| {{#Wiki_filter: | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 June 6, 2013 Mr. Michael Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer |
| [[Issue date::June 6, 2013]]
| |
| | |
| Mr. Michael Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer | |
|
| |
|
| Exelon Nuclear | | Exelon Nuclear |
Line 27: |
Line 24: |
| 4300 Winfield Rd. | | 4300 Winfield Rd. |
|
| |
|
| Warrenville, IL 60555 | | Warrenville, IL 60555 SUBJECT: PEACH BOTTOM ATOMIC POWER STATION - U.S. NUCLEAR REGULATORY COMMISSION MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT NO. 05000277/2013406 AND |
| | |
| SUBJECT: PEACH BOTTOM ATOMIC POWER STATION - U.S. NUCLEAR REGULATORY COMMISSION MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT NO. 05000277/2013406 AND | |
|
| |
|
| 05000278/2013406 | | 05000278/2013406 |
|
---|
Category:Letter
MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter ML24011A1702024-01-11011 January 2024 Washington State University, Revised Responses to Request for Additional Information in Reference to LAR 2023-1: License Amendment Request - Section 5 of the Technical Specifications and Bases IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24003A7892024-01-0303 January 2024 Washington State Univ., Request to Rescind Responses to Request for Additional Information in Reference to LAR 2023-1: License Amendment Request Section 5 of the Technical Specifications and Bases for the Washington State University Modifie ML24003A9152024-01-0303 January 2024 Washington State University, Change in Level 1 Management for the Wsu Reactor Facility ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A1952023-11-30030 November 2023 Response to Request for Additional Information in Reference to LAR 2023-1: License Amendment Request Section 5 of the Technical Specifications and Bases for the Washington State University Modified Triga Reactor and Facility License R-76, P ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L ML23261A6082023-09-20020 September 2023 Washington State University Rfai License Amendment Request for Section 5 of the Technical Specifications for the Washington State University Modified Triga Nuclear Reactor and Facility License R-76 IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23242A3122023-08-30030 August 2023 Washington State University Modified Triga Reactor, 2023 Annual Report ML23102A2052023-08-28028 August 2023 Examination Result Letter No. 50-027/OL-23-01, Washington State University ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 ML23220A3862023-08-0808 August 2023 License Amendment Request Section 5 of the Technical Specifications and Bases for the Washington State University Modified Triga Reactor and Facility License R-76, Proposed Amendment 22 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 2024-01-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 June 6, 2013 Mr. Michael Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer
Exelon Nuclear
4300 Winfield Rd.
Warrenville, IL 60555 SUBJECT: PEACH BOTTOM ATOMIC POWER STATION - U.S. NUCLEAR REGULATORY COMMISSION MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT NO. 05000277/2013406 AND
05000278/2013406
Dear Mr. Pacilio:
On May 9, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Peach Bottom Atomic Power Station. The inspection covered one of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on May 9, 2013, with Mr. Patrick Navin, Plant Manager, and other members of your staff.
The inspection examined activities conducted under your licenses as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your licenses. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains security-related information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or in ADAMS.
When separated from the Enclosure, this
document is DECONTROLLED. SECURITY-RELATED INFORMA TION If you chose to provide a response, and security-related information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Raymond J. Powell, Chief Technical Support and Assessment Branch Division of Reactor Projects
Docket Nos. 50-277, 50-278 License Nos. DPR-44, DPR-56
Nonpublic Enclosure:
NRC Inspection Report 05000277/2013406 and 05000278/2013406 w/Attachment: Supplemental Information (CONTAINS (OUO-SRI))
cc w/encl; w/OUO-SRI J. Kovalchick, Manager, Site Security D. Allard, Director, PA Bureau of Radiation Protection T. Levering, Director of Emergency Preparedness Planning, Maryland Department of the Environment A. Lauland, Homeland Security Advisor, Maryland
cc w/o encl; w/o OUO-SRI Distribution via ListServ
ML13157A197 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available (M.D. 3.4 Non-Public A.3) OFFICE RI/DRP RI/DRP RI/DRS RI/DRP NAME NWarnek MGray ADimitriadis RPowell DATE 06/05/13 05/22/13 05/22/13 06/06/13 SECURITY-RELATED INFORMA TION Distribution w/o encl; w/o OUO-SRI: (via E-mail)
W. Dean, RA
D. Lew, DRA D. Roberts, DRP M. Layton, DRP C. Miller, DRS J. Clifford, DRS M. Gray, DRP S. Hansell, DRP, SRI A. Ziedonis, DRP, RI S. Schmitt, Admin D. Huyck, RI OEDO