|
|
Line 20: |
Line 20: |
| submission of generic Westinghouse document for common H* results Based on the ongoing discussions about the documents being produced to support the license amendments for the H* based IARC the question was raised about the best approach for common information. Each plant will be required to perform a separate analysis and the basis and interface limitations of that analysis will be part of the application. However, it is my understanding that Westinghouse is generating one or two documents that will be used by all of the applicants with no modification to the Westinghouse report. | | submission of generic Westinghouse document for common H* results Based on the ongoing discussions about the documents being produced to support the license amendments for the H* based IARC the question was raised about the best approach for common information. Each plant will be required to perform a separate analysis and the basis and interface limitations of that analysis will be part of the application. However, it is my understanding that Westinghouse is generating one or two documents that will be used by all of the applicants with no modification to the Westinghouse report. |
| It makes sense to submit this particular item only one time the question arises as to the best method to achieve this. Normally, Westinghouse would submit the document (as a generic WCAP) to the NRC for incorporation in the Topical Review process. However, the review time for a normal TR is outside of our needs for the IARC. | | It makes sense to submit this particular item only one time the question arises as to the best method to achieve this. Normally, Westinghouse would submit the document (as a generic WCAP) to the NRC for incorporation in the Topical Review process. However, the review time for a normal TR is outside of our needs for the IARC. |
| I am soliciting opinions and concerns on the other options that have been suggested. | | I am soliciting opinions and concerns on the other options that have been suggested. |
| : 1) Incorporate all of the documents into the lead submittal (Vogtle) and allow all of the other plants to reference the appropriate attachments with justification for applicability to their site 2) Allow Westinghouse to submit the generic documents directly to the NRC as a general communication | | : 1) Incorporate all of the documents into the lead submittal (Vogtle) and allow all of the other plants to reference the appropriate attachments with justification for applicability to their site 2) Allow Westinghouse to submit the generic documents directly to the NRC as a general communication |
|
| |
|
Revision as of 19:52, 30 April 2019
|
---|
Category:E-Mail
MONTHYEARML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C 2024-09-03
[Table view] |
Text
From: Boyle, Patrick Sent: Friday, November 05, 2010 7:27 AM To: Sanders, Carleen; Chernoff, Harold; Hess, Thomas A.; Taylor, Robert; Miller, Ed Cc: Martin, Robert
Subject:
submission of generic Westinghouse document for common H* results Based on the ongoing discussions about the documents being produced to support the license amendments for the H* based IARC the question was raised about the best approach for common information. Each plant will be required to perform a separate analysis and the basis and interface limitations of that analysis will be part of the application. However, it is my understanding that Westinghouse is generating one or two documents that will be used by all of the applicants with no modification to the Westinghouse report.
It makes sense to submit this particular item only one time the question arises as to the best method to achieve this. Normally, Westinghouse would submit the document (as a generic WCAP) to the NRC for incorporation in the Topical Review process. However, the review time for a normal TR is outside of our needs for the IARC.
I am soliciting opinions and concerns on the other options that have been suggested.
- 1) Incorporate all of the documents into the lead submittal (Vogtle) and allow all of the other plants to reference the appropriate attachments with justification for applicability to their site 2) Allow Westinghouse to submit the generic documents directly to the NRC as a general communication
Primary concern with option 1 is the limitations imposed on the plants referencing the Vogtle submittal versus approved licensing action and other concerns regarding applicable details for each facility. Primary concern with option 2 is it is outside of the normal TR process, but the documents still need to be reviewed and evaluated and will form a basis for multiple Safety Evaluations.
Please share your thoughts and concerns on these options and indicate your preferred course of action.
Thanks, Patrick G. Boyle Project Manager (Hatch and Vogtle)
NRR-DORL Plant Licensing Branch II-1 Office: O-8D09
Phone: 301-415-3936 E-mail Properties Mail Envelope Properties ()
Subject:
submission of generic Westinghouse document for common H* results Sent Date: 11/5/2010 10:11:13 AM Received Date: 11/5/2010 7:27:00 AM From: Boyle, Patrick
Created By: Patrick.Boyle@nrc.gov
Recipients:
Carleen.Sanders@nrc.gov (Sanders, Carleen)
Tracking Status: None Harold.Chernoff@nrc.gov (Chernoff, Harold)
Tracking Status: None TAHess@southernco.com (Hess, Thomas A.)
Tracking Status: None Robert.Taylor@nrc.gov (Taylor, Robert)
Tracking Status: None Ed.Miller@nrc.gov (Miller, Ed)
Tracking Status: None Robert.Martin@nrc.gov (Martin, Robert)
Tracking Status: None
Post Office:
Files Size Date & Time
MESSAGE 13718 11/5/2010
Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False
Sensitivity: olNormal Recipients received: