MONTHYEARML0826102242008-09-11011 September 2008 Request for Extension to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Dated January 11, 2008 Project stage: Request ML0827402512008-10-0303 October 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0828901612008-10-10010 October 2008 Nine-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0906502492009-03-0202 March 2009 Commitment Due Date Change for Two Commitments Referenced in Nine-Month Response to NRC Generic Letter 2008-01 Project stage: Request ML0906200582009-03-0303 March 2009 Change in Regulatory Commitment Project stage: Other ML0913400242009-05-0707 May 2009 Revision to Commitment Made in Nine-Month Response to NRC Generic Letter 2008-01 Project stage: Request ML0913900122009-05-19019 May 2009 E-mail Cooper Nuclear Station - Change in Regulatory Commitment Project stage: Other ML0929606032009-11-0303 November 2009 Request for Additional Information, Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI NLS2009094, Response to Request for Additional Information Regarding Nine-Month Response to NRC Generic Letter 2008-012009-12-17017 December 2009 Response to Request for Additional Information Regarding Nine-Month Response to NRC Generic Letter 2008-01 Project stage: Response to RAI ML0935800222009-12-17017 December 2009 Response to Request for Additional Information Regarding Nine-Month Response to NRC Generic Letter 2008-01 Project stage: Response to RAI ML1004701992010-02-0202 February 2010 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter (GL) 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Request ML1007603962010-03-17017 March 2010 Correction to Closeout of Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other ML1006105132010-03-17017 March 2010 Closeout of Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other 2009-03-02
[Table View] |
Text
From:
Fred Lyon Sent:
Tuesday, May 19, 2009 7:32 AM To:
'Van Der Kamp, David' Cc:
'McCutchen, Edward L.'
Subject:
Change in Regulatory Commitment (TAC No. MD7815)
In its letter dated October 10, 2008, the Nebraska Public Power District (NPPD) committed to conduct ultrasonic testing (UT) by February 27, 2009, of locations identified in the condition reports to provide additional confirmation that HPCI, CS, and RHR systems are operable and to assist in determining future vent locations. The commitment was associated with your response to NRC Generic Letter 2008-01.
By letter dated May 7, 2009, NPPD revised the commitment to conduct UT, where practical, of locations identified in the condition reports to provide additional confirmation that HPCI, CS, and RHR systems are operable and to assist in determining future vent locations. Where UT is not practical, an evaluation will be performed to assess whether potential gas accumulation could affect system operation. The new completion date of the commitment is July 31, 2009.
The NRC staff acknowledges the change in commitment and has no objections.
E-mail Properties Mail Envelope Properties ()
Subject:
Change in Regulatory Commitment (TAC No. MD7815)
Sent Date: 05/19/2009 7:23:37 AM Received Date: 05/19/2009 7:32:00 AM From: Fred Lyon Created By: Fred.Lyon@nrc.gov Recipients:
dwvande@nppd.com ('Van Der Kamp, David')
Tracking Status: None elmccut@nppd.com ('McCutchen, Edward L.')
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 8629 05/19/2009 Options Expiration Date:
Priority: olImportanceNormal
ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: