MONTHYEARRS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-110, Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request.2022-09-20020 September 2022 Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request. RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-086, R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam.2022-08-10010 August 2022 R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam. RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-017, License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions for Calvert Cliffs2022-04-20020 April 2022 License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions for Calvert Cliffs RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-041, Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes2022-03-22022 March 2022 Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P RS-22-019, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-02-16016 February 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-015, Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC2022-02-0101 February 2022 Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC RS-22-008, Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report to Add References to NRC-Approved Topical Report with Admin2022-01-24024 January 2022 Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report to Add References to NRC-Approved Topical Report with Admin RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms RS-21-091, Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes2021-09-13013 September 2021 Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes RS-21-093, R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2021-09-0101 September 2021 R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-21-079, Notice of Disbursement of Decommissioning Trust Funds2021-07-20020 July 2021 Notice of Disbursement of Decommissioning Trust Funds RS-21-070, Proposed Alternative to Utilize Code Case N-8932021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 RS-21-056, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld2021-05-12012 May 2021 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld RS-21-054, Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations2021-04-29029 April 2021 Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations RS-21-047, Correction of Unit 1 Disbursement Total2021-04-0505 April 2021 Correction of Unit 1 Disbursement Total RS-21-044, Disbursement of Decommissioning Trust Funds2021-03-30030 March 2021 Disbursement of Decommissioning Trust Funds RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments RS-21-028, Fitness for Duty Performance Data Reports - Annual 20202021-02-26026 February 2021 Fitness for Duty Performance Data Reports - Annual 2020 RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-20-017, Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-8852021-02-0101 February 2021 Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-885 RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping RS-21-002, Company - Update to Correspondence Addressees and Service Lists2021-01-0404 January 2021 Company - Update to Correspondence Addressees and Service Lists RS-20-142, Proposed Alternative to Utilize Code Case N-8932020-11-16016 November 2020 Proposed Alternative to Utilize Code Case N-893 RS-20-140, Proposed Changes to Decommissioning Trust Agreements2020-10-30030 October 2020 Proposed Changes to Decommissioning Trust Agreements RS-20-111, Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-09-0202 September 2020 Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-20-110, Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-09-0202 September 2020 Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-20-062, Proposed Alternative to Utilize Code Case N-8852020-04-28028 April 2020 Proposed Alternative to Utilize Code Case N-885 2023-06-27
[Table view] Category:Status Report
MONTHYEARRS-17-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2017-03-30030 March 2017 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-16-046, Annual Property Insurance Status Report2017-03-29029 March 2017 Annual Property Insurance Status Report RS-16-094, Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isl2016-04-25025 April 2016 Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isla RS-16-028, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design- Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design- Basis External Events (Order Number EA-12-049) RS-15-054, February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-20020 February 2015 February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-15-055, February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)2015-02-20020 February 2015 February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) L-14-030, August 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-26026 August 2014 August 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML14069A3182014-02-27027 February 2014 February 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML14069A1802014-02-24024 February 2014 February 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13098A0842013-03-27027 March 2013 Decommissioning Funding Status Report ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML12024A3762011-12-28028 December 2011 State-of-the-Art Reactor Consequence Analyses, Current Status and Next Steps ML0908504002009-03-26026 March 2009 Units, 1 & 2, Nine Mile Point, Units, 1 & 2, and R.E. Ginna, 2009 Decommissioning Funding Status Report: Year End 2008 ML0723203822007-08-23023 August 2007 Status of the Acceptance Review Part One of the Combined License Application for Calvert Cliffs Nuclear Power Plant, Unit 3 ML0714100782007-05-17017 May 2007 Post-Accident Monitoring Report ML0710802622007-03-30030 March 2007 Biennial Report: Status of Decommissioning Funding Per 10 CFR 50.75(f)(1) ML0509400242005-03-29029 March 2005 Plants 2005 Report on Status of Decommissioning Funding ML0224007982002-02-0101 February 2002 E-mail from Beth Wetzel Bulletin 2001-01 Status Report ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2017-03-30
[Table view] |
Text
"Maria Korsnick A
NSenior Exeton Generation,, Vice President, Northeast Operations Chief Nuclear Officer, CENG 100 Constellation Way Suite 500P Constellation Energy Nuclear Group, LLC Baltimore, MD 21202 410-470-5133 Office 443-213-6739 Fax www.exeloncorp.com mada.korsnick@exeloncorp.com NRC Order No. EA-12-051 RS-15-055 February 20, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 Docket Nos. 50-317 and 50-318
Subject:
February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
Reference:
- 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12054A679)
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-051 (Reference 1) to Constellation Energy Nuclear Group, LLC (CENG) for Calvert Cliffs Nuclear Power Plant, LLC (CCNPP). Reference (1) requires submission of a status report at six-month intervals following submittal of the Overall Integrated Plan. The attachment to this letter provides the February 2015 six month status report for CCNPP. This report updates the milestone accomplishments since the submittal of the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no new regulatory commitments.
