ML17212A053: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:Millstone Power Station Unit 2 Safety Analysis Report Chapter 12 MPS2 UFSAR 12-i Rev. 35CHAPTER 12-CONDUCT OF OPERATIONS Table of ContentsSection Title Page12.1ORGANIZATIONAL STRUCTURE...............................................................12.1-112.1.1Management and Technical Support Organization..................................12.1-112.1.1.1Technical Support for Operations.............................................................12.1-112.1.1.2Organizational Arrangement.....................................................................12.1-112.1.2Operating Organization.............................................................................12.1-112.1.2.1Plant Organiza tion....................................................................................12.1-112.1.2.2Operating Shift Crews..............................................................................12.1-112.1.3Qualification of Nuclear Plant Personnel.................................................12.1-112.1.4References.................................................................................................12.1-112.2TRAINING PROGRAM...................................................................................
{{#Wiki_filter:Millstone Power Station Unit 2 Safety Analysis Report Chapter 12
12.2-112.2.1References.................................................................................................12.2-112.3EMERGENCY PLANNING.............................................................................
12.3-112.3.1References.................................................................................................12.3-112.4REVIEW AND AUDIT.....................................................................................
12.4-112.4.1Onsite Review...........................................................................................12.4-112.4.2Independent Review.................................................................................12.4-112.4.3Audits........................................................................................................12.4-1 12.4.4Other Review Groups...............................................................................12.4-112.4.5References.................................................................................................12.4-112.5PLANT PROCEDURES....................................................................................
12.5-112.5.1Administrative Procedures........................................................................12.5-112.5.1.1Conformance with Regulatory Guide 1.33...............................................12.5-112.5.1.2Preparation of Procedures.........................................................................12.5-112.5.1.3Procedures.................................................................................................12.5-1 12.5.2Operating and Maintenance Procedures...................................................12.5-312.5.2.1Control Room Operat ing Procedures........................................................12.5-312.5.2.1.1General Operating Procedures..................................................................12.5-312.5.2.1.2System Operati ng Procedures...................................................................12.5-312.5.2.1.3Abnormal Operating Procedures..............................................................12.5-312.5.2.1.4Emergency Operati ng Procedures............................................................12.5-412.5.2.2Station Procedures
....................................................................................
12.5-4 MPS2 UFSAR Table of Contents (Continued)
Section Title Page 12-ii Rev. 3512.5.2.2.1Radiation Protection Procedures...............................................................12.5-412.5.2.2.2Instrument Maintenance Instructions........................................................12.5-412.5.2.2.3Chemistry Procedures...............................................................................12.5-412.5.2.2.4Radioactive Waste Sy stem Procedures.....................................................12.5-412.5.2.2.5Material Contro l Procedures.....................................................................12.5-412.5.2.2.6Maintenance and Modifi cation Procedures..............................................12.5-512.5.2.2.7Fire Protection Procedures........................................................................12.5-512.5.2.2.8Special Proc edures....................................................................................12.5-512.6RECORDS.........................................................................................................12.6-112.7PHYSICAL SECURITY PLANS......................................................................12.7-112.7.1References.................................................................................................12.7-112.8QUALITY ASSURANCE PROGRAM............................................................
12.8-112.8.1Quality Assurance Program Description (QAPD) Topical Report...........12.8-112.9DELETED BY PKG FSC MP2-UCR-2011-014...............................................
12.9-1 MPS2 UFSAR12.1-1Rev. 35CHAPTER 12 - CONDUCT OF OPERATIONS 12.1 ORGANIZATIONAL STRUCTUREInformation regarding the organi zational structure is presented in Section 1.0, Organization, of the Quality Assurance Program Description (QAPD) T opical Report (Reference 12.1-1). With the exception given below, that informati on is incorporated herein by reference.The owner, holding 100 percent of the Millstone 2 nuclear plant, is Dominion Nuclear Connecticut, Inc.
12.1.1 MANAGEMENT AND TECHNICAL SUPPORT ORGANIZATI ON Information regarding the mana gement and technical support or ganization is presented in Section 1.0, Organization, of the QAPD Topical Report (Reference 12.1-1). That information is incorporated herein by reference.


12.1.1.1 Technical Support for OperationsThe organization providing techni cal support for operations is described in Section 1.0 of the QAPD Topical Report (Reference 12.1-1). That info rmation is incorporated herein by reference.
Table of Contents tion      Title                                                                                                          Page ORGANIZATIONAL STRUCTURE ............................................................... 12.1-1
12.1.1.2 Or ganizational ArrangementThe organizational arrangement is as described in Section 1.0 of the QAPD Topical Report (Reference 12.1-1). That information is incorporated herein by reference.
.1        Management and Technical Support Organization .................................. 12.1-1
12.1.2 OPERATING ORGANIZATION 12.1.2.1 Plant OrganizationThe plant organization is as shown in Reference 12.1-1.
.1.1     Technical Support for Operations............................................................. 12.1-1
12.1.2.2 Operating Shift CrewsThe minimum shift crew composition and license requirements during all modes of operation are contained in Section 6.2 of the Technical Specifications.
.1.2      Organizational Arrangement..................................................................... 12.1-1
12.1.3 QUALIFICATION OF NUCLEAR PLANT PERSONNEL Education and experience requ irements are established by Section 6.3 of the Technical Specifications
.2        Operating Organization............................................................................. 12.1-1 1.2.1      Plant Organization .................................................................................... 12.1-1
.12.
.2.2      Operating Shift Crews .............................................................................. 12.1-1
.3        Qualification of Nuclear Plant Personnel ................................................. 12.1-1
.4        References................................................................................................. 12.1-1 TRAINING PROGRAM ................................................................................... 12.2-1
.1       References................................................................................................. 12.2-1 EMERGENCY PLANNING ............................................................................. 12.3-1
.1        References................................................................................................. 12.3-1 REVIEW AND AUDIT..................................................................................... 12.4-1
.1        Onsite Review........................................................................................... 12.4-1
.2       Independent Review ................................................................................. 12.4-1
.3        Audits........................................................................................................ 12.4-1
.4        Other Review Groups ............................................................................... 12.4-1
.5        References................................................................................................. 12.4-1 PLANT PROCEDURES.................................................................................... 12.5-1
.1        Administrative Procedures........................................................................ 12.5-1
.1.1      Conformance with Regulatory Guide 1.33 ............................................... 12.5-1
.1.2     Preparation of Procedures ......................................................................... 12.5-1
.1.3      Procedures................................................................................................. 12.5-1
.2       Operating and Maintenance Procedures ................................................... 12.5-3
.2.1      Control Room Operating Procedures........................................................ 12.5-3
.2.1.1    General Operating Procedures .................................................................. 12.5-3
.2.1.2    System Operating Procedures ................................................................... 12.5-3
.2.1.3   Abnormal Operating Procedures .............................................................. 12.5-3
.2.1.4    Emergency Operating Procedures ............................................................ 12.5-4
.2.2      Station Procedures .................................................................................... 12.5-4 12-i                                                              Rev. 35


