RA-14-104, Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan

From kanterella
Jump to navigation Jump to search
Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan
ML14365A067
Person / Time
Site: Oyster Creek
Issue date: 12/30/2014
From: Jim Barstow
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
RA-14-104
Download: ML14365A067 (185)


Text

10 CFR 50.54(bb) 10 CFR 50.75(f)(3)

RA-14-104 December 30, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Oyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-16 NRC Docket Nos. 50-219 and 72-15

Subject:

Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan

Reference:

1) Letter from John G. Lamb (U. S. Nuclear Regulatory Commission) to Michael J. Pacilio (Exelon Generation Company, LLC), "Oyster Creek Nuclear Generating Station - Request for Information Regarding Preliminary Decommissioning Cost Estimate and Annual Decommissioning Funding Status Reports," dated September 17, 2014 (ML14252A703)
2) Letter RA-11-007 from Keith R. Jury (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, "Permanent Cessation of Operations at Oyster Creek Nuclear Generating Station," dated January 7, 2011 (ML110070507)

Exelon Generation Company, LLC (Exelon) is submitting this letter to provide a preliminary decommissioning cost estimate pursuant to 10 CFR 50.75(f)(3) and spent fuel management plan pursuant to 10 CFR 50.54(bb) 1 for Oyster Creek Nuclear Generating Station (OCNGS).

In accordance with 10 CFR 50.75, "Reporting and recordkeeping for decommissioning planning," paragraph (f)(3), "Each power reactor licensee shall at or about 5 years prior to the projected end of operations submit a preliminary decommissioning cost estimate which includes an up-to-date assessment of the major factors that could affect the cost to decommission." of this submittal contains a preliminary decommissioning cost estimate for OCNGS. The cost estimate is a preliminary estimate of anticipated costs and will be updated at various times as deemed appropriate by OCNGS and/or in compliance with regulatory requirements. The attached preliminary decommissioning cost estimate assumes that OCNGS permanently terminates operations on December 31, 2019, in accordance with the Reference 2 letter.

1 Section 50.54(bb) requires that licensees submit a spent fuel management plan to the NRC within two years following permanent shutdown or five years prior to the expiration of the operating license. The operating license for Oyster Creek Nuclear Generating Station expires in 2029. In Reference 2, Exelon provided notice of its intention to permanently cease operations effective December 31, 2019. As a result, Exelon is providing its spent fuel management plan within five years of the shutdown date.

U.S. Nuclear Regulatory Commission Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan Docket Nos. 50-219 and 72-15 December 30, 2014 Page 2 The major factors that could affect the cost estimate as well as contingencies to allow for unknown or unplanned occurrences during decommissioning are included in the attached preliminary decommissioning cost estimate. Additionally, soil and ground water remediation costs are included in the cost estimate. The required soil remediation is based on a report that evaluated the known or suspected contaminated soil at OCNGS as of January 2004 and evaluation of subsequent 10 CFR 50.75(g)(1) reports.

The attached preliminary decommissioning cost estimate evaluates three (3) options for decommissioning OCNGS. Exelon has not made a final determination of the decommissioning approach for OCNGS. For the purpose of choosing a decommissioning option to demonstrate adequacy of funding to meet regulatory requirements, the SAFSTOR option has been selected. Exelon reserves the right to choose a decommissioning option in accordance with its business needs, recognizing that it needs to assure the chosen option meets U.S. Nuclear Regulatory Commission (NRC) requirements for decommissioning funding.

As discussed in 10 CFR 50.54(bb), Conditions of licenses, paragraph (bb), a licensee shall submit written notification to the Commission for its review and preliminary approval of the program by which the licensee intends to manage and provide funding for the management of all irradiated fuel at the reactor following permanent cessation of operation of the reactor until title to the irradiated fuel and possession of the fuel is transferred to the Secretary of Energy for its ultimate disposal in a repository.

Accordingly, Attachment 2 of this submittal includes the Spent Fuel Management Plan for NRC review and preliminary approval. contains the projected annual cash flow required for decommissioning OCNGS based on the SAFSTOR scenario from the Attachment 1 cost estimate. (The cost estimate is in thousands of 2011 dollars. The Attachment 1 costs have been escalated to 2014 dollars in Attachment 3.) The costs for radiological decommissioning (license termination costs), spent fuel management, Independent Spent Fuel Storage Installation (ISFSI) decommissioning, and site restoration (non-radiological decommissioning) are reflected in Attachment 3. Exelon recognizes that an exemption from 10 CFR 50.82(a)(8)(i)(A) is required to use decommissioning trust funds for expenses other than decommissioning activities as the term decommissioning is defined in 10 CFR 50.2. contains the projected annual cash flow from the OCNGS decommissioning trust fund for decommissioning the site (including radiological decommissioning, spent fuel management, ISFSI decommissioning, and site restoration) based on the SAFSTOR scenario from the Attachment 1 cost estimate. The cash flow analysis conservatively assumes all expenses in a year are incurred at the beginning of year (i.e., beginning of year convention) during the decommissioning period.

U.S. Nuclear Regulatory Commission Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan Docket Nos. 50-219 and 72-15 December 30, 2014 Page 3 As of November 30, 2014, OCNGS decommissioning trust fund balances totaled $869.9 million. Escalated at 2% annual real rate of return to November 30, 2019, the trust fund will amount to $960.5 million before deducting decommissioning expenses, which exceeds the amount required to complete decommissioning of the site under the SAFSTOR scenario of the attached preliminary cost estimate.

In accordance with 10 CFR 50.54(bb), a copy of this notification will be maintained until the expiration of the OCNGS operating license. Additionally, OCNGS will notify the NRC of any significant changes in the proposed Spent Fuel Management Plan described in .

There are no new regulatory commitments contained in this letter.

If you have any questions or require additional information, please contact Richard Gropp at 610-765-5557.

