| | number = ML102650445 | | | number = ML102650445 |
| | issue date = 08/19/2010 | | | issue date = 08/19/2010 |
| | title = Beaver Valley, Unit 2 - Post Exam Comments and Technical References (Folder 1) | | | title = Post Exam Comments and Technical References (Folder 1) |
| | author name = | | | author name = |
| | author affiliation = NRC/RGN-I | | | author affiliation = NRC/RGN-I |
Line 14: |
Line 14: |
| | document type = License-Operator, Part 55 Examination Related Material | | | document type = License-Operator, Part 55 Examination Related Material |
| | page count = 2 | | | page count = 2 |
| | | project = TAC:U01821 |
| | | stage = Other |
| }} | | }} |
|
| |
|
Revision as of 13:21, 30 January 2019
|
---|
Category:License-Operator
MONTHYEARL-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23107A2502023-04-18018 April 2023 Requalification Program Inspection ML23010A1252023-01-10010 January 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22335A4542022-05-20020 May 2022 Security Agreements ML22335A4532022-04-29029 April 2022 Miscellaneous - Proctor Log ML22335A4372022-04-0404 April 2022 Outline and Op Test Checklists: 2.3-1; 2.3-2 ML22335A4292022-04-0404 April 2022 Events and Evolutions Checklist: 3.4-1 ML21176A0042021-06-25025 June 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21105A3712021-04-20020 April 2021 March 10, 2021, NRC Generic Fundamentals Examination Results for Beaver Valley Power Station, Unit 2 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML21088A0622021-03-26026 March 2021 Final Qa/Related Forms (Folder 1) ML21088A0672021-02-18018 February 2021 Handouts to Applicants (Folder 3) ML21088A0642021-02-18018 February 2021 Final Written Examination and Operating Test Outlines (Folder 3) ML21048A2302021-02-17017 February 2021 Operator Licensing Examination Approval ML21088A0692021-02-17017 February 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML21088A0632021-02-17017 February 2021 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML21088A0702021-02-17017 February 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML21074A3312021-02-0707 February 2021 Final Operating Test (Sections a, B, and C) (Folder 3) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML21088A0582020-12-10010 December 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML21088A0602020-12-10010 December 2020 Draft Written Examination (Folder 2) ML20325A0312020-11-20020 November 2020 Modified Questions for ADAMS Record ML21088A0592020-09-30030 September 2020 Draft Written Examination and Operating Test Outlines (Folder 2) L-20-134, Response to NRC Regulatory Issue Summary 2020-01 - Preparation and Scheduling of Operator Licensing Examinations2020-04-15015 April 2020 Response to NRC Regulatory Issue Summary 2020-01 - Preparation and Scheduling of Operator Licensing Examinations ML21074A3322020-01-17017 January 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19289C3342019-10-15015 October 2019 September 4, 2019, NRC Generic Fundamentals Examination Results for Beaver Valley Power Station, Unit 1 (Cover Letter Publicly Available, Enclosures Withheld from Public) ML18304A1702018-10-30030 October 2018 Senior Reactor and Reactor Operator Initial License Examinations ML18247A3812018-09-0404 September 2018 Initial Operator Licensing Operating Test Approval - Beaver Valley Power Station Unit 1 L-18-148, Response to NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations2018-05-16016 May 2018 Response to NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations ML18086B0252018-02-16016 February 2018 Facility Cover Letter - Ri - March 2018 - GFE ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18101B3042017-12-19019 December 2017 Final Qa/Related Forms (Folder 1) ML18019B1732017-12-0505 December 2017 Post Exam Comments and Technical References (Folder 1) ML17320A0132017-11-15015 November 2017 Senior Reactor and Reactor Operator Initial License Examinations ML18102A2242017-11-0101 November 2017 Facility Comments on Draft NRC-Developed Operating Test (Folder 2) ML18102A1582017-11-0101 November 2017 Facility Comments on Draft NRC-Developed Written Exam (Folder 2) ML17305A0862017-10-31031 October 2017 Initial Operator Licensing Written Examination Approval ML18102A1062017-10-19019 October 2017 Final Qa/Related Forms - Form ES-401-6 ML17278A0352017-10-0303 October 2017 September 6, 2017, NRC Generic Fundamentals Examination Results for Beaver Valley Power Station Unit 1, (Cover Letter Publicly Available, Enclosures Withheld from Public) ML18102A2692017-08-28028 August 2017 Draft Written Examination and Operating Test Outlines ML18102A5732017-08-28028 August 2017 Draft Written Examination (Folder 2) ML18102A9822017-08-28028 August 2017 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML17072A0122017-03-0909 March 2017 Senior Reactor and Reactor Operator Initial License Examinations ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML17003A2812016-11-28028 November 2016 Handouts to Applicants (Folder 3) ML17003A2782016-11-28028 November 2016 Final Qa/Related Forms - Forms ES-401 (Folder 1) ML16342C5202016-11-21021 November 2016 Exam Folder 1, Post-Exam Comments, Resolution and Tech References ML16300A1552016-10-26026 October 2016 Initial Operator Licensing Written Examination Approval - Beaver Valley Power Station, Unit 1 ML16342C5222016-10-24024 October 2016 Final Written Exam, Folder 3 ML17003A2762016-10-24024 October 2016 Final Qa/Related Forms (Folder 1) 2023-05-10