==1.4 REFERENCES==
tion      Title                                                                                                          Page
12.1-1Quality Assurance Program Description Topical Report.
.2.2.1   Radiation Protection Procedures............................................................... 12.5-4
MPS2 UFSAR12.2-1Rev. 35 12.2 TRAINING PROGRAM Formal training programs have be en established to train and qu alify the personnel who operate and maintain the Millstone nuclear units. These programs are structured to fulfill the requirements for training set forth in ACAD 91-015 (Reference 12.2-1). The pr ograms are based on a Systems Approach to Training and are a ccredited by the National Academy for Nuclear Training. Initial accreditation of these progr ams was awarded on August 21, 19 86, for operator training and on December 15, 1987, for Maintenance and Technical training. These programs are implemented for the following categories of nuclear power plant personnel:*Nonlicensed Operator*Reactor Operator*Senior Reactor Operator
.2.2.2    Instrument Maintenance Instructions........................................................ 12.5-4
*Shift Manager*Continuing (Requalification) Training for Licensed Personnel*Shift Technical Advisor
.2.2.3    Chemistry Procedures ............................................................................... 12.5-4
*Instrument and Control Technician*Electrical Maintenance Personnel*Mechanical Maintenance Personnel
.2.2.4    Radioactive Waste System Procedures..................................................... 12.5-4
*Chemistry Technician*Radiological Protection Technician*Engineering Support Personnel
.2.2.5    Material Control Procedures ..................................................................... 12.5-4
.2.2.6    Maintenance and Modification Procedures .............................................. 12.5-5
.2.2.7    Fire Protection Procedures........................................................................ 12.5-5
.2.2.8    Special Procedures .................................................................................... 12.5-5 RECORDS ......................................................................................................... 12.6-1 PHYSICAL SECURITY PLANS...................................................................... 12.7-1
.1        References................................................................................................. 12.7-1 QUALITY ASSURANCE PROGRAM ............................................................ 12.8-1
.1        Quality Assurance Program Description (QAPD) Topical Report........... 12.8-1 DELETED BY PKG FSC MP2-UCR-2011-014............................................... 12.9-1 12-ii                                                              Rev. 35


12.
ORGANIZATIONAL STRUCTURE rmation regarding the organizational structure is presented in Section 1.0, Organization, of Quality Assurance Program Description (QAPD) Topical Report (Reference 12.1-1). With the eption given below, that information is incorporated herein by reference.
owner, holding 100 percent of the Millstone 2 nuclear plant, is Dominion Nuclear necticut, Inc.
.1 MANAGEMENT AND TECHNICAL SUPPORT ORGANIZATION rmation regarding the management and technical support organization is presented in tion 1.0, Organization, of the QAPD Topical Report (Reference 12.1-1). That information is rporated herein by reference.
.1.1 Technical Support for Operations organization providing technical support for operations is described in Section 1.0 of the PD Topical Report (Reference 12.1-1). That information is incorporated herein by reference.
.1.2 Organizational Arrangement organizational arrangement is as described in Section 1.0 of the QAPD Topical Report ference 12.1-1). That information is incorporated herein by reference.
.2 OPERATING ORGANIZATION
.2.1 Plant Organization plant organization is as shown in Reference 12.1-1.
.2.2 Operating Shift Crews minimum shift crew composition and license requirements during all modes of operation are tained in Section 6.2 of the Technical Specifications.
.3 QUALIFICATION OF NUCLEAR PLANT PERSONNEL cation and experience requirements are established by Section 6.3 of the Technical cifications.
.4 REFERENCES
-1  Quality Assurance Program Description Topical Report.
12.1-1                                Rev. 35
 
mal training programs have been established to train and qualify the personnel who operate maintain the Millstone nuclear units. These programs are structured to fulfill the requirements training set forth in ACAD 91-015 (Reference 12.2-1). The programs are based on a Systems roach to Training and are accredited by the National Academy for Nuclear Training. Initial editation of these programs was awarded on August 21, 1986, for operator training and on ember 15, 1987, for Maintenance and Technical training. These programs are implemented the following categories of nuclear power plant personnel:
Nonlicensed Operator Reactor Operator Senior Reactor Operator Shift Manager Continuing (Requalification) Training for Licensed Personnel Shift Technical Advisor Instrument and Control Technician Electrical Maintenance Personnel Mechanical Maintenance Personnel Chemistry Technician Radiological Protection Technician Engineering Support Personnel


==2.1 REFERENCES==
==2.1 REFERENCES==
12.2-1ACAD 91-015, National Academy for Nuclear Training, "The Objectives and Criteria for Accreditation of Tr aining in the Nuclear Power Industry."
MPS2 UFSAR12.3-1Rev. 35 12.3 EMERGENCY PLANNINGThe Staff approved Millstone Nuclear Power Station Emergency Plan (Reference 12.3-1) addresses the criteria set fo rth in NUREG-0654, FEMA-REP-1, Criteria for Preparation and Evaluation of Radiological Emer gency Response Plans and Prepar edness in Support of Nuclear Power Plants, Revision 1, November 1980 an d NUREG-0737, Supplement
: 1. As such, the NRC approved Emergency Plan provides for an acceptable state of emergency preparedness and meets the requirements of 10 CFR Part 50 and Appendix E thereto.
12.


==3.1 REFERENCES==
-1   ACAD 91-015, National Academy for Nuclear Training, The Objectives and Criteria for Accreditation of Training in the Nuclear Power Industry.
12.3-1J. F. Opeka letter to U. S. Nuclear Regulatory Commission Document Control Desk, transmitting Revision 6 to the Millstone Nuclear Power Station, Unit Numbers 1, 2, and 3 Emergency Plan, dated 11/4/91, and subsequent revisions thereto submitted on an annual basis.
12.2-1                                     Rev. 35
MPS2 UFSAR12.4-1Rev. 35 12.4 REVIEW AND AUDIT A program describing the review and audit of activities important to and affecting station safety during the operational phase ha s been established and comp lies with Regulatory Guide 1.33, "Quality Assurance Program Re quirements (Operation)." The pr ogram provides a system to ensure that these activities are performed in accordance with company policy, rules, and approved procedures.
12.4.1 ONSITE REVIEW On site review is conducted by committee(s) as described in the Quality Assurance Program Description (QAPD) Topical Report (Reference 12.4-1).
12.4.2 INDEPENDENT REVIEW Independent review of activities af fecting the unit's safety is performed by the Management Safety Review Committee as described in the QAPD Topical Report.
12.4.3 AUDITSThe Audit Program for activities affe cting safety related systems, st ructures, or components is as described in the QAPD Topical Report.