Respectfully, James Barstow Director, Licensing and Regulatory Affairs Exelon Generation Company, LLC - Preliminary Decommissioning Cost Estimate for Oyster Creek Nuclear Generating Station - Spent Fuel Management Plan for Oyster Creek Nuclear Generating Station - Annual SAFSTOR Decommissioning Cost Cash Flow for Oyster Creek Nuclear Generating Station - Annual SAFSTOR Decommissioning Fund Cash Flow for Oyster Creek Nuclear Generating Station cc: Regional Administrator - NRC Region I NRG Senior Resident Inspector - Oyster Creek Nuclear Generating Station NRC Project Manager - Oyster Creek Nuclear Generating Station Director, Bureau of Nuclear Engineering, New Jersey Department of Environmental Protection Mayor of Lacey Township, Forked River, New Jersey

ATTACHMENT 1 PRELIMINARY DECOMMISSIONING COST ESTIMATE FOR OYSTER CREEK NUCLEAR GENERATING STATION

Document E16-1640-002, Rev. 4 DECOMMISSIONING COST ANALYSIS for the OYSTER CREEK NUCLEAR GENERATING STATION prepared for Exelon Generation Company LLC prepared by TLG Services, Inc.

Bridgewater, Connecticut December 2014

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page ii of xix APPROVALS Project Manager William A. Cloutier, Jr. Date Project Engineer John A. Carlson Date Technical Manager Francis W. Seymore Date TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page iii of xix TABLE OF CONTENTS SECTION PAGE EXECUTIVE

SUMMARY

............................................................................... vii-xix

1. INTRODUCTION ................................................................................................... 1-1 1.1 Objectives of Study ........................................................................................... 1-1 1.2 Site Description................................................................................................. 1-1 1.3 Regulatory Guidance ........................................................................................ 1-2 1.3.1 Nuclear Waste Policy Act...................................................................... 1-4 1.3.2 Low-Level Radioactive Waste Acts ...................................................... 1-7 1.3.3 Radiological Criteria for License Termination .................................... 1-8
2. DECOMMISSIONING ALTERNATIVES .......................................................... 2-1 2.1 DECON .............................................................................................................. 2-2 2.1.1 Period 1 - Preparations ......................................................................... 2-2 2.1.2 Period 2 - Decommissioning Operations .............................................. 2-5 2.1.3 Period 3 - Site Restoration .................................................................... 2-8 2.1.4 ISFSI Operations and Decommissioning ............................................ 2-9 2.2 SAFSTOR AND DELAYED DECOMMISSIONING ................................... 2-10 2.2.1 Period 1 - Preparations ....................................................................... 2-10 2.2.2 Period 2 - Dormancy ............................................................................ 2-11 2.2.3 Periods 3 and 4 - Delayed Decommissioning..................................... 2-12 2.2.4 Period 5 - Site Restoration .................................................................. 2-14
3. COST ESTIMATE ................................................................................................... 3-1 3.1 Basis of Estimate .............................................................................................. 3-1 3.2 Methodology ...................................................................................................... 3-1 3.3 Financial Components of the Cost Model ....................................................... 3-3 3.3.1 Contingency ........................................................................................... 3-3 3.3.2 Financial Risk ........................................................................................ 3-6 3.4 Site-Specific Considerations............................................................................. 3-7 3.4.1 Spent Fuel Management....................................................................... 3-7 3.4.2 Reactor Vessel and Internal Components ........................................... 3-9 3.4.3 Primary System Components ............................................................. 3-11 3.4.4 Main Turbine and Condenser............................................................. 3-11 3.4.5 Transportation Methods ..................................................................... 3-11 3.4.6 Low-Level Radioactive Waste Disposal ............................................. 3-12 3.4.7 Site Conditions Following Decommissioning .................................... 3-13 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page iv of xix TABLE OF CONTENTS (continued)

SECTION PAGE 3.5 Assumptions .................................................................................................... 3-14 3.5.1 Estimating Basis ................................................................................. 3-14 3.5.2 Labor Costs .......................................................................................... 3-14 3.5.3 Design Conditions................................................................................ 3-15 3.5.4 General ................................................................................................. 3-15 3.6 Cost Estimate Summary ............................................................................... 3-17

4. SCHEDULE ESTIMATE ...................................................................................... 4-1 4.1 Schedule Estimate Assumptions ..................................................................... 4-1 4.2 Project Schedule ................................................................................................ 4-2
5. RADIOACTIVE WASTES ..................................................................................... 5-1
6. RESULTS ................................................................................................................. 6-1
7. REFERENCES ........................................................................................................ 7-1 TABLES Summary of Decommissioning Cost Elements, DECON .............................. xvii Summary of Decommissioning Cost Elements, Delayed DECON ............... xviii Summary of Decommissioning Cost Elements, SAFSTOR ............................ xix 3.1 Schedule of Annual Expenditures, DECON ................................................. 3-18 3.2 Schedule of Annual Expenditures, Delayed DECON ................................... 3-19 3.3 Schedule of Annual Expenditures, SAFSTOR .............................................. 3-20 5.1 Decommissioning Waste Summary, DECON ................................................. 5-3 5.2 Decommissioning Waste Summary, Delayed DECON ................................... 5-4 5.3 Decommissioning Waste Summary, SAFSTOR.............................................. 5-5 6.1 Summary of Decommissioning Cost Elements, DECON ............................... 6-4 6.2 Summary of Decommissioning Cost Elements, Delayed DECON ................. 6-5 6.3 Summary of Decommissioning Cost Elements, SAFSTOR ............................ 6-6 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page v of xix TABLE OF CONTENTS (continued)

SECTION PAGE FIGURES 4.1 DECON Activity Schedule ................................................................................ 4-3 4.2 Decommissioning Timeline, DECON .............................................................. 4-5 4.3 Decommissioning Timeline, Delayed DECON................................................ 4-6 4.4 Decommissioning Timeline, SAFSTOR .......................................................... 4-7 APPENDICES A. Unit Cost Factor Development ............................................................................. A-1 B. Unit Cost Factor Listing ...................................................................................... B-1 C. Detailed Cost Analysis, DECON .......................................................................... C-1 D. Detailed Cost Analysis, Delayed DECON ........................................................... D-1 E. Detailed Cost Analysis, SAFSTOR ...................................................................... E-1 F. Work Difficulty Factor Adjustments.....................................................................F-1 G. Work Area Designation - GPU STN Index ......................................................... G-1 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page vi of xix Page Intentionally Left Blank TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page vii of xix EXECUTIVE

SUMMARY

This report presents updated estimates of the cost to decommission the Oyster Creek Nuclear Generating Station (Oyster Creek) for the identified decommissioning scenarios following a scheduled cessation of plant operations. The analysis relies upon site-specific, technical information, originally developed in an evaluation for the GPU Nuclear Corporation in 1997-99,[1] revised in subsequent evaluations in 2003-04[2] and 2008-09,[3] and finally updated to reflect current assumptions pertaining to the disposition of the nuclear unit and relevant industry experience in undertaking such projects. The updated estimates are designed to provide Exelon Generation Company (Exelon) with sufficient information to assess its financial obligations as they pertain to the eventual decommissioning of the nuclear station.

