Line 3: |
Line 3: |
| | issue date = 07/19/2012 | | | issue date = 07/19/2012 |
| | title = Application to Revise Watts Bar Nuclear Plant, Unit 1 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) | | | title = Application to Revise Watts Bar Nuclear Plant, Unit 1 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) |
| | author name = Shea J W | | | author name = Shea J |
| | author affiliation = Tennessee Valley Authority | | | author affiliation = Tennessee Valley Authority |
| | addressee name = | | | addressee name = |
Letter Sequence Request |
---|
|
|
MONTHYEARML1207501092012-03-15015 March 2012 Notice of Meeting with Tennessee Valley Authority to Discuss Pre-submittal Planning for Licensing Basis Change Regarding Hydrology for Watts Bar Nuclear Plant, Unit 1 Project stage: Request ML12097A3122012-03-29029 March 2012 3/29/2012 Meeting Slides - Pre-Submittal Meeting Regarding Watts Bar Unit 1 Hydrology Licensing Basis Change Project stage: Meeting ML12097A3062012-04-11011 April 2012 3/29/2012 Summary of Pre-Application Meeting with Tennessee Valley Authority on Changing the Licensing Basis for Hydrologic Engineering Project stage: Meeting ML12236A1672012-07-19019 July 2012 Application to Revise Watts Bar Nuclear Plant, Unit 1 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) Project stage: Request ML12226A5612012-08-10010 August 2012 Application to Revise Sequoyah Nuclear Plant Units I and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (SQN-TS-12-02) Project stage: Request ML12226A5622012-08-10010 August 2012 Enclosure 1, Evaluation of Proposed Changes Attachment 1 Proposed SQN Units 1 and 2 UFSAR Text Changes (Markups), Page 2.4-1 Through 2.4-41 Project stage: Request ML12226A5632012-08-10010 August 2012 Enclosure 1, Evaluation of Proposed Changes Attachment 1 Proposed SQN Units 1 and 2 UFSAR Text Changes (Markups), Page 2.4-42 Through Enclosure 2 Project stage: Request ML12276A3752012-10-0101 October 2012 Notification of Completion of Review of Updated Hydrologic Analysis Results for Impact on Watts Bar Nuclear Plant (WBN) Units 1 and 2 Final Environmental Statements Project stage: Other ML12292A3962012-10-19019 October 2012 Forthcoming Meeting with Tennessee Valley Authority Regarding Hydrology Issues Project stage: Request ML12319A1722012-11-14014 November 2012 Meeting Notice with Tennessee Valley Authority to Discuss Hydrology Issues at Watts Bar Nuclear Plant, Unit 1 Project stage: Request ML12348A2082012-12-13013 December 2012 Meeting Slides Re TVA Hydrology Update Slides Project stage: Request ML13010A1372013-01-11011 January 2013 Summary of Meeting with TVA Regarding Hydrology Updates Project stage: Request ML13037A3262013-01-31031 January 2013 Submittal Date for Supplement to Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-UFSAR-12-01) Project stage: Supplement CNL-14-026, Transmittal of Supplemental Clarification Information for the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01)2014-02-28028 February 2014 Transmittal of Supplemental Clarification Information for the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) Project stage: Supplement 2012-03-29
[Table View] |
|
---|
Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] |
Text
Attachment 4 to Enclosure I is to be withheld from public disclosure under 10 CFR 2.390.When separated from this attachment, this letter is decontrolled.
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 July 19, 2012 10 CFR 50.90 10 CFR 2.390(d)(1)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390
Subject:
Application to Revise Watts Bar Nuclear Plant Unit I Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No.ME8200 (WBN-UFSAR-1 2-01)
References:
- 1. Tennessee Valley Authority (TVA) Submittal to NRC Document Control Desk, "Commitments Related to Updated Hydrologic Analysis Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Unit 1," dated June 13, 2012 (ADAMS Accession No. ML12171A053)
- 2. NRC Meeting Summary, "Summary of March 29, 2012, Pre-Application Meeting with Tennessee Valley Authority on Changing the Licensing Basis for Hydrologic Engineering (TAC No. ME8200)," dated April 11, 2012 (ADAMS Accession No. ML12097A306)
In accordance with the provisions of 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," the Tennessee Valley Authority (TVA) is submitting a request for an amendment to Facility Operating License No. NPF-90 for Watts Bar Nuclear Plant (WBN), Unit 1.This license amendment request seeks approval to revise the WBN Unit 1 Updated Final Safety Analysis Report (UFSAR) to adopt a revised hydrologic analysis for the WBN Unit 1 site. These changes to the WBN Unit 1 UFSAR incorporate updates previously submitted in support of the initial licensing of WBN Unit 2 as well as more recently discovered input information.
Given that the WBN Unit 1 UFSAR and Unit 2 Final Safety Analysis Report (FSAR) are separate documents at this time, TVA will submit an update to the affected sections of the WBN Unit 2 FSAR on or before August 30, 2012 to assure that the hydrology licensing bases are consistent.
Printed -rycl pape U.S. Nuclear Regulatory Commission Page 2 July 19, 2012 The proposed changes in the updated hydrologic analysis include updated input information, and updates to methodology which includes use of the U.S. Army Corps of Engineers (USACE) Hydrologic Modeling System (HEC-HMS) and River Analysis System (HEC-RAS)software.
