{{#Wiki_filter:August 22, 2019 Mr. Brian R. Sullivan Site Vice President Entergy Nuclear Operations, Inc. | {{#Wiki_filter:August 22, 2019 Mr. Brian R. Sullivan Site Vice President Entergy Nuclear Operations, Inc. | ||
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA | Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 | ||
-5508 | |||
==SUBJECT:== | ==SUBJECT:== | ||
PILGRIM NUCLEAR POWER STATION | PILGRIM NUCLEAR POWER STATION - REQUEST FOR EXEMPTION FROM 10 CFR 50.82(a)(8)(i)(A) FOR HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (EPID L-2018-LLE-0020) | ||
- REQUEST FOR EXEMPTION FROM 10 CFR 50.82(a)(8)(i)(A) FOR HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (EPID L-2018-LLE- | |||
==Dear Mr. Sullivan:== | ==Dear Mr. Sullivan:== | ||
The U.S. Nuclear Regulatory Commission (NRC) has approved the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.82(a)(8)(i)(A) for Entergy Nuclear Generation Company (ENGC) (to be renamed Holtec Pilgrim, LLC) and Holtec Decommissioning International, LLC (HDI | |||
). This action is in response to your application dated November 16, 2018 , which requested the exemption to allow Holtec Pilgrim, LLC and HDI to use funds from the decommissioning trust fund for spent fuel management and site restoration activities for Pilgrim Nuclear Power Station (Pilgrim). This exemption was requested in relation to the November 16, 2018, request by Entergy Nuclear Operations, Inc. (ENOI), on behalf of itself , | The U.S. Nuclear Regulatory Commission (NRC) has approved the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) | ||
. | Section 50.82(a)(8)(i)(A) for Entergy Nuclear Generation Company (ENGC) (to be renamed Holtec Pilgrim, LLC) and Holtec Decommissioning International, LLC (HDI). This action is in response to your application dated November 16, 2018, which requested the exemption to allow Holtec Pilgrim, LLC and HDI to use funds from the decommissioning trust fund for spent fuel management and site restoration activities for Pilgrim Nuclear Power Station (Pilgrim). | ||
A copy of the exemption is enclosed. The exemption has been forwarded to the Office of the Federal Register for publication. | This exemption was requested in relation to the November 16, 2018, request by Entergy Nuclear Operations, Inc. (ENOI), on behalf of itself, ENGC (to be known as Holtec Pilgrim, LLC), Holtec International (Holtec), and HDI for NRC approval of the direct transfer of Entergys operating authority to HDI and the indirect transfer of control of the Pilgrim Renewed Facility Operating License and the General License for the Pilgrim Independent Spent Fuel Storage Installation (ISFSI) to Holtec, as the licensed owner. | ||
If you have any questions, please contact me at (301) 415-2855 or via e-mail at Scott.Wall@nrc.gov | |||
B. Sullivan A copy of the exemption is enclosed. The exemption has been forwarded to the Office of the Federal Register for publication. If you have any questions, please contact me at (301) 415-2855 or via e-mail at Scott.Wall@nrc.gov. | |||
-293 | Sincerely, | ||
/RA/ | |||
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 | |||
==Enclosure:== | ==Enclosure:== | ||
Exemption | Exemption cc: Listserv | ||
; | LTR ML19192A083; Exemption ML19192A086; FRN ML19192A087 | ||
*via memo ** via email OFFICE NRR/DORL/LPL3/PM NRR/DORL/LSPB/LA NRR/DLP/PFPB/BC(A)* | |||
OGC ** NRR/DORL/LPL3/BC(A) ** | NAME SWall JBurkhardt FMiller DATE 07/15/19 07/12/19 06/07/19 OFFICE NMSS/DUWP/RDB/BC** OGC ** NRR/DORL/LPL3/BC(A) ** | ||
NAME BWatson AGhosh LRegner DATE 07/15/19 | NAME BWatson AGhosh LRegner DATE 07/15/19 08/06/19 08/06/19 OFFICE NRR/DORL/D NRR/DORL/LPL3/PM NAME CErlanger (GSuber for) SWall DATE 08/22/19 08/22/19 | ||
SWall | |||
-293}} | ENCLOSURE EXEMPTION ENTERGY NUCLEAR OPERATIONS, INC. | ||
HOLTEC DECOMMISSIONING INTERNATIONAL, LLC PILGRIM NUCLEAR POWER STATION DOCKET NO. 50-293}} |
Revision as of 23:03, 7 October 2019
ML19234A365 | |
Person / Time | |
---|---|
Site: | Pilgrim |
Issue date: | 08/22/2019 |
From: | NRC/OGC |
To: | NRC/OCM |
SECY RAS | |
References | |
50-293-LT, 72-1044-LT, EPID L-2018-LLE-0020, License Transfer, RAS 55191 | |
Download: ML19234A365 (4) | |
Text
August 22, 2019 Mr. Brian R. Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
SUBJECT:
PILGRIM NUCLEAR POWER STATION - REQUEST FOR EXEMPTION FROM 10 CFR 50.82(a)(8)(i)(A) FOR HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (EPID L-2018-LLE-0020)
Dear Mr. Sullivan:
The U.S. Nuclear Regulatory Commission (NRC) has approved the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR)
Section 50.82(a)(8)(i)(A) for Entergy Nuclear Generation Company (ENGC) (to be renamed Holtec Pilgrim, LLC) and Holtec Decommissioning International, LLC (HDI). This action is in response to your application dated November 16, 2018, which requested the exemption to allow Holtec Pilgrim, LLC and HDI to use funds from the decommissioning trust fund for spent fuel management and site restoration activities for Pilgrim Nuclear Power Station (Pilgrim).
This exemption was requested in relation to the November 16, 2018, request by Entergy Nuclear Operations, Inc. (ENOI), on behalf of itself, ENGC (to be known as Holtec Pilgrim, LLC), Holtec International (Holtec), and HDI for NRC approval of the direct transfer of Entergys operating authority to HDI and the indirect transfer of control of the Pilgrim Renewed Facility Operating License and the General License for the Pilgrim Independent Spent Fuel Storage Installation (ISFSI) to Holtec, as the licensed owner.
B. Sullivan A copy of the exemption is enclosed. The exemption has been forwarded to the Office of the Federal Register for publication. If you have any questions, please contact me at (301) 415-2855 or via e-mail at Scott.Wall@nrc.gov.
Sincerely,
/RA/
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosure:
Exemption cc: Listserv
LTR ML19192A083; Exemption ML19192A086; FRN ML19192A087
- via memo ** via email OFFICE NRR/DORL/LPL3/PM NRR/DORL/LSPB/LA NRR/DLP/PFPB/BC(A)*
NAME SWall JBurkhardt FMiller DATE 07/15/19 07/12/19 06/07/19 OFFICE NMSS/DUWP/RDB/BC** OGC ** NRR/DORL/LPL3/BC(A) **
NAME BWatson AGhosh LRegner DATE 07/15/19 08/06/19 08/06/19 OFFICE NRR/DORL/D NRR/DORL/LPL3/PM NAME CErlanger (GSuber for) SWall DATE 08/22/19 08/22/19
ENCLOSURE EXEMPTION ENTERGY NUCLEAR OPERATIONS, INC.
HOLTEC DECOMMISSIONING INTERNATIONAL, LLC PILGRIM NUCLEAR POWER STATION DOCKET NO. 50-293