12.4.4 OTHER REVIEW GROUPS Other review groups evaluate, on a periodic basis, the effectiven ess of the units. These groups are:
Staff approved Millstone Nuclear Power Station Emergency Plan (Reference 12.3-1) resses the criteria set forth in NUREG-0654, FEMA-REP-1, Criteria for Preparation and luation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear er Plants, Revision 1, November 1980 and NUREG-0737, Supplement 1. As such, the NRC roved Emergency Plan provides for an acceptable state of emergency preparedness and meets requirements of 10 CFR Part 50 and Appendix E thereto.
independent consultants, task forces, nuclear industry management assessments, insurance inspections, etc.
.1 REFERENCES
-1  J. F. Opeka letter to U. S. Nuclear Regulatory Commission Document Control Desk, transmitting Revision 6 to the Millstone Nuclear Power Station, Unit Numbers 1, 2, and 3 Emergency Plan, dated 11/4/91, and subsequent revisions thereto submitted on an annual basis.
12.3-1                                Rev. 35


12.
rogram describing the review and audit of activities important to and affecting station safety ng the operational phase has been established and complies with Regulatory Guide 1.33, ality Assurance Program Requirements (Operation). The program provides a system to ure that these activities are performed in accordance with company policy, rules, and approved cedures.
4.1 ONSITE REVIEW site review is conducted by committee(s) as described in the Quality Assurance Program cription (QAPD) Topical Report (Reference 12.4-1).
4.2 INDEPENDENT REVIEW ependent review of activities affecting the unit's safety is performed by the Management ety Review Committee as described in the QAPD Topical Report.
  .3 AUDITS Audit Program for activities affecting safety related systems, structures, or components is as cribed in the QAPD Topical Report.
4.4 OTHER REVIEW GROUPS er review groups evaluate, on a periodic basis, the effectiveness of the units. These groups are:
pendent consultants, task forces, nuclear industry management assessments, insurance ections, etc.


==4.5 REFERENCES==
==4.5 REFERENCES==


12.4-1Quality Assurance Program Description Topical Report.
  -1   Quality Assurance Program Description Topical Report.
MPS2 UFSAR12.5-1Rev. 35 12.5 PLANT PROCEDURESStation procedures are written on a unit and station services leve l controlling the specifics of station operations, including specifications; maintenance and modification; periodic test, inspection, calibration, and special processes, and plant and equipment.
12.4-1                                   Rev. 35
12.5.1 ADMINISTRATIVE PROCEDURES 12.5.1.1 Conformance with Regulatory Guide 1.33 Regulatory Guide 1.33, issued February 1978, Qua lity Assurance Program Requirements, is used as guidance for the preparation of ad ministrative and station procedures
.12.5.1.2 Preparation of Procedures Preparation, review and ap proval of procedures is as described in the Qu ality Assurance Program Description (QAPD) Topical Report.
12.5.1.3 Procedures Administrative control and stat ion procedures cover a wide ra nge of topics. Major areas are described as follows.
Standing Orders to Operating Personnel Administrative control procedur es define the authorities a nd responsibilities of operating personnel. The procedures specify the number of personnel with reactor operator and senior reactor operator licenses required to be on site or at the contro ls in all plant conditions. The administrative procedures dire ct the proper maintenance, review, and disposition of operating records, establish requirements for shift turnover, and establish the author ity and responsibilities of the person in charge of the c ontrol room to limit access. Procedures also direct the assignment of shift personnel to duty stations, establish limi ts for scheduled worki ng hours, provide methods of timely and concise feedback of operating experience to applicable plant staff, and describe methods used to verify operational activities are performed correctly. Pl ant procedures also provide for shift turnover such that all necessary information is properly transmitted to the oncoming shifts.
Special Orders of a Transien t or Self-Cancelling Character Night orders are issued as ne cessary to provide guidance to operating shifts and are of a temporary nature but will be incorporated into an administ rative control if the need becomes permanent.
MPS2 UFSAR12.5-2Rev. 35 Equipment Control Procedures Instructions are written to sp ecify proper methods of obtaining clearances on plant equipment for maintenance or constructi on and to specify procedures for cont rol of jumpers, inhibits, and wire removal. The clearance procedure assigns responsibility fo r clearance issue to the shift supervisor. A licensed operator, after ensuring he is aware of the effect of the activity on the system, is required to authorize all maintena nce, tests, and surveillances performed on plant systems. Upon completion of the item, the document is returned to the operator for acceptance or for the purpose of returning the system to servi ce. The administrative procedures which control these evolutions provide the required explicit not ification of operational personne l whenever a safety related system is removed from and returned to service. The clearance procedure also contains certain restrictions on the issuance of a clearance. The instructions fo r control of jumpers, inhibits, and wire removal allow temporary al terations to critical structures, systems, or components to facilitate tests, maintenan ce, or operations. They specify administ rative procedures to be followed in performing such alterations.
Control of Maintenance and Modifications Administrative control procedures implement the review and appr oval requirements for maintenance and modifications. These procedures include the cont rol of plant modifications and maintenance on safety-related equipment. These procedures establish a framework of special process and maintenance procedures.
Master Surveillance Testing Schedule An administrative control procedure establishes a master test control list, implements the surveillance test program, and assigns responsib ility for review and a pproval of surveillance procedures in accordance with Technical Specifications. Written surveillance procedures are controlled as station or unit procedures.
Procedures for Logbook Usage and Control An administrative control proc edure establishes the requireme nts for logbook usage and control.Maintenance and Testing of Safety-Related Systems Procedures for maintenance and test ing of safety-related systems specify that prior to the removal of a safety-related system from service, the redundant system is verified operable. For equipment that requires specific surveillance in accordance with Technical Specifications, the surveillance testing is completed prior to re moving the system from service.These procedures are reviewed and improved, if necessary, to ensure operability of safety systems prior to taking credit for the system(s) to satisfy Technical Spec ification requirements.
MPS2 UFSAR12.5-3Rev. 35 Special Procedures Special procedures are prepared as necessary to support infrequent ly performed activities which are not to be included in the permanent list of station proce dures. A special pr ocedure can be written for any type of station procedure (i.e., maintenance, operating). The form of a special procedure is the same as the appl icable type of station procedure. All requirements for review, approval, revisions, and changes are the sa me as for permanent station procedures.
12.5.2 OPERATING AND MAINTENANCE PROCEDURES Operating and maintenance procedur es are divided into several cat egories which are described in the following subsections. The list of these procedures is contained in the Master Document Index.Operating and maintenance proce dures preparation is the res ponsibility of the appropriate department head. When a proce dure is written, the applicable Department Head/Manager is responsible to forward the pro cedure for review and approval in accordance with the QAPD Topical Report.


