ML18128A067 | 8 June 2018 | Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 | Incorporated by reference Through-Wall Leak Through-Wall Leakage |
CNRO-2017-00022, Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 1 | 17 November 2017 | Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 1 | Nondestructive Examination Finite Element Analysis Through-Wall Leak |
ML17093A894 | 12 May 2017 | Pilgrim Nuclear Power Station - Relief Requests PNPS-ISI-001 and PNPS-ISI-002, Relief from ASME Code Volumetric Examination Requirements for the Fourth 10-Year Inservice Inspection Interval (CAC Nos. MF8092 and MF8093) | |
ML16257A573 | 15 September 2016 | Issuance of Relief Request No. PRR-52-Relief from ASME Code, Section XI Requirements for Pressure Testing of Class 1 Pressure Retaining Components as a Result of Repair/Replacement Activity and Use of Code Case N-795 | Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Through Wall Leak |
ML16194A326 | 4 August 2016 | Issuance of Relief Request No. PRR-53 - Relief from ASME Code, Section XI Requirements for Ultrasonic Inspection Qualifications of Weld Overlays | Weld Overlay Incorporated by reference |
ML16096A269 | 6 June 2016 | Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 | Functionality Assessment Liquid penetrant |
ML16042A291 | 15 March 2016 | Issuance of Proposed Alternative Relief Request PRR-51, Relief from the Requirements of the ASME Code | Incorporated by reference Pressure and Temperature Limits Report |
ML16057A177 | 16 February 2016 | Supplement to Request for Approval of Pilgrim Relief Request (PRR)-52, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) Pressure Testing of Mechanical Joints as a Result of Performance of a Repair/Replacement Activity and Use of | |
ML15338A309 | 5 January 2016 | Relief Request PRR-50, Relief from the Requirement of the ASME Code, Implementation of Code Case N-702 | Nondestructive Examination Incorporated by reference |
CNRO-2015-00017, Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, D | 5 June 2015 | Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, Division | Liquid penetrant |
ML15103A069 | 21 April 2015 | Relief Request PRR-24 Regarding Nozzle-to-Vessel Welds and Nozzle Inner Radii Examination | Incorporated by reference |
ML14198A157 | 1 August 2014 | Relief Requests PR-03 and PR-05 Regarding the Inservice Testing Program (Tac MF0370) | |
ML12174A147 | 10 July 2012 | Safety Evaluation for Relief Request PRR-21, Rev 4, to Install a Weld Overlay on RPV-n14-1 Standby Liquid Control Safe-End Nozzle Weld at Pilgrim | Non-Destructive Examination Weld Overlay Hydrostatic Incorporated by reference Finite Element Analysis Stress corrosion cracking Liquid penetrant Dissimilar Metal Weld |
JAFP-11-0112, Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP | 3 October 2011 | Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP | |
ML092370549 | 11 September 2009 | Relief Request (PRR)19, Install a Weld Overlay on Jet Pump Instrumentation Nozzle Weld RPV-N9A-1- Pilgrim Nuclear Power Station | Non-Destructive Examination Weld Overlay Hydrostatic Incorporated by reference Finite Element Analysis Liquid penetrant Dissimilar Metal Weld |
ML091130456 | 30 April 2009 | Relief Request ISI-2008-1, Use of Later ASME Section XI Code Edition and Addenda for Repair and Replacement, Pressure Testing, and Destructive Testing Activities-Pilgrim Nuclear Power Station | Nondestructive Examination Incorporated by reference |
CNRO-2009-00003, Letter from Entergy Response to Request for Additional Information Regarding Request ISI-2008-1 Use of Later ASME Section Xl Code Edition and Addenda for Repair and Replacement, Pressure Testing, and Non Destructive Examination Activ | 17 March 2009 | Letter from Entergy Response to Request for Additional Information Regarding Request ISI-2008-1 Use of Later ASME Section Xl Code Edition and Addenda for Repair and Replacement, Pressure Testing, and Non Destructive Examination Activities | Nondestructive Examination |
ML081300408 | 27 May 2008 | Relief Request No. RV-07, Alternate to the ASME OM Code 5-Year Test Interval for Main Steam Safety Relief Valves - Pilgrim Nuclear Power Station | Incorporated by reference Foreign Material Exclusion |
ML080580199 | 14 February 2008 | Request for Approval of Relief Request No. PRR-16, Implementation of BWRVIP Guidelines in Lieu of ASME Section XI Code Requirements on Reactor Vessel Internals and Components Inspection | VT-2 EVT-1 |
