ML18115A267: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(10 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML18115A267
| number = ML18115A267
| issue date = 05/01/2018
| issue date = 05/01/2018
| title = Joseph M. Farley Nuclear Plant, Units 1 and 2, and Vogtle Electric Generating Plant, Units 1 and 2 Withdrawal of Proposed Alternatives FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-05-02 Instrument Lines on the Pressurizer (Epids L-2017-LLR-0115,L-201
| title = Withdrawal of Proposed Alternatives FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-05-02 Instrument Lines on the Pressurizer (Epids L-2017-LLR-0115,L-2017-LLR-0116)
| author name = Orenak M D
| author name = Orenak M
| author affiliation = NRC/NRR/DORL/LPLII-1
| author affiliation = NRC/NRR/DORL/LPLII-1
| addressee name = Gayheart C A
| addressee name = Gayheart C
| addressee affiliation = Southern Nuclear Operating Co, Inc
| addressee affiliation = Southern Nuclear Operating Co, Inc
| docket = 05000348, 05000364, 05000424, 05000425
| docket = 05000348, 05000364, 05000424, 05000425
| license number = NPF-002, NPF-008
| license number = NPF-002, NPF-008
| contact person = Orenak M D
| contact person = Orenak M
| case reference number = EPID L-2017-LLR-0115, EPID L-2017-LLR-0116
| case reference number = EPID L-2017-LLR-0115, EPID L-2017-LLR-0116
| document type = Letter
| document type = Letter
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc. BIN 038 40 Inverness Center Parkway Birmingham, AL 35201-1295 May 1, 2018
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 1, 2018 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
BIN 038 40 Inverness Center Parkway Birmingham, AL 35201-1295


==SUBJECT:==
==SUBJECT:==
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 -WITHDRAWAL OF PROPOSED ALTERNATIVES FNP-ISI-ALT-05-02 AND VEGP-ISI-ALT-04-02 REGARDING INSTRUMENT LINES ON THE PRESSURIZER (EPIDS L-2017-LLR-0115 AND L-2017-LLR-0116)  
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 -WITHDRAWAL OF PROPOSED ALTERNATIVES FNP-ISI-ALT-05-02 AND VEGP-ISI-ALT-04-02 REGARDING INSTRUMENT LINES ON THE PRESSURIZER (EPIDS L-2017-LLR-0115 AND L-2017-LLR-0116)


==Dear Ms. Gayheart:==
==Dear Ms. Gayheart:==
By letter dated October 6, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 172858088), Southern Nuclear Operating Company, Inc., (SNC) submitted proposed alternative FNP-ISI-ALT-05-02 for the Joseph M. Farley Nuclear Plant, Units 1 and 2, (Farley) and proposed alternative VEGP-ISI-ALT-04-02 for the Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). SNC proposed the use of alternative requirements for American Society of Mechanical Engineers (ASME) Class 1 upper level instrumentation lines on the pressurizers for Farley and Vogtle. By letter dated April 23, 2018 (ADAMS Accession No. ML 18113A447), SNC requested to withdraw FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02 because the proposed alternatives are not required due to previous U.S. Nuclear Regulatory Commission (NRC) approval during plant construction. This letter acknowledges the withdrawal of FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02. No further NRC staff review will be performed under EPIDs L-2017-LLR-0115 and L-2017-LLR-0116.
 
C. Gayheart If you have any questions, please contact me at (301) 415-3229 or via email at Michael.Orenak@nrc.gov. Docket Nos. 50-348, 50-364, 50-424, and 50-425 cc: Listserv Sincerely, ,Mvl oJ__ Michael Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation ML 18115A267 OFFICE DORL/LPL2-1 /PM DORL/LPL2-1/LA DORL/LPL2-1/BC NAME MOrenak KGoldstein MMarkley DATE 04/26/18 04/26/18 05/01/18
By letter dated October 6, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML172858088), Southern Nuclear Operating Company, Inc., (SNC) submitted proposed alternative FNP-ISI-ALT-05-02 for the Joseph M. Farley Nuclear Plant, Units 1 and 2, (Farley) and proposed alternative VEGP-ISI-ALT-04-02 for the Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). SNC proposed the use of alternative requirements for American Society of Mechanical Engineers (ASME) Class 1 upper level instrumentation lines on the pressurizers for Farley and Vogtle.
}}
By letter dated April 23, 2018 (ADAMS Accession No. ML18113A447), SNC requested to withdraw FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02 because the proposed alternatives are not required due to previous U.S. Nuclear Regulatory Commission (NRC) approval during plant construction. This letter acknowledges the withdrawal of FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02. No further NRC staff review will be performed under EPIDs L-2017-LLR-0115 and L-2017-LLR-0116.
 
C. Gayheart                               If you have any questions, please contact me at (301) 415-3229 or via email at Michael.Orenak@nrc.gov.
Sincerely,
                                            ,Mvl oJ__
Michael Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364, 50-424, and 50-425 cc: Listserv
 
ML18115A267 OFFICE     DORL/LPL2-1 /PM   DORL/LPL2-1/LA   DORL/LPL2-1/BC DORL/LPL2-1/PM NAME       MOrenak           KGoldstein       MMarkley       MOrenak DATE       04/26/18         04/26/18         05/01/18        05/01/18}}

Latest revision as of 07:41, 21 October 2019

Withdrawal of Proposed Alternatives FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-05-02 Instrument Lines on the Pressurizer (Epids L-2017-LLR-0115,L-2017-LLR-0116)
ML18115A267
Person / Time
Site: Vogtle, Farley  Southern Nuclear icon.png
Issue date: 05/01/2018
From: Michael Orenak
Plant Licensing Branch II
To: Gayheart C
Southern Nuclear Operating Co
Orenak M
References
EPID L-2017-LLR-0115, EPID L-2017-LLR-0116
Download: ML18115A267 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 1, 2018 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

BIN 038 40 Inverness Center Parkway Birmingham, AL 35201-1295

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 -WITHDRAWAL OF PROPOSED ALTERNATIVES FNP-ISI-ALT-05-02 AND VEGP-ISI-ALT-04-02 REGARDING INSTRUMENT LINES ON THE PRESSURIZER (EPIDS L-2017-LLR-0115 AND L-2017-LLR-0116)

Dear Ms. Gayheart:

By letter dated October 6, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML172858088), Southern Nuclear Operating Company, Inc., (SNC) submitted proposed alternative FNP-ISI-ALT-05-02 for the Joseph M. Farley Nuclear Plant, Units 1 and 2, (Farley) and proposed alternative VEGP-ISI-ALT-04-02 for the Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). SNC proposed the use of alternative requirements for American Society of Mechanical Engineers (ASME) Class 1 upper level instrumentation lines on the pressurizers for Farley and Vogtle.

By letter dated April 23, 2018 (ADAMS Accession No. ML18113A447), SNC requested to withdraw FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02 because the proposed alternatives are not required due to previous U.S. Nuclear Regulatory Commission (NRC) approval during plant construction. This letter acknowledges the withdrawal of FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02. No further NRC staff review will be performed under EPIDs L-2017-LLR-0115 and L-2017-LLR-0116.

C. Gayheart If you have any questions, please contact me at (301) 415-3229 or via email at Michael.Orenak@nrc.gov.

Sincerely,

,Mvl oJ__

Michael Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364, 50-424, and 50-425 cc: Listserv

ML18115A267 OFFICE DORL/LPL2-1 /PM DORL/LPL2-1/LA DORL/LPL2-1/BC DORL/LPL2-1/PM NAME MOrenak KGoldstein MMarkley MOrenak DATE 04/26/18 04/26/18 05/01/18 05/01/18