Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20094K95413 March 1992Forwards Supplemental Info Addressing Reasons for Delays Which Have Occurred in Schedule for Const of fossil-fueled Electric Generating Facility at Inola Station Site
ML20092M40020 February 1992Submits Addresses for DM Saunders & Jg Aronson,Per Request in Connection w/920226 Meeting.Addresses for R Butkin & M Graham W/Ok State Government Also Listed
ML20092K49414 February 1992Confirms 920205 Telcon Requesting Meeting Between NRC & Util on 920226 for Util to Present Matl Re Status of Inola Station Site to Demonstrate That Owner Have Satisfied Conditions Contained in 830307 OrderHydrostatic
ML20207L13810 November 1986FOIA Request for Info Between Connelly & Officials at NRC Technical Training Ctr in Chattanooga,Tn Re Requirements for Training of NRC Inspectors & for Info Re IE Investigation Into NRC Inspector Training Requirements
CY-85-367, FOIA Request for SECY-85-367A & SECY-85-37113 December 1985FOIA Request for SECY-85-367A & SECY-85-371
ML20134E32114 August 1985Advises of Corporate Approval of Change in Planned Dates for Commercial Operation for coal-fired Inola Station,To Be Built on Site of Canceled Black Fox Station.Units 1 & 2 Scheduled for Completion in Dec 1996 & 1998,respectively
ML20127A99614 June 1985Forwards Application for Waiver of Withdrawal Fees Under 10CFR170.12(b) & Brief in Support of Application,Per 850129 Meeting
ML20132B41512 June 1985Forwards Application for Waiver of Withdrawal Fees Under 10CFR170.12(b).NRC Delays in Issuance of CPs Deprived Util of Opportunity to Effect Withdrawal Before 1981 Operative Date of Regulation Charging Withdrawal Fees
ML20097C3239 August 1984Responds to Questions Re Beam Stops
ML20091R5728 June 1984Requests Precise Delineation of Applicable Regulations & Accounting of Prof Staff Hours Expended Re Review Costs Charged for Withdrawal of CP Application.Waiver of Any Interest Penalty Requested
ML20088A16410 April 1984Reiterates 840322 Request for Return of Reed Rept Under 10CFR2.790(b)(5).Reconsideration of Positions Taken in Oct 1980 Split Vote Re Release of GE Repts Requested. Certificate of Svc Encl
ML20087K00022 March 1984Requests Reconsideration of 801009 Split Vote to Release Reed Rept & Sub-Task Force Repts.Return of Repts Requested. Separate Views of Commissioner Hendrie & Certificate of Svc Encl
ML20080F8013 February 1984Requests Deletion of Gw Muench & Rl Range from Address Label
ML20069D86920 September 1982Forwards Black Fox Station Soil Stabilization & Erosion Control Program, Per ASLB 820618 Memorandum & Order.Plan Addresses Concerns Raised in NRC 820602 Submittal
ML20054K15323 June 1982Informs That Final Deficiency Repts for Listed Nonconformances Will Not Be Submitted Until Final Decision Is Made Re Const of Projects
ML20053D18228 May 1982Forwards JB West 820527 Affidavit on NRC Concerns Expressed During 820517 Site Visit Re Potential Offsite Environ Impact of Erosion & Siltation in Areas of Inclined Reactor Pressure Vessel Haul Road from Barge Slip Facilities
ML20041A56116 February 1982Announces Cancellation of Black Fox Station,Confirming 820216 Verbal Notification.Site Will Be Preserved for Const of Future Power Generation Projects
ML20040A96218 January 1982Forwards Ok Corporation Commission 820115 Decision in Cause 27068 Re Util Application for Rate Increase
ML20039E8566 January 1982Forwards DF Guyot Affidavit & Interim Containment Loads Rept,Mark III Containment, Revisions 3 & 4.Matls Pertinent to Contentions 3 & 16 Litigated in Dec 1978 & Feb 1979
ML20039B70511 December 1981Forwards Response to NRC 811203 Ltr Requesting Updated Info on Generic Issues A-10,A-31,A-36,A-42,A-43,A-44,A-45,A-46, A-47 & A-48 for SER Suppl.Svc List Encl
ML20039C6059 December 1981Suppls Response to 810912 & 0603 Ltrs Re Nonconformance Noted in QA Program Insp Rept 99900526/80-01.Revised Drawing List for Black Fox Facility Will Not Be Completed Until Apr 1982
ML20005C1005 November 1981Forwards Amend 18 to Psar.Amend Contains Matl Responsive to Two Hydrogen Control Requirements of near-term Cp/Mfg License Regulations Which Were Adopted by NRC on 810827. Related CorrespondenceSafe Shutdown
Hydrostatic
Fuel cladding
ML20140B2779 September 1981Forwards Amend 16 to Psar.Review Copies Forwarded w/810901 Ltr
ML20010H4028 September 1981Forwards Ok Corp Commission,Black Fox Station Economic Viability Study. Related Correspondence