The primary goal of the decommissioning is the removal and disposal of the contaminated systems and structures so that the plants operating license can be terminated. The analysis recognizes that spent fuel will be stored at the site in the plants storage pool and/or in an independent spent fuel storage installation (ISFSI) until such time that it can be transferred to a Department of Energy (DOE) facility.

Consequently, the estimates also include those costs to manage and subsequently decommission such storage facilities.

The estimates are based on numerous fundamental assumptions, including regulatory requirements, low-level radioactive waste disposal practices, high-level radioactive waste management options, site restoration requirements, and project contingencies. The estimates incorporate a minimum cooling period of approximately five and one-half years for the spent fuel that resides in the reactor building storage pool when operations cease. The estimates also include the dismantling of non-essential structures and limited restoration of the site.

Alternatives and Regulations The Nuclear Regulatory Commission (NRC or Commission) provided initial decommissioning requirements in its rule adopted on June 27, 1988.[4] In this rule, 1

Decommissioning Cost Analysis for the Oyster Creek Nuclear Generating Station , Document No.

G01-1271-003, TLG Services, Inc., February 1999 2

Decommissioning Cost Analysis for the Oyster Creek Nuclear Generating Station, Document No.

E16-1455-006, Rev. 0, TLG Services, Inc., March 2004 3

Decommissioning Cost Analysis for the Oyster Creek Nuclear Generating Station, Document No.

E11-1555-010, TLG Services, Inc., Rev. 1, March 2009 4

U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72 "General Requirements for TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page viii of xix the NRC set forth financial criteria for decommissioning licensed nuclear power facilities. The regulations addressed planning needs, timing, funding methods, and environmental review requirements for decommissioning. The rule also defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB.

DECON is defined as "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations."[5]

SAFSTOR is defined as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use."[6] Decommissioning is to be completed within 60 years, although longer time periods will be considered when necessary to protect public health and safety.

ENTOMB is defined as "the alternative in which radioactive contaminants are encased in a structurally long-lived material, such as concrete; the entombed structure is appropriately maintained and continued surveillance is carried out until the radioactive material decays to a level permitting unrestricted release of the property."[7] As with the SAFSTOR alternative, decommissioning is currently required to be completed within 60 years.

The 60-year restriction has limited the practicality for the ENTOMB alternative at commercial reactors that generate significant amounts of long-lived radioactive material. In 1997, the Commission directed its staff to re-evaluate this alternative and identify the technical requirements and regulatory actions that would be necessary for entombment to become a viable option. The resulting evaluation provided several recommendations, however, rulemaking has been deferred based upon several factors (e.g., no licensee has committed to pursuing the entombment option, the unresolved issues associated with the disposition of greater-than-Class C material (GTCC), and the NRCs current priorities) at least until after the additional research studies are complete. The Commission concurred with the staffs recommendation.

Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988 5

Ibid. Page FR24022, Column 3 6

Ibid.

7 Ibid. Page FR24023, Column 2 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page ix of xix In 1996 the NRC amended its decommissioning regulations to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process.[8] The amendments allow for greater public participation and better define the transition process from operations to decommissioning. Regulatory Guide 1.184, issued in July 2000, further described the methods and procedures acceptable to the NRC staff for implementing the requirements of the 1996 amendments relating to the initial activities and major phases of the decommissioning process. The costs and schedules presented in this analysis follow the general guidance and processes described in these regulations.

Decommissioning Scenarios The following scenarios were evaluated and are representative of the alternatives available to the owner. The current operating license expires in 2029; however, this study assumes that the plant will retire in 2019.

1. DECON: Decommissioning activities commence shortly after the cessation of plant operations. The spent fuel in the plants spent fuel storage pool is transferred to the ISFSI within five and one-half years. The equipment, structures, and portions of the plant containing radioactive contaminants are removed or decontaminated to a level that permits the facility to be released for unrestricted use. Non-essential structures are then demolished. Spent fuel storage operations continue at the site (ISFSI) until the transfer of the fuel to the DOE is complete, assumed to be in the year 2036.
2. Delayed DECON: In the second scenario, the unit is shutdown and prepared for dismantling similar to the DECON scenario; however, in this scenario, the unit enters an abbreviated period of storage prior to the actual start of field activities. The spent fuel discharged to the storage pool once operations cease remains in the pool until it can be transferred to a DOE facility. The ISFSI, used to support operations, is not used to off-load the storage pool.

Decommissioning is delayed until the transfer of the fuel from both the pool and ISFSI to the DOE is completed in the year 2036. The unit is then decommissioned.

3. SAFSTOR: The unit is placed into safe-storage in the third scenario.

Decommissioning is deferred beyond the fuel storage period to the maximum extent possible; termination of the license would conclude within the required 60-year period. The spent fuel in the plants spent fuel storage pool is 8

U.S. Code of Federal Regulations, Title 10, Parts 2, 50, and 51, "Decommissioning of Nuclear Power Reactors," NRC, Federal Register Volume 61, (p 39278 et seq.), July 29, 1996 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page x of xix transferred to the ISFSI within five and one-half years. Spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is complete, assumed to be in the year 2036. The plant remains in safe-storage following the removal of spent fuel from the site, timed to allow final decommissioning and license termination to be completed within 60 years of final shutdown. As with the first two scenarios, decommissioning activities are sequenced and integrated so as to minimize the total duration of the physical dismantling process.

