 -Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Note: 93TK-7A anchor bolt (note hairline crack in concrete right of bolt centerline)
None Evaluated by: Rick Casella C   3A2~&o~~~
Note:
Date: 10/29/12 I
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 506 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NF-D U"-I Seismic Walkdown Checklist (SWC) SWELl-683 Equipmenit ID No. 93TK-7B Equip. Class' 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel Generator B Fuel Oil Day Tank Location:
Al Porch                                                                 10129112
Bldg. EG Floor El. 272 Room, Area EDG B Room, Column 26.5 Line A4 Manufacturer, Model, Etc. (optional but recommended)
 
T312 Trinity Equip Corp Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of'equipment on the SWEL. The space below each'of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 504 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YN NEIl U[
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)         SWELl- 682 Equipment ID No. 93TK-7A             Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank PhotoaraDhs Note: 93TK-7A                                       Note: 93TK-7A
The anchorage configuration was verified and found to be acceptable.
 
This item is part of the 50% of SWEL items.2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 505 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[   Nr-n Ur-]
The anchorage is free of corrosion that is more than mild surface oxidation.
Seismic Walkdown Checklist (SWC)           SWELl- 682 Equipment ID No. 93TK-7A               Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Note: 93TK-7A anchorbolt (note hairline               Note:
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?Multiple visible hairline cracks on the foundation, from bottom of floor elevation through the center line of 7/8" bolts/anchors on both saddles.On the North saddle West end there is noticeable damage to the concrete foundation due to interaction of the concrete wall and the Fuel Day Tank Drain Line. The resolution to this deficiency is tracked by CR-JAF-2012-06090.
crack in concrete right of bolt centerline)
YE NE-]YE NrI- urE- N/AD YN NEI U-1 N/AD-YD NM UD] N/AD-1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 507 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NDI UEII Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel Generator B Fuel Oil Day Tank 5. Is the anchorage configuration consistent with plant documentation?
Attachment C           Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 506 of 573 ATTACHMENT       9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[   NF-D U"-I Seismic Walkdown Checklist (SWC)                     SWELl-683 Equipmenit ID No.       93TK-7B                   Equip. Class' 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Location: Bldg. EG                   Floor El. 272             Room, Area EDG B Room, Column 26.5 Line A4 Manufacturer, Model, Etc. (optional but recommended)               T312 Trinity Equip Corp Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of'equipment on the SWEL. The space below each'of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
YZ NDl UD- N/A[D (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
The anchorage configuration is consistent with DWG. No. 1.12-128 and SEWS for 93TK-7A, which has the same configuration as 93TK-7B.6. Based on the above anchorage evaluations, is the anchorage free of YEI NZ U[-]potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one       YE NE-]
Cracks in concrete pedestal at the anchorage and damage by the fuel day tank drain line jeopardizes the safety of the tank's support.The resolution to this deficiency is tracked by CR-JAF-2012-06090.
of the 50% of SWEL items requiring such verification)?
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchorageconfiguration was verified and found to be acceptable.
The equipment is free of soft targets.Y-I NDI UD3 NIA]8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
This item is part of the 50% of SWEL items.
: 9. Do attached lines have adequate flexibility to avoid damage?YN NDl U[D] N/AD]YE ND UD-- N/AD-10. Based on the above seismic interaction evaluations, is equipment free YO ND] UD-of potentially adverse seismic interaction effects?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?                 YE NrI- urE- N/AD The anchorageis free of bent, broken, missing or loose hardware.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 508 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NDl Ur-I Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel Generator B Fuel Oil Day Tank Other Adverse Conditions
: 3. Is the anchorage free of corrosion that is more than mild surface                 YN NEI U-1 N/AD-oxidation?
: 11. Have you looked for and found no other seismic conditions that could Y[ N- Ur-1 adversely affect the safety functions of the equipment?
The anchorage is free of corrosionthat is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the                   YD NM UD] N/AD-anchors?
Multiple visible hairline cracks on the foundation, from bottom of floor elevation through the center line of 7/8" bolts/anchors on both saddles.
On the North saddle West end there is noticeable damage to the concrete foundation due to interactionof the concrete wall and the Fuel Day Tank Drain Line. The resolution to this deficiency is tracked by CR-JAF-2012-06090.
1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 507 of 573 ATTACHMENT     9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NDI   UEII Seismic Walkdown Checklist (SWC)                 SWELl-683 Equipment ID No.       93TK-7B                 Equip. Class 21-Tanks &Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank
: 5. Is the anchorage configuration consistent with plant documentation?           YZ NDl UD- N/A[D (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorage configurationis consistent with DWG. No. 1.12-128 and SEWS for 93TK-7A, which has the same configuration as 93TK-7B.
: 6. Based on the above anchorage evaluations, is the anchorage free of             YEI NZ U[-]
potentially adverse seismic conditions?
Cracks in concrete pedestal at the anchorage and damage by the fuel day tank drain line jeopardizes the safety of the tank's support.
The resolution to this deficiency is tracked by CR-JAF-2012-06090.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?           Y-I NDI UD3 NIA]
The equipment is free of soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     YN NDl U[D] N/AD]
and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE ND UD-- N/AD-
: 10. Based on the above seismic interaction evaluations, is equipment free         YO ND] UD-of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 508 of 573 0 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NDl Ur-I Seismic Walkdown Checklist (SWC)             SWELl-683 Equipment ID No. 93TK-7B                 Equip. Class 21-Tanks &Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   N-   Ur-1 adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Pouria Pourqhobadi  
Evaluated by: Pouria Pourqhobadi .                                             Date: 01/21/2012 Donald Kolbera                                                           051     0 0112112012
.Date: 01/21/2012 Donald Kolbera 051 0 0112112012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 509 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl U--Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel Generator B Fuel Oil Day Tank Photographs Note: Diesel Fuel Day Tan 93TK-7B Note: Damage to north concrete pedestal by the Diesel Fuel Day Tank Drain Line (Valve 93EDG-71 1B)
 
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 510 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UMI Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 -Tanks and Heat Exchangers Equipment Description Emergency Diesel Generator C Jacket Water Heat Exchanger Location:
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 509 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl U--
Bldg. EG Floor El. 272 Room, Area CoL 25 line A4,AZ Manufacturer, Model, Etc. (optional but recommended)
Seismic Walkdown Checklist (SWC)       SWELl-683 Equipment ID No. 93TK-7B             Equip. Class 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Photographs Note: Diesel Fuel Day Tan 93TK-7B                   Note: Damage to north concrete pedestal by the Diesel Fuel Day Tank DrainLine (Valve 93EDG-71 1B)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YE NO of the 50% of SWEL items requiring such verification)?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 510 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UMI Seismic Walkdown Checklist (SWC)               SWELl- 686 Equipment ID No. 93WE-1C                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger Location: Bldg.       EG       Floor El.     272     Room, Area           CoL 25 line A4,AZ Manufacturer, Model, Etc. (optional but recommended)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage has all necessary hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
The anchorage shows no signs of any type of corrosion 4. Is the anchorage free of visible cracks in the concrete near the anchors?There are no cracks in the concrete near the anchors Y[ NEI U[-I N/A[--Y[ NE U[- N/A[-YE- NE U[-] N/A[,
Anchorage
'I Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 511 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ N[-] U-Seismic.Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-IC Equip. Class 21 -Tanks and Heat Exchangers Equipment Description Emergency Diesel Generator C Jacket Water Heat Exchanger 5. Is the anchorage configuration consistent with plant documentation?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YE NO of the 50% of SWEL items requiring such verification)?
YN NE-] U-I N/A[](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)(Ref. 1.12-35, 1.12-101, associated SEWS document)6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[:] U[I: potentially adverse seismic conditions?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             Y[    NEI U[-I N/A[--
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
The anchoragehas all necessaryhardware
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface             Y[    NE U[-  N/A[-
46EXJ-9C, I OC are epoxy soft targets. No credible seismic interactions
oxidation?
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NE-] U[i- N/AZ-YN NE] UE[ N/AZl YZ NE] U-I N/AZ]YZ N[] UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 512 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y] NEI Ur-I Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 -Tanks and Heat Exchangers Equipment Description Emergencv Diesel Generator C Jacket Water Heat Exchanger Other Adverse Conditions
The anchorage shows no signs of any type of corrosion
: 11. Have you looked for and found no other seismic conditions that could Y; NEI Ur adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YE- NE U[-] N/A[,
anchors?
There are no cracks in the concrete near the anchors
 
                                                                                                                      'I Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 511 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[   N[-] U-Seismic.Walkdown Checklist (SWC)               SWELl- 686 Equipment ID No.       93WE-IC                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger
: 5. Is the anchorage configuration consistent with plant documentation?         YN NE-] U-I N/A[]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
(Ref. 1.12-35, 1.12-101, associatedSEWS document)
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y[   N[:] U[I:
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[    NE-] U[i- N/AZ-
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NE] UE[ N/AZl and masonry block walls not likely to collapse onto the equipment?
46EXJ-9C, I OC are epoxy soft targets.No credible seismic interactions
: 9. Do attached lines have adequate flexibility to avoid damage?               YZ NE] U-I N/AZ]
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ N[] UE-of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 512 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y] NEI   Ur-I Seismic Walkdown Checklist (SWC)             SWELl- 686 Equipment ID No. 93WE-1C                 Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergencv Diesel GeneratorC Jacket Water Heat Exchanger Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y;   NEI Ur adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: R. Casella /A.G. Porch Date: 10/26/12 10/26/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 513 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI- ULI-Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 -Tanks and Heat Exchanqers Equipment Description Emergency Diesel Generator C Jacket Water Heat Exchanger Photographs Note: 93WE-IC (looking East)
Evaluated by: R. Casella /                                                     Date: 10/26/12 A.G. Porch                                                              10/26/12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 514 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NP UD Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 -Tanks and Heat Exchangers Equipment Description Emergency Diesel Generator C Jacket Water Heat Exchanger ed Foot Note: 93WE-1C Anchorage  
 
-Sliding Foot Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 515 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NDI U[Seismic Walkdown Checklist (SWC) SWELl -687 -Equipment ID No. 93WE-ID Equip. Class, 21 -Heat Exchangers Equipment Description Emergency Diesel Generator 0 Jacket Water Heat Exchanger Location:
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 513 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI-   ULI-Seismic Walkdown Checklist (SWC)       SWELl- 686 Equipment ID No. 93WE-1C             Equip. Class 21 - Tanks and Heat Exchanqers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger Photographs Note: 93WE-IC (looking East)
Bldg. EG Floor El. 272 Room, Area EG Room 0 C: 27, L: A4 Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 514 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NP UD Seismic Walkdown Checklist (SWC)       SWELl- 686 Equipment ID No. 93WE-1C             Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger ed Foot           Note: 93WE-1C Anchorage - Sliding Foot
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[-I NZ of the 50% of SWEL items requiring such verification)?
 
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The four (4) bolts are free of bent, broken, missing or loose hardware 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 515 of 573 ATTACHMENT       9.6                                                             SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[   NDI   U[
Seismic Walkdown Checklist (SWC)                     SWELl -687 -
Equipment ID No.         93WE-ID                   Equip. Class, 21 - Heat Exchangers Equipment Description Emergency Diesel Generator0 Jacket Water Heat Exchanger Location: Bldg. EG                   Floor El. 272             Room, Area EG Room 0 C: 27, L: A4 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[-I NZ of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YZ NDI    U[-  N/AD-The four (4) bolts are free of bent, broken, missing or loose hardware
: 3. Is the anchorage free of corrosion that is more than mild surface             YN NDI UD:      N/AD-oxidation?
The anchorage is free of any corrosion.
The anchorage is free of any corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?YZ NDI U[- N/AD-YN NDI UD: N/AD-YDI NDI U-I N/A[1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YDI NDI   U-I   N/A[
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 516 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NFI UFE Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 -Heat Exchangers Equipment Description Emergencv Diesel Generator 0 Jacket Water Heat Exchanger 5. Is the anchorage configuration consistent with plant documentation?
anchors?
YE-! NEI UE! N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
1 Enter the equipment class name from Appendix B: Classes of Equipment.
Item is not one of the 50% for which an anchorage configuration verification is required.6. Based on the above anchorage evaluations, is the anchorage free of YS NEI UE!potentially adverse seismic conditions?
 
Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 516 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   NFI UFE Seismic Walkdown Checklist (SWC)               SWELl-687 Equipment ID No.       93WE-ID                 Equip. Class 21 - Heat Exchangers Equipment Description Emergencv Diesel Generator0 Jacket Water Heat Exchanger
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 5. Is the anchorage configuration consistent with plant documentation?         YE-! NEI UE! N/A[
This component does not have soft targets.8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Masonry block wall divides the Delta and Bravo train in EDG.Modifications were made to enhance the walls as part of IE Bulletin 80-11. (Ref. Calculation No. JAF-CALC-EDG-02153 Rev 0) and IPEEE evaluations DI-96-011 Rev 0.9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
Item is not one of the 50% for which an anchorageconfiguration verification is required.
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.YEI NEI UE! N/AZ YE NE! UE! N/AE!YM N!-] U[-E N/AET YE NE!I uE Attachfnint C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 517 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NE] U-'Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 -Heat Exchangers Equipment Description Emergency Diesel Generator D Jacket Water Heat Exchanger Other Adverse Conditions
: 6. Based on the above anchorage evaluations, is the anchorage free of           YS NEI   UE!
: 11. Have you looked for and found no other seismic conditions that could YZ NEI ur adversely affect the safety functions of the equipment?
potentially adverse seismic conditions?
Based on the above anchorage evaluations, the anchorageis free of potentially adverse seismic conditions.
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YEI NEI  UE! N/AZ This component does not have soft targets.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YE NE! UE! N/AE!
and masonry block walls not likely to collapse onto the equipment?
Masonry block wall divides the Delta and Bravo train in EDG.
Modifications were made to enhance the walls as part of IE Bulletin 80-
: 11. (Ref. CalculationNo. JAF-CALC-EDG-02153 Rev 0) and IPEEE evaluationsDI-96-011 Rev 0.
: 9. Do attached lines have adequate flexibility to avoid damage?               YM N!-] U[-E  N/AET The attached lines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       YE NE!I  uE of potentially adverse seismic interaction effects?
The equipment is free of potentiallyadverse seismic interactioneffects.
 
Attachfnint C     Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 517 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y]     NE] U-'
Seismic Walkdown Checklist (SWC)             SWELl-687 Equipment ID No. 93WE-ID                 Equip. Class 21 - Heat Exchangers Equipment Description Emergency Diesel GeneratorD Jacket Water Heat Exchanger Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ NEI     ur adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Pouria Pourghobadi Date: 09/21/2012 Donald Kobergq09/21/2012 0912112012 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 518 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE ND UIur-Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 -Heat Exchangers Equipment Description Emergency Diesel Generator D Jacket Water Heat Exchanger Photoqraphs 0 Note: 93WE-ID Note:
Evaluated by: Pouria Pourghobadi Date: 09/21/2012 Donald Kobergq09/21/2012                                                 0912112012
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 519 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEII UE-Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class' 18- Instrument Racks Equipment Description Core Spray System Channel A Rack Location:
 
Bldg. RB Floor El. 242.8 Room, Area Col. 4, Line A Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 518 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE ND     UIur-Seismic Walkdown Checklist (SWC)       SWELl-687 Equipment ID No. 93WE-ID             Equip. Class 21 - Heat Exchangers Equipment Description Emergency Diesel GeneratorD Jacket Water Heat Exchanger Photoqraphs 0
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Note: 93WE-ID                                       Note:
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
YE NE-'2. Is the anchorage free of bent, broken, missing or loose hardware?Anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 519 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEII   UE-Seismic Walkdown Checklist (SWC)                     SWELl-690 Equipment ID No.         IR-25-01                 Equip. Class' 18- Instrument Racks Equipment Description Core Spray System Channel A Rack Location: Bldg. RB                   Floor El. 242.8           Room, Area Col. 4, Line A Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one     YE NE-'
of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YN NE:I UEJ N/AEl Anchorage is free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface               YM NEI    UEI N/AE oxidation?
Anchorage is free of corrosion that is more than mild surface oxidation.
Anchorage is free of corrosion that is more than mild surface oxidation.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The component is not anchored in concrete.YN NE:I UEJ N/AEl YM NEI UEI N/AE YE- NEI U[-- N/AN 1 Enter the equipment class name from Appendix B: Classes of Equipment.
: 4. Is the anchorage free of visible cracks in the concrete near the               YE- NEI U[-- N/AN anchors?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 520 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NE] UE&#xfd;Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System Channel A Rack 5. Is the anchorage configuration consistent with plant documentation?
The component is not anchoredin concrete.
YE-] NZ Ul-I N/A[I](Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
1 Enter the equipment class name from Appendix B: Classes of Equipment.
The rack is bolted to steel plates which are welded to an I-beam. The spacing between the anchors is 15 inches. They are not 18 inches as shown 7.70-81D due to interference with an I-beam.The resolution to this deficiency it tracked through CR-2012-JAF-08186.6. Based on the above anchorage evaluations, is the anchorage free of YE:' NO UE-]potentially adverse seismic conditions?
 
