05000259/FIN-2015001-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | HPCI Venting Procedures |
Description | An NRC identified non-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, was identifed for the licensee's failure to maintain adequate procedure acceptance criteria and cautions to verify operability of the HPCI system in accordance with Technical Specification Surveillance procedure SR 3.5.1.1. As immediate corrective action the licensee performed a prompt operability determination to verify the system remained operable, and plans to make changes to the TS surveillance procedure using the corrective action program. This violation was entered into the licensees corrective action program as PER 989728. The performance deficiency was more than minor because, if left uncorrected, it had the potential to lead to a more significant safety concern. Specifically the operability and availability of the HPCI system could be challenged by having procedural guidance which allows acceptable test results when the limiting void conditions may not be met. The finding was associated with the Mitigating Systems cornerstone. Using NRC Inspection Manual 0609, Appendix A, the finding screened as green because it did not represent an actual loss of function of at least a single train for greater than its technical specification allowed outage time, and did not represent an actual loss of function of one or more non-technical specification trains of equipment designated as high safety-significant in accordance with the licensees maintenance rule program for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. This finding has a crosscutting aspect in the area of Human Performance because the licensee did not challenge the unknown when, both, establishing the venting procedure acceptance criteria and when observing significant bubbles during the venting procedure. [H.11]. |
Site: | Browns Ferry |
---|---|
Report | IR 05000259/2015001 Section 1R04 |
Date counted | Mar 31, 2015 (2015Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.04 |
Inspectors (proximate) | A Ruh D Dumbacher D Retterer L Pressley M King T Stephen |
Violation of: | 10 CFR 50 Appendix B Criterion V Technical Specification Technical Specification - Procedures |
CCA | H.11, Challenge the Unknown |
INPO aspect | QA.2 |
' | |
Finding - Browns Ferry - IR 05000259/2015001 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Browns Ferry) @ 2015Q1
Self-Identified List (Browns Ferry)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||