[Table view] Category:Part 55 Examination Related Material
MONTHYEARL-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23010A1252023-01-10010 January 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22335A4542022-05-20020 May 2022 Security Agreements ML22335A4532022-04-29029 April 2022 Miscellaneous - Proctor Log ML22335A4292022-04-0404 April 2022 Events and Evolutions Checklist: 3.4-1 ML22335A4372022-04-0404 April 2022 Outline and Op Test Checklists: 2.3-1; 2.3-2 ML21176A0042021-06-25025 June 2021 Senior Reactor and Reactor Operator Initial License Examinations ML21088A0622021-03-26026 March 2021 Final Qa/Related Forms (Folder 1) ML21088A0672021-02-18018 February 2021 Handouts to Applicants (Folder 3) ML21088A0642021-02-18018 February 2021 Final Written Examination and Operating Test Outlines (Folder 3) ML21048A2302021-02-17017 February 2021 Operator Licensing Examination Approval ML21088A0702021-02-17017 February 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML21088A0632021-02-17017 February 2021 Final Qa/Related Form - Form ES-401-6 (Folder 1) ML21088A0692021-02-17017 February 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML21074A3312021-02-0707 February 2021 Final Operating Test (Sections a, B, and C) (Folder 3) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML21088A0602020-12-10010 December 2020 Draft Written Examination (Folder 2) ML21088A0582020-12-10010 December 2020 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML20325A0312020-11-20020 November 2020 Modified Questions for ADAMS Record ML21088A0592020-09-30030 September 2020 Draft Written Examination and Operating Test Outlines (Folder 2) L-20-134, Response to NRC Regulatory Issue Summary 2020-01 - Preparation and Scheduling of Operator Licensing Examinations2020-04-15015 April 2020 Response to NRC Regulatory Issue Summary 2020-01 - Preparation and Scheduling of Operator Licensing Examinations ML21074A3322020-01-17017 January 2020 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML18304A1702018-10-30030 October 2018 Senior Reactor and Reactor Operator Initial License Examinations ML18247A3812018-09-0404 September 2018 Initial Operator Licensing Operating Test Approval - Beaver Valley Power Station Unit 1 L-18-148, Response to NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations2018-05-16016 May 2018 Response to NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18101B3042017-12-19019 December 2017 Final Qa/Related Forms (Folder 1) ML18019B1732017-12-0505 December 2017 Post Exam Comments and Technical References (Folder 1) ML17320A0132017-11-15015 November 2017 Senior Reactor and Reactor Operator Initial License Examinations ML18102A2242017-11-0101 November 2017 Facility Comments on Draft NRC-Developed Operating Test (Folder 2) ML18102A1582017-11-0101 November 2017 Facility Comments on Draft NRC-Developed Written Exam (Folder 2) ML17305A0862017-10-31031 October 2017 Initial Operator Licensing Written Examination Approval ML18102A1062017-10-19019 October 2017 Final Qa/Related Forms - Form ES-401-6 ML17278A0352017-10-0303 October 2017 September 6, 2017, NRC Generic Fundamentals Examination Results for Beaver Valley Power Station Unit 1, (Cover Letter Publicly Available, Enclosures Withheld from Public) ML18102A2692017-08-28028 August 2017 Draft Written Examination and Operating Test Outlines ML18102A5732017-08-28028 August 2017 Draft Written Examination (Folder 2) ML18102A9822017-08-28028 August 2017 Draft Operating Test (Section a, Section B, Section C) (Folder 2) ML17072A0122017-03-0909 March 2017 Senior Reactor and Reactor Operator Initial License Examinations ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML17003A2812016-11-28028 November 2016 Handouts to Applicants (Folder 3) ML17003A2782016-11-28028 November 2016 Final Qa/Related Forms - Forms ES-401 (Folder 1) ML16342C5202016-11-21021 November 2016 Exam Folder 1, Post-Exam Comments, Resolution and Tech References ML16300A1552016-10-26026 October 2016 Initial Operator Licensing Written Examination Approval - Beaver Valley Power Station, Unit 1 ML16342C5222016-10-24024 October 2016 Final Written Exam, Folder 3 ML17003A2802016-10-24024 October 2016 Final Outlines (Folder 3) ML17003A2762016-10-24024 October 2016 Final Qa/Related Forms (Folder 1) ML17003A2822016-10-24024 October 2016 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML17003A2832016-09-30030 September 2016 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML16342C5212016-09-28028 September 2016 Exam Folder 3, Final Operating Examination 2023-05-10
[Table view] |
Text
Attachment A Facility Comments for Question # 78 Comment: The facility recommends accepting D as an alternate acceptable answer. The initial power level for the question was 95% with a small fuel element failure and a Dose equivalent 1-131 sample of 40lJCi/gm.