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 520 of 573 0 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE   NE] UE&#xfd; Seismic Walkdown Checklist (SWC)                 SWELl-690 Equipment ID No.       IR-25-01                 Equip. Class 18- Instrument Racks Equipment Description Core Spray System Channel A Rack
Y[ N[-I ULI N/AE-The soft targets are free from impact by nearby equipment and structures.
: 5. Is the anchorage configuration consistent with plant documentation?         YE-] NZ Ul-I N/A[I]
: 8. Are overhead equipment, distribution systems, Ceiling tiles and lighting, YN NE- UE- NIAE and masonry block walls not likely to collapse onto the equipment?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The overhead equipments and distribution systems ,are not likely to collapse onto the equipment.
The rack is bolted to steel plates which are welded to an I-beam. The spacing between the anchors is 15 inches. They are not 18 inches as shown 7.70-81D due to interference with an I-beam.
: 9. Do'attached lines have adequate flexibility to avoid damage? YS NEI UE- N/AE1 The attached lines have adequate flexibility.
The resolution to this deficiency it tracked through CR-2012-JAF-08186.
: 10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI UE of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effect Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 521 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEI U[--Seismic Walkdown Checklist (SWC) SWELI-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System Channel A Rack Other Adverse Conditions
: 6. Based on the above anchorage evaluations, is the anchorage free of         YE:' NO UE-]
: 11. Have you looked for and found no other seismic conditions that could YZ NEi UE-I adversely affect the safety functions of the equipment?
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[     N[-I ULI N/AE-The soft targets are free from impact by nearby equipment and structures.
: 8. Are overhead equipment, distribution systems, Ceiling tiles and lighting,   YN NE- UE- NIAE and masonry block walls not likely to collapse onto the equipment?
The overhead equipments and distributionsystems ,are not likely to collapse onto the equipment.
: 9. Do'attached lines have adequate flexibility to avoid damage?                 YS NEI     UE- N/AE1 The attached lines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free       Y[   NEI UE of potentially adverse seismic interaction effects?
The equipment is free of potentially adverse seismic interaction effect
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 521 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEI U[--
Seismic Walkdown Checklist (SWC)             SWELI-690 Equipment ID No. IR-25-01                 Equip. Class 18- Instrument Racks Equipment Description Core Spray System ChannelA Rack Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ   NEi UE-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald Koberci&#xfd; d Xj&#xfd;, Date: 9/25/12 Pouria Pourihobad, 9125112 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 522 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEI- U--Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System Channel A Rack Photographs Note: Instrument Panel Note: Rack Anchorage Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 523 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI UM Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class, 18 -Instrument Racks Equipment Description RHR Channel B Instrument Rack Location:
Evaluated by: Donald Koberci&#xfd;         d     Xj&#xfd;,                               Date: 9/25/12 Pouria Pourihobad,                                                       9125112
Bldg. RB Floor El. 242 Room, Area Col 3 Line D Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 522 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEI- U--
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)       SWELl-690 Equipment ID No. IR-25-01           Equip. Class 18- Instrument Racks Equipment Description Core Spray System ChannelA Rack Photographs Note: Instrument Panel                             Note: Rack Anchorage
Anchorage configuration verification is required.2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
The anchorage is free of corrosion that is more than mild surface oxidation.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 523 of 573 ATTACHMENT 9.6                                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI UM Seismic Walkdown Checklist (SWC)                     SWELl-696 Equipment ID No.         IR-25-62                 Equip. Class, 18 - Instrument Racks Equipment Description RHR Channel B Instrument Rack Location: Bldg. RB                   Floor El. 242             Room, Area Col 3 Line D Manufacturer, Model, Etc. (optional but recommended)
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The anchorage is not embedded in concrete.YE] NEI YN NEI U-I N/AF-Y[ NE] U[-L] N/A--YEll NEI UEI N/AN 1 Enter the equipment class name from Appendix B: Classes of Equipment.
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 524 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI Ur-Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack 5. Is the anchorage configuration consistent with plant documentation?
Anchorage
YN NEI U-- N/AE--(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 1. Is the anchorage configuration verification required (i.e., is the item one     YE] NEI of the 50% of SWEL items requiring such verification)?
The anchorage configuration is consistent with SEWS for IR-25-62, DWG. No. 7.70-81 6. Based on the above anchorage evaluations, is the anchorage free of YN NEI UEi potentially adverse seismic conditions?
Anchorage configurationverification is required.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?               YN NEI    U-I N/AF-The anchorageis free of bent, broken, missing or loose hardware.
The soft targets are free from impact by nearby equipments and structures.
: 3. Is the anchorage free of corrosion that is more than mild surface               Y[    NE] U[-L] N/A--
YN NEi UEi N/A[E 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NE- U[] N/A[-]and masonry block walls not likely to collapse onto the equipment?
oxidation?
The overhead equipments, distribution systems, ceiling tiles and lighting and masonry walls.9. Do attached lines have adequate flexibility to avoid damage?The attached lines have adequate flexibility.
The anchorageis free of corrosionthat is more than mild surface oxidation.
YZ NEI UE- N/A--10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The equipment is free of potentially adverse seismic interaction effects.
: 4. Is the anchorage free of visible cracks in the concrete near the               YEll NEI UEI N/AN anchors?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 525 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] N- UI--1 Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Other Adverse Conditions
The anchorageis not embedded in concrete.
: 11. Have you looked for and found no other seismic conditions that could Y[ N[l U[i adversely affect the safety functions of the equipment?
1 Enter the equipment class name from Appendix B: Classes of Equipment.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 524 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   NEI Ur-Seismic Walkdown Checklist (SWC)               SWELl-696 Equipment ID No.       IR-25-62               Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack
: 5. Is the anchorage configuration consistent with plant documentation?         YN NEI   U-- N/AE--
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageconfiguration is consistent with SEWS for IR-25-62, DWG. No. 7.70-81
: 6. Based on the above anchorage evaluations, is the anchorage free of         YN NEI   UEi potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YN NEi UEi N/A[E The soft targets are free from impact by nearbyequipments and structures.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NE- U[] N/A[-]
and masonry block walls not likely to collapse onto the equipment?
The overhead equipments, distributionsystems, ceiling tiles and lighting and masonry walls.
: 9. Do attached lines have adequate flexibility to avoid damage?                 YZ NEI   UE- N/A--
The attachedlines have adequate flexibility.
: 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
The equipment is free of potentiallyadverse seismic interactioneffects.
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 525 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] N-     UI--1 Seismic Walkdown Checklist (SWC)             SWELl-696 Equipment ID No. IR-25-62                 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   N[l U[i adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Donald KoberQ Pouria Pourghobadi Date: 9/23/12 9/23/12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 526 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE N[] Ur Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Photouraphs 0 Note: IR-25-62 Instrument rack Note:
Evaluated by: Donald KoberQ                                                     Date: 9/23/12 Pouria Pourghobadi                                                      9/23/12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 527 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI UI[-Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel Pool cooling skimmer surge tank A Location:
 
Bldg. RB Floor El. 344 Room, Area Col 4 Line D Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 526 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE N[] Ur Seismic Walkdown Checklist (SWC)       SWELl-696 Equipment ID No. IR-25-62           Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Photouraphs 0
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL; The space below each of the following questions may be used to record the results of judgments and findings.
Note: IR-25-62 Instrument rack                     Note:
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
Y[-' NO 2. Is the anchorage free of bent, broken, missing or loose hardware?The anchorage is free of bent, broken, missing or loose hardware.YO NEI ULII N/AEl 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 527 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI   UI[-
Seismic Walkdown Checklist (SWC)               SWEL2-001 Equipment ID No.     19TK-8A                 Equip. Class Tanks and heat exchangers Equipment Description Fuel Pool cooling skimmer surge tank A Location: Bldg. RB             Floor El. 344           Room, Area     Col 4 Line D Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL; The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[-'  NO of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YO NEI ULII N/AEl The anchorageis free of bent, broken, missing or loose hardware.
: 3. Is the anchorage free of corrosion that is more than mild surface             YO NEI U-] N/AEl oxidation?
No corrosion.
No corrosion.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The anchorage is free of cracks.YO NEI U-] N/AEl YO NEI UEI N/AR Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 528 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NDI UD-Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A 5. Is the anchorage configuration consistent with plant documentation?
: 4. Is the anchorage free of visible cracks in the concrete near the               YO NEI UEI N/AR anchors?
YEI- N[I UEI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
The anchorageis free of cracks.
: 6. Based on the above anchorage evaluations, is the anchorage free of YN ND] UD-potentially adverse seismic conditions?
 
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 528 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NDI     UD-Seismic Walkdown Checklist (SWC)                 SWEL2-001 Equipment ID No.       19TK-8A                 Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A
No soft targets on tank 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 5. Is the anchorage configuration consistent with plant documentation?           YEI- N[I   UEI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?The tank is structurally robust. It is supported at El. 369'. Any minimal lateral tank movement will not impact any SSCs Y[K NDI UD1 N/ADl YO ND: UD] N/AD1 Y' ND1 UD-- N/AD-I YE NDl UM Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 529 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE NMl UM Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Other Adverse Conditions
: 6. Based on the above anchorage evaluations, is the anchorage free of             YN ND] UD-potentially adverse seismic conditions?
: 11. Have you looked for and found no other seismic conditions that could YE NEI ULI adversely affect the safety functions of the equipment?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         Y[K NDI UD1 N/ADl No soft targets on tank
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,     YO ND: UD] N/AD1 and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 Y'  ND1 UD--  N/AD-I
: 10. Based on the above seismic interaction evaluations, is equipment free         YE NDl UM of potentially adverse seismic interaction effects?
The tank is structurallyrobust. It is supported at El. 369'. Any minimal lateraltank movement will not impact any SSCs
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 529 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE NMl   UM Seismic Walkdown Checklist (SWC)             SWEL2-001 Equipment ID No. 19TK-8A                 Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YE NEI     ULI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12 Alan Porch 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 530 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ N-- UI-I Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Photographs Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 531 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEil U-I Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch Location:
Evaluated by: Rick Casella                                                     Date: 9-28-12 9-28-12 Alan Porch Alan  Porch                                                  9-28-12
Bldg. RB Floor El. 344 Room, Area Col4 Line D Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 530 of 573 ATTACHMENT 9.6                                                       SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   N-- UI-I Seismic Walkdown Checklist (SWC)           SWEL2-001 Equipment ID No. 19TK-8A               Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Photographs
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
 
YEO NO 2. Is the anchorage free of bent, broken, missing or loose hardware?SWEL item is not independently supported; it is attached to a pipe stand running vertically which is supported at the top and bottom.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 531 of 573 0 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEil U-I Seismic Walkdown Checklist (SWC)               SWEL2-003 Equipment ID No.     19LS-65                 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A high level switch Location: Bldg. RB               Floor El. 344         Room, Area Col4 Line D Manufacturer, Model, Etc. (optional but recommended)
SWEL item is not independently supported; it is attached to a pipe stand running vertically which is supported at the top and bottom.4. Is the anchorage free of visible cracks in the concrete near the anchors?, SWEL item is not independently supported; it is attached to a pipe stand running vertically which is supported at the top and bottom.YE] NE] UE] N/A[YE] NE] UE] N/A[YE] NEI UE] N/As Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 532 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI UrII Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch 5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Y-I NEI ULi N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Uil potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEO NO of the 50% of SWEL items requiring such verification)?
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YE] NE] UE] N/A[
Flexible conduit is a soft target near item. There are no credible seismic interactions.
SWEL item is not independently supported; it is attachedto a pipe stand running vertically which is supportedat the top and bottom.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface             YE] NE] UE] N/A[
Fluorescent light in the room is located several feet from SWEL item.No interaction likely.9. Do attached lines have adequate flexibility to avoid damage?Conduit attached to the wall and has a flexible connection at the swell item. SWEL item is not independently supported, it is attached to a pipe stand running vertically which is supported at the top and bottom.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ N[i U[-I N/All YEI N[! UEi N/As YE N[:] UE] N/All Y[ NEI U[-]
oxidation?
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 533 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI] ULI Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch Other Adverse Conditions
SWEL item is not independentlysupported; it is attached to a pipe stand running vertically which is supported at the top and bottom.
: 11. Have you looked for and found no other seismic conditions that could YN NI-] U[-I adversely affect the safety functions of the equipment?
: 4. Is the anchorage free of visible cracks in the concrete near the               YE] NEI  UE] N/As anchors?,
SWEL item is not independently supported; it is attachedto a pipe stand running vertically which is supportedat the top and bottom.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 532 of 573 ATTACHMENT     9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   NEI UrII Seismic Walkdown Checklist (SWC)                 SWEL2-003 Equipment ID No.       19LS-65                 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch
: 5. Is the anchorage configuration consistent with plant documentation?           Y-I NEI ULi N/A[
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[   NEI Uil potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         Y[    N[i  U[-I N/All Flexible conduit is a soft target near item. There are no credible seismic interactions.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YEI N[!    UEi N/As and masonry block walls not likely to collapse onto the equipment?
Fluorescentlight in the room is located several feet from SWEL item.
No interactionlikely.
: 9. Do attached lines have adequate flexibility to avoid damage?                 YE N[:] UE] N/All Conduit attachedto the wall and has a flexible connection at the swell item. SWEL item is not independently supported,it is attached to a pipe stand running vertically which is supportedat the top and bottom.
: 10. Based on the above seismic interaction evaluations, is equipment free       Y[    NEI U[-]
of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 533 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI]   ULI Seismic Walkdown Checklist (SWC)             SWEL2-003 Equipment ID No. 19LS-65                 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A high level switch Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YN NI-] U[-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
No additional comments.Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 534 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NR UW--Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch Photographs Note:
No additionalcomments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 535 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NE I UMI Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. I9LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Location:
Evaluated by: Rick Casella                                                     Date: 9-28-12 Alan Porch                                                               9-28-12
Bldg. RB Floor El. 347 Room, Area Col4 Line D Manufacturer, Model, Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 534 of 573 ATTACHMENT 9.6                                                     SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   NR UW--
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
Seismic Walkdown Checklist (SWC)         SWEL2-003 Equipment ID No. 19LS-65             Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch Photographs Note:
Y[E] NO 2. Is the anchorage free of bent, broken, missing or loose hardware?The item is not supported independently.
 
: 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 535 of 573 ATTACHMENT   9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NE I UMI Seismic Walkdown Checklist (SWC)               SWEL2-004 Equipment ID No.     I9LS-67                 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Location: Bldg. RB           Floor El. 347           Room, Area     Col4 Line D Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[E] NO of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YEI  NEI  UE-] N/A]
The item is not supported independently.
The item is not supported independently.
: 4. Is the anchorage free of visible cracks in the concrete near the anchors?The item is not supported independently.
: 3. Is the anchorage free of corrosion that is more than mild surface              YEI  NE] UE[- N/AE oxidation?
No concrete.YEI NEI UE-] N/A]YEI NE] UE[- N/AE YE- NEI UEJ N/AO Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 536 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEIr Ur0-Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch 5. Is the anchorage configuration consistent with plant documentation?
The item is not supported independently.
YE- NEI UE- N/A[(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 4. Is the anchorage free of visible cracks in the concrete near the               YE- NEI UEJ N/AO anchors?
: 6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI ULI potentially adverse seismic conditions?
The item is not supportedindependently. No concrete.
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
 
YZ N[E] UEl N/AE-Flexible conduit is a soft target near item. There are no credible seismic interactions.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 536 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEIr Ur0-Seismic Walkdown Checklist (SWC)                 SWEL2-004 Equipment ID No.       19LS-67                 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A low-low level switch
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YEi NE UEi N/AZ and masonry block walls not likely to collapse onto the equipment?
: 5. Is the anchorage configuration consistent with plant documentation?           YE- NEI   UE- N/A[
: 9. Do attached lines have adequate flexibility to avoid damage? YZ NEl UE-] N/AEl 10. Based on the above seismic interaction evaluations, is equipment free YZ NE] UEi of potentially adverse seismic interaction effects?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 537 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI UE]Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Other Adverse Conditions
: 6. Based on the above anchorage evaluations, is the anchorage free of           YZ NEI   ULI potentially adverse seismic conditions?
: 11. Have you looked for and found no other seismic conditions that could YZ NEI U[-I adversely affect the safety functions of the equipment?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?         YZ N[E] UEl N/AE-Flexible conduit is a soft target near item. There are no credible seismic interactions.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YEi NE UEi N/AZ and masonry block walls not likely to collapse onto the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?                 YZ NEl UE-] N/AEl
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NE] UEi of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 537 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI   UE]
Seismic Walkdown Checklist (SWC)             SWEL2-004 Equipment ID No. 19LS-67                 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YZ NEI     U[-I adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
F~ CcLJ&Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 538 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI Ul']Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Photographs 0 Note:
Evaluated by: Rick Casella F~ CcLJ&                                          Date: 9-28-12 Alan Porch                                                               9-28-12
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 539 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NEI UL-I Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. ' 19FPC-33 Equip. Class 07-Pneumatic-operated valves Equipment Description Skimmer surcqe tanks A & B to cndsr hotwell isol valve inlet isol Location:
 
Bldg. RB Floor El. 326.9 Room, Area Col 3 line R Manufacturer, Model, Etc. (optional but recommended)
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 538 of 573 ATTACHMENT   9.6                                                   SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI   Ul']
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Seismic Walkdown Checklist (SWC)         SWEL2-004 Equipment ID No. 19LS-67             Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Photographs 0
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
Note:
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The item is an inline valve 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
 
The item is an inline valve 4. Is the anchorage free of visible cracks in the concrete near the anchors?The item is an inline valve YEI Nil UE- N/AH YE] N] U[:] N/AZ YE] NFI UE] N/A[
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 539 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NEI     UL-I Seismic Walkdown Checklist (SWC)               SWEL2-005 Equipment ID No. ' 19FPC-33                   Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surcqe tanks A & B to cndsr hotwell isol valve inlet isol Location: Bldg. RB               Floor El. 326.9       Room, Area Col 3 line R Manufacturer, Model, Etc. (optional but recommended)
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 540 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NE-] UM Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07-Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol 5. Is the anchorage configuration consistent with plant documentation?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
YI-- Nil UFI N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ N-I UE-potentially adverse seismic conditions?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NZ of the 50% of SWEL items requiring such verification)?
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YEI Nil UE- N/AH The item is an inline valve
No soft targets 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 3. Is the anchorage free of corrosion that is more than mild surface             YE] N] U[:] N/AZ oxidation?
The item is an inline valve
: 4. Is the anchorage free of visible cracks in the concrete near the               YE] NFI UE] N/A[
anchors?
The item is an inline valve
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 540 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[   NE-] UM Seismic Walkdown Checklist (SWC)               SWEL2-005 Equipment ID No.       19FPC-33               Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol
: 5. Is the anchorage configuration consistent with plant documentation?         YI-- Nil UFI N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[   N-I UE-potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YE-1 NEI  UL-l N/AN No soft targets
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN Nl! UE[ N/AZ!
and masonry block walls not likely to collapse onto the equipment?
Piping and overhead conduit well supported.
Piping and overhead conduit well supported.
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE-1 NEI UL-l N/AN YN Nl! UE[ N/AZ!YE- NEI UE1 N/AE YZ NEi U-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 541 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] ULII Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07-Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Other Adverse Conditions
: 9. Do attached lines have adequate flexibility to avoid damage?               YE- NEI UE1 N/AE
: 11. Have you looked for and found no other seismic conditions that could YE ND1 ULI adversely affect the safety functions of the equipment?
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ NEi U-of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 541 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] ULII Seismic Walkdown Checklist (SWC)               SWEL2-005 Equipment ID No.     19FPC-33               Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YE ND1 ULI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
No additional comments.0&#xfd;aAAZ Evaluated by: PiA,' ('a cnr.In Date: 9-28-12 Alan Pnrr~h 9-28-12 AI~in Porch 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 542 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE Nn UD Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07- Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Photographs 0 Note: 19FPC-33 valve shown on left side of photo. (The date provided on the bottom right cornet is not correct the date that the picture was taken. Malfunction with camera setting)Note: 19FPC-33 (The date provided on the bottom right cornet is not correct the date that the picture was taken. Malfunction with camera setting)
No additionalcomments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 543 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Location:
0&#xfd;aAAZ Evaluated by: PiA,' ('a cnr.In                                                 Date: 9-28-12 Alan Pnrr~h                                                             9-28-12 AI~in Porch                                                             9-28-12
Bldg. RB Floor El. 326.9 Room, Area Co/ 3 line R Manufacturer, Model,. Etc. (optional but recommended)
 
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 542 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE Nn UD Seismic Walkdown Checklist (SWC)           SWEL2-005 Equipment ID No. 19FPC-33               Equip. Class 07- Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Photographs 0
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
Note: 19FPC-33valve shown on left side of               Note: 19FPC-33 (The date provided on the photo. (The date provided on the bottom right          bottom right cornet is not correct the date that cornet is not correct the date that the picture        the picture was taken. Malfunction with camera was taken. Malfunction with camera setting)            setting)
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The item is an inline valve 3. Is the anchorage free of corrosion that is more than mild surface, oxidation?
 
The item is an inline valve 4. Is the anchorage free of visible cracks in the concrete near the anchors?The item is an inline valve YEI NEI U-EI N/AZ YEI NEI UEI N/AZ Y[E] NEI UEl, N/AZ Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 544 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ N-- UL-I Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve 5. Is the anchorage configuration consistent with plant documentation?
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 543 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[   NEI U-I Seismic Walkdown Checklist (SWC)               SWEL2-006 Equipment ID No.     19AOV-09               Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Location: Bldg. RB               Floor El. 326.9       Room, Area Co/ 3 line R Manufacturer, Model,. Etc. (optional but recommended)
YEI NEI Ur-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI U0I potentially adverse seismic conditions?
Anchorage
N/A Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
: 1. Is the anchorage configuration verification required (i.e., is the item one   YEI NZ of the 50% of SWEL items requiring such verification)?
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YEI  NEI U-EI N/AZ The item is an inline valve
: 3. Is the anchorage free of corrosion that is more than mild surface,             YEI NEI UEI    N/AZ oxidation?
The item is an inline valve
: 4. Is the anchorage free of visible cracks in the concrete near the               Y[E] NEI UEl, N/AZ anchors?
The item is an inline valve
 
Attachment C         Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 544 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ N-- UL-I Seismic Walkdown Checklist (SWC)               SWEL2-006 Equipment ID No.       19AOV-09               Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve
: 5. Is the anchorage configuration consistent with plant documentation?         YEI NEI Ur-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of           Y[   NEI U0I potentially adverse seismic conditions?
N/A Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       Y[  NE] U[i N/AF--
Piping and conduit above the item is well supported.
Piping and conduit above the item is well supported.
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YN NEI ur-] N/AL]
: 9. Do attached lines have adequate flexibility to avoid damage?10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?Y[ NE] U[i N/AF--YN NEI ur-] N/AL]YEI NEI U[] N/A[YZ N[: UEL Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 545 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NF] UL-Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Other Adverse Conditions
and masonry block walls not likely to collapse onto the equipment?
: 11. Have you looked for and found no other seismic conditions that could YS NOJ UJ-adversely affect the safety functions of the equipment?
: 9. Do attached lines have adequate flexibility to avoid damage?               YEI NEI    U[] N/A[
: 10. Based on the above seismic interaction evaluations, is equipment free       YZ N[: UEL of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 545 of 573 ATTACHMENT 9.6                                                           SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   NF] UL-Seismic Walkdown Checklist (SWC)             SWEL2-006 Equipment ID No. 19AOV-09               Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     YS NOJ     UJ-adversely affect the safety functions of the equipment?
Comments ('Additional pages may be added as necessary)
Comments ('Additional pages may be added as necessary)
No additional comments.''Li 6201-L Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 1 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 546 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI ULI Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operated valves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Photographs 40 Note: 19AOV-09 valve shown in center of picture. (The date provided on the bottom right comet is not correct the date that the picture was taken. Malfunction with camera setting)Note:
No additionalcomments.
Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 547 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE N[] U-I Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B drain valve Location:
Evaluated by: Rick Casella
Bldg. RB Floor El. 326 Room, Area Col 3 line T Manufacturer, Model, Etc. (optional but recommended)
                                  ''Li 6201-L                                   Date: 9-28-12 Alan Porch                                                             1 9-28-12
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings.
 