As a result of these proposed changes, the design basis flood (DBF) elevations at the WBN Unit 1 site are revised.These changes are determined to impact existing flood protection requirements for several WBN Unit 1 safety-related systems, structures, or components, which includes the Thermal Barrier Booster (TBB) Pump Motors and applicable Essential Raw Cooling Water (ERCW)equipment required for flood mode operation located on elevation 722.0 ft of the Intake Pumping Station (IPS). To restore margin for the TBB Pump Motors, a temporary flood protection barrier has been designed to be installed around the TBB Pump Motors prior to the event of a Stage I flood warning. Installation of the temporary flood protection barrier is in progress at WBN Unit 1. For the IPS, a compensatory measure of staged sandbags to be constructed into a berm at any time prior to or during the event of a Stage I flood warning has been implemented.
Permanent plant modifications are planned to restore or gain additional margin between the revised DBF elevations and these and other limiting safety-related systems, structures, and components.
The commitments to implement the permanent plant modification for the TBB Pump Motors and to address impact on the ERCW equipment in the IPS, as well as other actions regarding the updated hydrologic analysis, are provided in the first reference letter.Enclosure 1 provides a description, technical evaluation, regulatory evaluation and environmental consideration of the proposed technical changes. TVA is requesting NRC review and approval of all of the technical changes to the WBN Unit 1 UFSAR as described in Enclosure 1 to incorporate the cumulative effects that have occurred in the WBN Unit 1 hydrologic analysis since issuance of the Operating License. Specific technical changes are proposed in WBN Unit 1 UFSAR Sections 2.4, 2.4.1, 2.4.2, 2.4.3, 2.4.4, 2.4.11, and 2.4.14.Additional editorial changes are shown for WBN Unit 1 UFSAR Section 2.4 and do not require NRC review and approval.Attachment 1 to Enclosure 1 provides the existing WBN Unit 1 UFSAR text marked up to show the proposed changes.Attachment 2 to Enclosure 1 provides the proposed replacement WBN Unit 1 UFSAR Section 2.4 tables.Attachment 3 to Enclosure 1 provides the proposed replacement WBN Unit 1 UFSAR Section 2.4 figures suitable for public disclosure.
U.S. Nuclear Regulatory Commission Page 3 July 19, 2012 Attachment 4 to Enclosure 1 provides the proposed replacement WBN Unit 1 UFSAR Section 2.4 figures that contain security-related information identified by the designation"Security-Related Information
-Withhold Under 10 CFR 2.390." TVA hereby requests this information be withheld from public disclosure in accordance with the provisions of 10 CFR 2.390(d)(1).
Enclosure 2 provides responses to the issues identified by the NRC Staff in the second reference letter regarding the pre-application meeting held between TVA and the NRC Staff on March 29, 2012. The description, technical evaluation, regulatory evaluation and environmental consideration of the proposed technical changes provided in Enclosure 1 address these issues where applicable.
TVA requests that the NRC approve this amendment by July 19, 2013, to support licensing actions for submittal of the updated WBN Unit 2 FSAR consistent with the technical changes to the WBN Unit 1 UFSAR approved by the NRC, and subsequent preparation and submittal of the combined WBN Unit 1 and 2 UFSAR following WBN Unit 2 Operating License issuance.TVA has determined that there are no significant hazards considerations associated with the proposed changes and that the changes qualify for a categorical exclusion from environmental review pursuant to the provisions of 10 CFR 51.22(c)(9).
The WBN Plant Operations Review Committee and the WBN Nuclear Safety Review Board have reviewed the proposed changes and determined that operation of WBN in accordance with the proposed changes will not endanger the health and safety of the public.Additionally, in accordance with 10 CFR 50.91(b)(1), TVA is sending a copy of this letter and the enclosure to the Tennessee Department of Environment and Conservation.
Enclosure 3 contains a list of new regulatory commitments in this letter. Please address any questions regarding this request to Terry Cribbe at 423-751-3850.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 19th day of July 2012.Resp +fully, icelPresident, Nuclear Licensing
Enclosures:
- 1. Evaluation of Proposed Changes U.S. Nuclear Regulatory Commission Page 4 July 19, 2012 2. Evaluation of Issues from Pre-Application Meeting 3. List of New Regulatory Commitments cc (Enclosures):
NRC Regional Administrator
-Region II NRC Senior Resident Inspector
-Watts Bar Nuclear Plant, Unit 1 Director, Division of Radiological Health -Tennessee State Department of Environment and Conservation U.S. Nuclear Regulatory Commission Page 5 July 19, 2012 JWS NRC Project Manager -Watts Bar Nuclear Plant, Unit 1 NRC Project Manager -Watts Bar Nuclear Plant, Unit 2 G. P. Arent T. J. Carter E. W. Cobey G. M. Cook T. E. Cribbe W. D. Crouch S. M. Douglas K. D. Dutton D. E. Grissette D. H. Gronek D. K. Guinn D. E. Jernigan T. P. Morgan W. L. Prevatt J. W. Shea M. D. Skaggs P. D. Swafford E. J. Vigluicci NSRB EDMS