ML091600278 | 29 June 2009 | Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application | |
ML091600289 | 29 June 2009 | Request for Additional Information for Cooper Nuclear Station License Renewal | Coatings Aging Management |
IR 05000298/2009011 | 22 June 2009 | IR 05000298-09-011 on 05/11/09 - 05/15/09 for Cooper Nuclear Station | High Radiation Area Offsite Dose Calculation Manual Annual Radiological Effluent Release Report |
NLS2009049, Response to Request for Additional Information for License Renewal Application - Section B and C | 22 June 2009 | Response to Request for Additional Information for License Renewal Application - Section B and C | Aging Management Fire Protection Program |
TAC:ME1521 | 18 June 2009 | ||
NLS2009038, Relief Request from Certain Inservice Test Code Requirements, RV-06, Revision 0 | 18 June 2009 | Relief Request from Certain Inservice Test Code Requirements, RV-06, Revision 0 | Stroke time |
TAC:ME1388 | 16 June 2009 | ||
ML091670109 | 16 June 2009 | Acceptance Review for License Amendment Request | |
ML091380365 | 15 June 2009 | Audit Report Regarding the Cooper Nuclear Station, Unit 1, License Renewal Application | Non-Destructive Examination Weld Overlay Coatings VT-2 Aging Management Maintenance Rule Program Biofouling Fire Protection Program |
NLS2009040, Response to Request for Additional Information for License Renewal Application - Aging Management Programs | 15 June 2009 | Response to Request for Additional Information for License Renewal Application - Aging Management Programs | High Radiation Area Coatings Operating Basis Earthquake VT-2 Zebra Mussel Finite Element Analysis Aging Management Maintenance Rule Program Biofouling |
ML091671807 | 12 June 2009 | Cooper, Response to Nuclear Regulatory Commission Request Regarding Withholding Information from Public Disclosure | |
ML091750118 | 11 June 2009 | CNS Lr - Tornado Occurrences in Nemaha County, Ne 1950-2009 | |
ML091590022 | 11 June 2009 | Summary of Teleconference Held on 5/27/09, Between the U.S. NRC Staff and Nebraska Public Power District, Related to a Clarification on Certain RAIs (RAI 3.3.2.2.3.3-1, RAI 3.3.2.2.7.3-1, and RAI 3.3.2.2.7.3-2), for Cooper License Renewal | Fire Protection Program |
ML091560496 | 10 June 2009 | Summary of Telephone Conference Call Held on May 20, 2009, Between the USNRC Staff and NPPD, Related to a Clarification on Certain RAI (RAI B.1.15-3 and RAI B.1.15-4), for CNS Renewal | |
IR 05000298/2009008 | 9 June 2009 | IR 05000298-09-008; on 02/23/09 - 05/12/09; Cooper Nuclear Station; Special Inspection Into Emergency Diesel Generator Lubricating Oil Pipe Cracking and Amphenol Connector Deficiencies | Mission time Condition Adverse to Quality Significance Determination Process Operability Determination Loctite Operability Assessment |
ML091830055 | 8 June 2009 | Reply from Fish and Wildlife Service on Transmission Line for Cooper Nuclear Station License Renewal | |
ML091530316 | 8 June 2009 | Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application | Aging Management Tornado Generated Missile Large early release frequency Fire Protection Program |
TAC:ME1264 | 3 June 2009 | ||
ML091540080 | 3 June 2009 | Acceptance Review for Decommissioning Cost Analysis and Maintenance of Irradiated Fuel | |
NLS2009034, Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency and Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process | 2 June 2009 | Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency and Clarification of a Frequency Example Using the Consolidated Line Item Improvement Process | Incorporated by reference Scram Discharge Volume |
TAC:ME0352 | 1 June 2009 | ||
ML091520530 | 1 June 2009 | G20090007/OEDO-2009-0007 -Email Record of 6/1/09 Phone Call with Tom Lakosh, Informing of Prb'S Initial Recommendation to Reject Petition Request Pursuant 10 CFR 2.206 Reactors Near Yellowstone Caldera Eruptions Response Due by 6/8/09 | High winds Probabilistic Risk Assessment Earthquake |
ML091750088 | 1 June 2009 | CNS Lr - NDEQ 2009 Ambient Network Plan | |
NLS2009037, Response to Nuclear Regulatory Commission Request for Additional Information Alternative Source Term | 29 May 2009 | Response to Nuclear Regulatory Commission Request for Additional Information Alternative Source Term | Internal Flooding |
