 Issue dateTitleTopic
ML20207B37321 May 1999Notice of Violation from Insp on 990322-26,0514 & 21. Violations Noted:On 980225,licensee Delivered Licensed Matl to Carrier for Transport Under General License Pursuant to 10CFR71.12 & Did Not Comply with Terms & Conditions
ML20198B41914 December 1998Notice of Violation from Insp on 981109-13.Violation Noted: Failure to Control Decommissioning Operations So That Operators Would Verify That Disassembled Equipment Was Free from Visible U Deposits Before Staging with Other Equipment
ML20236R27417 July 1998Notice of Violation from Insp on 980615-19.Violation Noted: Operational Safety Activities Not Implemented Iaw/Documented Standard Operating Procedures Appropriate to Circumstances in Listed ExamplesFuel cladding
ML20198S49616 January 1998Notice of Violation from Insp on 971215-19 & 971222-24. Violation Noted:On 971218,licensee Discovered That U Compounds Other than Oxide Pellets Were Being Stored in Temporary Storage Locations
ML20199B9347 November 1997Notice of Violation from Insp on 971006-10.Violation Noted: April 1977 Loss of Moisture Control Incident at Dry Conversion Pilot Plant Was Not Adequately Reviewed & Appropriate Corrective Actions Were Not Taken
ML20216J08512 September 1997Notice of Violation from Insp on 970731.Violation Noted: on 970413,RL Rumley,Lead Operator,Defeated Breathing Zone Air Sampler by Placing Rubber Glove Over Air Sampler at Respective Work Station
ML20141K57823 May 1997Notice of Violation from Insp on 970414-18,23,24 & 0501. Violation Noted:On 960603,licensee Shipped 405 NT-IX Shipping Packages Containing Fissile Matl W/O Installing Cushioning Matl
ML20134C72430 January 1997Notice of Violation from Insp on 970106-10.Violation Noted: Field Change Made Under Open ECN (No.5533L) & Not Documented or Included W/Ecn Package Prior to Startup Approval on 960806
ML20133D0233 January 1997Notice of Violation from Insp on 961202-05.Violation Noted: Licensee Failed to Update Posted Criticality Safety Limit Card for UF6 Cylinder Wash Operation to Reflect Change in CCS Limit
ML20134K79212 November 1996Notice of Violation from Insp on 961021-25.Violation Noted: as of 961022,licensee Had Not Calibrated Three Sets of direct-reading Dosimeters Maintained for Er Since 950918,for Two Sets & Since 950725,for the Third Set
ML20149H45810 November 1994Notice of Violation from Insp on 940926-30 & 1012-14. Violations Noted:Licensee Did Not Provide Training to Operators Relative to Modification or Evaluate Need to Revise Operating Procedures Prior to Restarting Sys
ML20056C8412 July 1993Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $12,500.Noncompliance Noted:Ecn Not Used for Mod of Discharge Tube of Feed Hoppers on All Four Blenders by Installing Interlocks for Direct Control of Discharges
ML20126B3314 December 1992Notice of Violation from Insp on 921015-17 & 29.Violation Noted:Licensee Personnel Did Not Immediately Rept to Safety, Security & Licensing Abnormal Conditions Where U Accumulated in Unsafe Geometry Vessel
ML20195F98118 November 1988Notice of Violation from Insp on 880906-09 & 23.Violations Noted:Inadequate Survey Performed as Evidenced by Set of Coveralls Having Measurable Contamination Being Discovered on Coat Rack
ML20212K80614 August 1986Notice of Violation from Insp on 860721-25
ML20154K2205 March 1986Notice of Violation from Insp on 860203-07 & 20
ML20135A32330 August 1985Notice of Violation from Insp on 850729
ML20126L39217 April 1981Notice of Violation from Insp on 810312-13