ML20140B2851 September 1981Forwards Amend 16 to Psar.Remaining Copies Forthcoming.Amend Begins New Vol of Psar,Designated as Addendum I
ML20010D16418 August 1981Requests Svc List Be Revised Per Encl
ML20009D9318 July 1981Forwards Response to IE Bulletin 81-03, Flow Blockage of Cooling Water to Safety Sys Components by Corbicula Sp (Asiatic Clam) & Mytilus Sp (Mussel).Biofouling
ML20005A25425 May 1981Responds to NRC 810423 Ltr Re Nonconformance Noted in QA Program Insp Rept 99900039/81-01.Corrective Actions:Quality Procedures Established to Ensure Control of Insp Activities in Accordance W/Ansi RequirementsCoatings
ML20005A23018 May 1981Responds to NRC 810416 Ltr Requesting Info Re Status of Black Fox Unit 2 Reactor Vessel.No Activities Performed Since Last Visit
ML20003E2572 March 1981Forwards Ok Association of Electric Cooperatives 810122 Ltr Re Streamlining of Nuclear Plant Licensing & Development of Nuclear Power.Doe 810302 Response Encl
ML20126E69910 February 1981Opposes Facility
ML20002D32610 December 1980FOIA Request for Extracts of 27 safety-related Issues Identified by GE in Reed Rept
ML19345C27129 October 1980Requests Info Re Facilities W/Active CPs Pending,License Definitions & Requirements for Floating Nuclear Plants
ML19340B83321 October 1980Petitions Govt Representatives to Promote Use of Solar & wind-powered Energy & Phase Out Operation of Nuclear Plants as Quickly as Possible
ML19343A92421 October 1980Petition Urging Support for Wide Use of Solar & Wind Power, & Phasing Out of Nuclear Power Plants,Especially Black Fox, as Soon as Possible
ML19347B57010 October 1980Demands,On Behalf of Ge,That NRC Return GE Reed Rept Immediately Due to NRC Denial of Request That Rept Be Withheld from Disclosure Under 10CFR2.790.Rept Must Not Be Placed in PDR
ML19318B97520 June 1980Advises That List of Matls to Be Used in Const of Fire Stops & Characteristics Re Flammability & Fire Retardancy Will Be Provided 1 Yr Subsequent to Receipt of CP
ML19326D6375 May 1980Opposes Const of Facilities Until Adequate Emergency Response Plan Can Be Developed.Recommends Responsibility for Emergency Response Plan Be Placed W/Independent Consulting Svc,Not State of Ok
ML20126D3204 April 1980Forwards Corp Commission of State of Ok 800403 Order Denying Request for Approval to Sell Bonds.Psc of Ok Presently Reviewing Order W/View of Filing Appeal W/Ok Supreme Court
ML19309G5072 April 1980Notifies That Representative of Intervenor State of Ok Will Attend NRC 800403 Meeting W/Cp Owners Group.Deplores Fact That Meeting Is First Interaction Between NRC & Applicants Re Development of Generic Policy
ML20126D40326 March 1980Forwards D Plant Expressing Concern Re Possible Meltdown at Facilities.Requests Response
ML19309H47826 March 1980Requests Response to Encl D&D Plant Request That Environ & Site Suitability Hearings in Licensing Proceeding Be Reopened to Address Class 9 Accidents
ML18082A16424 March 1980Forwards Licensee Supplemental Brief Re Motion for Directed Certification & for Stay.Pendency of Class 9 Issue Before Commission Noted in Licensee Motion for Directed Certification & for Stay.Discussed on Pages 7-10
ML19344D69218 March 1980Submits Addl Info in Support of 800206 Request for Extension to Review ALAB-573 Class 9 Accident Issue.Lack of NRC Opposition to Ok Request & Recent Proliferation of Info Support Extension
ML19309B51415 March 1980Suggests Hearings on Const of Reactor Did Not Address Meltdown Issues.Tulsa Should Not Be Made Site for Potential Nuclear Mistake.Utils Should Build Plants Away from Populated Areas.Requests Reopening of Hearings
ML19309B52415 March 1980Requests That NRC Hold Meetings in Tulsa,Ok Re Emergency Evacuation Zone Around Nuclear Plants.Plans Should Be More Thorough to Protect People If Meltdown Should Occur
ML20126C61615 March 1980Expresses Concern Re NRC Refusal to Address Meltdown Issue at Hearings.Class 9 Accident Is Distinct Possibility & Should Be Thoroughly Examined.Environ & Site Suitablity Hearings Should Be Reopened
ML20126C55815 March 1980Suggests Local self-reliant,self-sufficient Communities Are Solution to Present Problems.Opposes All Forms of Nuclear Power.Min Amount of Energy from Coal & Gas Should Be Needed for Mfg Useful Tools,Bicycles & Efficient Tractors
ML19312D48829 February 1980Requests Reopening of Environ & Site Suitability Hearings for Facilities to Explore Issue of Meltdown
ML20126C03029 February 1980Urges Meetings in Tulsa,Ok Re Emergency Evacuation Area Around Facility.Current Plans Are Inadequate