ML072420161 | 27 September 2007 | Relief for the Reactor Core Shroud Stabilizer Assemblies | Finite Element Analysis Fuel cladding EVT-1 Flow Induced Vibration |
ML061870163 | 28 June 2006 | Request for Approval of ASME Code, Section XI, Third Ten-Year Relief Request, PRR-42, Examinations of Component Welds with Less than Essentially 100% Examination Coverage | VT-2 Liquid penetrant Dissimilar Metal Weld |
ML060660132 | 5 April 2006 | Relief Request No. PIL-05-R-002, | VT-2 Incorporated by reference |
ML060240055 | 22 March 2006 | Relief Request No. PRR-9, | Weld Overlay Incorporated by reference Dissimilar Metal Weld |
ML060120127 | 17 February 2006 | Relief Request No. PPR-05 | Nondestructive Examination Incorporated by reference Dissimilar Metal Weld |
ML051990276 | 29 August 2005 | Entergy Relief Request PR-03 High-Pressure Coolant Injection Pump | Incorporated by reference |
ML051920157 | 29 June 2005 | Fourth Ten-Year Inservice Inspection Program Plan and the Associated Relief Requests for NRC Approval | Safe Shutdown High Radiation Area Non-Destructive Examination Weld Overlay Hydrostatic Probabilistic Risk Assessment Coatings Nondestructive Examination VT-2 Incorporated by reference Flow Accelerated Corrosion Stress corrosion cracking Moisture barrier Cold shutdown justification Earthquake Liquid penetrant Pressure boundary leak Dissimilar Metal Weld Power Uprate Thermal fatigue |
ML042920358 | 25 February 2005 | Request - Alternative Repair Plan for Generic Letter 88-01, Reactor Pressure Vessel Nozzle-To Cap Weld in the Control Rod Drive Return Line | Weld Overlay Hydrostatic Nondestructive Examination Incorporated by reference Stress corrosion cracking Liquid penetrant |
ML042310008 | 6 January 2005 | Relief Request No. PRR-29, Relief from System Hydrostatic Test Requirements for Small Bore ASME Code Class 1 Reactor Coolant Pressure Boundary Vent, Drain and Branch Lines and Connections | High Radiation Area Hydrostatic Incorporated by reference |
ML042740664 | 14 October 2004 | Relief Request Nos. R-33, R-71, R 3-40(A) and R-41, James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Unit Nos. 2 and No. 3 and Pilgrim Nuclear Power Station | Incorporated by reference |
ML042950551 | 12 October 2004 | Response to NRC Request for Additional Information and Revised Relief Request, PRR-39, Rev. 1 | Weld Overlay Hydrostatic Nondestructive Examination VT-2 Stress corrosion cracking Liquid penetrant Dissimilar Metal Weld DM weld |
ML041740184 | 6 July 2004 | Relief Request, Nos. RR-34 and PRR for the Third 10-Year Inservice Inspection (ISI) Interval, MC1999 and MC2006 | Incorporated by reference |
ML041070088 | 6 July 2004 | Relief Request to Use American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) Case N-600 | |
ML040780705 | 30 April 2004 | Relief Request, Fourth 10-Year Inservice Testing (IST) Program and Request for Approval of IST Relief Requests | Ultimate heat sink Incorporated by reference |
ML040820516 | 22 March 2004 | Relief Request Nos. RR-68, RR3-37, and PRR-34 (TAC MC1559, MC1560, & MC1561) | Boric Acid Non-Destructive Examination Incorporated by reference |
ML040260013 | 26 February 2004 | Pilgrim Relief Request Review, Relief Request No. 38, Relief from ASME Code, Section XI, Appendix Viii, Supplement 11, Qualification Requirements for Full Structural Overlaid Wrought Austenitic Piping Welds. | Weld Overlay Nondestructive Examination Incorporated by reference Stress corrosion cracking |
JPN-03-020, Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-600 | 11 August 2003 | Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-600 | |
ML031270149 | 8 May 2003 | Relief Request, Relief from ASME Code, Section XI, Appendix Viii, Supplement 10, Performance Demonstration for Ultrasonic Examination Systems | Non-Destructive Examination Incorporated by reference Dissimilar Metal Weld |
ML030640204 | 11 April 2003 | Relief Request, Examinations of Reactor Pressure Vessel Circumferential Shell Welds | Incorporated by reference |
ML022400239 | 17 September 2002 | Relief, Code Relief Request from Section XI, the Pump and Valve Inservice Testing Program Regarding Inclusion of Additional Excess Flow Check Valves | |
ML021680062 | 5 June 2002 | Code Relief, Pilgrim Relief Request (PRR)-27 Relief from 1989 ASME Code Section XI Requirements for Certification of VT-2 Visual Examination Personnel | Nondestructive Examination VT-2 |