The SRO applicants were given a copy of Tech Spec 3.4.16 RCS Specific Activity and Tech Spec Figure 3.4.16-1 (Attachments 78-1 and 78-2). The applicants were asked to identify the Tech Spec required action and the bases for the action. LCO 3.4.16 Condition A is NOT met since the Dose equivalent 1-131 sample of 40IJCi/gm is greater than O.35IJCi/gm.
Condition A has two required actions, A.1 Verify Dose equivalent 1-131 within the acceptable region of Tech Spec Figure 3.4.16-1 AND A.2 Restore Dose equivalent 131 to within limit within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. On Tech Spec Figure 3.4.16-1 the Dose equivalent 1-131 of 40IJCi/gm is NOT within the acceptable region. LCD 3.4.16 Condition C is also NOT met and the required action is to be in Mode 3 with Tavg less than 500 OF within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. This was the answer key answer, choice B along with the correct bases. The intent of the question was to identify this required action. However, lAW ITS section 1.3 "Completion Times" Pg 1.3-1 and Pg 1.3-11 (Attachments 78-3 and 78-4) when multiple conditions apply to a single LCO all action times must be tracked and monitored from time of discovery to meet said condition.
Additionally, ITS Section 1.2 "Logical Connectors" page 1.2-1 (Attachment 78-5) states "both actions must be completed as long as the condition applies".
Therefore LCO 3.4.16 Required Action A.2, Restore Dose equivalent 1-131 to within limit within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is still a required action even though LCD 3.4.16 Condition C is more restrictive.
Restore Dose equivalent 1-131 to within limit within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> was choice D with the same bases as choice B. Based on this information, the facility recommends accepting D as an alternate acceptable answer.
Attachment A Facility Comments for Question # 90 Comment: The facility recommends deleting this question from the exam. The initial power level for question 90 was 75% NSA. The question then asked the SRO applicants to prioritize several VALID annunciators that were simultaneously received.
The applicants were asked to perform this prioritization lAW the guidance provided in 1/20M-48, "Adherence and Familiarization to Operating Procedures".
The annunciators listed in the choices were either yellow bordered, or no bordered.
lAW the guidance provided in 1/20M-48, "Adherence and Familiarization to Operating Procedures" paragraph E.2.c on page 12 (Attachment 90-1) the priority is: 1. First out annunciators
- 2. Red bordered annunciators
- 3. Yellow annunciators
- 4. No bordered annunciators The answer key answer, choice B was annunciator A5-8C, "US SERV TRMR 2C OVERCURRENT GEN TRIP since this is a First Out annunciator.
The intent of the question was to simply apply this procedural requirement to the stated situation.
However, if annunciator A5-8C, "US SERV TRMR 2C OVERCURRENT GEN TRIP is received, initiating device 251-206G is activated (Attachment 90-2). This will initiate a turbine trip (Attachment 90-3), which will initiate a reactor trip (Attachment 90-4) and the EOP network will be entered. lAW the guidance provided in 1/20M-48, "Adherence and Familiarization to Operating Procedures" paragraph E.1 on page 11 (Attachment 90-5) the EOPs take priority over Alarm Response Procedures (ARPs), and the ARPs are only to be reviewed as time permits. Asking applicants for the priority of yellow bordered, or no bordered Annunciators during EOP implementation is NOT a valid question since ARPs have no priority and are to be addressed only as time permits. Based on this information, the facility recommends deleting this question from the exam.