U-601289, Monthly Operating Rept for Sept 1988 for Clinton Power Station Unit 1

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Sept 1988 for Clinton Power Station Unit 1
ML20207N606
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/30/1988
From: Holtzscher D
ILLINOIS POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
U-601289, NUDOCS 8810190251
Download: ML20207N606 (6)


Text

. _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ .

, Pcge 1 ef 5 Attcchment to -

U-601289 CHALLENGES TO MAIN STEAM SAFETY / RELIEF VALVES f Month September 1988 None  !

t l

I l

l

\

l l

l l

l l

l l

l (Y\

(N I'

G810190251 880930 '

' I PDR ADOCK 05000461 ' t R PDC i

4

. . Pega 2 of 5 Attcchment to U-601289 MONTHLY OPERATING REPORT FOPJtAT AND INSTRUCTIONS AVERACE DAILY UNIT POWER LEVEL DOCKET NO. 50-461 UNIT Clinton 1 .,

DATE 09/30/88 COMPLETED BY D. L. Holtzscher TEI.EPHONE (217) 935-8881 X3400 MONTH September'1988 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 915 17 904 2 906 18 83) 3 614 19 902 1

4 763 ,

20 915 5 882 21 916 6 915 22 911  ;

7 913 23 901 8 916 24 558 j 9 913 25 649 l

10 920 26 _

854 .

11 888 27 904 12 911 28 906 f

13 913 29 898 14 914 30 898 15 913 31 N/A i 16 905 INSTRUCTIO.uS On this form. list the average daily unit power level in MWe-Net for each Jay in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of l

the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the averngs daily unit power output sheet should be footnoted to explain the

apparent anomaly.

l t

. -----ww- --.x.m,

  • . Pcg3 3 of 5 Attcchm:nt to U-601289 OPERATING DATA REPORT DOCKET NO. 50-461 UNIT Clinton 1 DATE 09/30/88 COMPLETED BY D. L. Holtzscher TELEPHONE (217) 935-8881 X3400 OPERATING STATUS
1. REPORTING PERIOD: September 1988 GROSS HOURS IN REPORTING PERIOD: 720
2. CURRENTLY AUTHORIZED POWER LEVEL (HWt): 2894 MAX. DEPEND CAPACITY (MDC)

(MWe-Net): 930 DESIGN ELECTRICAL RATING (MWe-Net): 933

3. POWER LEVEL TO VHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR WAS CRITICAL... 720 5463 6361.3 REACTOR RESERVE SHUTDOWN HOURS......... 0 0 0 6.
7. HOUPS GENERATOR ON LINE................ 720 5361.7 6260 0 0 0
8. UNIT RESERVE SHUTDOWN HOURS............
9. GROSS THERMAL ENERGY GENERATED (MWH)... 1,970,540 14,207,327 16,352,827
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 655,749 4,694,154 5.410,804 NET ELECTRICAL ENERGY GENERATED (MWH). . 625,213 4,472,768 5,156,871 11.
12. REACTOR SERVICE FACTOR................. 100% 83.1% 85.1%
13. REACTOR AVAILABILITY FACTOR............ 100% 83.1% 85.1%

14 UNIT SERVICE FACTOR.................... 100% 81.5% 83.8%

UNIT AVAILABILITY FACTOR............... 100% 81.5% 83.8%

15.

16 UNIT CAPACITY FACTOR (Using MDC)....... 93.4% 73.1% 74.2% __

17. UNIT CAPACITY FACTOR (Using Design MWe) 93.1% 72.9% 74.0%

UNIT FORCED OUTAGE RATE................ 0.0% 3.3% 2.8%

18.

19. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE, DATE, AND DURATION OF EACH): Refuel Outage. 01/03/89, 69 days
20. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUPt N/A FORECAST ACHIEVED
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION)*

INITIAL CRITICALITY 2/27/87 INITIAL ELECTRICITY (Synchror.iration) 4/24/87 COMPLETION OF WARP.ANTY RUN 10/09/87

Page 4 cf 5 Attachment ta U-601289 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-461 UNIT Clinton 1 DATE 09/30/88 COMPLETED BY D. L. Holtzscher TELEPHONE t217) 935-&J81 X3400 REPORT MONT11 September 1988 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION TEE REACTOR OR REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS NO. DATE S: SCHEDULED (HOURS) j 0 B: Reduced power to 1: Manual Reason 22 880903 S approximately 60% of reduction of rated power to allow reactor A-Equipment Failure control rod pattern recirculation (explain) adj ustment. flow and manual B-Maintenance or Test insertion of C-Fefueling control rods. D-Regulatr,ry Restriction E-Operator Training &

0 B: Redsced power to 1: Manual insertion License Examination 23 880925 5 approximately 60% of control W s F-Adrainistrative of ra ed power to and reduction C-Operational Error allow repair work in reactor (explain) on feedvater system recirculation H-Other steam leaks. flaw.

j Method I

1-Manual 2-Manual Scram 3-Auto Scram 4-Continued

~.

. Pego 5 of 5 -

Attcch :nt to U-601289 REFUELING INFORMATION

1) Name of facility Clinton Power Station
2) Scheduled date for next refueling shutdown January 3. 1989
3) Scheduled date for restart following refueling March 12 1989 l
4) Will refueling or resumption of operation thereafter require a Technical  :

Specification change or other license amendment? Yes I If Yes list in general what these will be: ,

An Operating License and Tachnical Specification change in response to the Reduced Feedwater Temperature Analysis, and Maximum Extended Operating Domain (MEOD) Analysis, i

5) Have the reload fuel design and core configuration been reviewed by the Facility Review Group (FRG) to determine whether any unreviewed safety '

questions are associated with the core reload? Yes 1

If no such review has takt.n place, when is it scheduled? N/A _

l

6) Scheduled date(s) for submitting proposed licensing action and supporting information:

The reload license amendment was submitted on September 6. 1988. .

i 7) List any iuportant licensing considerations associated with refueling f e.g., new or different fuel design or supplier, unreviewed design or r performance analysis methods, significant changes in fuel design new '

operating procedures. ,

i HEOD Analysis. C.E. "Barrier Fuel" will be used to replace

[

discharged fuel. l

' {

8) Number of fuel assemblies a) in the core 624 b) in the spent fuel storage pool 0 l i
9) The present licensed spent fuel pool storage cepacity 2.522 The size of any requested or planned increase in licensed storage  ;

capacity 0 (number of Nel assemblies) t l

10) The projected date of the last refueling that can be discharged to the spent fuel pool, assuming the present licensed capacity 2010 [

t 1 i

I r  !

l

{ I

F'

L30-88 Q O -14 )-LP 1A.120 Ill/NO/S POLVER 00AIPANY CLINTCN POWER St ATION P.o. Box 67s, cLINTON. lutNo;$ 61727 10CFR50.36 RG 1.16 Oc t obs.t r 14, 1988 Docket No. 50-461 Document Control Desk U.S. Nuclear Regulatory Cocunission k'ashington, D.C. 20555

Subject:

Clinton Power Station Unit 1 September 1988 Ponthly Operating Report NPF-62 Dear Sirs Please find enclosed the Monthly Operating Report for Clinton Power Station, Unit 1 for the period ending September 30, 1988.

Sincerely yours.

~

7 D. L. Holtzscher Acting Manager - Liceneing and Safety CSL/kar Enclosure cc Peg. tonal Administrato , Region III USNRC

} ,\r