Methodology The methodology used to develop the estimates described within this document follows the basic approach originally presented in the cost estimating guidelines [9]

developed by the Atomic Industrial Forum (now Nuclear Energy Institute). This reference describes a unit factor method for determining decommissioning activity costs. The unit factors used in this analysis incorporate site-specific costs and the latest available information on worker productivity in decommissioning.

An activity duration critical path is used to determine the total decommissioning program schedule. The schedule is relied upon in calculating the carrying costs, which include program management, administration, field engineering, equipment rental, and support services such as quality control and security. This systematic approach for assembling decommissioning estimates ensures a high degree of confidence in the reliability of the resulting cost estimate.

Contingency Consistent with standard cost estimating practice, contingencies are applied to the decontamination and dismantling costs as "specific provision for unforeseeable elements of cost within the defined project scope, particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur.[10] The cost elements in the estimates are based on ideal conditions; therefore, the types of unforeseeable events that are almost certain to occur in decommissioning, based on industry experience, are addressed through a percentage contingency applied on a line-item basis. This contingency factor is a nearly universal element in all large-scale construction and demolition projects. It should be noted that contingency, as 9

T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986 10 Project and Cost Engineers Handbook, Second Edition, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, p. 239 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xi of xix used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.

The use and role of contingency within decommissioning estimates is not a safety factor issue. Safety factors provide additional security and address situations that may never occur. Contingency funds, by contrast, are expected to be fully expended throughout the program. Inclusion of contingency is necessary to provide assurance that sufficient funding will be available to accomplish the intended tasks.

Low-Level Radioactive Waste Disposal The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for shallow-land disposal. With the passage of the Low-Level Radioactive Waste Policy Act in 1980,[11] and its Amendments of 1985,[12] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

New Jersey is a member of the three-state Atlantic Interstate Low-Level Radioactive Waste Management Compact, formed after South Carolina formally joined the Northeast Regional Compact. The Barnwell Low-Level Radioactive Waste Management Facility located in South Carolina is expected to be available to support the decommissioning of Oyster Creek. It is also assumed that Exelon can access other disposal sites, should it prove cost-effective. As such, rate schedules for both the Barnwell and the EnergySolutions facility in Clive, Utah are used to generate disposal costs.

For the purpose of this analysis, the EnergySolutions facility is used as the basis for estimating the disposal cost for the lowest level and majority of the radioactive waste (Class A [13]). EnergySolutions does not have a license to dispose of the more highly radioactive waste (Classes B and C), for example, generated in the dismantling of the reactor vessel. The disposal cost for this material is based upon the rate schedule for the Barnwell facility.

The dismantling of the components residing closest to the reactor core generates radioactive waste considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level 11 Low-Level Radioactive Waste Policy Act of 1980, Public Law 96-573, 1980 12 Low-Level Radioactive Waste Policy Amendments Act of 1985, Public Law 99-240, 1986 13 U.S. Code of Federal Regulations, Title 10, Part 61, Licensing Requirements for Land Disposal of Radioactive Waste TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xii of xix Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance. As such, the GTCC radioactive waste in this study is assumed to be packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.

The GTCC material is either stored with the spent fuel at the ISFSI or shipped directly to a DOE facility as it is generated (depending upon the timing of the decommissioning and whether the spent fuel has been removed from the site prior to the start of decommissioning).

A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for Oyster Creek reflect the savings from waste recovery/volume reduction.

High-Level Radioactive Waste Management Congress passed the Nuclear Waste Policy Act (NWPA) in 1982, assigning the federal governments long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The DOE was to begin accepting spent fuel by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, even with the License Application for a geologic repository submitted by the DOE to the NRC in 2008. The current Administration has cut the budget for the repository program while promising to conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle and make recommendations for a new plan.[14]

Towards this goal, the Administration appointed a Blue Ribbon Commission on Americas Nuclear Future (Blue Ribbon Commission) to make recommendations for 14 Blue Ribbon Commission on Americas Nuclear Future Charter, http://cybercemetery.unt.edu/archive/brc/20120620215336/http://brc.gov/index.php?q=page/charter TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xiii of xix a new plan for nuclear waste disposal. The Blue Ribbon Commissions charter includes a requirement that it consider [o]ptions for safe storage of used nuclear fuel while final disposition pathways are selected and deployed.[15]

On January 26, 2012, the Blue Ribbon Commission issued its Report to the Secretary of Energy containing a number of recommendations on nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

[T]he United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities[16]

[T]he United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste.[17]

In January 2013, the DOE issued the Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, in response to the recommendations made by the Blue Ribbon Commission and as a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel...[18]

With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites; Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and 15 Ibid.

16 Blue Ribbon Commission on Americas Nuclear Future, Report to the Secretary of Energy, http://www.brc.gov/sites/default/files/documents/brc_finalreport_jan2012.pdf, p. 32, January 2012 17 Ibid., p.27 18 Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, U.S. DOE, January 11, 2013 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xiv of xix Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048.[19]

The NRCs review of DOEs license application to construct a geologic repository at Yucca Mountain was suspended in 2011 when the Administration slashed the budget for completing that work. However, the US Court of Appeals for the District of Columbia Circuit recently issued a writ of mandamus (in August 2013) [20]

ordering NRC to comply with federal law and restart its review of DOE's Yucca Mountain repository license application to the extent of previously appropriated funding for the review.

Completion of the decommissioning process is dependent upon the DOEs ability to remove spent fuel from the site in a timely manner. DOEs repository program had assumed that spent fuel allocations would be accepted for disposal from the nations commercial nuclear plants, with limited exceptions, in the order (the queue) in which it was discharged from the reactor.[21] With a large fleet of reactors, Exelon may be able to re-assign allocations between its units to minimize on-site storage costs.

