RBG-47513, Application for Technical Specification Changes; Technical Specification Task Force (TSTF) Improved Standard Technical Specification Change Traveler, TSTF-423, Technical Specifications End States

From kanterella
Jump to navigation Jump to search

Application for Technical Specification Changes; Technical Specification Task Force (TSTF) Improved Standard Technical Specification Change Traveler, TSTF-423, Technical Specifications End States
ML14338A867
Person / Time
Site: River Bend Entergy icon.png
Issue date: 11/03/2014
From: Olson E
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RBG-47513
Download: ML14338A867 (8)


Text

Entergy Operations, Inc.

River Bend Station Enterg- 5485 U.S. Highway 61N St. Francisville, LA 70775 Tel 225-381-4374 Eric Olson Site Vice President RBG-47513 November 3, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

SUBJECT:

Application for Technical Specification Changes; Technical Specification Task Force (TSTF) Improved Standard Technical Specification Change Traveler, TSTF-423,. "Technical Specifications End States."

River Bend Station, Unit 1 Docket No. 50-458 License No. NPF-47 References 1 Entergy Letter dated June 13, 2013, Application for Technical Specification Changes; Technical Specification Task Force (TSTF)

Improved Standard Technical Specification Change Traveler, TSTF-423, "Technical Specifications End States." (RBG-47322) 2 NRC Email dated July 29, 2014, River Bend Station, Unit 1, Request for Additional Information Regarding Technical Specification Task Force Traveler (TSTF) - 423 (TAC No. MF2299) 3 Entergy Letter dated August 28, 2014, Application for Technical Specification Changes; Technical Specification Task Force (TSTF)

Improved Standard Technical Specification Change Traveler, TSTF-423, "Technical Specifications End States." (RBG-47499)

Dear Sir or Madam:

In Reference 1 Entergy Operations, Inc. (Entergy) submitted a request for an amendment to the Technical Specifications (TS) for River Bend Station (RBS), Unit 1 During the review the NRC identified the need to reference the commitments contained in the standard Technical Specification Change Traveler (TSTF). As discussed, Entergy proposes to include the reference with the current listing of License Conditions.

Currently the RBS Operating License has 21 license conditions on pages 3 through 6d.

-, onditions 20 and 21 refer to past operating cycles and therefore, are no longer needed.

A061 (

ý-( jzi--

RBG-47513 Page 2 of 3 Entergy proposes to delete conditions 20 and 21 then replace 20 with the new condition referencing the commitments required by the standard TSTF Safety Evaluation. These commitments will be included in USAR Section 16. The proposed License Condition also includes the provision to evaluate changes to the commitments through the use of the 10 CFR 50.59 process.

The proposed changes to pages 6c and 6d of the Operating License are in Attachment 1. contains the regulatory commitments in this letter.

If you have any questions or require additional information, please contact Mr. J. A. Clark at (225) 381-4177 I declare under penalty of perjury that the foregoing is true and correct. Executed on November 3, 2014.

Sincerely, EO/JAC/bmb Attachments:

1. Proposed License Condition cc: Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Blvd.

Arlington, TX 76011-4511 NRC Senior Resident Inspector P. 0. Box 1050 St. Francisville, LA 70775 U. S. Nuclear Regulatory Commission Attn: Mr. Alan Wang MS O-8B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852

/

RBG-47513 Page 3 of 3 Department of Environmental Quality Office of Environmental Compliance Radiological Emergency Planning and Response Section JiYoung Wiley P.O. Box 4312 Baton Rouge, LA 70821-4312 Public Utility Commission of Texas Attn: PUC Filing Clerk 1701 N. Congress Avenue P. 0. Box 13326 Austin, TX 78711-3326 RBF1-14-0165 LAR 2013-02

Attachment I RBG-47513 Proposed License Condition

-6c-(20) Commitments made as required by standard TSTF Safety Evaluation, as discussed in the notice of availability, will be maintained as described in USAR Section 16. This condition applies to the following TSTFs as approved.

TSTF-423 Changes to the commitments can be made in accordance with 10 CFR 50.59.

Amendment No. 157 184

-6d-(21) Deleted Amendment No. 4-62 184

.1

Attachment 2 RBG-47513 Regulatory Commitments

RBG-47513 .

Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.

TYPE (Check one) SCHEDULED ONE- CONTINUING COMPLETION COMMITMENT TIME COMPLIANCE DATE ACTION Entergy proposes to delete conditions 20 and 21 X Upon then replace 20 with the new condition referencing Implementation the commitments required by the standard TSTF Safety Evaluation. These commitments will be included in USAR Section 16.