Plant operations are performed in accordance with written and approved Station and Department procedures.
ion procedures are written on a unit and station services level controlling the specifics of ion operations, including specifications; maintenance and modification; periodic test, ection, calibration, and special processes, and plant and equipment.
5.1 ADMINISTRATIVE PROCEDURES
  .1.1 Conformance with Regulatory Guide 1.33 ulatory Guide 1.33, issued February 1978, Quality Assurance Program Requirements, is used uidance for the preparation of administrative and station procedures.
  .1.2 Preparation of Procedures paration, review and approval of procedures is as described in the Quality Assurance Program cription (QAPD) Topical Report.
  .1.3 Procedures ministrative control and station procedures cover a wide range of topics. Major areas are cribed as follows.
nding Orders to Operating Personnel ministrative control procedures define the authorities and responsibilities of operating onnel. The procedures specify the number of personnel with reactor operator and senior tor operator licenses required to be on site or at the controls in all plant conditions. The inistrative procedures direct the proper maintenance, review, and disposition of operating rds, establish requirements for shift turnover, and establish the authority and responsibilities he person in charge of the control room to limit access. Procedures also direct the assignment hift personnel to duty stations, establish limits for scheduled working hours, provide methods imely and concise feedback of operating experience to applicable plant staff, and describe hods used to verify operational activities are performed correctly. Plant procedures also vide for shift turnover such that all necessary information is properly transmitted to the oming shifts.
cial Orders of a Transient or Self-Cancelling Character ht orders are issued as necessary to provide guidance to operating shifts and are of a porary nature but will be incorporated into an administrative control if the need becomes manent.
12.5-1                                  Rev. 35


Independent position verification of safety-related components/sy stems (valves, breakers, and control switches) with no indication in the cont rol room are performed prior to the return-to-service of the component/system.
ructions are written to specify proper methods of obtaining clearances on plant equipment for ntenance or construction and to specify procedures for control of jumpers, inhibits, and wire oval. The clearance procedure assigns responsibility for clearance issue to the shift supervisor.
12.5.2.1 Control Room Operating Procedures 12.5.2.1.1 General Operating ProceduresThese procedures cover major plant evolutions. Step-by-step instructions are provided for the function or task with the appropriate cross reference to system operating procedures for details of specific system operation. Appropriate pr ecautions and limitations are included.
icensed operator, after ensuring he is aware of the effect of the activity on the system, is uired to authorize all maintenance, tests, and surveillances performed on plant systems. Upon pletion of the item, the document is returned to the operator for acceptance or for the purpose eturning the system to service. The administrative procedures which control these evolutions vide the required explicit notification of operational personnel whenever a safety related em is removed from and returned to service. The clearance procedure also contains certain rictions on the issuance of a clearance. The instructions for control of jumpers, inhibits, and e removal allow temporary alterations to critical structures, systems, or components to litate tests, maintenance, or operations. They specify administrative procedures to be followed erforming such alterations.
12.5.2.1.2 System Operating Procedures These procedures provide step-by-step details for syst ems operations with appropriate prerequisites, precautions, limitations, and alarm responses. Ea ch procedure covers the expected modes of operation of the syst em as well as startup, shutdow n, filling and ve nting, and standby operation as applicable.
trol of Maintenance and Modifications ministrative control procedures implement the review and approval requirements for ntenance and modifications. These procedures include the control of plant modifications and ntenance on safety-related equipment. These procedures establish a framework of special cess and maintenance procedures.
12.5.2.1.3 Abnormal Operating Procedures Operating procedures are prepar ed for abnormal operation of th e unit. Abnormal operation is a condition that could degrade into an emergency or could violate T echnical Specifications if proper MPS2 UFSAR12.5-4Rev. 35 action were not taken. These pr ocedures identify the sympto ms of the abnormal condition, automatic actions that may occur, and the appropriate immediate and subseque nt operator actions.
ster Surveillance Testing Schedule administrative control procedure establishes a master test control list, implements the eillance test program, and assigns responsibility for review and approval of surveillance cedures in accordance with Technical Specifications. Written surveillance procedures are trolled as station or unit procedures.
12.5.2.1.4 Emergency Operating ProceduresEmergency operating procedures ar e prepared for conditions which might possibly lead to injury of plant personnel or the public if the release of radioactivity in excess of established limits occurs. These procedures include symptoms of the emergency c onditions, automatic actions that may or should occur, and immediate and subse quent operator actions. All immediate actions are required to be memorized by the operator since th e primary responsibility for detection of an emergency and initiation of corrective action rests upon the operator.
cedures for Logbook Usage and Control administrative control procedure establishes the requirements for logbook usage and control.
12.5.2.2 Station ProceduresStation procedures are written by the chemistry, health physics, security, generati on test, building services, stores, nuclear records, computer operations, station serv ices engineering and any other station group. These procedur es control the specific activities of these departments in support of unit or station operation (may be common site or unit specific). Station calibration procedures written by the maintenance or instrument departments are also station procedures.
ntenance and Testing of Safety-Related Systems cedures for maintenance and testing of safety-related systems specify that prior to the removal safety-related system from service, the redundant system is verified operable. For equipment requires specific surveillance in accordance with Technical Specifications, the surveillance ing is completed prior to removing the system from service.
12.5.2.2.1 Radiation Protection ProceduresRadiation Protection procedures support Section 13.5 and 10 CFR 20 requirements.
se procedures are reviewed and improved, if necessary, to ensure operability of safety systems r to taking credit for the system(s) to satisfy Technical Specification requirements.
12.5.2.2.2 Instrument Maintenance Instructions Instrument maintenance instructi ons are prepared for the perfor mance of periodic calibration, testing, and channel checking of safety-related pl ant instrumentation and all instruments used to satisfy Te chnical Specification re quirements. These instructions ensure measurement accuracies adequate to maintain plant safety parameters within operational and safety limits. In addition, instrument maintenance instructi ons outline the periodic calibrati on and accuracy requirements of test equipment necessary to support the calibration of safety-related instrumentation.
12.5-2                                  Rev. 35
12.5.2.2.3 Chemistry Procedures Chemistry procedures are prepared covering the routine analysis and sampling methods to ensure compliance with plant chemistry and discharge limits.12.5.2.2.4 Radioactive Waste System Procedures Procedures for operation of radwaste systems are included in system operating procedures.
 