Assuming a 2025 start date for DOE initiating transfer of commercial spent fuel to a federal facility (based upon the proposed timeline for the availability of the larger interim storage facility), the assemblies generated from Oyster Creek operations are projected to be shipped from the Oyster Creek site in the years 2034 through 2036 (assuming the cessation of plant operations in 2019). This equates to 76 multi-purpose canisters (at 61 assemblies per canister).

An ISFSI, operated under a Part 50 General License (in accordance with 10 CFR 72, Subpart K[22]), has been constructed to support continued plant operations. This 19 Ibid., p.2 20 United States Court of Appeals for the District Of Columbia Circuit, In Re: Aiken County, et al, August 2013 http://www.cadc.uscourts.gov/internet/opinions.nsf/BAE0CF34F762EBD985257BC6004DEB 18/$file/11-1271-1451347.pdf 21 U.S. Code of Federal Regulations, Title 10, Part 961.11, Article IV - Responsibilities of the Parties, B. DOE Responsibilities, 5.(a) DOE shall issue an annual acceptance priority ranking for receipt of SNF and/or HLW at the DOE repository. This priority ranking shall be based on the age of SNF and/or HLW as calculated from the date of discharge of such materials from the civilian nuclear power reactor. The oldest fuel or waste will have the highest priority for acceptance 22 U.S. Code of Federal Regulations, Title 10, Part 72, Subpart K, General License for Storage of Spent Fuel at Power Reactor Sites.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xv of xix analysis assumes that the facility can be expanded to support decommissioning operations (in the DECON and SAFSTOR scenarios).

The spent fuel in the wet storage pools at the cessation of plant operations is expected to be transferred to the ISFSI (DECON and SAFSTOR scenarios) within the first five and one-half years following shutdown. Once the wet storage pool is emptied, the reactor building can be either decontaminated and dismantled or prepared for long-term storage. The pool is kept operational in the Delayed DECON scenario until the spent fuel stored in the pool can be transferred to the DOE.

Exelons strongly held position is that the DOE has a contractual obligation to accept Oyster Creeks fuel in a timely manner and consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim. However, at this time, including the cost of storing spent fuel in this study is the most reasonable approach because it insures the availability of sufficient decommissioning funds at the end of the stations life if the DOE has not met its contractual obligation to take the fuel.

Site Restoration The efficient removal of the contaminated materials at the site will result in damage to many of the site structures. Blasting, coring, drilling, and the other decontamination activities will substantially damage power block structures, potentially weakening the footings and structural supports. Prompt demolition once the license is terminated is clearly the most appropriate and cost-effective option. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures with a work force already mobilized is more efficient and less costly than if the process were deferred. Experience at shutdown generating stations has shown that plant facilities quickly degrade without maintenance, adding additional expense and creating potential hazards to the public and the demolition work force.

Consequently, this analysis assumes that non-essential site structures within the restricted access area are removed to a nominal depth of three feet below the local grade level wherever possible. The site is then graded and stabilized.

Summary The costs to decommission Oyster Creek were evaluated for several decommissioning scenarios, incorporating the attributes of both the DECON and SAFSTOR decommissioning alternatives. Regardless of the timing of the decommissioning activities, the estimates assume the eventual removal of all the contaminated and activated plant components and structural materials, such that TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xvi of xix the facility operator may then have unrestricted use of the site with no further requirement for an operating license. Delayed decommissioning is initiated after the spent fuel has been removed from the site and is accomplished within the 60-year period required by current NRC regulations. In the interim, the spent fuel remains in storage at the site until such time that the transfer to a DOE facility can be completed. Once the transfer is complete, the storage facilities are also decommissioned.

The scenarios analyzed for the purpose of generating the estimates are described in Section 2. The assumptions are presented in Section 3, along with schedules of annual expenditures. The major cost contributors are identified in Section 6, with detailed activity costs, waste volumes, and associated manpower requirements delineated in Appendices C, D, and E. Cost summaries for the various scenarios are provided at the end of this section for the major cost components.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xvii of xix

SUMMARY

OF DECOMMISSIONING COST ELEMENTS DECON (thousands of 2011 dollars)

Cost Element Total Decontamination 22,297 Removal 148,522 Packaging 22,786 Transportation 17,598 Waste Disposal 64,400 Off-site Waste Processing 10,024 Program Management [1] 417,042 Spent Fuel Pool Isolation 11,822 Spent Fuel Management[2] 100,110 Insurance and Regulatory Fees 20,929 Energy 13,156 Characterization and Licensing Surveys 19,885 Property Taxes 21,212 Miscellaneous Equipment 6,800 Site O&M 3,127 Total [3] 899,710 Cost Element NRC License Termination 665,975 Spent Fuel Management 177,146 Site Restoration 56,589 Total [3] 899,710

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xviii of xix

SUMMARY

OF DECOMMISSIONING COST ELEMENTS DELAYED DECON (thousands of 2011 dollars)

Cost Element Total Decontamination 23,573 Removal 134,505 Packaging 17,207 Transportation 13,288 Waste Disposal 39,463 Off-site Waste Processing 11,541 Program Management [1] 501,758 Spent Fuel Pool Isolation 11,822 Spent Fuel Management[2] 37,454 Insurance and Regulatory Fees 25,123 Energy 18,772 Characterization and Licensing Surveys 21,402 Property Taxes 25,586 Miscellaneous Equipment 10,399 Site O&M 8,327 Total [3] 900,219 Cost Element NRC License Termination 541,703 Spent Fuel Management 299,125 Site Restoration 59,390 Total [3] 900,219

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Page xix of xix

SUMMARY

OF DECOMMISSIONING COST ELEMENTS SAFSTOR (thousands of 2011 dollars)

Cost Element Total Decontamination 23,321 Removal 137,788 Packaging 16,136 Transportation 11,848 Waste Disposal 37,361 Off-site Waste Processing 11,589 Program Management [1] 556,588 Spent Fuel Pool Isolation 11,822 Spent Fuel Management[2] 96,744 Insurance and Regulatory Fees 57,478 Energy 24,479 Characterization and Licensing Surveys 21,402 Property Taxes 68,922 Miscellaneous Equipment 18,942 Site O&M 21,895 Total [3] 1,116,314 Cost Element NRC License Termination 873,828 Spent Fuel Management 183,117 Site Restoration 59,369 Total [3] 1,116,314

