| issue date = 12/29/2009
| issue date = 12/29/2009
| title = Revision of Schedule for the Conduct of Review of the Duane Arnold Energy Center License Renewal Application
| title = Revision of Schedule for the Conduct of Review of the Duane Arnold Energy Center License Renewal Application
| author name = Harris B K
| author name = Harris B
| author affiliation = NRC/NRR/DLR/RPB1
| author affiliation = NRC/NRR/DLR/RPB1
| addressee name = Costanzo C
| addressee name = Costanzo C

Revision as of 15:36, 11 July 2019

Revision of Schedule for the Conduct of Review of the Duane Arnold Energy Center License Renewal Application
ML093451650
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 12/29/2009
From: Harris B
License Renewal Projects Branch 1
To: Costanzo C
Florida Power & Light Co
Harris B
References
TAC MD9769
Download: ML093451650 (5)


Text

December 29, 2009 Mr. Christopher Costanzo Vice President, Nuclear Plant Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769)

Dear Mr. Costanzo:

Enclosed is a revised schedule for the review of the Duane Arnold Energy Center license renewal application. The schedule updates the issuance date of the safety evaluation report and the associated Advisory Committee on Reactor Safeguards meeting for license renewal.

If you have any questions, please contact me by telephone at 301-415-2277 or by e-mail at brian.harris2@nrc.gov. Sincerely, /RA/

Brian K. Harris, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331

Enclosure:

As stated

cc w/encl: See next page December 29, 2009 Mr. Christopher Costanzo Vice President, Nuclear Plant Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769)

Dear Mr. Costanzo:

Enclosed is a revised schedule for the review of the Duane Arnold Energy Center license renewal application. The schedule updates the issuance date of the safety evaluation report and the associated Advisory Committee on Reactor Safeguards meeting for license renewal.

If you have any questions, please contact me by telephone at 301-415-2277 or by e-mail at brian.harris2@nrc.gov. Sincerely, /RA/

Brian K. Harris, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331

Enclosure:

As stated

cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession No. ML093451650 OFFICE: PM:RPB1:DLR LA:DLR BC:RPB1:DLR PM:RPB1:DLR NAME: BHarris SFigueroa BPham BHarris DATE: 12/14/09 12/14/09 12/29/09 12/29/09 OFFICIAL AGENCY RECORD Letter to Christopher Costanzo from Brian K. Harris dated December 29, 2009

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource -------------

B. Harris C. Eccelston K. Feintuch M. Spencer, OGC Duane Arnold Energy Center cc: Mr. M. S. Ross Vice President and Associate General Counsel Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

Ms. Marjan Mashhadi Senior Attorney Florida Power & Light Company 801 Pennsylvania Avenue, NW Suite 220 Washington, DC 20004

Mr. Steven R. Catron Manager, Regulatory Affairs Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324

U.S. Nuclear Regulatory Commission Resident Inspector

=s Office Rural Route #1 Palo, IA 52324 Mr. Mano Nazir Senior Vice President and Nuclear Chief Operating Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408 Mr. D. A. Curtland Plant Manager Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785

Abdy Khanpour Vice President, Engineering Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408 Ms. Melanie Rasmussen Radiation Control Program Director Bureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319-0075

Chairman, Linn County Board of Supervisors 930 1st Street SW Cedar Rapids, IA 52404 Mr. Raj Kundalkar, Vice President Fleet Organizational Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

Mr. McHenry Cornell Director, Licensing and Performance Improvement Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 ENCLOSURE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION UPDATED REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 10/01/08 10/01/08 Publish Federal Register Notice (FRN) - LRA availability 08/26/08 08/29/08 Publish FRN - acceptance and opportunity for hearing 10/01/08 10/01/08 Publish FRN - intent to conduct environmental scoping 10/08/08 10/09/08 Public Meeting - license renewal overview / environmental scoping meeting10/22/08 10/22/08 Deadline for filing hearing requests and petitions for intervention 12/01/08 12/01/08 Environmental scoping period ends 12/08/08 12/08/08 Audit - Scoping & Screening Methodology 08/20/09 08/20/09 Audit - Aging Management 08/10/09 08/10/09 Audit - Environmental 06/15/09 06/15/09 Issue draft Supplemental Environmental Impact Statement (SEIS) 01/15/10 Publish FRN - draft SEIS available for comments 01/29/10 Issue Safety Evaluation Report (SER) with open items 05/05/10 Public Meeting - draft SEIS meeting 03/03/10 End of draft SEIS comment period 04/14/10 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 06/10/10 Issue final SEIS 10/08/10 Issue final SER 09/03/10 U.S. EPA FRN Published - availability of final SEIS 10/15/10 ACRS full committee meeting 10/12/10 Decision - Director NRR (22 months if no hearing) 12/10/10