12.5.2.2.5 Material Control Procedures This topic is covered by administr ative procedures in Section 12.5.1.3.
cial procedures are prepared as necessary to support infrequently performed activities which not to be included in the permanent list of station procedures. A special procedure can be ten for any type of station procedure (i.e., maintenance, operating). The form of a special cedure is the same as the applicable type of station procedure. All requirements for review, roval, revisions, and changes are the same as for permanent station procedures.
MPS2 UFSAR12.5-5Rev. 35 12.5.2.2.6 Maintenance and Modification Procedures Maintenance procedures are prepared to cover safety-related work which requires a specific technique or sequence not normally part of an individual's routine skill.
  .2 OPERATING AND MAINTENANCE PROCEDURES rating and maintenance procedures are divided into several categories which are described in following subsections. The list of these procedures is contained in the Master Document ex.
The procedures support the requirements and programs of Section 12.5.1.33 which covers administrative control of maintenance and modification.
rating and maintenance procedures preparation is the responsibility of the appropriate artment head. When a procedure is written, the applicable Department Head/Manager is onsible to forward the procedure for review and approval in accordance with the QAPD ical Report.
12.5.2.2.7 Fire Protection Procedures The Fire Protection Program is described in Section 9.10.
nt operations are performed in accordance with written and approved Station and Department cedures.
12.5.2.2.8 Special Procedures This topic is covered by administrative procedures.
ependent position verification of safety-related components/systems (valves, breakers, and trol switches) with no indication in the control room are performed prior to the return-to-ice of the component/system.
MPS2 UFSAR12.6-1Rev. 35 12.6 RECORDSRecords are kept and maintained in accordance wi th the applicable federa l, state, and operating license requirements. The records and retention program is as desc ribed in the Quality Assurance Program Description Topical Report. These controls include all quality related records including plant and as-built drawings.
  .2.1 Control Room Operating Procedures
MPS2 UFSAR12.7-1Rev. 35 12.7 PHYSICAL SECURITY PLANSThe security plan (Reference 12.7-1) states the security measures to be employed by the licensee for the protection of Millstone Units 1, 2, and 3 at the Millstone Nuclear Power Station, Waterford, Connecticut, against radiological sabotage. The plan s have been submitted in accordance with 10 CFR Part 73, Section 73.55, "Requirements for Physical Protection of Licensed Activities in Nuclear Power Re actors Against Radiological Sabotage."These plans include measures to de ter or prevent malicious actions that could result in the release of radioactive materials into the environmen t through sabotage. This protection is provided through the use of armed guards, physical barriers, m onitors, personnel access controls, alarms, communications, response to security conti ngencies, and liaison with appropriate law enforcement agencies.
  .2.1.1 General Operating Procedures se procedures cover major plant evolutions. Step-by-step instructions are provided for the ction or task with the appropriate cross reference to system operating procedures for details of cific system operation. Appropriate precautions and limitations are included.
12.
  .2.1.2 System Operating Procedures se procedures provide step-by-step details for systems operations with appropriate equisites, precautions, limitations, and alarm responses. Each procedure covers the expected des of operation of the system as well as startup, shutdown, filling and venting, and standby ration as applicable.
  .2.1.3 Abnormal Operating Procedures rating procedures are prepared for abnormal operation of the unit. Abnormal operation is a dition that could degrade into an emergency or could violate Technical Specifications if proper 12.5-3                                  Rev. 35
 
  .2.1.4 Emergency Operating Procedures ergency operating procedures are prepared for conditions which might possibly lead to injury plant personnel or the public if the release of radioactivity in excess of established limits urs. These procedures include symptoms of the emergency conditions, automatic actions that or should occur, and immediate and subsequent operator actions. All immediate actions are uired to be memorized by the operator since the primary responsibility for detection of an rgency and initiation of corrective action rests upon the operator.
  .2.2 Station Procedures ion procedures are written by the chemistry, health physics, security, generation test, building ices, stores, nuclear records, computer operations, station services engineering and any other ion group. These procedures control the specific activities of these departments in support of or station operation (may be common site or unit specific). Station calibration procedures ten by the maintenance or instrument departments are also station procedures.
  .2.2.1 Radiation Protection Procedures iation Protection procedures support Section 13.5 and 10 CFR 20 requirements.
  .2.2.2 Instrument Maintenance Instructions rument maintenance instructions are prepared for the performance of periodic calibration, ing, and channel checking of safety-related plant instrumentation and all instruments used to sfy Technical Specification requirements. These instructions ensure measurement accuracies quate to maintain plant safety parameters within operational and safety limits. In addition, rument maintenance instructions outline the periodic calibration and accuracy requirements of equipment necessary to support the calibration of safety-related instrumentation.
  .2.2.3 Chemistry Procedures mistry procedures are prepared covering the routine analysis and sampling methods to ensure pliance with plant chemistry and discharge limits.
  .2.2.4 Radioactive Waste System Procedures cedures for operation of radwaste systems are included in system operating procedures.
  .2.2.5 Material Control Procedures s topic is covered by administrative procedures in Section 12.5.1.3.
12.5-4                                    Rev. 35
 
ntenance procedures are prepared to cover safety-related work which requires a specific nique or sequence not normally part of an individuals routine skill.
procedures support the requirements and programs of Section 12.5.1.33 which covers inistrative control of maintenance and modification.
.2.2.7 Fire Protection Procedures Fire Protection Program is described in Section 9.10.
.2.2.8 Special Procedures s topic is covered by administrative procedures.
12.5-5                            Rev. 35
 
ords are kept and maintained in accordance with the applicable federal, state, and operating nse requirements. The records and retention program is as described in the Quality Assurance gram Description Topical Report. These controls include all quality related records including t and as-built drawings.
12.6-1                                    Rev. 35
 
security plan (Reference 12.7-1) states the security measures to be employed by the licensee the protection of Millstone Units 1, 2, and 3 at the Millstone Nuclear Power Station, erford, Connecticut, against radiological sabotage. The plans have been submitted in ordance with 10 CFR Part 73, Section 73.55, Requirements for Physical Protection of ensed Activities in Nuclear Power Reactors Against Radiological Sabotage.
se plans include measures to deter or prevent malicious actions that could result in the release adioactive materials into the environment through sabotage. This protection is provided ugh the use of armed guards, physical barriers, monitors, personnel access controls, alarms, munications, response to security contingencies, and liaison with appropriate law orcement agencies.


==7.1 REFERENCES==
==7.1 REFERENCES==
12.7-1J. F. Opeka letter to the Nuclear Regu latory Commission, "Millstone Nuclear Power Station Unit Numbers 1, 2, and 3 Physical Se curity Plan, Revision 15," dated December 16, 1991, and subsequent revisions thereto.
 
MPS2 UFSAR12.8-1Rev. 35 12.8 QUALITY ASSURANCE PROGRAM 12.8.1 QUALITY ASSURANCE PROGRAM DESCRIPTION (QAPD) TOPICAL REPOR TA comprehensive Quality Assura nce Program (QAP) has been de veloped and implemented to assure conformance with establ ished regulatory requirements, se t forth by the Nuclear Regulatory Commission, and accepted industry standards. The participants in the QAP assure that the design, procurement, construction, testi ng, operation, maintenance, repair , and modification of nuclear power plants are performed in a safe and effective manner.The QAPD Topical Report complies with the requirements set forth in Appendix B of 10 CFR Part 50, along with applicable sections of the Safety Analysis Report (SAR) for each license application, and is responsive to NUREG-0800, which describes the information presented in the Quality Assurance Sectio n of the SARs for nuclear power plants.The QAP is also established, maintained, and executed with regard to Radioactive Material Transport Packages as allowed by 10 CFR 71.101(f).The QAPD Topical Report is submitted periodically to the NRC in accordance with 10 CFR 50.54(a).
  -1  J. F. Opeka letter to the Nuclear Regulatory Commission, Millstone Nuclear Power Station Unit Numbers 1, 2, and 3 Physical Security Plan, Revision 15, dated December 16, 1991, and subsequent revisions thereto.
MPS2 UFSAR12.9-1Rev. 35 12.9 DELETED BY PKG FSC MP2-UCR-2011-014}}
12.7-1                                    Rev. 35
 
8.1 QUALITY ASSURANCE PROGRAM DESCRIPTION (QAPD) TOPICAL REPORT omprehensive Quality Assurance Program (QAP) has been developed and implemented to re conformance with established regulatory requirements, set forth by the Nuclear Regulatory mmission, and accepted industry standards. The participants in the QAP assure that the design, curement, construction, testing, operation, maintenance, repair, and modification of nuclear er plants are performed in a safe and effective manner.
QAPD Topical Report complies with the requirements set forth in Appendix B of CFR Part 50, along with applicable sections of the Safety Analysis Report (SAR) for each nse application, and is responsive to NUREG-0800, which describes the information ented in the Quality Assurance Section of the SARs for nuclear power plants.
QAP is also established, maintained, and executed with regard to Radioactive Material nsport Packages as allowed by 10 CFR 71.101(f).
QAPD Topical Report is submitted periodically to the NRC in accordance with CFR 50.54(a).
12.8-1                                  Rev. 35
 
12.9-1 Rev. 35}}

Latest revision as of 23:56, 29 October 2019

Final Safety Analysis Report, Rev. 35, Chapter 12, Conduct of Operations
ML17212A053
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/29/2017
From:
Dominion Nuclear Connecticut
To:
Office of Nuclear Reactor Regulation
Shared Package
ML17212A038 List:
References
17-208
Download: ML17212A053 (16)


Text

Millstone Power Station Unit 2 Safety Analysis Report Chapter 12

Table of Contents tion Title Page ORGANIZATIONAL STRUCTURE ............................................................... 12.1-1

.1 Management and Technical Support Organization .................................. 12.1-1

.1.1 Technical Support for Operations............................................................. 12.1-1

.1.2 Organizational Arrangement..................................................................... 12.1-1

.2 Operating Organization............................................................................. 12.1-1 1.2.1 Plant Organization .................................................................................... 12.1-1

.2.2 Operating Shift Crews .............................................................................. 12.1-1

.3 Qualification of Nuclear Plant Personnel ................................................. 12.1-1

.4 References................................................................................................. 12.1-1 TRAINING PROGRAM ................................................................................... 12.2-1

.1 References................................................................................................. 12.2-1 EMERGENCY PLANNING ............................................................................. 12.3-1

.1 References................................................................................................. 12.3-1 REVIEW AND AUDIT..................................................................................... 12.4-1

.1 Onsite Review........................................................................................... 12.4-1

.2 Independent Review ................................................................................. 12.4-1

.3 Audits........................................................................................................ 12.4-1

.4 Other Review Groups ............................................................................... 12.4-1

.5 References................................................................................................. 12.4-1 PLANT PROCEDURES.................................................................................... 12.5-1

.1 Administrative Procedures........................................................................ 12.5-1

.1.1 Conformance with Regulatory Guide 1.33 ............................................... 12.5-1

.1.2 Preparation of Procedures ......................................................................... 12.5-1

.1.3 Procedures................................................................................................. 12.5-1

.2 Operating and Maintenance Procedures ................................................... 12.5-3

.2.1 Control Room Operating Procedures........................................................ 12.5-3

.2.1.1 General Operating Procedures .................................................................. 12.5-3

.2.1.2 System Operating Procedures ................................................................... 12.5-3

.2.1.3 Abnormal Operating Procedures .............................................................. 12.5-3

.2.1.4 Emergency Operating Procedures ............................................................ 12.5-4

.2.2 Station Procedures .................................................................................... 12.5-4 12-i Rev. 35

tion Title Page

.2.2.1 Radiation Protection Procedures............................................................... 12.5-4

.2.2.2 Instrument Maintenance Instructions........................................................ 12.5-4

.2.2.3 Chemistry Procedures ............................................................................... 12.5-4

.2.2.4 Radioactive Waste System Procedures..................................................... 12.5-4

.2.2.5 Material Control Procedures ..................................................................... 12.5-4

.2.2.6 Maintenance and Modification Procedures .............................................. 12.5-5

.2.2.7 Fire Protection Procedures........................................................................ 12.5-5

.2.2.8 Special Procedures .................................................................................... 12.5-5 RECORDS ......................................................................................................... 12.6-1 PHYSICAL SECURITY PLANS...................................................................... 12.7-1

.1 References................................................................................................. 12.7-1 QUALITY ASSURANCE PROGRAM ............................................................ 12.8-1

.1 Quality Assurance Program Description (QAPD) Topical Report........... 12.8-1 DELETED BY PKG FSC MP2-UCR-2011-014............................................... 12.9-1 12-ii Rev. 35

ORGANIZATIONAL STRUCTURE rmation regarding the organizational structure is presented in Section 1.0, Organization, of Quality Assurance Program Description (QAPD) Topical Report (Reference 12.1-1). With the eption given below, that information is incorporated herein by reference.

owner, holding 100 percent of the Millstone 2 nuclear plant, is Dominion Nuclear necticut, Inc.

