L-2023-103, Inservice Inspection Examination Report | 3 August 2023 | Inservice Inspection Examination Report | Moisture barrier |
L-2023-023, Revised Steam Generator Tube Inspection Report | 3 March 2023 | Revised Steam Generator Tube Inspection Report | Non-Destructive Examination |
SBK-L-22036, Steam Generator Tube Inspection Report | 25 April 2022 | Steam Generator Tube Inspection Report | Aging Management |
SBK-L-22003, Inservice Inspection Examination Report | 24 January 2022 | Inservice Inspection Examination Report | Boric Acid Hydrostatic Moisture barrier Pressure Boundary Leakage Through Wall Leak |
SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan | 4 January 2022 | Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan | Non-Destructive Examination Weld Overlay Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Aging Management Liquid penetrant Dissimilar Metal Weld Scaffolding Flow Induced Vibration |
SBK-L-20132, Fourth Interval Inservice Testing (IST) Program | 21 October 2020 | Fourth Interval Inservice Testing (IST) Program | Safe Shutdown Boric Acid Ultimate heat sink Mission time Grab sample Stroke time Safe Shutdown Earthquake Probabilistic Risk Assessment Operating Basis Earthquake Temporary Modification Surveillance Frequency Control Program Cold shutdown justification Power-Operated Valves Power Operated Valves Grace period |
SBK-L-20103, Inservice Inspection Examination Report | 27 July 2020 | Inservice Inspection Examination Report | Boric Acid Hydrostatic VT-2 Moisture barrier Pandemic |
SBK-L-19052, Steam Generator Tube Inspection Report | 19 April 2019 | Steam Generator Tube Inspection Report | Aging Management |
SBK-L-19001, Inservice Inspection Examination Report | 24 January 2019 | Inservice Inspection Examination Report | Boric Acid Pressure Boundary Leakage |
SBK-L-17166, Generator Tube Inspection Report | 17 October 2017 | Generator Tube Inspection Report | |
SBK-L-17117, Inservice Inspection Examination Report | 18 July 2017 | Inservice Inspection Examination Report | Moisture barrier |
SBK-L-16100, Inservice Testing Program for the Third 10-Year Interval | 21 July 2016 | Inservice Testing Program for the Third 10-Year Interval | Safe Shutdown Boric Acid Ultimate heat sink Grab sample Stroke time Safe Shutdown Earthquake Operating Basis Earthquake Temporary Modification Cold shutdown justification Power-Operated Valves Power Operated Valves |
SBK-L-16015, Inservice Inspection Examination Report | 10 February 2016 | Inservice Inspection Examination Report | Moisture barrier |
SBK-L-14119, Inservice Inspection Examination Report | 14 June 2014 | Inservice Inspection Examination Report | |
SBK-L-13019, Inservice Inspection Examination Report | 28 January 2013 | Inservice Inspection Examination Report | |
SBK-L-11197, Request for Alternative to Use ASME Code Case N-716 to Implement Risk-Informed Inservice Inspection Program | 7 November 2011 | Request for Alternative to Use ASME Code Case N-716 to Implement Risk-Informed Inservice Inspection Program | High winds Weld Overlay Internal Flooding Probabilistic Risk Assessment Nondestructive Examination VT-2 Seismically rugged Large early release frequency Dissimilar Metal Weld |
SBK-L-11191, Third Ten-Year Interval Inservice Inspection Relief Requests | 26 September 2011 | Third Ten-Year Interval Inservice Inspection Relief Requests | Boric Acid VT-2 |
SBK-L-11170, Inservice Inspection Examination Report | 11 August 2011 | Inservice Inspection Examination Report | |
SBK-L-11132, Submittal of Third Ten-Year Interval Inservice Inspection and Second Ten-Year Containment Inservice Inspection Program | 22 June 2011 | Submittal of Third Ten-Year Interval Inservice Inspection and Second Ten-Year Containment Inservice Inspection Program | Boric Acid Weld Overlay Hydrostatic Nondestructive Examination VT-2 Moisture barrier Dissimilar Metal Weld |
SBK-L-10027, Inservice Inspection Examination Report for Inspections Conducted Prior to and During the Thirteenth Refueling Outage That Concluded on November 12, 2009 | 9 February 2010 | Inservice Inspection Examination Report for Inspections Conducted Prior to and During the Thirteenth Refueling Outage That Concluded on November 12, 2009 | Through-Wall Leak Dissimilar Metal Weld |
ML092920156 | 7 October 2009 | Seabrook Station - 10 CFR 50.55a Request 2AR-07, Second Interval ISI Program Category B-P Exams - 10-Year Class 1 System Leakage Test | Boric Acid Hydrostatic VT-2 |
SBK-L-09122, Response to Request for Additional Information Regarding a Request for Relief from Inservice Inspection Requirements | 27 May 2009 | Response to Request for Additional Information Regarding a Request for Relief from Inservice Inspection Requirements | Boric Acid VT-2 |
SBK-L-09038, Supplement to Request for Relief from Inservice Inspection Requirements | 24 February 2009 | Supplement to Request for Relief from Inservice Inspection Requirements | VT-2 |
SBK-L-08135, Inservice Inspection Examination Report for Inspections Conducted Prior to and During the Twelfth Refueling Outage | 21 July 2008 | Inservice Inspection Examination Report for Inspections Conducted Prior to and During the Twelfth Refueling Outage | Hydrostatic |
SBK-L-07088, Steam Generator Inservice Inspection | 23 May 2007 | Steam Generator Inservice Inspection | |
SBK-L-07024, Inservice Inspection Examination Report, for Inspections Conducted Prior to and During the Eleventh Refueling Outage That Concluded on November 10, 2006 | 2 February 2007 | Inservice Inspection Examination Report, for Inspections Conducted Prior to and During the Eleventh Refueling Outage That Concluded on November 10, 2006 | Hydrostatic |
SBK-L-05145, Inservice Inspection Examination Report | 29 July 2005 | Inservice Inspection Examination Report | Hydrostatic |
SBK-L-04040, Steam Generator Inservice Inspection | 12 October 2004 | Steam Generator Inservice Inspection | |
ML040360108 | 18 February 2004 | Review of Steam Generator Tube Inservice Inspection Report for the 2002 Refueling Outage | |
ML040370626 | 29 January 2004 | Transmittal of Inservice Inspection Examination Report | Hydrostatic |
ML033180464 | 3 November 2003 | Steam Generator Tubes Plugged During Ninth Inservice Inspection | |
ML032731415 | 23 September 2003 | Revision to Inservice Test Program Relief Request PR-3 | |
ML031220028 | 24 April 2003 | Generator Inservice Inspection | |
ML022550050 | 29 August 2002 | Inservice Inspection Examination Report | Hydrostatic Nondestructive Examination VT-2 Liquid penetrant |