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 1 of 9

1. INTRODUCTION This report presents updated estimates of the cost to decommission the Oyster Creek Nuclear Generating Station (Oyster Creek), for the scenarios described in Section 2, following a scheduled cessation of plant operations. The analysis relies upon site-specific, technical information from an earlier evaluation prepared in 2008-09,[1] updated to reflect current assumptions pertaining to the disposition of the nuclear unit and relevant industry experience in undertaking such projects. The current estimates are designed to provide Exelon Generation Company (Exelon),

with sufficient information to assess their financial obligations, as they pertain to the eventual decommissioning of the nuclear unit. It is not a detailed engineering document, but a financial analysis prepared in advance of the detailed engineering that will be required to carry out the decommissioning 1.1 OBJECTIVES OF STUDY The objectives of this study are to prepare comprehensive estimates of the cost to decommission Oyster Creek, to provide a sequence or schedule for the associated activities, and to develop waste stream projections from the decontamination and dismantling activities. The plants operating license currently expires on April 9, 2029; however, this study assumes that the plant will be retired on December 31, 2019.

1.2 SITE DESCRIPTION The Oyster Creek nuclear unit is about two miles inland from the shore of Barnegat Bay on the coast of New Jersey. The site is approximately nine miles south of Toms River, New Jersey; about fifty miles east of Philadelphia, Pennsylvania; and sixty miles south of Newark, New Jersey. The generating station is comprised of a single reactor with supporting facilities.

Oyster Creek was designed and constructed by the General Electric Company Atomic Power Equipment Department as a turnkey project. The reactor is a single-cycle, forced circulation boiling water reactor producing steam for direct use in the steam turbine. The reactor vessel and the recirculation system are contained within the drywell of a pressure absorption containment system housed within the reactor building. The primary containment system consists of the drywell, vent pipes, and a pool of water contained in the absorption chamber (torus). The reactor building encloses the primary containment system, thereby providing a secondary containment.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 2 of 9 Oyster Creek presently operates under a full term operating license at a maximum thermal power level of about 1930 MWth with a corresponding gross electrical output of approximately 670 MWe. Heat produced in the reactor is converted to electrical energy by the steam and power conversion system. A turbine-generator system converts the thermal energy of steam produced by the reactor into mechanical shaft power and then into electrical energy. The turbine consists of a high-pressure, double-flow turbine element and three double-flow, low-pressure turbine elements all aligned in tandem. The generator is a direct-driven 60 Hertz, 24,000 volt, conductor-cooled, synchronous generator rated at 687,500 kVA. The turbine is operated in a closed feedwater cycle which condenses the steam; the heated feedwater is returned to the reactor. Heat rejected in the main condensers is removed by the circulating water system.

The circulating water system provides the heat sink required for removal of waste heat in the power plants thermal cycle. Water is drawn from Barnegat Bay through a 140 foot wide intake canal which follows the general course of the south branch of Forked River. The system has the principal function of removing heat by absorbing this energy in the main condenser. After passing through the plant condensers, the water is routed through the discharge canal which empties into Barnegat Bay.

1.3 REGULATORY GUIDANCE The Nuclear Regulatory Commission (NRC or Commission) provided initial decommissioning requirements in its rule "General Requirements for Decommissioning Nuclear Facilities," issued in June 1988.[2]* This rule set forth financial criteria for decommissioning licensed nuclear power facilities.

The regulation addressed decommissioning planning needs, timing, funding methods, and environmental review requirements. The intent of the rule was to ensure that decommissioning would be accomplished in a safe and timely manner and that adequate funds would be available for this purpose.

Subsequent to the rule, the NRC issued Regulatory Guide 1.159, Assuring the Availability of Funds for Decommissioning Nuclear Reactors,[3] which provided additional guidance to the licensees of nuclear facilities on the financial methods acceptable to the NRC staff for complying with the requirements of the rule. The regulatory guide addressed the funding requirements and provided guidance on the content and form of the financial assurance mechanisms indicated in the rule.

  • Annotated references for citations in Sections 1-6 are provided in Section 7.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 3 of 9 The rule defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB. The DECON alternative assumes that any contaminated or activated portion of the plants systems, structures, and facilities are removed or decontaminated to levels that permit the site to be released for unrestricted use shortly after the cessation of plant operations.

The rule also placed limits on the time allowed to complete the decommissioning process. For SAFSTOR, the process is restricted in overall duration to 60 years, unless it can be shown that a longer duration is necessary to protect public health and safety. The guidelines for ENTOMB are similar, providing the NRC with both sufficient leverage and flexibility to ensure that these deferred options are only used in situations where it is reasonable and consistent with the definition of decommissioning. At the conclusion of a 60-year dormancy period (or longer for ENTOMB if the NRC approves such a case), the site would still require significant remediation to meet the unrestricted release limits for license termination.

The ENTOMB alternative has not been viewed as a viable option for power reactors due to the significant time required to isolate the long-lived radionuclides for decay to permissible levels. However, with recent rulemaking permitting the controlled release of a site, the NRC has re-evaluated this alternative.[4] The resulting feasibility study, based upon an assessment by Pacific Northwest National Laboratory, concluded that the method did have conditional merit for some, if not most, reactors. However, the staff also found that additional rulemaking would be needed before this option could be treated as a generic alternative. The NRC had considered rulemaking to alter the 60-year time for completing decommissioning and to clarify the use of engineered barriers for reactor entombments.[5] However, the NRCs staff has recommended that rulemaking be deferred, based upon several factors, e.g., no licensee has committed to pursuing the entombment option, the unresolved issues associated with the disposition of greater-than-Class C material (GTCC), and the NRCs current priorities, at least until after the additional research studies are complete. The Commission concurred with the staffs recommendation.

The NRC published amendments to its decommissioning regulations in 1996.[6]

When the regulations were originally adopted in 1988, it was assumed that the majority of licensees would decommission at the end of the facilitys operating licensed life. Since that time, several licensees permanently and prematurely ceased operations. Exemptions from certain operating requirements were required once the reactor was defueled to facilitate the decommissioning. Each case was handled individually, without clearly defined generic requirements.