.1 MANAGEMENT AND TECHNICAL SUPPORT ORGANIZATION rmation regarding the management and technical support organization is presented in tion 1.0, Organization, of the QAPD Topical Report (Reference 12.1-1). That information is rporated herein by reference.

.1.1 Technical Support for Operations organization providing technical support for operations is described in Section 1.0 of the PD Topical Report (Reference 12.1-1). That information is incorporated herein by reference.

.1.2 Organizational Arrangement organizational arrangement is as described in Section 1.0 of the QAPD Topical Report ference 12.1-1). That information is incorporated herein by reference.

.2 OPERATING ORGANIZATION

.2.1 Plant Organization plant organization is as shown in Reference 12.1-1.

.2.2 Operating Shift Crews minimum shift crew composition and license requirements during all modes of operation are tained in Section 6.2 of the Technical Specifications.

.3 QUALIFICATION OF NUCLEAR PLANT PERSONNEL cation and experience requirements are established by Section 6.3 of the Technical cifications.

.4 REFERENCES

-1 Quality Assurance Program Description Topical Report.

12.1-1 Rev. 35

mal training programs have been established to train and qualify the personnel who operate maintain the Millstone nuclear units. These programs are structured to fulfill the requirements training set forth in ACAD 91-015 (Reference 12.2-1). The programs are based on a Systems roach to Training and are accredited by the National Academy for Nuclear Training. Initial editation of these programs was awarded on August 21, 1986, for operator training and on ember 15, 1987, for Maintenance and Technical training. These programs are implemented the following categories of nuclear power plant personnel:

Nonlicensed Operator Reactor Operator Senior Reactor Operator Shift Manager Continuing (Requalification) Training for Licensed Personnel Shift Technical Advisor Instrument and Control Technician Electrical Maintenance Personnel Mechanical Maintenance Personnel Chemistry Technician Radiological Protection Technician Engineering Support Personnel

2.1 REFERENCES

-1 ACAD 91-015, National Academy for Nuclear Training, The Objectives and Criteria for Accreditation of Training in the Nuclear Power Industry.

12.2-1 Rev. 35

Staff approved Millstone Nuclear Power Station Emergency Plan (Reference 12.3-1) resses the criteria set forth in NUREG-0654, FEMA-REP-1, Criteria for Preparation and luation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear er Plants, Revision 1, November 1980 and NUREG-0737, Supplement 1. As such, the NRC roved Emergency Plan provides for an acceptable state of emergency preparedness and meets requirements of 10 CFR Part 50 and Appendix E thereto.

.1 REFERENCES

-1 J. F. Opeka letter to U. S. Nuclear Regulatory Commission Document Control Desk, transmitting Revision 6 to the Millstone Nuclear Power Station, Unit Numbers 1, 2, and 3 Emergency Plan, dated 11/4/91, and subsequent revisions thereto submitted on an annual basis.

12.3-1 Rev. 35

rogram describing the review and audit of activities important to and affecting station safety ng the operational phase has been established and complies with Regulatory Guide 1.33, ality Assurance Program Requirements (Operation). The program provides a system to ure that these activities are performed in accordance with company policy, rules, and approved cedures.

4.1 ONSITE REVIEW site review is conducted by committee(s) as described in the Quality Assurance Program cription (QAPD) Topical Report (Reference 12.4-1).

4.2 INDEPENDENT REVIEW ependent review of activities affecting the unit's safety is performed by the Management ety Review Committee as described in the QAPD Topical Report.

.3 AUDITS Audit Program for activities affecting safety related systems, structures, or components is as cribed in the QAPD Topical Report.

4.4 OTHER REVIEW GROUPS er review groups evaluate, on a periodic basis, the effectiveness of the units. These groups are:

pendent consultants, task forces, nuclear industry management assessments, insurance ections, etc.

4.5 REFERENCES

-1 Quality Assurance Program Description Topical Report.

12.4-1 Rev. 35

ion procedures are written on a unit and station services level controlling the specifics of ion operations, including specifications; maintenance and modification; periodic test, ection, calibration, and special processes, and plant and equipment.

5.1 ADMINISTRATIVE PROCEDURES

.1.1 Conformance with Regulatory Guide 1.33 ulatory Guide 1.33, issued February 1978, Quality Assurance Program Requirements, is used uidance for the preparation of administrative and station procedures.

.1.2 Preparation of Procedures paration, review and approval of procedures is as described in the Quality Assurance Program cription (QAPD) Topical Report.

.1.3 Procedures ministrative control and station procedures cover a wide range of topics. Major areas are cribed as follows.

nding Orders to Operating Personnel ministrative control procedures define the authorities and responsibilities of operating onnel. The procedures specify the number of personnel with reactor operator and senior tor operator licenses required to be on site or at the controls in all plant conditions. The inistrative procedures direct the proper maintenance, review, and disposition of operating rds, establish requirements for shift turnover, and establish the authority and responsibilities he person in charge of the control room to limit access. Procedures also direct the assignment hift personnel to duty stations, establish limits for scheduled working hours, provide methods imely and concise feedback of operating experience to applicable plant staff, and describe hods used to verify operational activities are performed correctly. Plant procedures also vide for shift turnover such that all necessary information is properly transmitted to the oming shifts.

cial Orders of a Transient or Self-Cancelling Character ht orders are issued as necessary to provide guidance to operating shifts and are of a porary nature but will be incorporated into an administrative control if the need becomes manent.

12.5-1 Rev. 35

ructions are written to specify proper methods of obtaining clearances on plant equipment for ntenance or construction and to specify procedures for control of jumpers, inhibits, and wire oval. The clearance procedure assigns responsibility for clearance issue to the shift supervisor.

icensed operator, after ensuring he is aware of the effect of the activity on the system, is uired to authorize all maintenance, tests, and surveillances performed on plant systems. Upon pletion of the item, the document is returned to the operator for acceptance or for the purpose eturning the system to service. The administrative procedures which control these evolutions vide the required explicit notification of operational personnel whenever a safety related em is removed from and returned to service. The clearance procedure also contains certain rictions on the issuance of a clearance. The instructions for control of jumpers, inhibits, and e removal allow temporary alterations to critical structures, systems, or components to litate tests, maintenance, or operations. They specify administrative procedures to be followed erforming such alterations.

trol of Maintenance and Modifications ministrative control procedures implement the review and approval requirements for ntenance and modifications. These procedures include the control of plant modifications and ntenance on safety-related equipment. These procedures establish a framework of special cess and maintenance procedures.

ster Surveillance Testing Schedule administrative control procedure establishes a master test control list, implements the eillance test program, and assigns responsibility for review and approval of surveillance cedures in accordance with Technical Specifications. Written surveillance procedures are trolled as station or unit procedures.

cedures for Logbook Usage and Control administrative control procedure establishes the requirements for logbook usage and control.

ntenance and Testing of Safety-Related Systems cedures for maintenance and testing of safety-related systems specify that prior to the removal safety-related system from service, the redundant system is verified operable. For equipment requires specific surveillance in accordance with Technical Specifications, the surveillance ing is completed prior to removing the system from service.

se procedures are reviewed and improved, if necessary, to ensure operability of safety systems r to taking credit for the system(s) to satisfy Technical Specification requirements.