Additional space is provided at the end of this checklist for documenting other comments.Anchorage 1. Is the anchorage configuration verification required (i.e., is the item one Y[I NEK of the 50%of SWEL items requiring such verification)?
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 546 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI   ULI Seismic Walkdown Checklist (SWC)           SWEL2-006 Equipment ID No. 19AOV-09               Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Photographs 40 Note: 19AOV-09 valve shown in center of               Note:
: 2. Is the anchorage free of bent, broken, missing or loose hardware?The item is an inline valve.3. Is the anchorage free of corrosion that is more than mild surface oxidation?
picture. (The date provided on the bottom right comet is not correct the date that the picture was taken. Malfunction with camera setting)
The item is an inline valve.4. Is the anchorage free of visible cracks in the concrete near the anchors?The item is an inline valve.YEI- N[-1 Ul"] N/As YEI NEIl UIE N/AZ YEl NElI- U[E] N/AZ Attachment C Engineering Report No. JAF-RPT-12-00015' Rev. 0 Page 548 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NRi Ul-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B drain valve 5. Is the anchorage configuration consistent with plant documentation?
 
Y[I NE] U[ N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Attachment C             Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 547 of 573 ATTACHMENT 9.6                                                                 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE N[] U-I Seismic Walkdown Checklist (SWC)               SWEL2-007 Equipment ID No.     19FPC-01               Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Location: Bldg. RB               Floor El. 326         Room, Area Col 3 line T Manufacturer, Model, Etc. (optional but recommended)
: 6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI UE]potentially adverse seismic conditions?
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Interaction Effects 7. Are soft targets free from impact by nearby equipment or structures?
Anchorage
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
: 1. Is the anchorage configuration verification required (i.e., is the item one   Y[I NEK of the 50%of SWEL items requiring such verification)?
None overhead.
: 2. Is the anchorage free of bent, broken, missing or loose hardware?             YEI- N[-1 Ul"] N/As The item is an inline valve.
Fluorescent light directly south will not damage hand wheel if it fails.9. Do attached lines have adequate flexibility to avoid damage?No line attached.10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?YE] NEI UE] N/AS YZ NE] UE] N/AE]YE] NE] UE] N/AZ YN N[] UE-Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 549 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEI] U-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B drain valve Other Adverse Conditions
: 3. Is the anchorage free of corrosion that is more than mild surface             YEI NEIl UIE N/AZ oxidation?
: 11. Have you looked for and found no other seismic conditions that could Y[ NEI U[1 adversely affect the safety functions of the equipment?
The item is an inline valve.
: 4. Is the anchorage free of visible cracks in the concrete near the               YEl NElI-U[E] N/AZ anchors?
The item is an inline valve.
 
Attachment C         Engineering Report No. JAF-RPT-12-00015' Rev. 0 Page 548 of 573 ATTACHMENT 9.6                                                               SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NRi   Ul-Seismic Walkdown Checklist (SWC)                 SWEL2-007 Equipment ID No.       19FPC-01               Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve
: 5. Is the anchorage configuration consistent with plant documentation?         Y[I NE] U[     N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
: 6. Based on the above anchorage evaluations, is the anchorage free of         Y[   NEI UE]
potentially adverse seismic conditions?
Interaction Effects
: 7. Are soft targets free from impact by nearby equipment or structures?       YE] NEI UE] N/AS
: 8. Are overhead equipment, distribution systems, ceiling tiles and lighting,   YZ NE] UE] N/AE]
and masonry block walls not likely to collapse onto the equipment?
None overhead. Fluorescentlight directly south will not damage hand wheel if it fails.
: 9. Do attached lines have adequate flexibility to avoid damage?               YE] NE] UE] N/AZ No line attached.
: 10. Based on the above seismic interaction evaluations, is equipment free       YN N[] UE-of potentially adverse seismic interaction effects?
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 549 of 573 ATTACHMENT   9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[   NEI] U-Seismic Walkdown Checklist (SWC)             SWEL2-007 Equipment ID No. 19FPC-01                 Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Other Adverse Conditions
: 11. Have you looked for and found no other seismic conditions that could     Y[   NEI U[1 adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
Comments (Additional pages may be added as necessary)
No additional comments.Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12 Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 550 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NEI- UI-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operated valves Equipment Description Skimmer surge tanks A & B drain valve Photographs Note: 19FPC-01 (The date provided on the bottom right cornet is not correct the date that the picture was taken. Malfunction with camera setting)Note: 19FPC-O1(The date provided on the bottom right cornet is not correct the date that the picture was taken. Malfunction with camera setting)0}}
No additionalcomments.
Evaluated by: Rick Casella                                                     Date: 9-28-12 Alan Porch                                                               9-28-12
 
Attachment C       Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 550 of 573 ATTACHMENT 9.6                                                         SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[   NEI- UI-Seismic Walkdown Checklist (SWC)           SWEL2-007 Equipment ID No. 19FPC-01               Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Photographs Note: 19FPC-01 (The date provided on the               Note: 19FPC-O1(The date provided on the bottom right cornet is not correct the date that      bottom right cornet is not correct the date that the picture was taken. Malfunction with camera         the picture was taken. Malfunction with camera setting)                                              setting) 0}}

Latest revision as of 19:06, 11 November 2019

Engineering Report JAF-RPT-12-00015, Rev. 0, Jaf Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3 Seismic, Book 2 of 3, Attachment C, Pages 283 Through 573
ML12342A141
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 11/21/2012
From: Losev Y, Pourghobadi P
Entergy Nuclear
To:
Office of Nuclear Reactor Regulation
References
JAFP-12-0134 JAF-RPT-12-00015, Rev. 0
Download: ML12342A141 (269)


Text

JAF-RPT-1 2-00015 Rev. 0 JAF SEISMIC WALKDOWN REPORT FOR RESOLUTION OF FUKUSHIMA NEAR-TERM TASK FORCE RECOMMENDATION 2.3 SEISMIC NOVEMBER 2012 BOOK 2 OF 3

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 283 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y-I N- UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class' 1- Motor Control Center Equipment Description Reactor building Motor Control Center Location: Bldg. RB Floor El. 272' Room, Area Col 8, Line Y Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO NE-]

of the 50% of SWEL items requiring such verification)?

2. Is the anchorage free of bent, broken, missing or loose hardware? YE-] NE- UM N/AE--
3. Is the anchorage free of corrosion that is more than mild surface YE] NE:] UM N/A-Z oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YE-- NEJ UN N/A-anchors?

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 284 of 573 ATTACHMENT 9.6 SEisMiC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YF-- NE] UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center

5. Is the anchorage configuration consistent with plant documentation? YE] NEi U[ N/AE]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of Y[- NEI U[

potentially adverse seismic conditions?

Interaction Effects

7. Are softtargets free from impact by nearby equipment or structures? YE NE: UE- N/A[E
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO NEi UE N/AEF and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YE NEI UEi N/AE1
10. Based on the above seismic interaction evaluations, is equipment free YE NEI U[:]

of potentially adverse seismic interaction effects?

Attachment C EngiheiJrig Report No. JAF-RPT-12-00015 Rev. 0 Page 285 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YOI NE] U[

Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor buildinQ Motor Control Center Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NI- UI1 adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: A.G. Porch L Date: 10/31/2012 C. Sawatzke 103/21 1013112012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 286 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0-- NEL U[

Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center Equipment Description Reactor building Motor Control Center Photographs Note: 71BMCC-6 Front View Note: 71BMCC-6 Attached Lines

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 287 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5of 5 Status: YLI NO UN Seismic Walkdown Checklist (SWC) SWELl-456 Equipment ID No. 71BMCC-6 Equip. Class 1- Motor Control Center EauiDment DescriDtion Reactorbuildina Motor Control Center Note: 71BMCC-6 Side View Note:

0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 288 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: Y[ NR U-Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class' 14 - Distribution Panels Equipment Description Relay Room DistributionCabinet Location: Bldg. RR Floor El. 284.8 Room, Area Col. 10, Line F Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YN NEI of the 50% of SWEL items requiring such verification)?

The anchorageconfiguration verification is required. /

2. Is the anchorage free of bent, broken, missing or loose hardware? YE NZ U[I N/AE-The bottom right hand corner Unistrut Channel nut has failed. The resolution to this deficiency is to be tracked by CR-JAF-2012-07954
3. Is the anchorage free of corrosion that is more than mild surface YZ NEI UE- N/AE-oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YZ NEI UE- N/A[-]

anchors?

Anchorage is free of visible cracks in the concrete near the anchors.

Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 289 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NE] U-Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14 - Distribution Panels Equipment Description Relay Room DistributionCabinet

5. Is the anchorage configuration consistent with plant documentation? YE] NEl uEr N/A[-1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfiguration is consistent with the SEWS for 71DC-A2 (Rev. 0). The panel is anchored with four 3/8" bolts to a pairof unistrut channels, which are welded to a steel building column.

6. Based on the above anchorage evaluations, is the anchorage free of YEl NE UI-I potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NEI UE[ N/AE The soft targets are free from impact by nearby equipments and structures.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NE] UE- N/AEF and masonry block walls not likely to collapse onto the equipment?

The overhead equipments and distributionsystems are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? Y] NEI UEi N/AEl The attachedlines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YZ NEl UE1 of potentially adverse seismic interaction effects?

The equipment is free of potentiallyadverse seismic interactioneffects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 290 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NE-l U-II Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14 - Distribution Panels Equipment Description Relay Room Distribution Cabinet Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YM NE] UE-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Koberqa

  • Z/; Date: 9/24/12 Pnllri* Pnmlrnhnh*di 9/24/12.

Pouria Pou-hobadi

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 291 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ ND- UD--

Seismic Walkdown Checklist (SWC) SWELl-457 Equipment ID No. 71DC-A2 Equip. Class 14- DistributionPanels Equipment Description Relay Room DistributionCabinet Photoaraghs NUoe r-ufdiU UfIlNIsU1 lndfifIn IVUL, efer to question 2.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 292 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[-] NEl U[

Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class' 3 Medium VoltaQe, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Location: Bldg. RB Floor El. 300 Room, Area Col 2 Line R Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NE of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YE NEI ULI N/AE1 The anchorage is not visible for anchorage.
3. Is the anchorage free of corrosion that is more than mild surface YE: NE-- UN N/AF-E oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YE] NE: U[ N/AE anchors?

' Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 293 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE] NE] UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Voltage, Metal clad Switchgear Equipment Description L 15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW

5. Is the anchorage configuration consistent with plant documentation? YEI NE-] U[-E N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEr NEI UZ potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NEI U[E] N/AE-No soft targets.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NE"] UE- N/AE-and masonry block walls not likely to collapse onto the equipment?

8' lighting fixture would not likely to hit SWEL Item. If chain (1 of 2) break, SWEL is secured- no seismic concern.

9. Do attached lines have adequate flexibility to avoid damage? YE NEI' uE] N/AE
10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI UE' of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 294 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YEl- Nil UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Volta-ge, Metal clad Switchgear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N[] UI'I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: A. G, Porch LQ, ~ Date: 11/01/2012 C. Sawatzke C.Saatk 1/0/21 1110112012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 295 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-I NEI UN Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Volta-ge, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Photoaraphs Note:Note: 71DSC-11561 Note: 71DSC-11561

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 296 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Yr-] NEI UH Seismic Walkdown Checklist (SWC) SWELl- 462 Equipment ID No. 71DSC-11561 Equip. Class 3 Medium Voltage, Metal clad Switch-gear Equipment Description L15 UNIT SUBSTATION TRANSF T-13 HIGH SIDE DISC SW Note: 71DSC-11561 Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 297 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YD NDI U[

Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 711NV-3A Equip. Class, 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Location: Bldg. RB Floor El. 344.6' 'Room, Area RB 344.6, CoL5.5, Line P Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YZ NO of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiring anchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YD NEI UN N/AD The expansion anchors and mounting bolts are free of bent, broken, missing or loose hardware.

Panelsneed to be removed and anchorageof internalcomponents needs to be checked.

3. Is the anchorage free of corrosion that is more than mild surface YZ ND U[-D N/AD oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE. ND UD N/ADI anchors?

There are hairline cracks in the grout on top of concrete foundation, and are deemed insignificant based on engineeringjudgment.

'Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 298 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YOI ND- UZ Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 71/NV-3A Equip. Class 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter

5. Is the anchorage configuration consistent with plant documentation? YZ NOI U-I N/A[-

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The 5/8", 3/4", and 1" Hilti Kwik Bolt 3 anchors and the 1/2" ASTM A449 mounting bolts are configuredin accordance with the JAF-CALC 00042 calculation, Rev. 3 per EC-1 7239, DWG. No 1.26-2 and 1.26-102.

6. Based on the above anchorage evaluations, is the anchorage free of YOI ND UN potentially adverse seismic conditions?

The external anchorageis free of potentiallyadverse seismic conditions.

Panels need to be removed and anchorageof internal components needs to be checked.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE ND UD N/AD Soft targets are free from impact from nearby equipment or structures.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NO uD-I N/AD and masonry block walls not likely to collapse onto the equipment?

Light fixtures near the SWEL item need safety latches to prevent it from falling down during a seismic event. However the light fixtures will not damage the SWEL item.

9. Do attached lines have adequate flexibility to avoid damage? YE NDI UD N/ADl The lines attached to the SWEL item have adequate flexibility to avoid damage.
10. Based on the above seismic interaction evaluations, is equipment free YE NEI U-ofpotentially adverse seismic interaction effects?

Based on the above seismic interactionevaluations, the equipment is free of potentially adverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 299 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[-- NE] UZ Seismic Walkdown Checklist (SWC) SWELI-470 Equipment ID No. 71INV-3A Equip. Class 16-Battery Chargersand inverters Equipment Description LPCI MOV Indep Power SupplyA Inverter Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI UE-adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Harpreet Ghuman 1 . Date: 09/30/2012 Yaroslav Losev 09/30/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 300 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YD-] Nn U]

Seismic Walkdown Checklist (SWC) SWELl-470 Equipment ID No. 71INV-3A Equip. Class 16-Battery Chargersand Inverters Equipment Description LPCI MOV Indep Power Supply A Inverter Photographs Note: Picture of equipment 71NV-3A. Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 301 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[E NE! U[

Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class' 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)

Location: Bldg. EG Floor El. 272 Room, Area Col 18.5 Line A1 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-) NO of the 50% of SWEL items requiring such verification)?

Tha anchorageis not visible-Deferred.

2. Is the anchorage free of bent, broken, missing or loose hardware? Y[:] N[-l] U N/AL]-
3. Is the anchorage free of corrosion that is more than mild surface Y[E] NEi UO N/A[:]

oxidation?

4. Is the'anchorage free of visible cracks in the concrete near the Y[-! NE! UM N/A[-]

anchors?

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 302 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NEI U[

Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch-gear Distribution (Bus 12500)

5. Is the anchorage configuration consistent with plant documentation? YEI NEI UEi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YE] NEl UZ potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NE UEi N/AEl No soft targets.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEl UEi N/AEl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YE NEl U[E N/AE-
10. Based 6n the above seismic interaction evaluations, is equipment free YE NEI UE-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 303 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YWI NM. UN Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switchqear Distribution (Bus 12500)

Other Adverse Conditions

11. Have you looked for and found no other seismic'conditions that could YZ N[l U[-

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: A Porch Date: 11/01/2012 C. Sawatzke 11/1/01 1110112012

Attachment C Engineerng Report No. JAF-RPT-12-00015 Rev. 0 Page 304 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YrI N[- UZ Seismic Walkdown Checklist (SWC) SWELl- 474 Equipment ID No. 71L25 Equip. Class 2 Low Voltage Switch gear and Breaker Panel Equipment Description 600V Switch-ear Distribution (Bus 12500)

Photographs Note: 71L25 Note: 71L25 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 305 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[ NR- UL]

Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class' 2 - Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switch-gear DistributiohBUS 12600 Location: Bldg. EB Floor El. 272 Room, Area C: 18.5, L: B Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the-SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist fordocumenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ NEI of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YN N-- U-I N/A--

Anchorage is free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface YO NEI Ur- N/AE-oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE N[I u]Li N/A[-]

anchors?

Anchorage is free of visible cracks in the concrete near the anchors.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 306 of 573 O ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI U--

Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2 - Low Voltage Switchgearsand Breaker Panels Equipment Description 600V Switchpear DistributionBUS 12600

5. Is the anchorage configuration consistent with plant documentation? YE NIl UEI N/All (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfigurationis consistent with the SEWS for 71L26 (Rev. 0). The plug welds were confirmed.

6. Based on the above anchorage evaluations, is the anchorage free of YZ NE-] UE]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN NEI UE] N/A[-]

The soft targets are free from impact by nearby equipment and structure.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NE:] UE] N/AE1 and masonry block walls not likely to collapse onto the equipment?

Masonary block wall divides the East and West Electric bay.'

Modifications were made to enhance the walls as part of IE Bulliten 80-

11. (Ref. CalculationNo. C012, "HCLPFfor block walls EB-272-1,2")
9. Do attached lines have adequate flexibility to avoid damage? YM NEI U[] N/AE1 The attached lines have adequateflexibility.
10. Based on the above seismic interaction evaluations, is equipment free YE NEI U-of potentially adverse seismic interaction effects?

The equipment is free of adverse seismic interactioneffect.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 307 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NEI U--

Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2- Low Voltage Switch-gears and Breaker Panels Equipment Description 600V Switchqear DistributionBUS 12600 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI UE-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Kobercq Date: 9/25/12 Pouria Pourqhobadi 9/25/12 9125112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 308 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ Nr"] U--

Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2 - Low Voltafge Switch-gears and Breaker Panels Equipment Description 600V Switch-gear DistributionBUS 12600 Photographs Note: 71L26 Note: Bottom Comer Panel Open

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 309 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nr] U-Seismic Walkdown Checklist (SWC) SWELl-475 Equipment ID No. 71L26 Equip. Class 2- Low Voltage Switch gears and Breaker Panels Eauipment Description 600V Switchqear DistributionBUS 12600 Note: Cabinet Base Plug Weld Note:

0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 310 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YE NEI UE Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class' 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)

Location: Bldg. RB Floor El. 272 Room, Area Co/ 1.5 Line W Manufacturer,; Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the'results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YFI NEI UZ N/AE-Not Readily accessible.
3. Is the anchorage free of corrosion that is more than mild surface YE-- NE-, U[ N/AE-]

oxidation?

