MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23300A0022023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 ML23143A0872023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 And Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] |
Text
~Enter gy Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel: (601)368-5000 Mandy K. Halter Director, Nuclear Licensing 10 CFR 50.82 January 9, 2019 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Clarification of Post-Shutdown Decommissioning Activities Report Pilgrim Nuclear Power Station Docket No. 50-293 Renewed License No. DPR-35 LETTER NUMBER: 2.19.002
REFERENCES:
- 1. Letter, Entergy Nuclear Operations, Inc. to USNRC, "Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report,"
2.18.070, dated November 16, 2018 (ML18320A034)
- 2. Letter, Entergy Nuclear Operations, Inc. to USNRC, "Decommissioning Funding Status Report per 10 CFR §50.75(f)(1) and 10 CFR 50.82(a)(8)(v) -- Entergy Nuclear Operations, Inc.,"
CNR0-2018-00012 , dated March 29, 2018 (ML180888369)
- 3. Letter, Entergy Nuclear Operations, Inc. to USNRC, "Update to Spent Fuel Management Plan Pursuant to 10 CFR 50.54(bb)," 2.18.071, dated November 16, 2018 (ML18320A036)
- 4. Letter, Entergy Nuclear Operations, Inc. to USNRC, "Request for Exemption from 10 CFR 50.82(a)(8)(i)(A)," 2.18.069, dated November 16, 2018 (ML18320A037)
Dear Sir or Madam:
In Reference 1, Entergy Nuclear Operations, Inc. (Entergy), on behalf of itself and Entergy Nuclear Generation Company (ENGC), submitted a Post-Shutdown Decommissioning Activities Report (PSDAR) and Site-Specific Decommissioning Cost Estimate (DCE), provided as Attachment 1 to the PSDAR, for Pilgrim Nuclear Power Station (PNPS).
The purpose of this letter is to provide clarifying information on the PSDAR and DCE.
License Termination and Spent Fuel Management Expenses Table 3.2a of the PNPS DCE identifies the estimated annual expenditures for license term-ination activities. For the year 2018, the _license termination expenses are estimated to be
$19.142 million. Of that amount, approximately $10.895 million is for license termination planning. The remaining license termination expenses for 2018 are related to the evaluation of A/) /) /
2.19.002 I Page 2 of 3 alternatives to the SAFSTOR decommissioning method (Activity Oa.2.9 in Appendix C of the DCE).
License termination planning costs are a subset of the license termination costs. Consistent with Title 10 Code of Federal Regulations (CFR) 50.82(a)(8)(ii), the total estimated cost for license termination planning activities is $18.496 million, which corresponds to 3 percent ofthe 10 CFR 50.75(c) minimum amount for PNPS ($616.56 million), as reported in Reference 2. The decommissioning planning period for PNPS is approximately 12 months in length, and the costs are distributed over the years 2018 (approximately 7 months) and 2019 (approximately 5 months). This amount is reflected in Appendix C of the DCE as Activity Oa.2.8. As noted above, the estimated license termination planning cost for 2018 is approximately $10.895 million, and the balance of license termination planning expenses ($7.601 million) would be incurred in 2019. A summary of the breakdown of total license termination arid license termination planning costs for 2018 and.2019 is provided below.
License Termination Costs for 2018 and 2019
($ Millions)
Planning (3%) SAFSTOR Alternative Total Evaluation 2018 $10.895 $8.247 $19.142 2019 $7.601 $5.753 $13.354 Total $18.496 $14.000 $32.496 To date, Entergy has not taken any distribution from the nuclear decommissioning trust (NOT) to reimburse for any of the expenses related to license termination or license termination planning activities. Expenses identified in the DCE are not necessarily indicative of Entergy's intention to seek reimbursement from the NOT. 10 CFR 50.82(a)(8)(i) governs what the NOT may be used for, and 10 CFR 50.82(a)(8)(ii) provides the restrictions on accessing the NOT. Column 6 of Table 5 (Annual Cash Flow Analysis) of Reference 3 shows that the first disbursement from the NOT is expected to occur in 2019, which corresponds with the scheduled permanent cessation of operations and permanent removal of fuel from the reactor vessel.
Table 3.2b of the DCE identifies the estimated annual expenditures for spent fuel management activities and includes $16.133 million for 2018. To date, Entergy has not taken any distribution from the NOT to reimburse for any of the expenses related to spent fuel management or spent fuel management planning activities. Entergy understands that an exemption from 10 CFR 50.82(a)(8)(i)(A) must be granted prior to reimbursing any spent fuel management-relat ed expenses from the NOT. A request for exemption was submitted as Reference 4.
Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Costs The total cost for decommissioning the PNPS ISFSI is reported in Appendix D of the DCE
($9.421 million). The cost is reported in Appendix C of the DCE as a license termination expense (Activity 4b.2.5). In SAFSTOR, it is assumed that the ISFSI is decommissioned along with the plant. As such, the $9.421 million is included in Table 3.2a of the DCE, in years 2076-2078, as follows:
2.19.002 / Page 3 of 3 2076 $2.652 million 2077 $4.050 million 2078 $2.719 million Total $9.421 million This letter contains no new regulatory commitments.
Should you have any questions concerning this letter or require additional information, please contact Mr. Peter J. Miner at (508) 830-7127.
Sincerely, MKH/plc cc:
Mr. David C. Lew Regional Administrator, Region I U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Mr. John Lamb, Senior Project Manager Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-9012 Washington, DC 20555-0001 Mr. John Giarrusso, Jr.
Planning, Preparedness and Nuclear Section Chief Mass. Emergency Management Agency 400 Worcester Road Framingham, MA 01702 Mr. John Priest, Director Massachusetts Department of Public Health Radiation Control Program Commonwealth of Massachusetts 529 Main Street, Suite 1M2A Charlestown, MA 02129-1121 NRC Resident Inspector Pilgrim Nuclear Power Station