12.5-2 Rev. 35

cial procedures are prepared as necessary to support infrequently performed activities which not to be included in the permanent list of station procedures. A special procedure can be ten for any type of station procedure (i.e., maintenance, operating). The form of a special cedure is the same as the applicable type of station procedure. All requirements for review, roval, revisions, and changes are the same as for permanent station procedures.

.2 OPERATING AND MAINTENANCE PROCEDURES rating and maintenance procedures are divided into several categories which are described in following subsections. The list of these procedures is contained in the Master Document ex.

rating and maintenance procedures preparation is the responsibility of the appropriate artment head. When a procedure is written, the applicable Department Head/Manager is onsible to forward the procedure for review and approval in accordance with the QAPD ical Report.

nt operations are performed in accordance with written and approved Station and Department cedures.

ependent position verification of safety-related components/systems (valves, breakers, and trol switches) with no indication in the control room are performed prior to the return-to-ice of the component/system.

.2.1 Control Room Operating Procedures

.2.1.1 General Operating Procedures se procedures cover major plant evolutions. Step-by-step instructions are provided for the ction or task with the appropriate cross reference to system operating procedures for details of cific system operation. Appropriate precautions and limitations are included.

.2.1.2 System Operating Procedures se procedures provide step-by-step details for systems operations with appropriate equisites, precautions, limitations, and alarm responses. Each procedure covers the expected des of operation of the system as well as startup, shutdown, filling and venting, and standby ration as applicable.

.2.1.3 Abnormal Operating Procedures rating procedures are prepared for abnormal operation of the unit. Abnormal operation is a dition that could degrade into an emergency or could violate Technical Specifications if proper 12.5-3 Rev. 35

.2.1.4 Emergency Operating Procedures ergency operating procedures are prepared for conditions which might possibly lead to injury plant personnel or the public if the release of radioactivity in excess of established limits urs. These procedures include symptoms of the emergency conditions, automatic actions that or should occur, and immediate and subsequent operator actions. All immediate actions are uired to be memorized by the operator since the primary responsibility for detection of an rgency and initiation of corrective action rests upon the operator.

.2.2 Station Procedures ion procedures are written by the chemistry, health physics, security, generation test, building ices, stores, nuclear records, computer operations, station services engineering and any other ion group. These procedures control the specific activities of these departments in support of or station operation (may be common site or unit specific). Station calibration procedures ten by the maintenance or instrument departments are also station procedures.

.2.2.1 Radiation Protection Procedures iation Protection procedures support Section 13.5 and 10 CFR 20 requirements.

.2.2.2 Instrument Maintenance Instructions rument maintenance instructions are prepared for the performance of periodic calibration, ing, and channel checking of safety-related plant instrumentation and all instruments used to sfy Technical Specification requirements. These instructions ensure measurement accuracies quate to maintain plant safety parameters within operational and safety limits. In addition, rument maintenance instructions outline the periodic calibration and accuracy requirements of equipment necessary to support the calibration of safety-related instrumentation.

.2.2.3 Chemistry Procedures mistry procedures are prepared covering the routine analysis and sampling methods to ensure pliance with plant chemistry and discharge limits.

.2.2.4 Radioactive Waste System Procedures cedures for operation of radwaste systems are included in system operating procedures.

.2.2.5 Material Control Procedures s topic is covered by administrative procedures in Section 12.5.1.3.

12.5-4 Rev. 35

ntenance procedures are prepared to cover safety-related work which requires a specific nique or sequence not normally part of an individuals routine skill.

procedures support the requirements and programs of Section 12.5.1.33 which covers inistrative control of maintenance and modification.

.2.2.7 Fire Protection Procedures Fire Protection Program is described in Section 9.10.

.2.2.8 Special Procedures s topic is covered by administrative procedures.

12.5-5 Rev. 35

ords are kept and maintained in accordance with the applicable federal, state, and operating nse requirements. The records and retention program is as described in the Quality Assurance gram Description Topical Report. These controls include all quality related records including t and as-built drawings. 12.6-1 Rev. 35

security plan (Reference 12.7-1) states the security measures to be employed by the licensee the protection of Millstone Units 1, 2, and 3 at the Millstone Nuclear Power Station, erford, Connecticut, against radiological sabotage. The plans have been submitted in ordance with 10 CFR Part 73, Section 73.55, Requirements for Physical Protection of ensed Activities in Nuclear Power Reactors Against Radiological Sabotage.

se plans include measures to deter or prevent malicious actions that could result in the release adioactive materials into the environment through sabotage. This protection is provided ugh the use of armed guards, physical barriers, monitors, personnel access controls, alarms, munications, response to security contingencies, and liaison with appropriate law orcement agencies.

7.1 REFERENCES

-1 J. F. Opeka letter to the Nuclear Regulatory Commission, Millstone Nuclear Power Station Unit Numbers 1, 2, and 3 Physical Security Plan, Revision 15, dated December 16, 1991, and subsequent revisions thereto.

12.7-1 Rev. 35

8.1 QUALITY ASSURANCE PROGRAM DESCRIPTION (QAPD) TOPICAL REPORT omprehensive Quality Assurance Program (QAP) has been developed and implemented to re conformance with established regulatory requirements, set forth by the Nuclear Regulatory mmission, and accepted industry standards. The participants in the QAP assure that the design, curement, construction, testing, operation, maintenance, repair, and modification of nuclear er plants are performed in a safe and effective manner.

QAPD Topical Report complies with the requirements set forth in Appendix B of CFR Part 50, along with applicable sections of the Safety Analysis Report (SAR) for each nse application, and is responsive to NUREG-0800, which describes the information ented in the Quality Assurance Section of the SARs for nuclear power plants.

QAP is also established, maintained, and executed with regard to Radioactive Material nsport Packages as allowed by 10 CFR 71.101(f).

QAPD Topical Report is submitted periodically to the NRC in accordance with CFR 50.54(a).

12.8-1 Rev. 35

12.9-1 Rev. 35