/

4. Is the anchorage free of visible cracks in the concrete near the YE1 NE: UZ N/AE-1 anchors?

1Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 311 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)

5. Is the anchorage configuration consistent with plant documentation? Y[E- NE- UE- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEl NEI UO potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NE: UE- N/A[E No soft targets.
8. Are overhead equipment, distribution systems, ceiling tiles-and lighting, YE NEI U[-E N/AE-]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YE NEJ UE: N/AEl
10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI UM of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 312 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YIEI NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)

Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI UMII adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Area above 71MCC-161 is highly congested; cable trays, piping and conduits appearwell supported.

Supports, hardware etc are intact.

Evaluated by: A. Porch Date: 10/31/2012 C. Sawatzke (,*. 10/31/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 313 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE]-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Equipment Description 600V Motor Control Center (Bus 116100)

Photographs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 314 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI- NEI UE Seismic Walkdown Checklist (SWC) SWELl- 481 Equipment ID No. 71MCC-161 Equip. Class 1 Motor Control Center Eauibment DescriDtion 600V Motor Control Center (Bus 116100)

Note: 71MCC-161 Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 315 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YEI NE] UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class' I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)

Location: Bldg. EB Floor El. 272 Room, Area Col. 18 Line A Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-I NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[-- NE] U[ N/AE]
3. Is the anchorage free of corrosion that is more than mild surface YO- NE] UE N/Ar-oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YO- NE] UL N/AE]

anchors?

' Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 316 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YDI NF- UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)

5. Is the anchorage configuration consistent with plant documentation? YLI NR UI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEI NEI--U[

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEI NEI- UL- N/A[

No soft targets.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NEI ui- N/A[--

and masonry block walls not likely to collapse onto the equipment?

9, Do attached lines have adequate flexibility to avoiddamage? YN NDI UD- N/ADl 10, Based on the above seismic interaction evaluations, is equipment free Y] N[:D U-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 317 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE] NEI UE Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class I Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)

Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YO NEI UEI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: A.Porch / Date: 11/1/2012.

C. Sawatzke ;____________ 11/1/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 318 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWELl- 487 Equipment ID No. 71MCC-252 Equip. Class 1 Motor Control Centers and Wall-mounted contactors Equipment Description 600V Motor Control Center (Bus 125200)

Photographs 0

Note: 71MCC-252 Note: 71MCC-252

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 319 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[ NEI UZ Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)

Location: Bldg. EG Floor El. 272 Room, Area Col 23 line A1 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YI-] NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[I NEI UZ N/AD-
3. Is the anchorage free of corrosion that is more than mild surface YDI NDI U[ N/ADl oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YZ NDl UiD N/ADl anchors?

No cracks noted.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 320 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE] U[

Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus 125400)

5. Is the anchorage configuration consistent with plant documentation? Y[-] Nr--] ULJ N/An (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEI NEI UZ potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN NEI U[I- N/A[-]
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEl UJI N/A[-]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? Y[ ND-] UI- N/AD-
10. Based on the above seismic interaction evaluations, is equipment free YE NEI Ur of potentially adverse seismic interaction effects?

Attachment C Enigineerind Report No. JAF-RPT-1 2-00015 Rev. 0 Page 321 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YD- NEI- UZ Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center (Bus '125400)

Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N[:]U[_

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R Casella '1"- ( z* Date: 10-31-12 A Porch APorch 10-31-12 10-31-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 322 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI NEI UN Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Equipment Description 600V Motor Control Center(Bus 125400)

Photographs Note: Conduit, duct, and cable tray above 71MCC-254 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 323 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEI NE UE Seismic Walkdown Checklist (SWC) SWEL 1- 489 Equipment ID No. 71MCC-254 Equip. Class Motor Control Centers and Wall-mounted Contactors Eauioment Descriotion 600V Motor Control Center (Bus 125400)

Note: Fillet welds at base of 71MCC-254 Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 324 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NnL Uni" Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class' 1 - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)

Location: Bldg. EB Floor El. 272 Room, Area Col. 18, Line B Manufacturer,-Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ N[-]

of the 50% of SWEL items requiring such verification)?

The anchorageconfiguration verification is required.

2. Is the anchorage free of bent, broken, missing or loose hardware? YNI N[D U[-- N/A[D]

Anchorage is free of bent, broken, missing or loos hardware.

3. Is the anchorage free of corrosion that is more than mild surface YM ND-] ULI N/AD--

oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE ND U[D] N/AD anchors?

Anchorage is free of visible cracks in the concrete near the anchors.

' Enter the equipment class nirre from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 325 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ ND:] Ur-]

Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)

5. Is the anchorage configuration consistent with plant documentation? Y[ NDI UE- N/AD1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfiguration is consistentwith SEWS for 71MCC-262.

The 1/8" fillets 2" Long 20" center were field verified in accordancewith DWG. No. 1.43-88.

6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI UD-potentially adverse seismic conditions?.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN NDI UD- N/A[D]

The soft targets are free from imact by nearby equipment and structures

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ ND-- UD- N/AD-and masonry block walls not likely to collapse onto the equipment?

Masonary block wall divides the East and West Electric bay.

Modifications were made to enhance the walls as part of IE Bulliten 80-

11. (Ref. CalculationNo. C012, "HCLPFfor block walls EB-272-1,2")
9. Do attached lines have adequate flexibility to avoid damage? YZ ND'- UD-- N/AD-The attachedlines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YIE NDI UD-I of potentially adverse seismic interaction effects?

The equipment is free of potentially adverse seismic interactioneffects.

Attachm eht C Engihieei'hg Report No. JAF-RPT-12-00015 Rev. 0 Page 326 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NM* U-'

Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class .1 - Motor Control Centers and Wall Mounted 7 Contractors Equipment Description 600V Motor Control Center (BUS 12600)

Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE N[-I UrII adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Kobergq*7d. _ _ _ _ Date: 9/25/12 PouriaPourqhobadi 9/25/12 9125112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 327 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI U[-I Seismic Walkdown Checklist (SWC) SWELl-491 Equipment ID No. 71MCC-262 Equip. Class 1 - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 12600)

Photographs Note: 71MCC-262 Note: Base Welds

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 328 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YEI NE UN Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class' 1 - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)

Location: Bldg. EB Floor El. 272 Room, Area Col. 25.5, Line Al Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NEI of the 50% of SWEL items requiring such verification)?

The anchorageconfiguration verification is required.

2. Is the anchorage free of bent, broken, missing or loose hardware? YEI NE UE N/AE[-
3. Is the anchorage free of corrosion that is more than mild surface YEr NE1 UN N/AE oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YEr NEI UN N/AEr-anchors?

IEnter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 329 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE- N[] U]

Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)

5. Is the anchorage configuration consistent with plant documentation? YE NEI UZ N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YE NEI UZ potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YM NEI U[l N/AI-The soft targets are free from imact by nearby equipment and structures
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UE N/AE-and masonry block walls not likely to collapse onto the equipment?

masonary block walls have been evaluated and enhancedaccordingto DC# DI-96-011, Rev 0 as partIPEEE evaluations.

9. Do attached lines have adequate flexibility to avoid damage? YZ' NE UE N/AE The attachedlines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YE NE UE-of potentially adverse seismic interaction effects?

The equipment is free of potentially adverse seismic interactioneffects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 330 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y-- NEl] UZ Seismic Walkdown Checklist (SWC) S SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)

Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y] N[-] U--

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)-

Evaluated by: HarptreetGhuman Date: 9/25/12 Yaroslav Losev 9/25/12 9125112 ' '

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 331 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YEI- NEI U]

Seismic Walkdown Checklist (SWC) SWELl-493 Equipment ID No. 71MCC-264 Equip. Class I - Motor Control Centers and Wall Mounted Contractors Equipment Description 600V Motor Control Center (BUS 126400)

Photographs Note: 71MCC-264 Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 332 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[Z N7-" U7i Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 'Equip. Class' 4- Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Location: Bldg. CS Floor El. 272 Room, Area Col. 11. Line C Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ NEi of the 50% of SWEL items requiring such verification)? -
2. Is the anchorage free of bent, broken, missing or loose hardware? YN NEI u[-] N/AD--

Anchorage is free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface YN NE! U[] N/A[:

oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation

4. Is the anchorage free of visible cracks in the concrete near the YN NEI U'- N/Ar-anchors?

Anchorage is free of visible cracks in the concrete near the anchors.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 333 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N-- U-Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 - Transformers Equipment Description Emerqency Distribution 15kVA Transformer 71MCC-253-OD3

5. Is the anchorage configuration consistent with plant documentation? Y[D NI-] U[-I N/A[-

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfigurationis consistent with SEWS for 71PT-71ACA2 (Rev. 0). The transformeris wall mounted with four Y2" shells.

6. Based on the above anchorage evaluations, is the anchorage free of YO NEil U-I potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[D NEIl U[] N/AL]

The soft targets are free from impact by nearby equipments and structures.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ N[l U- N/AL]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment and distributionsystems are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YZ NEI] Ui N/AZl The attachedlines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YZ NEI- UE]

of potentially adverse seismic interaction effects?

The equipment is free of potentially adverse seismic interactioneffects.

Atta himedt C Engineeriihg Report No. JAF-RPT-12-00015 Rev. 0 Page 334 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEI UE-]

Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 - Transformers Equipment Description Emergency Distribution15kVA Transformer 71MCC-253-OD3 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NLJ ULI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Kober Date: 9/25/12 PouriaPourqhobadi/9/25/12 9125112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 335 of 573 S ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI-- U--

Seismic Walkdown Checklist (SWC) SWELl-494 Equipment ID No. 71PT-71ACA2 Equip. Class 4 - Transformers Equipment Description Emergency Distribution 15kVA Transformer 71MCC-253-OD3 Photographs 0

Note: 71PT-71ACA2Transformer Note: 71PT-71ACA2Transformer

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page,336 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: Y[ N[] UL' Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emerqencv Distribution7.5 Kva Transformer Location: Bldg. EG Floor El. 272' Room, Area CoL 24 Line A Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

- Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-] NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[ NR] UE] N/AE]

The anchoragehas all necessary hardware

3. Is the anchorage free of corrosion that is more than mild surface YN NEI UE] N/AE]

oxidation?

There are no signs of any corrosion on the anchorage

4. Is the 'anchorage free of visible cracks in the concrete near the YN NE] U[] N/AE]

anchors?

There are no cracks in the concrete near the anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 337 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE No' U--

Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emeraencv Distribution7.5 Kva Transformer

5. Is the anchorage configuration consistent with plant documentation? YE- NEý UE- N/AE (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YN NEI Ur-E potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NE- UEI N/AE-]

Only soft target is anchored cable

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEI UE] N/AE-and masonry block walls not likely to collapse onto the equipment?

All conduit located overhead is all well supported.

9. Do attached lines have adequate flexibility to avoid damage? YN N[E] uEr N/AEj Only has attached conduit and armored cable. Both have adequate flexibility
10. Based on the above seismic interaction evaluations, is equipment free YE NE:] U-of potentially adverse seismic interaction effects?

Attachment C .Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 338 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NM UM Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emergency Distribution7.5 Kva Transformer Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE N[i ULI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R. Casella/ Date: 10-26-12 A.G. Porch/ 10-26-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 339 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NO Ul--

Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description Emergency Distribution 7.5 Kva Transformer Photographs 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 340 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NR] UE]

Seismic Walkdown Checklist (SWC) SWELl- 495 Equipment ID No. 71PT-71ACA4 Equip. Class 4-Transformers Equipment Description EmerQency Distribution 7.5 Kva Transformer 0

Note: 71PT-71ACA4 anchorage Note: 71PT-71ACA4

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 341 of 573 AT'rACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ N] U"I Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class' 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Location: Bldg. RB Floor El. 272' Room, Area RB South East, Col. 14, Line A Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YZ NEI of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiringanchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YN N[:] UL- N/A[--

Only three anchors actually penetrate through the block wall and are fastened to the back side with a plate and an L2x2 structuralangle.

This is acceptable since the SEWS evaluation addressedthis anchorageconfiguration and found that it was acceptable.

3. Is the anchorage free of corrosion that is more than mild surface YZ NR ULI N/ADl oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y[ ND1 U[- N/Ar-D anchors?

The transformerunit is anchoredto a block wall. There are no visible cracks on the wall.

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 342 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[K NEI UiD Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2

5. -1s the anchorage configuration consistent with plant documentation? YZ NO UEij] N/AE1 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Four (4), 1/2" anchors attach the transformerto the wall. Only three out of four anchorspenetrate through the wall and are fastened on the back of the wall by structuralmembers and a steel plate. Only three anchors are utilized in the analysis. The 4, 1/2" anchors are configured in accordancewith the SEWS document for equipment 71PT-71ACUPS, Rev. 0.

6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[E ULI potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEI N[:- U[-] N/An There are no soft targets on the equipment.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE, NEI ULI N/AE1 and masonry block walls not likely to collapse onto the equipment?

The masonry block walls were evaluated in calculation C012, "HCLPF for Block Walls EB-272-1, 2" underproject USI A-46/IPEEE Seismic Evaluation Project,and were found to be acceptable. The overhead equipment, distributionsystems, ceiling tiles and lighting not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YE NEI UEI N/AE-The lines attachedto the SWEL item have adequate flexibility to avoid damage.
10. Based on the above seismic interaction evaluations, is equipment free YE NE- u0 of potentially adverse seismic interaction effects?

Based on the above seismic interactionevaluations, the equipment is free of potentially adverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 343 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEi Ul-'

Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N[I- ULI adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Harpreet Ghuman

  • Date: 09/28/2012 Yaroslav Losev. 09/28/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 344 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NR Ur-]

Seismic Walkdown Checklist (SWC) SWELl-498 Equipment ID No. 71PT-71ACUPS Equip. Class 04-Transformers Equipment Description UninterruptableBus 37.5KVA Transformer 71MCC-252-OD2 Photographs Note: Pictureof equipment 71PT-71ACUPS. Note: Picture of the anchorage attachment to the wall on the back side.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 345 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ ND U-II Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 - Battery Racks /

Equipment Description 125 Volt Station Battery A Location: Bldg. BR Floor El. 272 Room, Area Col 12 Line E Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO NEI-of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[ NEI U[1 N/AI[I The anchorage has all necessary hardware
3. Js the anchorage free of corrosion that is more than mild surface YO N[-] uJ-I N/AD-1 oxidation?

Minor paint chipping was found at specific locations. This is not a structural concern

4. Is the anchorage free of visible cracks in the concrete near the YZ NDI ul- N/AD anchors?

The concrete is free of cracking in the areas near the anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 346 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ- NE-I U' Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 - Battery Racks Equipment Description 125 Vo/t Station Battery A

5. Is the anchorage configuration consistent with plant documentation? YE N'-Z U-- N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.20-3, 1.20-8, associated SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free,of YO N] UMi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NEl UZ1 N/A[-
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UE] N/A[--

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YN Nih u-] N/AZ1 Flexible conduit connections to station batteries have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YZ NZI U[-

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 347 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI U--

Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15- Battery Racks Equipment Description 125 Volt Station Battery A Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NI-- UI-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Rick Casella C ~& Date: 10/30/12 Al Porch 10/30/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 348 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI Ur-]

Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 - Battery Racks Equipment Description 125 Volt Station BatteryA PhotoaraDhs Note: 71SB-1 Note: 71SB-1

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 349 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YN NEI- UF Seismic Walkdown Checklist (SWC) SWELl- 501 Equipment ID No. 71SB-1 Equip. Class_15 - Battery Racks EauiDment DescriDtion 125 Volt Station Batterv A Note: 71SB-1 anchorage Note: 71SB-1 anchorage 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 350 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEI UF]

Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class' 15-Batter-i Racks Equipment Description 125 Volt Station Battery B Location: Bldg. BR Floor El. 272' Room, Area BR3. Col. 12, Line F Manufacturer, Model, Etc., (optional but recommended)

Instructionsfor Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the-following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YM NE]

of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiringanchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YN NEI ULI N/AL]

The seventy two (72), 1/2" diameter expansion anchors are free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface Y[ NEI U[--] N/AL-oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE NIl U[] N/AL-]

anchors?

There are no visible cracks in the concrete near the anchors.

'Enter the equipment class bname from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 351 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI] ULJ Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B

5. Is the anchorage configuration consistent with plant documentation? YN NEI U-I N/A[-]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The frames of the racks are spaced at 27" on center. There are two racks mounted to each other (back to back) at the center location. The racks on the sides are by themselves. The 72, 1/2" expansion anchors (18 for the side racks, and 36 for the center rack) are configured in accordance with the EC36608 and drawing 1.20-3.

6. Based on the above anchorage evaluations, is the anchorage free of YE NE-- UEi potentially adverse seismic conditions?

Based on the above anchorageevaluations, the anchorageis free of potentiallyadverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ N-- u[--1 N/A --

There are no soft targets on the equipment.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NE: UE- N/AZ-and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YZ NEI U[-] N/AZ!

The lines attached to the SWEL item have adequate flexibility to avoid damage.

10. Based on the above seismic interaction evaluations, is equipment free YZ NEI UE-of potentially adverse seismic interaction effects?

Based on the above seismic interactionevaluations, the equipment is free of potentiallyadverse seismic interactioneffects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 352 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NrI- U-'

Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y; N[I- UI-adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhuman Date: 09/30/2012 Yaroslav Losev 09/30/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 353 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N- UF-Seismic Walkdown Checklist (SWC) SWELl-502 Equipment ID No. 71SB-2 Equip. Class 15-Battery Racks Equipment Description 125 Volt Station Battery B Photoqraphs Note: Picture of equipment 71SB-2. Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 354 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEIl U[]

Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Location: Bldg. BR Floor El. 282 Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YO NEIl U-] N/A-]

Visible anchorageis free of bent, broken, missing or loose hardware.

3. Is the anchorage free~of corrosion that is more than mild surface Y[ NEI U[E] N/AL]

oxidation?

Visible anchorageis free of corrosion.

4. Is the anchorage free of visible cracks in the concrete near the Y[ NEI UiE N/A[-I anchors?

No cracks.

Attachment C Engineering Report No, JAF-RPT-12-00015 Rev. 0 Page 355 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NM ULI Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlinq Unit

5. Is the anchorage configuration consistent with plant documentation? YEI N[-] UD N/AZ-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YZ Ni-i U-I potentially adverse seismic conditions?

Interaction Effects

.7. Are soft targets free from impact by nearby equipment or structures? YE N[-] uM N/AD-

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEi UE1 N/AE-and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YE NEl UD1 N/AD-]
10. Based on the above seismic interaction evaluations, is equipment free YE N[E UM of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 356 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI U[-]

SeismicWalkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handling Unit Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI U-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Missing mounting screws on door of unit 2 missing screws on west hinged door 1 missing screw on east hinged door All screws missing on bottom row of door panel The existing screws will keep the door secured. This condition will not create any credible adverse seismic interaction.

Although only a portion of the anchorage was visible, the existing SEWS for 72AHU-30A shows significantanchoragemargin.

Evaluated by: R. Casella *C Date: 10-30-12 I

A. Porch 10-30-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 357 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YS NOl UR Seismic Walkdown Checklist (SWC) SWELl- 508 Equipment ID No. 72AHU-30A Equip. Class 10. Air Handlers Equipment Description Battery Room A Air Handlingq Unit Photographs Note: 72AHU-30A Note: 72AHU-30A

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 358 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE]- ULI Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Location: Bldg. BR Floor El. 282 Room, Area Col 12 line E Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YN N[I:

of the 50% of SWEL items requiring such verification)?

2. Is the anchorage free of bent, broken, missing or loose hardware? Y[ N[:] U[] N/A[-]

3/8" anchor bolts to floor (4 locations-4 bolts per location) are slightly skewed. This condition was noted and accepted in the SEWS A-46 evaluation.

3. Is the anchorage free of corrosion that is more than mild surface YO NIEJ UEI N/AEJ oxidation?

The bolting shows signs of minor surface oxidation. This is not a structural concern

4. Is the anchorage free of visible cracks in the concrete near the YOI NO~ U[:] N/AEL]

anchors?