The NRC amended the decommissioning regulations in 1996 to clarify TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 4 of 9 ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process. The new amendments allow for greater public participation and better define the transition process from operations to decommissioning.

Under the revised regulations, licensees will submit written certification to the NRC within 30 days after the decision to cease operations. Certification will also be required once the fuel is permanently removed from the reactor vessel.

Submittal of these notices will entitle the licensee to a fee reduction and eliminate the obligation to follow certain requirements needed only during operation of the reactor. Within two years of submitting notice of permanent cessation of operations, the licensee is required to submit a Post-Shutdown Decommissioning Activities Report (PSDAR) to the NRC. The PSDAR describes the planned decommissioning activities, the associated sequence and schedule, and an estimate of expected costs. Prior to completing decommissioning, the licensee is required to submit applications to the NRC to terminate the license, which will include a License Termination Plan (LTP).

1.3.1 Nuclear Waste Policy Act Congress passed the Nuclear Waste Policy Act (NWPA) in 1982,[7]

assigning the federal governments long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The DOE was to begin accepting spent fuel by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, even with the License Application for a geologic repository submitted by the DOE to the NRC in 2008. The current Administration has cut the budget for the repository program while promising to conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle and make recommendations for a new plan.

Towards this goal, the Administration appointed a Blue Ribbon Commission on Americas Nuclear Future (Blue Ribbon Commission) to make recommendations for a new plan for nuclear waste disposal. The Blue Ribbon Commissions charter includes a requirement that it consider [o]ptions for safe storage of used nuclear fuel while final disposition pathways are selected and deployed.[8]

On January 26, 2012, the Blue Ribbon Commission issued its Report to the Secretary of Energy containing a number of recommendations on TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 5 of 9 nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

[T]he United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities

[T]he United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste.[9]

In January 2013, the DOE issued the Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, in response to the recommendations made by the Blue Ribbon Commission and as a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel...[10]

With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites; Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048.

The NRCs review of DOEs license application to construct a geologic repository at Yucca Mountain was suspended in 2011 when the Administration slashed the budget for completing that work. However, the US Court of Appeals for the District of Columbia Circuit recently issued a writ of mandamus (in August 2013)[11] ordering NRC to comply with federal law and restart its review of DOE's Yucca Mountain TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 6 of 9 repository license application to the extent of previously appropriated funding for the review.

Completion of the decommissioning process is dependent upon the DOEs ability to remove spent fuel from the site in a timely manner.

DOEs repository program had assumed that spent fuel allocations would be accepted for disposal from the nations commercial nuclear plants, with limited exceptions, in the order (the queue) in which it was discharged from the reactor.[12] With a large fleet of reactors, Exelon may be able to re-assign allocations between its units to minimize on-site storage costs.

Assuming a 2025 start date for DOE initiating transfer of commercial spent fuel to a federal facility (based upon the proposed timeline for the availability of the larger interim storage facility), the assemblies generated from Oyster Creek operations are projected to be shipped from the Oyster Creek site in the years 2034 through 2036 (assuming the cessation of plant operations in 2019). This equates to 76 multi-purpose canisters (at 61 assemblies per canister).

An ISFSI, operated under a Part 50 General License (in accordance with 10 CFR 72, Subpart K[13]), has been constructed to support continued plant operations. This analysis assumes that the facility can be expanded to support decommissioning operations (in the DECON and SAFSTOR scenarios).

The spent fuel in the wet storage pools at the cessation of plant operations is expected to be transferred to the ISFSI (DECON and SAFSTOR scenarios) within the first five and one-half years following shutdown. Once the wet storage pools are emptied, the reactor buildings can be either decontaminated and dismantled or prepared for long-term storage. The spent fuel pools are kept operational in the Delayed DECON scenario until the transfer of spent fuel from the pools to the DOE can be completed.

Exelons strongly held position is that the DOE has a contractual obligation to accept Oyster Creeks fuel in a timely manner and consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim. However, at this time, including the cost of storing spent fuel in this study is the most reasonable approach because it insures the availability of sufficient TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 7 of 9 decommissioning funds at the end of the stations life if the DOE has not met its contractual obligation to take the fuel.

1.3.2 Low-Level Radioactive Waste Acts The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for shallow-land disposal. With the passage of the Low-Level Radioactive Waste Policy Act in 1980,[14] and its Amendments of 1985,[15] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

New Jersey is a member of the three-state Atlantic Interstate Low-Level Radioactive Waste Management Compact, formed after South Carolina formally joined the Northeast Regional Compact. The Barnwell Low-Level Radioactive Waste Management Facility, located in South Carolina, is expected to be available to support the decommissioning of Oyster Creek. It is also assumed that Exelon can access other disposal sites, should it prove cost-effective. As such, rate schedules for both the Barnwell and the EnergySolutions facility in Clive, Utah are used to generate disposal costs.

For the purpose of this analysis, the EnergySolutions facility is used as the basis for estimating the disposal cost for the lowest level and majority of the radioactive waste (Class A [16]). EnergySolutions does not have a license to dispose of the more highly radioactive waste (Classes B and C), for example, generated in the dismantling of the reactor vessel.

The disposal cost for this material is based upon the rate schedule for the Barnwell facility.

The dismantling of the components residing closest to the reactor core generates radioactive waste considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste.

However, to date, the federal government has not identified a cost for TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 8 of 9 disposing of GTCC or a schedule for acceptance. As such, the GTCC radioactive waste in this study is assumed to be packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.

The GTCC material is either stored with the spent fuel at the ISFSI or shipped directly to a DOE facility as it is generated (depending upon the timing of the decommissioning and whether the spent fuel has been removed from the site prior to the start of decommissioning).

A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for Oyster Creek reflect the savings from waste recovery/volume reduction.

