Line 59: | Line 59: | ||
, do hereby state as follows: | , do hereby state as follows: | ||
: 1. I am employed as a Project Manager in the Division of License Renewal in the U.S. Nuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation | : 1. I am employed as a Project Manager in the Division of License Renewal in the U.S. Nuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation | ||
("NRR"). I serve as a project manager for the Fermi Nuclear Power Plant, Unit 2 | |||
, license renewal application ("LRA"). Among other things, I am managing the preparation of the hearing file and mandatory disclosures in connection with the LRA at issue in this proceeding. | , license renewal application ("LRA"). Among other things, I am managing the preparation of the hearing file and mandatory disclosures in connection with the LRA at issue in this proceeding. | ||
: 2. I hereby certify that all potentially relevant materials required to be disclosed pursuant to 10 C.F.R. § 2.336(b) and (c) in the above-captioned proceeding have been disclosed in the attached Hearing File Index and that the disclosures are accurate and complete for documents identified as of August 2 7, 201 5. 3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information | : 2. I hereby certify that all potentially relevant materials required to be disclosed pursuant to 10 C.F.R. § 2.336(b) and (c) in the above-captioned proceeding have been disclosed in the attached Hearing File Index and that the disclosures are accurate and complete for documents identified as of August 2 7, 201 5. 3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information |
Revision as of 17:12, 27 April 2019
ML15244B412 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 09/01/2015 |
From: | Kanatas C E NRC/OGC |
To: | Arnold G S, Spritzer R M, Trikouros N G Atomic Safety and Licensing Board Panel |
SECY RAS | |
References | |
50-341-LR, ASLBP 14-933-01-LR-BD01, RAS 28244 | |
Download: ML15244B412 (5) | |
Text
U N I T E D S T A T E S N U C L E A R R E G U L A T O R Y C O M M I S S I O NWASHINGTON, DC 20555 - 0001 September 1, 201 5 In the Matter of DTE ELECTRIC COMPANY (Fermi Nuclear Power Plant, Unit 2)
Docket No. 50
-341-LR Dear Administrative Judges
- Pursuant to 10 C.F.R.
§§ 2.336 and 2.1203 and as modified by the Atomic Safety and Licensing Board's ("Board") Initial Scheduling Order ("ISO") dated February 27, 2015 , the U.S. Nuclear Regulatory Commission ("NRC") staff ("Staff") is providing notification that a supplement to the hearing file has be en created for this proceeding. The hearing file includes the Staff's documents subject to disclosure under 10 C.F.R.
§§ 2.336 and 2.1203 and the ISO. On or about September 4, 2015 , materials in the hearing file may be accessed through the Agencywide Documents Access and Management System ("ADAMS")
or through the Electronic Hearing Docket ("EHD")
, which may be accessed at http://adams.nrc.gov/ehd/. An index containing the ADAMS accession number, document date, and document title or description of each item in the hearing file is appended hereto as Attachment 1. Pursuant to 10 C.F.R. § 2.336(c), attached is the Affidavit of Elaine Keegan, certifying that all potentially relevant materials required by this section have been disclosed, and that the disclosures are accurate and complete as to documents identified as of August 2 7 , 2 01 5 (Attachment 2). The Staff notes that it has made a good faith effort to identify and characterize all documents meeting the criteria of 10 C.F.R.
§ 2.336(b) and 10 C.F.R.
§ 2.1203 in this proceeding, while excluding those documents for which there is a claim of privilege or protected status, based on the information and documentation reasonably available to it.
In identifying these documents, the Staff does not concede their relevance to the issues to be decided in this proceeding.
Administrative Judge Ronald M. Spritzer, Chair Atomic Safety and Licensing Board Panel Mail Stop:
T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555
-001 Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel Mail Stop:
T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555
-0001 Administrative Judge Gary S. Arnold Atomic Safety and Licensing Board Panel Mail Stop:
T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555
-00 01 The Staff anticipates publishing the Draft Supplemental Environmental Impact Statement in October 2015 and the Final Supplemental Environmental Impact Statement in June 2016. The Safety Evaluation Report ("SER") with open items is anticipated to be published in January 2 01 6. The schedule for the publication of the final SER is to be determined at this time.
1 Respectfully submitted, /signed (electronically) by/
Catherine E. Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O
-15 D21 Washington, DC 20555
-0001 Telephone: (301) 415-2321 E-mail: catherine.kanatas@nrc.gov Date of Signature: September 1, 2015
Enclosures:
Attachment 1: Hearing File Index Attachment 2: Affidavit of Elaine Keegan
1 See Letter to Mr. Vito Kaminskas, DTE Electric Co.
, from Christopher G. Miller, NRC, "Schedule Revision for the Safety Review of the Fermi 2 License Renewal Application (TAC No. MF4222) (Aug. 28, 2015) (ADAMS Accession No. ML15238B790).
Attachment 1
-- Fermi Nuclear Power Plant, Unit 2 License Renewal Hearing File Index Supplemental Disclosure #4
- September 1, 2015 ID # ADAMS Accession Number Document Date Document Title/Description 0022 6 ML15243A208 08/0 3/2015 [External_Sender] Incorrect email address for Michael J. Keegan / Spent Fuel Pool Concerns at Fermi 2
- Redacted Version
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
) ) DTE ELECTRIC COMPANY
) Docket No. 50
-341-LR ) (Fermi Nuclear Power Plant, Unit 2)
)
AFFIDAVIT OF ELAINE KEEGAN CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)
I, Elaine Keegan
, do hereby state as follows:
- 1. I am employed as a Project Manager in the Division of License Renewal in the U.S. Nuclear Regulatory Commission's ("NRC") Office of Nuclear Reactor Regulation
("NRR"). I serve as a project manager for the Fermi Nuclear Power Plant, Unit 2
, license renewal application ("LRA"). Among other things, I am managing the preparation of the hearing file and mandatory disclosures in connection with the LRA at issue in this proceeding.
- 2. I hereby certify that all potentially relevant materials required to be disclosed pursuant to 10 C.F.R. § 2.336(b) and (c) in the above-captioned proceeding have been disclosed in the attached Hearing File Index and that the disclosures are accurate and complete for documents identified as of August 2 7, 201 5. 3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information
, and belief. /Executed in Accord with 10 C.F.R. § 2.304(d)
/ Elaine Keegan Senior Project Manager Division of License Renewal, NRR U.S. Nuclear Regulatory Commission Washington, DC 20555 Telephone: 301
-415-8517 E-mail: Elaine.Keegan@nrc.gov Executed in Rockville, Maryland this 27 th day of August, 201 5 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of
) ) DTE ELECTRIC COMPANY
) Docket No. 50
-341-LR ) (Fermi Nuclear Power Plant, Unit 2)
) CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305, I hereby certify that copies of
- Letter from Catherine E. Kanatas to the Board, dated September 1, 2015; Attachment 1
- Hearing File Index; and Attachment 2
- Affidavit of Elaine Keegan , have been served upon the Electronic Information Exchange, the NRC's E
-Filing System, in the above
-captioned proceeding, this 1st day of September, 2015. /Signed (electronically) by/
Catherine E. Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O
-15 D21 Washington, DC 20555
-0001 Telephone: (301) 415-2321 E-mail: catherine.kanatas@nrc.gov Date of Signature: September 1, 2015