The concrete nearby the anchorage has no cracking

Attachment C Engineering Report No. JAF-RPT-12-00015 I Rev. 0 Page 359 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ NEI U-]

Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan

5. Is the anchorage configuration consistent with plant documentation? Y[ N[I UI- N/A[-]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageis consistent with A-46 SEWS for 72FN-31A.

6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Ur-1 potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN N[] ULI N/A-1
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEI ULI N/A[:]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YS NW- UW- N/A~l
10. Based on the above seismic interaction evaluations, is equipment free YN NEI UM of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 360 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NE] UM Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEJ UEi adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R Casella * . Date: 10-30-12 10-30-12...

A Porch 10-30-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 361 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE N-] Ur-I Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans Equipment Description Battery Room A Recirc Fan Photographs 0

Note: 72FN-31A Note: 72FN-31A anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 362 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N-- Ur-Seismic Walkdown Checklist (SWC) SWELl- 516 Equipment ID No. 72FN-31A Equip. Class Fans EauiDment DescriDtion Batten/ Room A Recirc Fan Note: 72FN-31A anchorage of fan assembly Note:

to vibration isolatorand to floor 0

Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 363 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YO NEI Un Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Location: Bldg. BR Floor El. 282 Room, Area 12, E Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ NE of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI NM U[E N/AE-]

East Hat - SW & NE bolts slightly skewed but have contact with hat flange. SE & NE bolts have less than full threadencasement

(<Threadsbelow full encasement). Blot size is 3/8 inch. Each hat secure to floor with bolts. These issues judged to not be a seismic concern.

3. Is the anchorage free of corrosion that is more than mild surface YN NEI UE1 N/AE1 oxidation?

The bolting shows signs of minor surface oxidation. The oxidation is not a seismic concern

4. Is the anchorage free of visible cracks in the concrete near the YE NEl U[E- N/AE-anchors?

No cracking was present

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 364 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ Nr- U-Seismic Walkdown Checklist (SWC) SWELl-518 Equipment ID No. 72FN-46A Equip. Class_09 - Fans-Equipment Description Battery Room A Exhaust Fan

5. Is the anchorage configuration consistent with plant documentation? YZ N[-- U[I- N/AI--

(Note: This question only applies if the item is one of the 50% for which anchorage configuration verification is required.)

Y2 inch bolts at connection between fan/motor s/zid and vibration damper (1.79-474, SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of YE NEIl U-I potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEI N[E UE-- N/A[
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO NEIl UEI N/AEl and masonry block walls not likely to collapse onto the equipment?

Flex conduit has adequate flexibility.

9. Do attached lines have adequate flexibility to avoid damage? YZ Nl UEl N/AFl
10. Based on the above seismic interaction evaluations, is equipment free YN N[-] U-1 of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 365 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE N1 UI--

Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YM NEI UD-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary) cUUL-uy L. va I VU(*L*

k Y4 VIt,Lflý 11 Date: 10/30/12

&62JI ~

Al Porch 10130112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 366 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09- Fans Equipment Description Battery Room A Exhaust Fan Photographs 0

Note: 72FN-46A anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 367 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[ NR" Ur-]

Seismic Walkdown Checklist (SWC) SWELl- 518 Equipment ID No. 72FN-46A Equip. Class_09 - Fans EauiDment DescriDtion Battery I Room A Exhaust Fan Note: 72FN-46A showing vibration isolators Note: 72FN-46A showing one anchorto floor installed at a slight skew 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 368 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NE' UM-Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class' 09-Fans Equipment Description Battery Room B Exhaust Fan Location: Bldg. BR Floor El. 282' Room, Area BR4, Col. 12, Line F Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO Nl of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiring anchorage configurationverification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YO NO ul-I N/A--

One anchoris missing on the North East corner of the skid; however, this is already documented in the SEWS evaluation and was found to be acceptable. One anchoris loose on the North West corner of the skid.The resolution to this deficiency is tracked through CR-JAF-2012-06538

3. Is the anchorage free of corrosion that is more than mild surface YZ NEIrUI-- N/A[]

oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE Nil UiL N/A[-l anchors?

There are no visible cracks in the concrete near the SWEL item.

Enter the equipment class name from Appendix B: Classes of Equipment.

Atiachm ent C Erigineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 369 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YN ND Ut]

Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan

5. Is the anchorage configuration consistent with plant documentation? YE Nt] Ut] N/At]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The 8, 1/4" expansion anchorsare configured in accordancewith the SEWS document for 72FN-46A ,which has the same configuration as 72FN-46B, except for one missing bolt, which was evaluate in SEWS to be OK).

6. Based on the above anchorage evaluations, is the anchorage free of YtI NZ UEi potentially adverse seismic conditions?

Based on.the above anchorage evaluations,the anchorageis not free of potentiallyadverse seismic conditions. See item 2.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y] NEI .Ut] N/At]

Soft targets are free from impact by nearby equipment.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NtI Uti N/At]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? Y[ NtI Ut] N/At]

The lines attached to the SWEL item have adequateflexibility to avoid damage.

10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI U-1 of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations,the equipment is free of potentially adverse seismic interactioneffects.

Attachrmient C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 370 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NEI UI-I Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YS N[-] U["]

adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhumanbI *jAA. Date: 09/30/2012 Yaroslav Losev 09/30/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 371 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI UL-Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Equipment Description Battery Room B Exhaust Fan Photographs 0

Note: Picture of equipment 72FN-46B. Note: Picture showing the missing anchoron the skid for the SWEL item.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 372 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NI'- UI-]

Seismic Walkdown Checklist (SWC) SWELl-519 Equipment ID No. 72FN-46B Equip. Class 09-Fans Eauipment Description Battery Room B Exhaust Fan Note: Picture showing the loose anchoron Note:

the skid for the SWEL item.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 373 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI U-I Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class, 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Location: Bldg. BR Floor El. 272' Room, Area BR5, Col. 11.5, Line C Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE:] NZ of the 50% of SWEL items requiring such verification)?

The item is not one of the 50% of SWEL items requiringanchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or-loose hardware? YZ ND1 U[-I N/AD-The equipment is stitch welded in four (4) locations and the welds are intact and do not appeardamaged.
3. Is the anchorage free of corrosion that is more than mild surface Y[ N[-' UD- N/Ar-oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y[ Nr-- U-I N/A[]

anchors?

There are no visible cracks in the concrete near the SWEL item.

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 374 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI UM Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel

5. Is the anchorage configuration consistent with plant documentation? YEI NEI U[-] N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Item is not one of the 50% for which an anchorageconfiguration verification is required.

6. Based on the above anchorage evaluations, is the anchorage free of YN NEi UiE potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NEI UEi N/AEl Soft targets are free from impact by nearbyequipment.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UEi N/AE[

and masonry block walls not likely to collapse onto the equipment?

Safety latches for the overheadlight fixtures should be installed. There is a masonry block wall near the equipment; however, the wall was evaluated under IPEEEeffort to reinforce the block walls underJAF-RPT-MISC-0221 1, Section 3.1.4.1, page 3-44, Table 3.1.4.1.

There is a 1" gap between cable tray I TCO77R and the SWEL item; however, based on engineeringjudgment this is a sufficient amount of space during a seismic event to where there will be no interaction between SWEL equipment and raceway.

9. Do attached lines have adequate flexibility to avoid damage? YE NEI uE1 N/AEl The lines attached to the SWEL item have adequateflexibility to avoid damage.
10. Based on the above seismic interaction evaluations, is equipment free YE N[l UEl of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations,the equipment is free of potentially adverse seismic interaction effects.

Attachmen t C Engin:eering Report No. JAF-RPT-12-00015 Rev. 0 Page 375 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N[II URI Seismic Walkdown Checklist (SWC) SWELI-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI UI--

adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Harpreet Ghuman Date: 09/30/2012 Yaroslav Losev 09/30/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 376 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEZ UF--j Seismic Walkdown Checklist (SWC) SWELl-522 Equipment ID No. 72HV-7A Equip. Class 20-Instrument and Control Panels Equipment Description Admin Building Ventilation Control Panel Photographs Note: Picture of equipment 72HV-7A. Note: Picture showing the 1"gap between the cable tray ITCO77R and the SWEL item.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 377 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NE]I UF7 Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan Location: Bldg. EG Floor El. 272', Room, Area Col. 24 Line Al Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-7--NM of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YE NEI UL] N/A[-'

Ability to discern condition of anchoragewas difficult based on distance to anchorage from our location. Based on what we could see, anchoragewas free of bent, broken or missing hardware.

3. Is the anchorage free of corrosion that is more than mild surface Y[9 NEI UL-E N/A[]

oxidation?

No corrosion was evident, based on limited view from floor.

4. Is the anchorage free of visible cracks in the concrete near the YEL N[l U[-] N/AN anchors?

The component is connected to steel. There is no concrete.

EN-DC-168 REV 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 378 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE ND UEI Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergencv Diesel GeneratorA Vent Supplv Fan

5. Is the anchorage configuration consistent with plant documentation? Y[-- NE] UE- N/AS (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YE NEi ULi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEi NEI UE] N/AN There are no soft targets on this equipment.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UEi N/AE]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YE] NE] U--] N/A[

No attachedlines

10. Based on the above seismic interaction evaluations, is equipment free YE N[] UE]

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 379 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI U-]

Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. Q2FN-1A Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE NEI U[I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: A.G. Porch / Date: 10/26/12 R. Casella I 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 380 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI UL-I Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-IA Equip. Class 9- Fans Equipment Description Emergzency Diesel GeneratorA Vent Supply Fan Photographs Note: 92FN-IA Note: 92FN-IA 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 381 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NEI U-Seismic Walkdown Checklist (SWC) SWELl- 555 Equipment ID No. 92FN-1A Equip. Class 9- Fans Equipment Description Emergency Diesel GeneratorA Vent Supply Fan

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 382 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NRI URl Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-IOIA Equip. Class 19- Temperature Sensor Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector Location: Bldg. EG Floor El. 300 Room, Area Col. 23 Line A2, AZ Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-1 NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YE NEI UE1 N/A--

Ability to discern condition of anchorage was difficult based on distance to anchoragefrom our location. Based on what we could see-to the ceiling mounted component, it appearedto be secured to the flange of the roof steel.

3. Is the anchorage free of corrosion that is more than mild surface YZ N[I] ULI N/A[-]

oxidation?

Ability to discern condition of anchorage was difficult based on distance to anchoragefrom our location. Based on what we could see to the ceiling mounted component, it appearedto be secured to the flange of the roof steel.

4. Is the anchorage free of visible cracks in the concrete near the YI- ND- UD- N/AO anchors?

There is no concrete. The component is mounted to steel beam flange.

EN-DC-168 REV 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 383 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NR Ur Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-1OIA Equip. Class 19 - Temperature Sensor.

Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector

5. Is the anchorage configuration consistent with plant documentation? Y-] NF] U-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI UI-potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact-by nearby equipment or structures? YZ N[-] U-1 N/AE-
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YLI N[: U[I N/Az and masonry block walls not likely to collapse onto the equipment?

Attached to overhead roof steel beam, there are no visible objects to fall on the SWEL item.

9. Do attached lines have adequate flexibility to avoid damage? Y[W NEI UEII N/AZ
10. Based on the above seismic interaction evaluations, is equipment free YZ NE] Ur-of potentially adverse seismic interaction effects?

EN-DC-168 REV 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 384 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI] U-I!

Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-1O1A Equip. Class 19 - Temperature Sensor Equipment Description Emergency Diesel GeneratorRoom A South Side Resist Temperature Detector Other Adverse Conditions

11. Have you looked for~and found no other seismic conditions that could YZ NEi UrI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

(see photo)

Evaluated by: A.G. Porch , Date: 10/26/12 R. Casella / 10/26/12 EN-DC-1 68 REV 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 385 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ N[:] UFW Seismic Walkdown Checklist (SWC) SWELl- 577 Equipment ID No. 92RTD-101A Equip. Class 19 - Temperature Sensor Equipment Description Emerqency Diesel GeneratorRoom A South Side Resist Temperature Detector Photographs Note: 92RTD-IOIA Note: 92RTD-IOIA EN-DC-168 REV 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 386 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE] U-1 Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-1O1B Equip. Class' 19 - Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Location: Bldg. EG Floor El. 272 Room, Area C: 27, L:A2 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NM of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YN N[i UiEl N/AD-The unit is at high elevation. No close visual inspection is possible.

Based on review of drawings, and weight of the equipment, the anchorage was determined to be adequate

3. Is the anchorage free of corrosion that is more than mild surface Y[ NEI Ui[E N/A[:

oxidation?

The unit is at high elevation. No close visual inspection is possible

4. Is the anchorage free of visible cracks in the concrete near the Y[ N[Il U[-- N/Ar-Z anchors?

The unit is at high elevation. No close visual inspection is possible

'Enter the equipment class name from Appendix B: Classes of Equipment.

Afttchmient C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 387 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NrIi U--

Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No.- 92RTD-IOIB Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector

5. Is the anchorage configuration consistent with plant documentation? Y[I NEI U[- N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of Y] Nil U[I potentially adverse seismic conditions?

The anchorageis free of any potentiallyadverse seismic condition.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ NEI ULI N/AEl The soft targets are free from impact by nearbyequipment and structures.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NEI UEI N/AEZ and masonry block walls not likely to collapse onto the equipment?

Unit is mounted on a masonry block wall. The block walls have been evaluated and enhanced in accordance with DC# D1-96-011, RevO as part of IPEEE evaluations.

9. Do attached lines have adequate flexibility to avoid damage? YZ NE U[- N/A-Attached lines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free Y; N[il UIý of potentially adverse seismic interaction effects?

The equipment is free of potentiallyadverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 388 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEl UI Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-IO1B Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI U[-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Pouria Pour hobadi Date: 9/21/12 Donald Kobera 9/21/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 389 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NE] UFi-Seismic Walkdown Checklist (SWC) SWELl-578 Equipment ID No. 92RTD-101B Equip. Class 19- Temperature Sensors Equipment Description EDG B Room South Side Resistance Temperature Detector Photographs Note :_92R TD-101B Temperature sensor installed Note:

on concrete block.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 390 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE Nr- U[I Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-Al Equip. Class 12-Air Comoressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl Location: Bldg. EG Floor El. 272' Room, Area Col. 24 Line A2 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YN Nil of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YN N[i U[I N/AE--

Anchorage contains all necessary hardware

3. Is the anchorage free of corrosion that is more than mild surface YE NE UE N/AR oxidation?

The anchorage has a small amount of paint chipping that is not a structural concern

4. Is the anchorage free of visible cracks in the concrete near the YO NEJ UL[ N/AR anchors?

There are no cracks in the concrete around the anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 391 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEI UD Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1I. Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl

5. Is the anchorage configuration consistent with plant documentation? YE NE:] ULI N/AFi (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.12-2, associated SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of YE N[I U-]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN N-] U[] N/A[]

Soft targets = 1/4" tubing (cu) see photo; Cable trays, conduit and 2" diameter air piping well supported (Note tubing in tube track - secure -

SAT). No soft target issues - SAT.

8, Are overhead equipment, distribution systems, ceiling tiles and lighting, Y] NE] U[] N/AEr and masonry block walls not likely to collapse onto the equipment?

Lighting, masonry wall, cable trays - all SAT.

9. Do attached lines have adequate flexibility to avoid damage? YE NE] ULI N/AE]

Flex conduit and air hose (air start system ref.. 93RV-101A) - all SAT.

10. Based on the above seismic interaction evaluations, is equipment free YZ N[-] UM of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 392 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NE]UUF-1 Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-Al Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorAl Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N--] U-I adversely affect the safety functions of the equipment?

All SAT.

Comments (Additional pages may be added as necessary)

Some cracks running E-W along masonry wall near concrete pad (see photo) - not an issue (i.e.

shrinkage/settlement cracks). Not considered adverse to anchorage system.

Evaluated by: R. Casella / Date: 10/26/12 A.G. Porch / 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 393 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NF-- UI-Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1 Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorA I Photographs Note: 93AC-A1 AC-Al including anchorage on east end

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 394 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NEIru[]

Seismic Walkdown Checklist (SWC) SWELl- 581 Equipment ID No. 93AC-A1 Equip. Class 12-Air Compressors Equipment Description Emergency Diesel GeneratorA Air Start CompressorA 1 0

Note: 93A C-A I anchorage 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 395 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ Nn U[j Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al Location: Bldg. EG Floor El. 272' Room, Area 24, A2 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO NEI of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YZ NE: UE- N/A[E-Anchorage contains all necessary hardware
3. Is the anchorage free of corrosion that is more than mild surface YZ NE: UEl N/A-oxidation?

Mild surface oxidation and paint chipping was observed - no structural concerns

4. Is the anchorage free of visible cracks in the concrete near the YEI NO U[-- N/AE-anchors?

Settlement crack in slab along masonry block wall approximately 4" South of wall. Not an issue based on load on anchor - OK.

Hairline crack (very light) - SAT.

Welds - leg to base plate and tank - SAT

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 396 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-Al Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al

5. Is the anchorage configuration consistent with plant documentation? YN NEI UE- N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1./12-43, associated SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI UIE]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targetsfree from impact by nearby equipment or structures? Y[ NEI U[I N/AZl 93EDG-701A (3/4" drain valve - air receiver drain valve) only soft target

- free from seismic effects (ppg above is well supported) - SAT

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NEI ULi N/AZl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y[ NEI ULi N/AZ-
10. Based on the above seismic interaction evaluations, is equipment free YZ NEI U[-

of potentially adverse seismic interaction effects?

Attachrmient C Engirdering Report No. JAF-RPT-12-00015 Rev. 0 Page 397 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI U0-Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 *Equip. Class 21 Equipment Description Emergency Diesel GeneratorA Air Start Receiver Al Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YO NEI UE-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Other air tanks are typical of 93AR-A1 Evaluated by: R. Casella I Date: 10/26/122 A.G. Porch 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 398 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEi UI-]

Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emergencv Diesel GeneratorA Air Start Receiver A 1 Photographs Note: 93AR-Alincluding support legs (note -

3rd support leg in rearcannot be seen in this photo)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 399 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NO ULI Seismic Walkdown Checklist (SWC) SWELl- 582 Equipment ID No. 93AR-A1 Equip. Class 21 Equipment Description Emerqency Diesel GeneratorA Air Start Receiver A l Note: 93AR-A I anchorage to floor at 2 of the 3 legs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 400 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NDI U[-]

Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class' 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Location: Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26.5 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YjN NEI of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiringanchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YO ND-] ULI N/AD1 The three (3), 3/8" expansion anchors are free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YN NEI U-] N/AD-oxidation? )

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YN NDI UD1 N/ADl anchors?

There are concrete hairline cracks within the vicinity of the anchors but they do not pass through the center of any of the anchors. Therefore, based on engineeringjudgment there will be no significantreduction in the anchorstrength due to these cracks and is deemed acceptable.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 401 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YN NEI ULI Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2

5. Is the anchorage configuration consistent with plant documentation? YE NEi U[iI N/A[-]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The configuration of the three (3), 3/8" expansion anchors are consistent with the SEWS documentation for equipment 93AR-Al (same as 93AR-B2).

6. Based on the above anchorage evaluations, is the anchorage free of YO NE] UiE potentially adverse seismic conditions?

Based on the above anchorageevaluations, the anchorageis free of potentially adverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YO NE]I UiE N/AL]

The soft targets are free from impact by nearby equipment or structures.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NE] Ul] N/AL-]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? Y[ NEI UE] N/AL]

The lines attached to the SWEL item have adequate flexibility to avoid damage.

10. Based on the above seismic interaction evaluations, is equipment free YE NE] uIE]

of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations, the equipment is free of potentiallyadverse seismic interactioneffects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 402 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ N'-' U--

Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 18-Instrument Racks Equipment Description EDG B Air Start Receiver B2 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI- U[]

adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhuman IW. Date: 09/21/2012 Yaroslav Losev--S 09/21/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 403 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NR-] ULI Seismic Walkdown Checklist (SWC) SWELl-594 Equipment ID No. 93AR-B2 Equip. Class 21-Tanks and Heat Exchangers Equipment Description EDG B Air Start Receiver B2 Photographs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 404 of 573 S ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YI-- NEI UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel Location: Bldg. EG Floor El. 272 Room, Area 24, GI Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YED N[:]

of the 50% of SWEL items requiring such verification)?

2. Is the anchorage free of bent, broken, missing or loose hardware? Y[I NEI U[I N/AE]
3. Is the anchorage free of corrosion that is more than mild surface YE-] NE] ULI N/AE]-

oxidation?

4. Is the anchorage free of visible cracks in the concrete near the Y[E] NE] UN N/A[-]

anchors?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 405 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel

5. Is the anchorage configuration consistent with plant documentation? YI- NEI US N/AZl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEI NEi US potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YS NEI UE] N/A[-
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YS NEI uEr N/A[Z and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YZ NEI] UE] N/A
10. Based on the above seismic interaction evaluations, is equipment free YZ NEI UE]

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 406 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE] NEI] U Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 - Instrument and Control Panels Equipment Description EDG A Engine Control Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE NE] UE]

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Conduit (rigid)is supportedby unistrut vertical/ laterally (via knee brace); There is approximately5 feet of flex conduit at inter with top of panel. Therefore any seismic loads below rigid conduit support will be dissipatedby flex.

Evaluated by: Rick Casella C 42 Date: 10/29/12 Al Porch 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 407 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y-'LI NE] UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 - Instrumentand Control Panels Equipment Description EDG A EnQine Control Panel Photographs 0

ix conduit rising off top of panel

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 408 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YLI Nil UN Seismic Walkdown Checklist (SWC) SWELl- 624 Equipment ID No. 93ECP-A Equip. Class_20 - Instrumentand Control Panels Equipment Description EDG A Engine Control Panel 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 409 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI Ur-D Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class' 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Location: Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26, Line A3 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE Ni:

of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiringanchorage configuration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? YM NIl UL N/A-]

The four (4) 3/4" expansion anchors are free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface YE NrI U[IE] N/A[--

oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE Nil U[- N/A[--

anchors?

The anchors are free of visible cracks in the concrete.

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 410 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NF1 UF-Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel

5. Is the anchorage configuration consistent with plant documentation? YZ NEI UI- N/AE-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The configurationof the four (4), 3/4" expansion anchors is consistent with the SEWS documentation for equipment 93ECP-A (same as 93ECP-B).

6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Uil potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y] NEI UE- N/AZl The soft targets are free from impact by nearby equipment or structures.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEl UZ-- N/A--

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YN NE UEi N/AZ The lines attachedto the SWEL item have adequate flexibility to avoid damage.
10. Based on the above seismic interaction evaluations, is equipment free YN NO UE-of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations, the equipment is free of potentiallyadverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 411 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEIl ULI Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[-] NO UF-Z adversely affect the safety functions of the equipment?

Top of the Control Panel is unsupported. The SWES evaluation determined that the panel is acceptable without these anchors; however the same evaluation does not include the load transferred from the overhead conduits attached to the panel. These conduits drop approximately 10 ft vertically into the panel without any lateralsupport to minimize the interactionload to the panel. Based on engineering judgment, during a seismic event a significant lateralload from the conduits will contribute to the moment arm transferredto the base anchors which potentiallycould result in failure of the anchorsand overturn the panel. The resolution to this deficiency is tracked through LB-01.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhuman " . Date: 09/21/2012 Yaroslav Losev 09/21/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 412 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YNI NEIr ULI Seismic Walkdown Checklist (SWC) SWELl-625 Equipment ID No. 93ECP-B Equip. Class 20-Instrument and Control Panels Equipment Description EDG B Engine Control Panel Photographs Note: Picture of equipment 93ECP-B. Note: the Note: Picture showing that the control panel is conduits attached at the top of the panel are the not attached/supportedat the top.

ones that extend approximately 10' vertically.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 413 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Yo] NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Location: Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE] NE of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[E] Nr] ULI N/A[-]
3. Is the anchorage free of corrosion that is more than mild surface Y[E] NE] UN N/AE-]

oxidation?

4. Is the anchorage free of visible cracks in the concrete near the Y[E] NE] UN N/AE]

anchors?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0, Page 414 of 573 0

ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NEI UE Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel

5. Is the anchorage configuration consistent with plant documentation? YE] N[-1 UI- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YEI NE UM potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ NE-I UE1 N/AEl
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[D NM UEl N/AEl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YO NEl UE N/A[E]
10. Based on the above seismic interaction evaluations, is equipment free YN NEl U[E]

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 415 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YF-- NE] UZ Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[D N[i Uil adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Need support detail Evaluated by: Rick Casella FC~4. Date: 10/29/12 Al Porch 10129112 10/29/12 -

Al Porch

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 416 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YEI- NEl U[

Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Photographs

ýg anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 417 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YEr- NR- UO Seismic Walkdown Checklist (SWC) SWELl- 628 Equipment ID No. 93ECSP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A Engine Control Sub-Panel Note: 93ECSP-A anchorage M-

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 418 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ N[E U[

Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class' 20 - Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Location: Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YZ NE of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YE]I NEI UN N/AZ-The four (4) 3/8" Hilti anchorsare free of bent, broken, missing or loose hardware.

Panels need to be removed and anchorage of internal components needs to be checked.

3. Is the anchorage free of corrosion that is more than mild surface YZ NEI uE- N/AZ-oxidation?

The anchorageis free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y[ NE-] UE] N/AZ!

anchors?

The anchorageis free of visible cracks in the concrete nearthe anchors.

Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 419 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NE] UFL Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20 - Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel

5. Is the anchorage configuration consistent with plant documentation? Y[ NEL UI- N/ALl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The configurationof the four (4), 3/8" Hilti Anchors is consistentwith SEWS for 93 ECSP-A Rev 0, which is identicalto ECSP-B.

6. Based on the above anchorage evaluations, is the anchorage free of YI- NEI ULI potentially adverse seismic conditions?

Panels need to be removed and anchorage of internal components needs to be checked.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ NEL ULE N/A[L
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ N[L U[L N/AL-and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y[ NEL UL[] N/ALE
10. Based on the above seismic interaction evaluations, is equipment free Y[ N[-]7LIu of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 420 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI U-'

Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YEE N[i UMI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Harpreet Ghuman -M-.--: Date: 9/21/12 Yaroslav Losev 9121112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 421 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YN N[-E ULI-Seismic Walkdown Checklist (SWC) SWELl-629 Equipment ID No. 93ECSP-B Equip. Class 20- Instrument and Control Panels Equipment Description EDG-B Engine Control Sub Panel Photographs Note: 93ECSP-B Engine Control Sub Panel Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 422 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YN NEI UF]

Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Enqine Generators Equipment Description Emergency Diesel GeneratorC Location: Bldg. EG Floor El. 272' Room, Area Col. 24 line A4, AZ Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic.Walkdown of an item of equipment on the SWEL. The space below each of the following questions. may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO NEI of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YO N[-- UI- N/A[-

Anchorage contains all necessary hardware

3. Is the anchorage free of corrosion that is more than mild surface YO NEI- uE N/AZJ oxidation?

The anchorage is free of any corrosion

4. Is the anchorage free of visible cracks in the concrete near the YEI NO UE- N/A-,

anchors?

Hairline cracks in grout at various bolt locations (previously addressed at 93EDG-D and documented in CR-JAF-2012-06090)

Attachment C Engireerin* Report No. JAF-RPT-12-00015 Rev. 0 Page 423 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] Ur[7 Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description EmerQency Diesel GeneratorC

5. Is the anchorage configuration consistent with plant documentation? YZ NEI U-I N/AFZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.12-95, associated SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of YN NEil UII potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NEI u- N/A[--

Numerous soft targets on EDG. No credible seismic impacts

8. Are' overhead equipment, distribution systems, ceiling tiles and lighting, YO NEI uE- N/AEl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YE NEI UE- N/A[E
10. Based on the above seismic interaction evaluations, is equipment free YE N[l UEI of potentially adverse seismic interaction effects?

Atta6ficihht C IEngineering Report No. JAF-RPT-12-00015 Rev. 0 Page 424 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NEI UD--

Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description Emeraencv Diesel GeneratorC Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI UE]

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R. Casella Date: 10/26/12 A.G. Porch/I1/61 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 425 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NEI ULI Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators Equipment Description EmerQency Diesel GeneratorC Photographs Note: 93EDG-C Note: 93EDG-C

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 426 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ N-- Ui Seismic Walkdown Checklist (SWC) SWELl- 634 Equipment ID No. 93EDG-C Equip. Class Engine Generators EauiDment DescriDtion Emeraencv Diesel GeneratorC Note: 93EDG-C Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 427 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UE-I Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Location: Bldg. EG Floor El. 272 Room, Area Col. 26.5 Manufacturer, Model, Etc. (optional but recommended) , EMD Engine Portec Gen Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an' item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NEil of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YO Nil UEi N/A[-

The anchorageis free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface YE Nil UI[I N/A[-L oxidation?

Mild surface corrosion on the bolts. No impact on seismic adequacy.

4. Is the anchorage free of visible cracks in the concrete near the YZ N['] U-] N/AE' anchors?

Anchors on north side'of unit - Hairline crack in grout adjacent to the 3 rd anchor from the Northeast corner. Crack continues on concrete at base of unit. Hairline crack 4" S of 5t anchor from northeast. Both the 7 th and, 8 th bolts have hair line cracks at the bolts in the grout.

Anchors on south side of unit - Additional hair line cracks similar to north side.

The above condition is addressed in CR-JAF-2012-06345. As discussed in the response to CA #1, the existing condition is acceptable with no adverse seismic effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 428 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] U-II Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No., 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD

5. Is the anchorage configuration consistent with plant documentation? YN N[E U'-J N/A[l (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YZ N[-] UEI potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEJ NE .UN N/AEl
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y ] N[-I UE1 N/AEl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y ] N['- UE N/AE[
10. Based on the above seismic interaction evaluations, is equipment free YE NEI UE-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 429 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ N[IIý UI-Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI UI-adversely affect the safety functions of the equipment?

Support for 2" air line has 2 bolts on each side that are either flush with the nuts or less than full thread engagement. This condition was addressed in CR-JAF-2012-06345. There is no adverse seismic impact resulting from this condition.

Comments (Additional pages may be added as necessary)

Hair line crack from support of south air start line. Vertical side less pronounced. This item is addressed in CR-JAF-2012-06345. This does not constitute an adverse seismic condition.

Evaluated by: Rick Casella Date: 9-27-12 Alan Porch 9-27-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 430 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NnI- UL-1 Seismic Walkdown Checklist (SWC) SWELl -635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Equipment Description Emergency Diesel GeneratorD Photographs Note: 93EDG-D Note: 93EDG-D

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 431 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ Nn-] U--

Seismic Walkdown Checklist (SWC) SWELl-635 Equipment ID No. 93EDG-D Equip. Class Engine Generator Eauipment Description Emerqencv Diesel GeneratorD Note: 93EDG-D crack in grout in proximity of Note: 93EDG Anchor Bolt (8 on each side of anchorbolt Unit) 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 432 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YO-- NEI[ U[

Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Location: Bldg. EG Floor El. 272 Room, Area 24, A1 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEl-- NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[-D N[-] U[ N/ADI
3. Is the anchorage free of corrosion that is more than mild surface YEI NDI U[ N/AD-oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YD7 NDI U[ N/AD-anchors?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 433 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YEI NE] UI Seismic Walkdown Checklist (SWC) SWELl -636 Equipment ID No. 93EGP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel

5. Is the anchorage configuration consistent with plant documentation?. YOI Nil ULi N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YLI NOi U[

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NlO UI[ N/All
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO NO] U[] N/A-l!

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YE NEI Ui] N/Al]
10. Based on the above seismic interaction evaluations, is equipment free YE NE! Ui of potentially adverse seismic interaction effects?

See Comments.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 434 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE UN Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Other Adverse Conditions,

11. Have you looked for and found no other seismic conditions that could Yg NE] UEý adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Question 10: In a seismic event, if light fixture was decoupled from I of its 2 supporting chains, out-of-plane swinging motion (i.e. toward 93EGO-A) would be limited and will not contact the panel. No adverse seismic interaction.

gc~

Evaluated by: Rick Casella Date: 10/29/12 Al Porch LCII K%-~~& 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 435 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE] NE] U[

Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Photographs Note: 93EGP-A

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 436 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YR-7 NEO U[

Seismic Walkdown Checklist (SWC) SWELl-636 Equipment ID No. 93EGP-A Equip. Class 20 - Instrument and Control Panels Equipment Description EDG A GeneratorControl Panel Note: Conduit off top of 93EGP-A Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 437 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y] NEI U[I Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class' 20 - Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorB Control Panel Location: Bldg. EG- Floor El. 272 Room, Area Col. 26, Line A1 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ NEI of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI NE-] UN N/AE]

External anchorageis free of bent, broken, missing or loose hardware.

Panels need to be removed and anchorageof internalcomponents needs to be checked.

3. Is the anchorage free of corrosion that is more than mild surface YE NE] uEl N/AE]

oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y[ N] UI-E] N/AE-anchors?

Anchorage is free of visible cracks in the concrete near the anchors.

1 Enter the equipment class'name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 438 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YZ NRI- UII Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20 - Instrumentation and Control Panels Equipment Description EmerQencv Diesel GeneratorB Control Panel

5. Is the anchorage configuration consistent with. plant documentation? YN Nil UI-- N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfigurationis consistent with the SEWS for 93EGP-B (Rev. 0). The front welding consists of six 1" x 1/8" fillets, the back welding consists of six 1" seam welds plus one 2" corner weld.

6. Based on the above anchorage evaluations, is the anchorage free of YN NEIl UEl potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ NOl U- N/AL
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE Nil] U[- N/A[]

and masonry block walls not likely to collapse onto the equipment?

Cable from tray I TC456B is overhanging the tray. Will not damage the cabinet in a seismic event

9. Do attached lines have adequate flexibility to avoid damage? YZ NO U[I- N/A[-
10. Based on the above seismic interaction evaluations, is equipment free YN NE] ULi of potentially adverse seismic interaction effects?

)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 439 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST'FORM Sheet 3 of 5 Status: YZ NE] ULI Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentationand Control Panels Equipment Description Emergencv Diesel GeneratorB Control Panel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NE-1 UE-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Koberq I Date: 9/27/12 PouriaPourqhobadi 9/27/1 9127112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 440 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NFD Ur Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorB Control Panel Photographs 0

Note: 93EGP-B Panel 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 441 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF] U-J Seismic Walkdown Checklist (SWC) SWELl-637 Equipment ID No. 93EGP-B Equip. Class 20- Instrumentation and Control Panels Equipment Description Emergencv Diesel GeneratorB Control Panel Note: 93EGP-B Panel base welds. Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 442 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE[ NE UN Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emerqencv Diesel GeneratorA and C ForcedParallelingPanel Location: Bldg. EG Floor El. 272' Room, Area 24.5. A Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ N[-I of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[E] NEi ULI N/A[-D
3. Is the anchorage free of corrosion that is more than mild surface YE- NEl UN N/AEl oxidation?
4. Is the anchorage free of visible cracks in the concrete near the YE: NEJ UN N/AE:

anchors?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 443 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NEl UN Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C Forced ParallelingPanel

5. Is the anchorage configuration consistent with plant documentation? Y[E NEI U[ N/AEl (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YE] NEI U[

potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE] NEl UE- N/A[K
8. Are overhead equipment, distribution systems, ceiling tiles and lighting,. YN'NE]UE1 N/AEl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YE[ NEI UE- N/A2
10. Based on the above seismic interaction evaluations, is equipment free YN NEI UE1 of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 444 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Yr-D NEI U[

Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C ForcedParallelingPanel Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI Un adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Conduits 1CK402RC and 1CC421 RE off the top of 93FPAC 1st support is 3' 9" above top of box. This exceeds 3' spacing given in IS-E-05. Not a seismic concern low 'g' levels in EDG switchgear at Elevation 272.

Evaluated by: R. Casella " Date: 10/26/12 A.G. Porch I 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 445 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE[ NE- U[

Seismic Walkdown Checklist (SWC) SWELl- 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergency Diesel GeneratorA and C Forced ParallelingPanel Photographs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 446 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[L- N-] UN Seismic Walkdown Checklist (SWC) SWELl - 640 Equipment ID No. 93FPAC Equip. Class Instrumentation and Control Panels Equipment Description Emergiency Diesel GeneratorA and C Forced ParallelingPanel Note: 93FPAC

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 447 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y] NEI U[-

Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Location: Bldg. BR Floor El. 282 Room, Area 12, E Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YZ NEI UE]- N/AE1 The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YZ! NEI U-E] N/A[]

oxidation?

The anchorageis free of corrosion.

4. Is the anchorage free of visible cracks in the concrete near the Y-E] NEI UE] N/A[

anchors?

No concrete.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 448 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ ND UMI Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator

5. Is the anchorage configuration consistent with plant documentation? Yr-] NF-O U-I N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of YZ NI UEI potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NEI UD N/AD
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO NOl U-I N/AEI and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YO ND- U[-' N/A[
10. Based on the above seismic interaction evaluations, is equipment free YO NO UM of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 449 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEil Ur-Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE NEIl UL adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Attached to South side SWEL item 93ECP-A (see photo)

Evaluated by: Rick Casella Date: 10/29/12 Al Porch 10/29/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 450 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ Nil U[-]

Seismic Walkdown Checklist (SWC) SWELl- 642 Equipment ID No. 93LI-102A Equip. Class_18 - Instrument Racks Equipment Description EDG A Fuel Oil Day Tank A Level Indicator Photographs Note: 93LI-102A (locatedon 93ECP-A) Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 451 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN Nil UI-J Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class' 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Location: Bldg. EG Floor El. 272' Room, Area EG Room B, Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEl- NE of the 50% of SWEL items requiring such verification)?

The evaluated item in this SWC is not partof the 50% of the SWEL items requiring anchorageconfiguration verification.

2. Is the anchorage free of bent, broken, missing or loose hardware? Y[ NDI Ur- N/A[-D The four (4) self-tapping screws are free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YN NEI U[-I N/AD-oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y-I NEI U['] N/AE anchors?

Gage/Instrumentis attached to a steel panel.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 452 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE N-- U-I Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator

5. Is the anchorage configuration consistent with plant documentation? YI- NEI UI- N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)*

Item is not one of the 50% for which an anchorage configuration verification is required.

6. Based on the above anchorage evaluations, is the anchorage free of YE NEi UI--

potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorageis free of potentiallyadverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ N[il UiE N/AL]

The soft targets are free from impact by nearby equipment or structures.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NI-] UE] N/Al]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YE NEI UL] N/A-]

The lines attachedto the SWEL item have adequate flexibility to avoid damage.

10. Based on the above seismic interaction evaluations, is equipment free YE NFL UiL of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations,the equipment is free of potentiallyadverse seismic interaction effects.

Attachment C Etginee-ing Report No. JAF-RPT-12-00015 Rev. 0 Page 453 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[Z NEI UDI Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI U-I adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhuman Date: 09/21/2012 V 0912112012 0/121 Yaroslaii Los~e V

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 454 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl UI' Seismic Walkdown Checklist (SWC) SWELl-643 Equipment ID No. 93LI-102B Equip. Class 18-Instrument Racks Equipment Description EDG B Fuel Oil Day Tank B Level Indicator Photographs Note: Picture of equipment 93L0-102B. Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 455 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NEil UI-Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Location: Bldg. EG Floor El. 272 Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE- NE of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y9 NR] U[I N/A[]

The anchorageis free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface Y[D NEi U[- N/AZ!

oxidation?

The anchorageis free of corrosion.

4. Is the anchorage free of visible cracks in the concrete near the YE] N[-] UE] N/A[

anchors?