ML091200017 | 29 May 2009 | Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the Application by the Nebraska Public Power District, for Renewal of the Operating License for Cooper Nuclear Station Unit 1 | Open House License Renewal Siren |
NLS2009039, Response to Request for Additional Information for License Renewal Application - Balance-of-Plant Scoping and Screening | 28 May 2009 | Response to Request for Additional Information for License Renewal Application - Balance-of-Plant Scoping and Screening | Safe Shutdown Aging Management |
NLS2009041, 2008 Annual Financial Report | 26 May 2009 | 2008 Annual Financial Report | Decommissioning Funding Plan |
IR 05000298/2009007 | 22 May 2009 | IR 0500298-09-007 on 03/23/09 - 04/10/09 for Cooper Nuclear Station | High Radiation Area Significance Determination Process Operability Determination Substantial potential for an overexposure Operability Assessment Overexposure |
ML091610511 | 21 May 2009 | Comments of Paul D. Parmenter on Behalf of State of Missouri Emergency Management Agency, Re Pr 50 and 52 Enhancements to Emergency Preparedness Regulations Requesting for an Extension of the Comment Period | |
ML091390012 | 19 May 2009 | E-mail Cooper Nuclear Station - Change in Regulatory Commitment | |
NLS2009036, Response to Request for Additional Information for License Renewal Application Environmental Report | 18 May 2009 | Response to Request for Additional Information for License Renewal Application Environmental Report | Safe Shutdown Grab sample Coatings Emergency Lighting Aging Management Annual Radioactive Effluent Release Report Earthquake Fire Protection Program |
ML091390813 | 15 May 2009 | Cooper - Transmittal of Annual Radiological Environmental Report January 1, 2008 Through December 31, 2008 | |
IR 05000298/2009403 | 12 May 2009 | IR 05000298-09-403, on 04/17/2009, for Cooper, Physical Security Inspection | Affidavit |
ML091830056 | 8 May 2009 | Nebraska Public Power District; Cooper Nuclear Station License Renewal 345kV Transmission Line Marking Proposal | |
ML091400110 | 8 May 2009 | License Renewal Consultation Email with Nebraska Game and Park Commission | |
ML091270258 | 7 May 2009 | Assessment Followup Letter - Cooper Nuclear Station 05/07/2009 | |
NLS2009035, Revision to Commitment Made in Nine-Month Response to NRC Generic Letter 2008-01 | 7 May 2009 | Revision to Commitment Made in Nine-Month Response to NRC Generic Letter 2008-01 | |
NLS2009033, Revision to the Safeguards Plan | 5 May 2009 | Revision to the Safeguards Plan | |
ML091190637 | 1 May 2009 | Request for Additional Information for Cooper Nuclear Station License Renewal | Safe Shutdown Coatings Aging Management Biofouling EVT-1 |
ML091190597 | 1 May 2009 | Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application (TAC No. MD9763 and MD9737) | |
ML090970414 | 30 April 2009 | Summary of Site Audit Related to the Review of the License Review Application for Cooper Nuclear Station, Unit 1 | |
NLS2009029, Annual Radioactive Effluent Release Report, ODAM Submittal and Summary of Changes to the Process Control Program | 30 April 2009 | Annual Radioactive Effluent Release Report, ODAM Submittal and Summary of Changes to the Process Control Program | Annual Radioactive Effluent Release Report Process Control Program |
IR 05000298/2009002 | 30 April 2009 | IR 05000298-09-002 on 01/01/09 - 03/24/09 for Cooper | Probabilistic Risk Assessment Temporary Modification Corrosion bonding Significance Determination Process Fire Protection Program Scaffolding Power change |
ML090920286 | 29 April 2009 | Request for Withholding Information from Public Disclosure | |
ML091400101 | 28 April 2009 | Request for Additional Information License Renewal Application, AMP Audit April 20-24, 2009 | Coatings Aging Management Biofouling EVT-1 |
ML091170031 | 28 April 2009 | Environmental Site Audit Regarding Cooper Nuclear Station Unit 1 License Renewal Application | |
ML091130617 | 24 April 2009 | Biweekly Notice, Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations | Safe Shutdown Fitness for Duty Shutdown Margin Post Accident Monitoring |
TAC:ME0848 | 22 April 2009 | ||
ML091120540 | 22 April 2009 | Acceptance Review for License Amendment Request | |
ML091070269 | 16 April 2009 | EPA Comment on the Cooper Nuclear Station License Renewal Application |