If you have any questions regarding this submittal, please contact Mr. Michael J. Fick, Acting Regulatory Assurance Manager, at (410) 495-6714.
U.S. Nuclear Regulatory Commission February 20, 2015 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 0 th day of February, 2015.
Respectfully, Mary G. Korsnick MGK/GGM
Attachment:
Six-Month Status Report (February 2015) for Reliable Spent Fuel Pool Instrumentation cc: Regional Administrator, Region I, USNRC NRC Project Manager, NRR - Calvert Cliffs Nuclear Power Plant NRC Senior Resident Inspector - Calvert Cliffs Nuclear Power Plant S. Gray, MD-DNR
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015)
FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION CALVERT CLIFFS NUCLEAR POWER PLANT, LLC February 20, 2015
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015) FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION
- 1. Introduction The Calvert Cliffs Nuclear Power Plant, LLC (CCNPP) Overall Integrated Plan (OIP) was submitted to the Nuclear Regulatory Commission (NRC) in February 2013 (Reference 1),
documenting the requirements to install reliable spent fuel pool level instrumentation (SFP LI), in response to NRC Order Number EA-1 2-051 (Reference 2). Subsequently, a supplement to the CCNPP SFP LI OIP was submitted to the NRC in March 2013 (Reference 3). By letter dated June 19, 2013 (Reference 4), the NRC requested that CENG respond to a request for additional information (RAI) regarding the CCNPP OIP for Reliable Spent Fuel Pool Instrumentation. By letter dated July 3, 2013 (Reference 5), CENG responded to the June 19, 2013 RAI. By letter dated August 27, 2013, CENG provided the first Six-Month Status Report (Reference 8). By letter dated November 15, 2013 (Reference 9), the NRC issued the CCNPP, Unit Nos. 1 and 2 Interim Staff Evaluation (ISE) and RAI regarding the Overall Integrated Plan for Implementation of Order EA-12-051. By letter dated February 24, 2014, CENG provided the second Six-Month Status Report (Reference 11). By letter dated August 26, 2014, Exelon provided the third Six-Month Status Report (Reference 12).
In compliance with NRC Order EA-12-051, CENG selected to install the VEGAPULS 62ER Through Air Radar system at CCNPP. The RSFPI contractor, AREVA, completed the engineering design, fabrication of the waveguide, fabrication of the power control panels and procurement of the VEGA instruments that are integrated into the wide-range Spent Fuel Pool Level Instrumentation System. The AREVA design was then integrated into the CCNPP Engineering Change Package (ECP). The engineering contractor, Sargent & Lundy prepared the design package and Exelon's Design Engineering Department at CCNPP performed the owner reviews and approval of the ECP.
Once AREVA fabricated all the components, they were all assembled and a factory performance test (FAT) was performed to demonstrate the system would perform as designed.
The FAT performed the initial calibration, checked performance over the entire range of the instrument, and verified continued operation under extended loss of AC power (ELAP) conditions. The FAT was completed successfully, AREVA issued the test report, and the system was installed at CCNPP.
Following completion of implementation activities, each of the SFP Level Instrument systems was subjected to a site acceptance test (SAT) to perform a final calibration check and to demonstrate that the instrument systems perform as designed. The SAT demonstrated that with the installation of an antenna horn cover there was no loss of system performance. SAT results were reviewed to determine acceptability of the installed system in preparation for turnover to Plant Operations. The wide-range RSFPI has been turned over to CCNPP Plant Operations.
During implementation of the ECP, plant procedures were changed, and operations and maintenance personnel were trained on the new instrumentation system as well as the new procedures.
This attachment provides an update of milestone accomplishments since submittal of the last six-month status report in August 2014, including any changes to the compliance method, schedule, or need for relief/relaxation and associated basis (if applicable). This will be the last RSFPI six-month status report, Exelon having completed the successful installation and 1 of 5
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015) FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION turnover of the system to CCNPP Plant Operations. Exelon will submit a letter to the NRC addressing compliance with NRC Order EA-12-051.
- 2. Milestone Accomplishments The following milestones have been completed since the development of the OIP (References 1 and 3), and are current as of February 15,2015.
- Submitted Overall Integrated Plan 1Q2013
- Issued Purchase Order for Instrumentation 2Q2013
- Commenced Engineering and Design 202013
" Selected Instrumentation and Technology 2Q2013
- Submitted first six-month update 3Q2013
- Submitted second six-month update 1Q2014
" Completed Engineering and Design 1Q2014
- Commenced Installation of SFP Instruments 2Q2014
- Provided responses to ISE RAIs 2Q2014
- Submitted third six-month update 3Q2014
- Completed installation and system turnover to Operations 4Q2014
- 3. Milestone Schedule Status Table 1 provides an update to the milestone schedule to support the OIP. It provides the activity status of each item and the completion date.
2 of 5
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015) FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION Table 1 Status of CCNPP Reliable Spent Fuel Pool Instrumentation QIP Milestones Target Revised Completion Status Target Milestone Date Completion Date Commence Engineering and Design 2Q2013 Complete Complete Engineering and Design 3Q2013 Complete 1Q2014 Receipt of SFP Instruments 1 Q2014 Complete Installation CommenceIntrmets2Q2014 of SFP Complete Instruments Complete Installation of SFP 4Q2014 Complete Instruments Close out Project/Plant Turnover 3Q2014 Complete 4Q2014 Respond to NRC ISE RAI 3Q2014 Complete Issue EA-12-051 Compliance Letter 2Q2015 Not Started
- 4. Changes to Compliance Method Changes were made to the information provided in the OIP that do not change the compliance method with Nuclear Energy Institute (NEI) 12-02 (Reference 7). These changes continue to meet the guidance in JLD-ISG-2012-03 (Reference 6) and NEI 12-02 (Reference 7).
- 5. Need for Relief/Relaxation and Basis for the Relief/Relaxation CCNPP expects to comply with the order implementation date and no relief/relaxation is required at this time.
- 6. Open Items from Overall Integrated Plan and Draft Safety Evaluation Since the July 2013 RAI (Response 5) and August 2013 Six-Month Status Report (Reference 8), the NRC provided CENG with its ISE and RAI regarding the CCNPP OIP for Reliable Spent Fuel Pool Instrumentation (Reference 9). Open item and regulatory commitments that were identified in References 5 and 8 have been superseded by a commitment made in the February 2014 six-month Status report in response to the ISE RAIs issued in Reference 9. Following a series of meetings between the industry, the NEI and the NRC, it was agreed that responses to the ISE RAI could be placed in a plant-specific, electronic file location, the CCNPP ePortal, which the NRC could access. In accordance with this agreement, responses to the CCNPP ISE RAI were uploaded to the ePortal and the NRC was advised via e-mail of this action. Appendix 1 of the August 2014 six-month Status report (Reference 12) also provided the ISE RAI and the CCNPP responses.
The ISE open items are considered closed. Open items documented in the OIP that were superseded by the ISE RAI have been closed. There are no Draft Safety Evaluation open items.
- 7. Potential Draft Safety Evaluation Impacts Not applicable. There is no draft safety evaluation.
3 of 5
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015) FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION
- 8. References The following references support the updates to the OIP described in this attachment.
- 1. Letter from M. G. Korsnick (CENG) to Document Control Desk (NRC), Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28, 2013 (ML13066A172).
- 2. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12054A679).
- 3. Letter from M. G. Korsnick (CENG) to Document Control Desk (NRC), Supplement to Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated March 8, 2013 (ML13073A155).
- 4. Letter from N. S. Morgan (NRC) to G. H. Gellrich (CENG), Calvert Cliffs Nuclear Power Plant, Units Nos. 1 and 2 - Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, Order EA-12-051(TAC Nos. MF1 140 and MF1141), dated June 19, 2013 (ML13164A393)
- 5. Letter from M .D. Flaherty (CENG) to Document Control Desk (NRC), Response to Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) (TAC Nos. MF1140 and MF1141), dated July 3, 2013 (ML13190A017).
- 6. NRC JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, August 29, 2012 (ML12221A339).
- 7. NEI 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," Revision 1, August 2012 (ML12240A307).
- 8. Letter from E. D. Dean (CENG) to Document Control Desk (NRC), Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated August 27, 2013 (ML13254A279).
- 9. Letter from M. C. Thadani (NRC) to J. A. Spina (CENG), Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, and Nine Mile Point Nuclear Station, Unit Nos. 1 and 2, Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos.
MF1131, MF1132, MF1140, and MF1141), dated November 15, 2013 (ML13281A205).
10.Memorandum from C .A. Hunt (NRC) to M. A. Mitchell (NRC), Summary of the November 26, 2013 Public Meeting to Discuss Industry Responses to Staff Interim Evaluations for Spent Fuel Pool Instrumentation, dated December 26, 2013 (ML133478030).
4 of 5
ATTACHMENT SIX-MONTH STATUS REPORT (FEBRUARY 2015) FOR MITIGATION STRATEGIES FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION
- 11. Letter from M. G. Korsnick (CENG) to Document Control Desk (NRC), Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 24, 2014.
12.Letter from M. G. Korsnick (CENG) to Document Control Desk (NRC), Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated August 26, 2014.
5 of 5