No concrete.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 456 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y] NI]I UII Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler

5. Is the anchorage configuration consistent with plant documentation? YEI-I NEI ULi N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of YEE Nil ULi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NEI U[i N/AEI (See Photo)
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UDI N/ADl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YEl NDi UiD N/AD-
10. Based on the above seismic interaction evaluations, is equipment free YE N[I Uil of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 457 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NEI U-III Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Other Adverse Cond itions

11. Have you looked for and found no other seismic conditions that could YE NO UF adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Rick Casella C2~(G~ Date: 10/29/12 Al Porch 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 458 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE Nn' U-Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Photographs Note: 93LOE-IA (large rectangular Note: 93LOE-1A (long rectangularcomponent component in center of picture) at top)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 459 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NI U-L Seismic Walkdown Checklist (SWC) SWELl- 646 Equipment ID No. 93LOE-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Lube Oil Cooler Note: 93LOE-1A (it is the rectangularshaped Note:

component mounted on angle)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0-Page 460 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NM U[--

Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Classi 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Location: Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments; Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI No of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or Ioosehardware? Y[ NEI uEr N/AE-The anchorageis free of bent broken, missing, or loose hardware
3. Is the anchorage free of corrosion that is more than mild surface Y[ NE-1 UE:] N/AE-]

oxidation?

The anchorageis free of corrosion.

4. Is the anchorage free of visible cracks in the concrete near the YEI N[:E UE- N/A[

anchors?

'Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 461 of 573 01 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U--

Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-1B Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler

5. Is the anchorage configuration consistent with plant documentation? YE-] N-] U-- N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEi U[]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YS NE] UE]- N/A[-

Soft targets in this SWEL item are gauges. They are free from any impact by nearby equipment.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NEI U[] N/AE-1 and masonry block walls not likely to collapse onto the equipment?

The north wall of the room, is a masonary block wall but it has been enhanced accordingto DC# D1-96-011, Rev 0 as part IPEEE evaluations.

9. Do attached lines have adequate flexibility to avoid damage? YN NEI U[] N/A[:]

The attached line have adequate flexibility.

10. Based on the above seismic interaction evaluations, is equipment free YIE NEI UE]

of potentially adverse seismic interaction effects?

The equipment is free of any adverse seismic interaction.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev., 0 Page 462 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NE] U-]

Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N[i ULI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

I/

Evaluated by: Pouria Pourcqhobadi Date: 9/21/12 9/2 1/1 Donald Koberci .9121112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 463 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y0 Nr-] UL--

Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-1B Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Photographs Note: 93LOE-1B EDG B Lube Oil Cooler Note: 93LOE-IB EDG B Lube Oil Cooler 0

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 464 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NF-] UL-]

Seismic Walkdown Checklist (SWC) SWELl-647 Equipment ID No. 93LOE-IB Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG B Lube Oil Cooler Note: 93LOE-1B EDG B Lube Oil Cooler Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 465 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: YZ NEI[ U-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-Cl Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil TransferPump C1 Location: Bldg. EG Floor El. 272' Room, Area 24.5i A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[ Nil of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YN NI-] UE[ N/A--

The anchorage contains all necessary hardware

3. Is the anchorage free of corrosion that is more than mild surface YN NE] U[I] N/AL]

oxidation?

The anchorage has mild oxidation on its surface. There is no structural concern

4. Is the anchorage free of visible cracks in the concrete neat the YN NER U[] N/AE-]

anchors?

There are no cracks in the concrete near the anchors

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 466 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil Transfer Pump C1

5. Is the anchorage configuration consistent with plant documentation? YE NFi ULi N/A-(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.12-99, associated SEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of YE Nil ULi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN NEI- Ui- N/All]
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEi U[-I N/AF]

and masonry block walls not likely to collapse onto the equipment?

9, Do attached lines have adequate flexibility to avoid damage? YE Nil UL] N/AZ!

10. Based on the above seismic interaction evaluations, is equipment free YN NEI U-I of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 467 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YN NEIl U-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel GeneratorC Fuel Oil TransferPump C1 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN NEI UI--

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R. Casella / Date: 10/26/12 A.G. Porch 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 468 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEIl UE]

Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergency Diesel GeneratorC Fuel Oil TransferPump C1 Photographs Note: 93P1-Co Note: 93PI-Cl

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 469 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEI UI-Seismic Walkdown Checklist (SWC) SWELl- 658 Equipment ID No. 93P1-C1 Equip. Class Horizontal Pumps Equipment Description Emergencv Diesel GeneratorC Fuel Oil Transfer PumD C1 Note: 93P1-C1 anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 470 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI] UrI-I Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-DI Equip. Class' 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Location: Bldg. EG Floor El. 272' Room, Area EG Room D, Col. 26.5, Line A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE N[:]

of the 50% of SWEL items requiring such verification)?

The item is one of the 50% of SWEL items requiringanchorage

  • configuration verification.
2. Is the anchorage free of bent, broken, missing or loose hardware? YN ND-I U-- N/AD-The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface Y[ NDI UIE N/AD--

oxidation?

Anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the Y[ NDl U-- N/ADl anchors?

The anchorageis free of visible cracks in the concrete near the anchors.

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 471 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ Nil U[]

Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-D1 Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil TransferPump D1

5. Is the anchorage configuration consistent with plant documentation? Y[ NEI USI N/AL]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The configurationof the six (6), 1/2" Phillips studs is consistent with the SEWS documentation for equipment 93P1-A 1 (same as 93P1-D1),

Rev. 0 and drawing 1.12-99, Rev. 4.

6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI U[-]

potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorage is free of potentially adverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE- NE] UE] N/AO There are no soft targets on the equipment.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NE] UE] N/AL]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipment, distributionsystems, ceiling tiles and lighting, and masonry block walls are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YJ NE] UL] N/AL]

The lines attachedto the SWEL item have adequate flexibility to avoid damage.

10. Based on the above seismic interaction evaluations, is equipment free YZ N[] UE of potentially adverse seismic interaction effects?

Based on the above seismic interaction evaluations, the equipment is free of potentially adverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 472 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NO UIT, Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-D1 Equip. Class 05-Horizontal Pump Equipment Description EDG 0 Fuel Oil TransferPump D1 Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN NEI ULI adversely affect the safety functions of the equipment?

No other seismic conditions that could adversely affect the safety functions of the equipment in the area were found.

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: HarpreetGhuman bM - Date: 09/21/2012 Yaroslav Losev 09/21/2012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 473 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NII UII--

Seismic Walkdown Checklist (SWC) SWELl-660 Equipment ID No. 93P1-Dl Equip. Class 05-Horizontal Pump Equipment Description EDG D Fuel Oil Transfer Pump D1 Photographs Note: Picture of equipment 93P1-DI. Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 474 of 573 0

ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NR UR Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class 06 - Vertical Pumps Equipment Description EDG A CirculatingLube Oil Pump Location: Bldg. EG Floor El. 272 Room, Area 24 A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-I NM of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[I- Nil Ui] N/AM 93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.
3. Is the anchorage free of corrosion that is more than mild surface YEI NE] U[] WN/A oxidation?

93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage.of its own.

4. Is the anchorage free of visible cracks in the concrete near the Y[] NEI u-1 N/A0 anchors?

No concrete.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 475 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NEI UI-]

Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 - Vertical Pumps_

Equipment Description EDG A CirculatinQ Lube Oil Pump

5. Is the anchorage configuration consistent with plant documentation? Y-I N[-] Ur- N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[] UE]

potentially adverse seismic conditions?

93P-2A (SWEL 1-662) is not anchored. It is connected to its motor which is bolted, but the pump is in-line with no anchorage of its own.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NE:] U[] N/A[]

Flex conduit off motor.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NE] UE] N/A[-]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines haveadequate flexibility to avoid damage? YE NEI UE] N/AR-
10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 476 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NW- U[-

Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 - Vertical Pumps._

Equipment Description EDG A Circulating Lube Oil Pump Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NWJ UM adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

See Photos Evaluated by: Rick Casella C £i426~~ Date: 10/29/12 10/29/12 Al Porch Al Porch 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 477 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE ND1 U-I!

Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 - Vertical Pumps Equipment Description EDG A Circulatinq Lube Oil Pump Photographs Note: 93P-2A Note: 93P-2A

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 478 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE ND-] U-Seismic Walkdown Checklist (SWC) SWELl- 662 Equipment ID No. 93P-2A Equip. Class_06 - Vertical Pumps.

Equipment Description EDG A CirculatinqLube Oil Pump 0

Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 479 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NE] UEI-Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class' 5- HorizontalPump Equipment Description Emergencv Diesel GeneratorB CirculatingLube Oil Pump Location: Bldg. EG Floor El. 272 Room, Area C: 26, L: A3 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Yr--] NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YZ NE]l U-E N/AZ-The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YZ NEI UE- N/AE" oxidation?

The anchorageis free of corrosion.

4. Is the anchorage free of Visible cracks in the concrete near the YEI NEI UE- N/AZ anchors?

No concrete

' Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 480 of 573.

ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status. Y[ NEI- UE Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- HorizontalPump Equipment Description Emergency Diesel GeneratorB CirculatingLube Oil Pump

5. Is the anchorage configuration consistent with plant documentation? YEI NEIl Url N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y] NEIr UI-potentially adverse seismic conditions?

Interaction Effects

.7. Are soft targets free from impact by nearby equipment or structures? YEI NE] UEl N/AEl The soft targets are free from impact by nearby equipment and structures.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO NE: u[-- N/AE-and masonry block walls not likely to collapse onto the equipment?

The overhead equipment and distributionsystems are not likely to collapse onto the equipment.

9. Do attached lines have adequate flexibility to avoid damage? YO NEI UE N/A The attachedlines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YE N[IUE1 of potentially adverse seismic interaction effects?

The equipment is free of potentially adverse seismic interaction effects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 481 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ N[] U[-/

Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- HorizontalPump Equipment Description Emergency Diesel GeneratorB CirculatingLube Oil Pump Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI UI-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Koberq Date: 9/21/12 Pouria Pourghobadi , 9/21/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 482 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NEI ULI Seismic Walkdown Checklist (SWC) SWELl-663 Equipment ID No. 93P-2B Equip. Class 5- Horizontal Pump Equipment Description Emergency Diesel GeneratorB Circulating Lube Oil Pump Photographs Note: 93P-2B Pump Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 483 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YZ NE] U[--

Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump Location: Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y-I NZ of the 50% of SWEL items requiring such verification)?

Dwg not available under 93P-3A (Not used for anchorage)

2. Is the anchorage free of bent, broken, missing or loose hardware? YZ NEI Uil N/AI-]

Anchorage was free of bent, broken, missing and loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface Y[ NEI U[:] N/AZ3 oxidation?

No corrosion was evident

4. Is the anchorage free of visible cracks in the concrete near the YEIl NE]i UE] N/AN anchors?

There is no concrete

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 484 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ ND U0I Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump

5. Is the anchorage configuration consistent with plant documentation? Yi-] Nr- ULI N/A[9 (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NDI U[]

potentially adverse seismic conditions?

Anchorage is free of potentially adverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ ND: UD- N/A[D]

Protectedby superstructureabove pump.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NDI uD- N/AD-]

and masonry block walls not likely to collapse onto the equipment?

(See #7 above)

9. Do attached lines have adequate flexibility to avoid damage? YZ ND- u[-] N/AD1
10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI U[-

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 485 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y[ NE ULI Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 - Horizontal Pumps Equipment Description EDG A Fuel Oil Pump Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN NE:1 Ur-adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

(Photos)

Evaluated by: Rick Casella Date: 10/29/12 Al Porch LC~, K~& 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 486 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YE NFI U-I Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 - HorizontalPumps Equipment Description EDG A Fuel Oil Pump Photoaraphs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 487 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NFI] Ur-]

Seismic Walkdown Checklist (SWC) SWELl- 670 Equipment ID No. 93P-4A Equip. Class 05 - Horizontal Pumps Eauipment DescriDtion EDG A Fuel Oil PumD Note: 93P-4A (could not get any closer picture Note:

of anchorage)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 488 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NEI UE]

Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class' 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Location: Bldg. EG Floor El. 272 Room, Area C: 26.5. L: A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YO] NM of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YO N[-] Ur] N/A[-]

The anchorageis free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface Y[ NE] UE] N/AE]

oxidation?

The anchorageis free of corrosion.

4. Is the anchorage free of visible cracks in the concrete near the YE] N[E] UE] N/A]

anchors?

No concrete.-The equipment is mounted on the generatorskid.

I Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 489 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEI U[-]

Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_2 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump

5. Is the anchorage configuration consistent with plant documentation? Y[-I NEI UE] N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NE] UiI potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEi NE] UM] N/A[

8, Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NEI UE] N/AE]

and masonry block walls not likely to collapse onto the equipment?

9, Do attached lines have adequate flexibility to avoid damage? YN NEI UE] N/AEI

10. Based'on the above seismic interaction evaluations, is equipment free YM NEI u--

of potentially adverse seismic interaction effects?

2 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 490 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NE] Un Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_3 5- Horizontal Pumps Equiipment Description EDG B Fuel Oil Pump Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN NEI UI--

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Pump missing equipment tag. The issue was brought to site personnel attention immediately.

Evaluated by: Pouria Evaluated by: PouriaPourQhobadi Date: 9/21/12 Donald Kobera 9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 491 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NR UM-1 Seismic Walkdown Checklist (SWC) SWELl-671 Equipment ID No. 93P-4B Equip. Class_4 5- Horizontal Pumps Equipment Description EDG B Fuel Oil Pump Photographs Note: EDG B Fuel Oil Pump Note:

4 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 492 of 573 ATTACHMENT 9.6 k SEISMIC WALKOOWN CHECKLIST FORM Sheet I of 5 Status: Y[ NE] U-Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description EDG A Jacket Water Expansion Tank Location: Bldg. EG Floor El. 272 Room, Area 24, A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE[ NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YM NEI UE- N/AE[

The anchorage is free of bent, broken, missing or loose hardware.

3. Is the anchorage free of corrosion that is more than mild surface YO NE: UE- N/AE[

oxidation?

No corrosion evident.

4. Is the anchorage free of visible cracks in the concrete near the Y[E] NE:] UE- N/AM anchors?

There is-no concrete.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 493 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: YE NiI UI--1 Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-IA Equip. Class_21 - Tanks and Heat Exchangers Equipment Description

5. Is the anchorage configuration consistent with plant documentation? YEI N[il UZ1 N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of YN Nil UI potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ N[il ULi N/A[-]
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEI' UI1 N/AL]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YZ N[] Ul] N/A--
10. Based on the above seismic interaction evaluations, is equipment free YN N[] U[]

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 494 of 573 ATTACHMENT 9.6 SEISMIC WALKOOWN CHECKLIST FORM Sheet 3 of 5 Status: YZ NEI. ULI Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip, Class_21 - Tanks and Heat Exchangers Equipment Description Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN N[-]UM adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Tank well supported; no interactioneffects noted. Mounted on diesel skid / frame.

Evaluated by: Rick Casella Pte2 2~A-~L~

Date: 10/29/12 Al Porch 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 495 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: Y[ Nn- U-iJ Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description Photographs Note: 93TK-IA shown on EDG A unit

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 496 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YE NEIr Ur]

Seismic Walkdown Checklist (SWC) SWELl- 674 Equipment ID No. 93TK-1A Equip. Class_21 - Tanks and Heat Exchangers Equipment Description Note: 93TK-IA underside Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 497 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI URi--

Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-1B Equip. Class' 21 - Tanks and Heat Exchanqers Equipment Description Emergency Diesel GeneratorB Jacket Water Expansion Tank Location: Bldg. EG Floor El.. 272 Room, Area Col. 26, Line A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YI-] NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YN NDI U[I N/AD-The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YE NDI U[: N/AD:

oxidation?

The anchorageis free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YD'- NDl UDI N/A[

anchors?

IEnter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 498 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE ND UIý Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-IB Equip. Class_2 21 - Tanks and Heat Exchangers Equipment Description Emerqencv Diesel GeneratorB Jacket Water Expansion Tank

5. Is the anchorage configuiration consistent with plant documentation? YLI NEI UE- N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NI ULiD potentially adverse-seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE NEI UE N/AE-
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NEI UE- N/AAE7 and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y[ NEI UE N/AAE-
10. Based on the above seismic interaction evaluations, is equipment free YO NE uEr of potentially adverse seismic interaction effects?

2 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 499 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] U[D1 Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-IB Equip. Class_3 21 - Tanks and Heat Exchangers Equipment Description Emergencv Diesel GeneratorB Jacket Water Expansion Tank Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NE-1 UF--

adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: PouriaPourghobadi Date: 9/21/12 Donald Koberaq 9/21/12 3 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 500 of 573 ATrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NZ- UI--

Seismic Walkdown Checklist (SWC) SWELl-675 Equipment ID No. 93TK-1B Equip. Class_4 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorB Jacket Water Expansion Tank Photographs Note: 93TK-IB Front view Note: 93TK-IB Side view 4 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-1 2-00015 Rev. 0 Page 501 of 573 0 A.nrACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 5 Status: Y[ NEI Ur-Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Location: Bldg. EG Floor El. 272 Room, Area 24,A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[, NEI of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YZ N[: Ui- N/A[-D

'Anchorage contains all necessaryhardware

3. Is the anchorage free of corrosion that is more than mild surface YZ ND U0iD N/ADl oxidation?

Anchorage contains no corrosion

4. Is the anchorage free of visible cracks in the concrete near the YDI NZ UDl N/AD-anchors?

Hairline cracks ( @ x) at anchorsprimarilyat top of concrete pedestal (refer to 93TK-7B and CR-JAF-2012-06090)

Aita6hment C Entgineeiring Report No. JAF-RPT-12-00015 Rev. 0 Page 502 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ NE] Ufi Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 - Tanký and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank

5. Is the anchorage configuration consistent with plant documentation? Y[ NEI U-I N/A-]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.12-128, associatedSEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of Y Z NEl UEi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ NE] UE- N/AEl
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y[ NEI ur- N/AZl and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y[ NEI U[-] N/AZl
10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 503 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: YE NE] U--

Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE N[:I U[-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

None Evaluated by: Rick Casella C 3A2~&o~~~

Date: 10/29/12 I

Al Porch 10129112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 504 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YN NEIl U[

Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank PhotoaraDhs Note: 93TK-7A Note: 93TK-7A

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 505 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: Y[ Nr-n Ur-]

Seismic Walkdown Checklist (SWC) SWELl- 682 Equipment ID No. 93TK-7A Equip. Class 21 - Tanks and Heat Exchangers Equipment Description EDG A Fuel Oil Day Tank Note: 93TK-7A anchorbolt (note hairline Note:

crack in concrete right of bolt centerline)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 506 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NF-D U"-I Seismic Walkdown Checklist (SWC) SWELl-683 Equipmenit ID No. 93TK-7B Equip. Class' 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Location: Bldg. EG Floor El. 272 Room, Area EDG B Room, Column 26.5 Line A4 Manufacturer, Model, Etc. (optional but recommended) T312 Trinity Equip Corp Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of'equipment on the SWEL. The space below each'of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NE-]

of the 50% of SWEL items requiring such verification)?

The anchorageconfiguration was verified and found to be acceptable.

This item is part of the 50% of SWEL items.

2. Is the anchorage free of bent, broken, missing or loose hardware? YE NrI- urE- N/AD The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YN NEI U-1 N/AD-oxidation?

The anchorage is free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YD NM UD] N/AD-anchors?

Multiple visible hairline cracks on the foundation, from bottom of floor elevation through the center line of 7/8" bolts/anchors on both saddles.

On the North saddle West end there is noticeable damage to the concrete foundation due to interactionof the concrete wall and the Fuel Day Tank Drain Line. The resolution to this deficiency is tracked by CR-JAF-2012-06090.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 507 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y] NDI UEII Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks &Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank

5. Is the anchorage configuration consistent with plant documentation? YZ NDl UD- N/A[D (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorage configurationis consistent with DWG. No. 1.12-128 and SEWS for 93TK-7A, which has the same configuration as 93TK-7B.

6. Based on the above anchorage evaluations, is the anchorage free of YEI NZ U[-]

potentially adverse seismic conditions?

Cracks in concrete pedestal at the anchorage and damage by the fuel day tank drain line jeopardizes the safety of the tank's support.

