Quarter | Site | Title | Topic | |
---|---|---|---|---|
05000424/FIN-2017003-01 | 2017Q3 | Vogtle | Failure to Implement and Establish Appropriate Work Instructions Affecting Safety-Related Chiller | |
05000260/FIN-2017002-04 | 2017Q2 | Browns Ferry | Failure to Implement Corrective Actions to Prevent the Recurrence of a Reactor Scram Due to IRM spiking | |
05000324/FIN-2016003-03 | 2016Q3 | Brunswick | Inadequate Procedure for the 2B RHRSW Subsystem Operability Test | |
05000321/FIN-2016010-02 | 2016Q2 | Hatch | Failure to Identify N2E Nozzle Weld Through-Wall Flaw | Condition Adverse to Quality Significance Determination Process |
05000389/FIN-2016001-02 | 2016Q1 | Saint Lucie | Failure to Provide Detailed Work Instructions Resulted in a Unit Transient | Significance Determination Process |
05000390/FIN-2016001-06 | 2016Q1 | Watts Bar | Failure to Track Applicable Technical Specification Action Statement for Charging Pump Inoperability | |
05000324/FIN-2015004-01 | 2015Q4 | Brunswick | Inadequate Procedure for the 2C RHRSW Booster Pump Motor Bearings | |
05000348/FIN-2015404-01 | 2015Q4 | Farley | Security | |
05000280/FIN-2015002-02 | 2015Q2 | Surry | A MDAFW Pump Motor Outboard Bearing Damaged | Significance Determination Process |
05000364/FIN-2015002-02 | 2015Q2 | Farley | Failure to Evaluate Impacts of Degraded Condition on the Unit 1 TDAFW Pump | Functionality Assessment |
05000259/FIN-2015001-01 | 2015Q1 | Browns Ferry | HPCI Venting Procedures | Maintenance Rule Program |
05000400/FIN-2014005-01 | 2014Q4 | Harris | Failure to Adequately Implement the Equipment Clearance Procedure | Unanalyzed Condition Internal Flooding Significance Determination Process |
05000425/FIN-2014005-03 | 2014Q4 | Vogtle | Failure to Follow Procedures Renders Safety Related Battery Charger Inoperable | Significance Determination Process |
05000424/FIN-2014004-02 | 2014Q3 | Vogtle | Inoperability of Unit 1 Emergency Containment Coolers due to Incorrect Tagout | Significance Determination Process |
05000395/FIN-2014003-02 | 2014Q2 | Summer | Failure to Develop Adequate Post Modification Testing for the Alternate Seal Injection System | |
05000280/FIN-2013002-01 | 2013Q1 | Surry | Failure to Follow Procedure Results in Inoperability of One Train of Charging Pump Service Water | Significance Determination Process |
05000250/FIN-2012004-01 | 2012Q3 | Turkey Point | Operation at power with Unit 3 feedwater flow transmitter connected incorrectly | Significance Determination Process |
05000424/FIN-2011005-01 | 2011Q4 | Vogtle | Human Performance Error Results in Inoperability of TDAFW Pump | |
05000338/FIN-2011005-01 | 2011Q4 | North Anna | Failure to Follow Procedure to Ensure Proper Calibration of RHR Valve Control Circuit | Significance Determination Process |
05000250/FIN-2011002-01 | 2011Q1 | Turkey Point | Failure to Monitor a Reactivity Change Results in Power Operation Above 100 Percent | |
05000335/FIN-2011002-02 | 2011Q1 | Saint Lucie | Failure to Follow Procedures and Guidelines to ensure RAB Doors are Completely Dogged Closed | Significance Determination Process |
05000400/FIN-2010005-02 | 2010Q4 | Harris | Failure to Follow Procedure Results in Emergency Safeguards Sequencer Actuation and Safety Injection Signal (SIS) while the Plant was in Mode 6 | Significance Determination Process |
05000280/FIN-2010005-02 | 2010Q4 | Surry | Failure to Follow Procedure Results in Inadvertent Actuation of Safety Injection | Significance Determination Process |
05000400/FIN-2010005-05 | 2010Q4 | Harris | Failure to Follow Procedure to Properly Align the MOC Switch Contacts Associated With Breaker 1A-6 Results in Actuation of the B MDAFW Pump | Significance Determination Process |