The resolution to this deficiency is tracked by CR-JAF-2012-06090.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y-I NDI UD3 NIA]

The equipment is free of soft targets.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NDl U[D] N/AD]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YE ND UD-- N/AD-
10. Based on the above seismic interaction evaluations, is equipment free YO ND] UD-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 508 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NDl Ur-I Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks &Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ N- Ur-1 adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Pouria Pourqhobadi . Date: 01/21/2012 Donald Kolbera 051 0 0112112012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 509 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEIl U--

Seismic Walkdown Checklist (SWC) SWELl-683 Equipment ID No. 93TK-7B Equip. Class 21-Tanks & Heat Exchangers Equipment Description Emergency Diesel GeneratorB Fuel Oil Day Tank Photographs Note: Diesel Fuel Day Tan 93TK-7B Note: Damage to north concrete pedestal by the Diesel Fuel Day Tank DrainLine (Valve 93EDG-71 1B)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 510 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 5 Status: YE NO UMI Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger Location: Bldg. EG Floor El. 272 Room, Area CoL 25 line A4,AZ Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? Y[ NEI U[-I N/A[--

The anchoragehas all necessaryhardware

3. Is the anchorage free of corrosion that is more than mild surface Y[ NE U[- N/A[-

oxidation?

The anchorage shows no signs of any type of corrosion

4. Is the anchorage free of visible cracks in the concrete near the YE- NE U[-] N/A[,

anchors?

There are no cracks in the concrete near the anchors

'I Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 511 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 5 Status: Y[ N[-] U-Seismic.Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-IC Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger

5. Is the anchorage configuration consistent with plant documentation? YN NE-] U-I N/A[]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

(Ref. 1.12-35, 1.12-101, associatedSEWS document)

6. Based on the above anchorage evaluations, is the anchorage free of Y[ N[:] U[I:

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NE-] U[i- N/AZ-
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NE] UE[ N/AZl and masonry block walls not likely to collapse onto the equipment?

46EXJ-9C, I OC are epoxy soft targets.No credible seismic interactions

9. Do attached lines have adequate flexibility to avoid damage? YZ NE] U-I N/AZ]
10. Based on the above seismic interaction evaluations, is equipment free YZ N[] UE-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 512 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 5 Status: Y] NEI Ur-I Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergencv Diesel GeneratorC Jacket Water Heat Exchanger Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y; NEI Ur adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: R. Casella / Date: 10/26/12 A.G. Porch 10/26/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 513 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 5 Status: YZ NEI- ULI-Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 - Tanks and Heat Exchanqers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger Photographs Note: 93WE-IC (looking East)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 514 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 5 of 5 Status: YZ NP UD Seismic Walkdown Checklist (SWC) SWELl- 686 Equipment ID No. 93WE-1C Equip. Class 21 - Tanks and Heat Exchangers Equipment Description Emergency Diesel GeneratorC Jacket Water Heat Exchanger ed Foot Note: 93WE-1C Anchorage - Sliding Foot

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 515 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NDI U[

Seismic Walkdown Checklist (SWC) SWELl -687 -

Equipment ID No. 93WE-ID Equip. Class, 21 - Heat Exchangers Equipment Description Emergency Diesel Generator0 Jacket Water Heat Exchanger Location: Bldg. EG Floor El. 272 Room, Area EG Room 0 C: 27, L: A4 Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-I NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YZ NDI U[- N/AD-The four (4) bolts are free of bent, broken, missing or loose hardware
3. Is the anchorage free of corrosion that is more than mild surface YN NDI UD: N/AD-oxidation?

The anchorage is free of any corrosion.

4. Is the anchorage free of visible cracks in the concrete near the YDI NDI U-I N/A[

anchors?

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 516 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NFI UFE Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 - Heat Exchangers Equipment Description Emergencv Diesel Generator0 Jacket Water Heat Exchanger

5. Is the anchorage configuration consistent with plant documentation? YE-! NEI UE! N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

Item is not one of the 50% for which an anchorageconfiguration verification is required.

6. Based on the above anchorage evaluations, is the anchorage free of YS NEI UE!

potentially adverse seismic conditions?

Based on the above anchorage evaluations, the anchorageis free of potentially adverse seismic conditions.

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YEI NEI UE! N/AZ This component does not have soft targets.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YE NE! UE! N/AE!

and masonry block walls not likely to collapse onto the equipment?

Masonry block wall divides the Delta and Bravo train in EDG.

Modifications were made to enhance the walls as part of IE Bulletin 80-

11. (Ref. CalculationNo. JAF-CALC-EDG-02153 Rev 0) and IPEEE evaluationsDI-96-011 Rev 0.
9. Do attached lines have adequate flexibility to avoid damage? YM N!-] U[-E N/AET The attached lines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free YE NE!I uE of potentially adverse seismic interaction effects?

The equipment is free of potentiallyadverse seismic interactioneffects.

Attachfnint C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 517 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NE] U-'

Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 - Heat Exchangers Equipment Description Emergency Diesel GeneratorD Jacket Water Heat Exchanger Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI ur adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Pouria Pourghobadi Date: 09/21/2012 Donald Kobergq09/21/2012 0912112012

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 518 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE ND UIur-Seismic Walkdown Checklist (SWC) SWELl-687 Equipment ID No. 93WE-ID Equip. Class 21 - Heat Exchangers Equipment Description Emergency Diesel GeneratorD Jacket Water Heat Exchanger Photoqraphs 0

Note: 93WE-ID Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 519 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEII UE-Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class' 18- Instrument Racks Equipment Description Core Spray System Channel A Rack Location: Bldg. RB Floor El. 242.8 Room, Area Col. 4, Line A Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE NE-'

of the 50% of SWEL items requiring such verification)?

2. Is the anchorage free of bent, broken, missing or loose hardware? YN NE:I UEJ N/AEl Anchorage is free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YM NEI UEI N/AE oxidation?

Anchorage is free of corrosion that is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YE- NEI U[-- N/AN anchors?

The component is not anchoredin concrete.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 520 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YE NE] UEý Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System Channel A Rack

5. Is the anchorage configuration consistent with plant documentation? YE-] NZ Ul-I N/A[I]

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The rack is bolted to steel plates which are welded to an I-beam. The spacing between the anchors is 15 inches. They are not 18 inches as shown 7.70-81D due to interference with an I-beam.

The resolution to this deficiency it tracked through CR-2012-JAF-08186.

6. Based on the above anchorage evaluations, is the anchorage free of YE:' NO UE-]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ N[-I ULI N/AE-The soft targets are free from impact by nearby equipment and structures.
8. Are overhead equipment, distribution systems, Ceiling tiles and lighting, YN NE- UE- NIAE and masonry block walls not likely to collapse onto the equipment?

The overhead equipments and distributionsystems ,are not likely to collapse onto the equipment.

9. Do'attached lines have adequate flexibility to avoid damage? YS NEI UE- N/AE1 The attached lines have adequate flexibility.
10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI UE of potentially adverse seismic interaction effects?

The equipment is free of potentially adverse seismic interaction effect

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 521 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] NEI U[--

Seismic Walkdown Checklist (SWC) SWELI-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System ChannelA Rack Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEi UE-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald Koberciý d Xjý, Date: 9/25/12 Pouria Pourihobad, 9125112

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 522 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YZ NEI- U--

Seismic Walkdown Checklist (SWC) SWELl-690 Equipment ID No. IR-25-01 Equip. Class 18- Instrument Racks Equipment Description Core Spray System ChannelA Rack Photographs Note: Instrument Panel Note: Rack Anchorage

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 523 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YN NEI UM Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class, 18 - Instrument Racks Equipment Description RHR Channel B Instrument Rack Location: Bldg. RB Floor El. 242 Room, Area Col 3 Line D Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YE] NEI of the 50% of SWEL items requiring such verification)?

Anchorage configurationverification is required.

2. Is the anchorage free of bent, broken, missing or loose hardware? YN NEI U-I N/AF-The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface Y[ NE] U[-L] N/A--

oxidation?

The anchorageis free of corrosionthat is more than mild surface oxidation.

4. Is the anchorage free of visible cracks in the concrete near the YEll NEI UEI N/AN anchors?

The anchorageis not embedded in concrete.

1 Enter the equipment class name from Appendix B: Classes of Equipment.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 524 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI Ur-Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack

5. Is the anchorage configuration consistent with plant documentation? YN NEI U-- N/AE--

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

The anchorageconfiguration is consistent with SEWS for IR-25-62, DWG. No. 7.70-81

6. Based on the above anchorage evaluations, is the anchorage free of YN NEI UEi potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YN NEi UEi N/A[E The soft targets are free from impact by nearbyequipments and structures.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NE- U[] N/A[-]

and masonry block walls not likely to collapse onto the equipment?

The overhead equipments, distributionsystems, ceiling tiles and lighting and masonry walls.

9. Do attached lines have adequate flexibility to avoid damage? YZ NEI UE- N/A--

The attachedlines have adequate flexibility.

10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?

The equipment is free of potentiallyadverse seismic interactioneffects.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 525 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y] N- UI--1 Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ N[l U[i adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Donald KoberQ Date: 9/23/12 Pouria Pourghobadi 9/23/12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 526 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE N[] Ur Seismic Walkdown Checklist (SWC) SWELl-696 Equipment ID No. IR-25-62 Equip. Class 18- Instrument Racks Equipment Description RHR Channel B Instrument Rack Photouraphs 0

Note: IR-25-62 Instrument rack Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 527 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: YZ NEI UI[-

Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel Pool cooling skimmer surge tank A Location: Bldg. RB Floor El. 344 Room, Area Col 4 Line D Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL; The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[-' NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YO NEI ULII N/AEl The anchorageis free of bent, broken, missing or loose hardware.
3. Is the anchorage free of corrosion that is more than mild surface YO NEI U-] N/AEl oxidation?

No corrosion.

4. Is the anchorage free of visible cracks in the concrete near the YO NEI UEI N/AR anchors?

The anchorageis free of cracks.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 528 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NDI UD-Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A

5. Is the anchorage configuration consistent with plant documentation? YEI- N[I UEI- N/AN (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of YN ND] UD-potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[K NDI UD1 N/ADl No soft targets on tank
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YO ND: UD] N/AD1 and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? Y' ND1 UD-- N/AD-I
10. Based on the above seismic interaction evaluations, is equipment free YE NDl UM of potentially adverse seismic interaction effects?

The tank is structurallyrobust. It is supported at El. 369'. Any minimal lateraltank movement will not impact any SSCs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 529 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YE NMl UM Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE NEI ULI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Rick Casella Date: 9-28-12 9-28-12 Alan Porch Alan Porch 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 530 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ N-- UI-I Seismic Walkdown Checklist (SWC) SWEL2-001 Equipment ID No. 19TK-8A Equip. Class Tanks and heat exchangers Equipment Description Fuel pool cooling skimmer surge tank A Photographs

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 531 of 573 0 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YN NEil U-I Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A high level switch Location: Bldg. RB Floor El. 344 Room, Area Col4 Line D Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEO NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YE] NE] UE] N/A[

SWEL item is not independently supported; it is attachedto a pipe stand running vertically which is supportedat the top and bottom.

3. Is the anchorage free of corrosion that is more than mild surface YE] NE] UE] N/A[

oxidation?

SWEL item is not independentlysupported; it is attached to a pipe stand running vertically which is supported at the top and bottom.

4. Is the anchorage free of visible cracks in the concrete near the YE] NEI UE] N/As anchors?,

SWEL item is not independently supported; it is attachedto a pipe stand running vertically which is supportedat the top and bottom.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 532 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NEI UrII Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch

5. Is the anchorage configuration consistent with plant documentation? Y-I NEI ULi N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI Uil potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ N[i U[-I N/All Flexible conduit is a soft target near item. There are no credible seismic interactions.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YEI N[! UEi N/As and masonry block walls not likely to collapse onto the equipment?

Fluorescentlight in the room is located several feet from SWEL item.

No interactionlikely.

9. Do attached lines have adequate flexibility to avoid damage? YE N[:] UE] N/All Conduit attachedto the wall and has a flexible connection at the swell item. SWEL item is not independently supported,it is attached to a pipe stand running vertically which is supportedat the top and bottom.
10. Based on the above seismic interaction evaluations, is equipment free Y[ NEI U[-]

of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 533 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI] ULI Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A high level switch Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YN NI-] U[-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 534 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NR UW--

Seismic Walkdown Checklist (SWC) SWEL2-003 Equipment ID No. 19LS-65 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A high level switch Photographs Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 535 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE NE I UMI Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. I9LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Location: Bldg. RB Floor El. 347 Room, Area Col4 Line D Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[E] NO of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI NEI UE-] N/A]

The item is not supported independently.

3. Is the anchorage free of corrosion that is more than mild surface YEI NE] UE[- N/AE oxidation?

The item is not supported independently.

4. Is the anchorage free of visible cracks in the concrete near the YE- NEI UEJ N/AO anchors?

The item is not supportedindependently. No concrete.

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 536 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NEIr Ur0-Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentationand Control Panels Equipment Description Skimmer surge tank A low-low level switch

5. Is the anchorage configuration consistent with plant documentation? YE- NEI UE- N/A[

(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)

6. Based on the above anchorage evaluations, is the anchorage free of YZ NEI ULI potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YZ N[E] UEl N/AE-Flexible conduit is a soft target near item. There are no credible seismic interactions.
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YEi NE UEi N/AZ and masonry block walls not likely to collapse onto the equipment?
9. Do attached lines have adequate flexibility to avoid damage? YZ NEl UE-] N/AEl
10. Based on the above seismic interaction evaluations, is equipment free YZ NE] UEi of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 537 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NEI UE]

Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YZ NEI U[-I adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

Evaluated by: Rick Casella F~ CcLJ& Date: 9-28-12 Alan Porch 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 538 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI Ul']

Seismic Walkdown Checklist (SWC) SWEL2-004 Equipment ID No. 19LS-67 Equip. Class 20. Instrumentation and Control Panels Equipment Description Skimmer surge tank A low-low level switch Photographs 0

Note:

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 539 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YZ NEI UL-I Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. ' 19FPC-33 Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surcqe tanks A & B to cndsr hotwell isol valve inlet isol Location: Bldg. RB Floor El. 326.9 Room, Area Col 3 line R Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI Nil UE- N/AH The item is an inline valve
3. Is the anchorage free of corrosion that is more than mild surface YE] N] U[:] N/AZ oxidation?

The item is an inline valve

4. Is the anchorage free of visible cracks in the concrete near the YE] NFI UE] N/A[

anchors?

The item is an inline valve

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 540 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: Y[ NE-] UM Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol

5. Is the anchorage configuration consistent with plant documentation? YI-- Nil UFI N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ N-I UE-potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE-1 NEI UL-l N/AN No soft targets
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN Nl! UE[ N/AZ!

and masonry block walls not likely to collapse onto the equipment?

Piping and overhead conduit well supported.

9. Do attached lines have adequate flexibility to avoid damage? YE- NEI UE1 N/AE
10. Based on the above seismic interaction evaluations, is equipment free YZ NEi U-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 541 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: YZ NE] ULII Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07-Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YE ND1 ULI adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

No additionalcomments.

0ýaAAZ Evaluated by: PiA,' ('a cnr.In Date: 9-28-12 Alan Pnrr~h 9-28-12 AI~in Porch 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 542 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE Nn UD Seismic Walkdown Checklist (SWC) SWEL2-005 Equipment ID No. 19FPC-33 Equip. Class 07- Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve inlet isol Photographs 0

Note: 19FPC-33valve shown on left side of Note: 19FPC-33 (The date provided on the photo. (The date provided on the bottom right bottom right cornet is not correct the date that cornet is not correct the date that the picture the picture was taken. Malfunction with camera was taken. Malfunction with camera setting) setting)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 543 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet I of 4 Status: Y[ NEI U-I Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Location: Bldg. RB Floor El. 326.9 Room, Area Co/ 3 line R Manufacturer, Model,. Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one YEI NZ of the 50% of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI NEI U-EI N/AZ The item is an inline valve
3. Is the anchorage free of corrosion that is more than mild surface, YEI NEI UEI N/AZ oxidation?

The item is an inline valve

4. Is the anchorage free of visible cracks in the concrete near the Y[E] NEI UEl, N/AZ anchors?

The item is an inline valve

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 544 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ N-- UL-I Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve

5. Is the anchorage configuration consistent with plant documentation? YEI NEI Ur-] N/AZ (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI U0I potentially adverse seismic conditions?

N/A Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? Y[ NE] U[i N/AF--

Piping and conduit above the item is well supported.

8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YN NEI ur-] N/AL]

and masonry block walls not likely to collapse onto the equipment?

9. Do attached lines have adequate flexibility to avoid damage? YEI NEI U[] N/A[
10. Based on the above seismic interaction evaluations, is equipment free YZ N[: UEL of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 545 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NF] UL-Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could YS NOJ UJ-adversely affect the safety functions of the equipment?

Comments ('Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Rick Casella

Li 6201-L Date: 9-28-12 Alan Porch 1 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 546 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: YE NEI ULI Seismic Walkdown Checklist (SWC) SWEL2-006 Equipment ID No. 19AOV-09 Equip. Class 7. pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B to cndsr hotwell isol valve Photographs 40 Note: 19AOV-09 valve shown in center of Note:

picture. (The date provided on the bottom right comet is not correct the date that the picture was taken. Malfunction with camera setting)

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 547 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 1 of 4 Status: YE N[] U-I Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Location: Bldg. RB Floor El. 326 Room, Area Col 3 line T Manufacturer, Model, Etc. (optional but recommended)

Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.

Anchorage

1. Is the anchorage configuration verification required (i.e., is the item one Y[I NEK of the 50%of SWEL items requiring such verification)?
2. Is the anchorage free of bent, broken, missing or loose hardware? YEI- N[-1 Ul"] N/As The item is an inline valve.
3. Is the anchorage free of corrosion that is more than mild surface YEI NEIl UIE N/AZ oxidation?

The item is an inline valve.

4. Is the anchorage free of visible cracks in the concrete near the YEl NElI-U[E] N/AZ anchors?

The item is an inline valve.

Attachment C Engineering Report No. JAF-RPT-12-00015' Rev. 0 Page 548 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 2 of 4 Status: YZ NRi Ul-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve

5. Is the anchorage configuration consistent with plant documentation? Y[I NE] U[ N/As (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
6. Based on the above anchorage evaluations, is the anchorage free of Y[ NEI UE]

potentially adverse seismic conditions?

Interaction Effects

7. Are soft targets free from impact by nearby equipment or structures? YE] NEI UE] N/AS
8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YZ NE] UE] N/AE]

and masonry block walls not likely to collapse onto the equipment?

None overhead. Fluorescentlight directly south will not damage hand wheel if it fails.

9. Do attached lines have adequate flexibility to avoid damage? YE] NE] UE] N/AZ No line attached.
10. Based on the above seismic interaction evaluations, is equipment free YN N[] UE-of potentially adverse seismic interaction effects?

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 549 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 3 of 4 Status: Y[ NEI] U-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Other Adverse Conditions

11. Have you looked for and found no other seismic conditions that could Y[ NEI U[1 adversely affect the safety functions of the equipment?

Comments (Additional pages may be added as necessary)

No additionalcomments.

Evaluated by: Rick Casella Date: 9-28-12 Alan Porch 9-28-12

Attachment C Engineering Report No. JAF-RPT-12-00015 Rev. 0 Page 550 of 573 ATTACHMENT 9.6 SEISMIC WALKDOWN CHECKLIST FORM Sheet 4 of 4 Status: Y[ NEI- UI-Seismic Walkdown Checklist (SWC) SWEL2-007 Equipment ID No. 19FPC-01 Equip. Class 7. Pneumatic-operatedvalves Equipment Description Skimmer surge tanks A & B drain valve Photographs Note: 19FPC-01 (The date provided on the Note: 19FPC-O1(The date provided on the bottom right cornet is not correct the date that bottom right cornet is not correct the date that the picture was taken. Malfunction with camera the picture was taken. Malfunction with camera setting) setting) 0