05000400/FIN-2010003-01 | 2010Q2 | Harris | Failure to Follow Procedure to Install the Load Block 5 Auxiliary Relay | Significance Determination Process |
05000338/FIN-2010003-01 | 2010Q2 | North Anna | Failure to Demonstrate Effective Control of a Pressurizer PORV 1-RC-PCV-1455C Performance in Accordance with the Maintenance Rule | |
05000390/FIN-2010003-02 | 2010Q2 | Watts Bar | Lack of Procedure Implementation Results in 1B EDG being started with 15 Cylinder Plugs Open | Significance Determination Process |
05000338/FIN-2010002-04 | 2010Q1 | North Anna | Failure to Follow Procedures Results in Loss of Offsite Power to 1H and 2J emergency Buses | Offsite Circuit |
05000338/FIN-2010002-01 | 2010Q1 | North Anna | Inadequate Procedure Implementation Results in Inoperability of a Fire Suppression System | |
05000269/FIN-2009005-04 | 2009Q4 | Oconee | Failure to Comply with Radiological Postings and the Requirements for Entering a Posted High Radiation Area | High Radiation Area Significance Determination Process Substantial potential for overexposure Overexposure |
05000424/FIN-2009004-02 | 2009Q3 | Vogtle | Human Performance Error Renders 2B EDG Inoperable | |
05000424/FIN-2009004-03 | 2009Q3 | Vogtle | Human Performance Error Renders NSCW Pump #5 Inoperable | |
05000324/FIN-2009004-02 | 2009Q3 | Brunswick | Failure to Follow Plant Procedure Caused Loss of E2 Bus | Significance Determination Process |
05000269/FIN-2009004-02 | 2009Q3 | Oconee | Unit 3 Trip Due to Generator Phase Differential Lockout | |
05000261/FIN-2009003-01 | 2009Q2 | Robinson | Failure to properly restore service water to the evaporative air coolers resulting in emergency diesel generator inoperability. | |
05000250/FIN-2009003-01 | 2009Q2 | Turkey Point | Failure to Implement Procedures for Conducting a Valve Alignment Causes Spill of Reactor Coolant And Contamination Of a Plant Employee | |
05000250/FIN-2009003-02 | 2009Q2 | Turkey Point | Failure to Implement TS Requirements Resulting From Loss of Configuration Control of the 3C Main Steam Isolation Valve | Stroke time |
05000259/FIN-2009003-03 | 2009Q2 | Browns Ferry | Failure to Comply with the Requirements of an RWP by Entering a Posted High Radiation Area | High Radiation Area Significance Determination Process Substantial potential for overexposure |
05000327/FIN-2009002-01 | 2009Q1 | Sequoyah | Pressurizer Pressure Transient due to Inadequate Maintenance Procedure | Significance Determination Process |
05000324/FIN-2009002-04 | 2009Q1 | Brunswick | Unauthorized Maintenance Results in Loss of Shutdown Cooling (Section 1R20) | Significance Determination Process |
05000321/FIN-2009002-01 | 2009Q1 | Hatch | Improper Core Drill Location Results in Secondary Containment Inoperability | |
05000302/FIN-2009002-03 | 2009Q1 | Crystal River | Inadequate Peer and Peer Checking Resulted in Connecting Improper Test Equipment and a Manual Plant Trip | |
05000390/FIN-2008005-03 | 2008Q4 | Watts Bar | Performing Non-Authorized Activities on Exciter Field Breaker Results in Reactor Trip | Significance Determination Process |
05000280/FIN-2008005-02 | 2008Q4 | Surry | Inadequate Review of Vendor Information Led to Unit 1 Manual Reactor Trip | |
05000335/FIN-2008005-01 | 2008Q4 | Saint Lucie | Unit 1 Loss of Shutdown Cooling | Significance Determination Process |
05000424/FIN-2008005-01 | 2008Q4 | Vogtle | Unauthorized Entries Into High Radiation Areas | High Radiation Area Significance Determination Process Substantial potential for overexposure |
05000324/FIN-2008005-03 | 2008Q4 | Brunswick | Inadvertent Rack Out of the 2A Core Spray Pump Circuit Breaker | |
05000269/FIN-2008002-01 | 2008Q1 | Oconee | Inadequate Installation of SSF DG Field Flash | |
05000321/FIN-2008002-02 | 2008Q1 | Hatch | Failure to Follow Equipment Clearance Procedures Results in Control Room Ventilation Inoperability |