1.3.3 Radiological Criteria for License Termination In 1997, the NRC published Subpart E, Radiological Criteria for License Termination,[17] amending 10 CFR §20. This subpart provides radiological criteria for releasing a facility for unrestricted use. The regulation states that the site can be released for unrestricted use if radioactivity levels are such that the average member of a critical group would not receive a Total Effective Dose Equivalent (TEDE) in excess of 25 millirem per year, and provided that residual radioactivity has been reduced to levels that are As Low As Reasonably Achievable (ALARA).

The decommissioning estimates for Oyster Creek assume that the site will be remediated to a residual level consistent with the NRC-prescribed level as well as the State of New Jerseys remedial action levels for radioactive material.

It should be noted that the NRC and the Environmental Protection Agency (EPA) differ on the amount of residual radioactivity considered acceptable in site remediation. The EPA has two limits that apply to radioactive materials. An EPA limit of 15 millirem per year is derived from criteria established by the Comprehensive Environmental TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 1, Page 9 of 9 Response, Compensation, and Liability Act (CERCLA or Superfund).[18]

An additional limit of 4 millirem per year, as defined in 40 CFR §141.16, is applied to drinking water.[19]

On October 9, 2002, the NRC signed an agreement with the EPA on the radiological decommissioning and decontamination of NRC-licensed sites. The Memorandum of Understanding (MOU)[20] provides that EPA will defer exercise of authority under CERCLA for the majority of facilities decommissioned under NRC authority. The MOU also includes provisions for NRC and EPA consultation for certain sites when, at the time of license termination, (1) groundwater contamination exceeds EPA-permitted levels; (2) NRC contemplates restricted release of the site; and/or (3) residual radioactive soil concentrations exceed levels defined in the MOU.

The MOU does not impose any new requirements on NRC licensees and should reduce the involvement of the EPA with NRC licensees who are decommissioning. Most sites are expected to meet the NRC criteria for unrestricted use, and the NRC believes that only a few sites will have groundwater or soil contamination in excess of the levels specified in the MOU that trigger consultation with the EPA. However, if there are other hazardous materials on the site, the EPA may be involved in the cleanup. As such, the possibility of dual regulation remains for certain licensees. The present study does not include any costs for this occurrence.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 1 of 14

2. DECOMMISSIONING ALTERNATIVES Detailed cost estimates were developed to decommission Oyster Creek for three variations of the approved decommissioning alternatives: DECON and SAFSTOR.

Although the scenarios differ with respect to technique, process, cost, and schedule, they attain the same result: the ultimate release of the site for unrestricted use.

Three decommissioning scenarios were evaluated for the nuclear station. The scenarios selected are representative of alternatives available to the owner and are defined as follows:

1. DECON: Decommissioning activities commence shortly after the cessation of plant operations. The spent fuel in the plants spent fuel storage pool is transferred to the ISFSI within five and one-half years. The equipment, structures, and portions of the plant containing radioactive contaminants are removed or decontaminated to a level that permits the facility to be released for unrestricted use. Non-essential structures are then demolished. Spent fuel storage operations continue at the site (ISFSI) until the transfer of the fuel to the DOE is complete, assumed to be in the year 2036.
2. Delayed DECON: In the second scenario the unit is shutdown and prepared for dismantling similar to the DECON scenario; however, in this scenario, the unit enters an abbreviated period of storage prior to the actual start of field activities. The spent fuel discharged to the storage pool once operations cease remains in the pool until it can be transferred to a DOE facility. The ISFSI, used to support operations, is not used to off-load the storage pool.

Decommissioning is delayed until the transfer of the fuel from both the pool and ISFSI to the DOE is completed in the year 2036. The unit is then decommissioned.

3. SAFSTOR: The unit is placed into safe-storage in the third scenario.

Decommissioning is deferred beyond the fuel storage period to the maximum extent possible; termination of the license would conclude within the required 60-year period. The spent fuel in the plants spent fuel storage pool is transferred to the ISFSI within five and one-half years. Spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is complete, assumed to be in the year 2036. The plant remains in safe-storage following the removal of spent fuel from the site, timed to allow final decommissioning and license termination to be completed within 60 years of final shutdown. As with the first two scenarios, decommissioning activities are TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 2 of 14 integrated so as to minimize the total duration of the physical dismantling process.

The following sections describe the basic activities associated with each alternative.

Although detailed procedures for each activity identified are not provided, and the actual sequence of work may vary, the activity descriptions provide a basis not only for estimating but also for the expected scope of work (i.e., engineering and planning at the time of decommissioning).

The conceptual approach that the NRC has described in its regulations divides decommissioning into three phases. The initial phase commences with the effective date of permanent cessation of operations and involves the transition of both plant and licensee from reactor operations (i.e., power production) to facilitate de-activation and closure. During the first phase, notification is to be provided to the NRC certifying the permanent cessation of operations and the removal of fuel from the reactor vessel. The licensee would then be prohibited from reactor operation.

The second phase encompasses activities during the storage period or during major decommissioning activities, or a combination of the two. The third phase pertains to the activities involved in license termination. The decommissioning estimates developed for Oyster Creek are also divided into phases or periods; however, demarcation of the phases is based upon major milestones within the project or significant changes in the projected expenditures.

2.1 DECON The DECON alternative, as defined by the NRC, is "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations." This study does not address the cost to dispose of the spent fuel residing at the site; such costs are funded through a surcharge on electrical generation. However, the study does estimate the costs incurred with the interim on-site storage of the fuel pending shipment by the DOE to an off-site disposal facility.

2.1.1 Period 1 - Preparations In anticipation of the cessation of plant operations, detailed preparations are undertaken to provide a smooth transition from plant operations to site decommissioning. Through implementation of a staffing transition plan, the organization required to manage the TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 3 of 14 intended decommissioning activities is assembled from available plant staff and outside resources. Preparations include the planning for permanent defueling of the reactor, revision of technical specifications applicable to the operating conditions and requirements, a characterization of the facility and major components, and the development of the PSDAR.

Engineering and Planning The PSDAR, required before or within two years after permanent cessation of operations, provides a description of the licensees planned decommissioning activities, a timetable, and the associated financial requirements of the intended decommissioning program. Upon receipt of the PSDAR, the NRC will make the document available to the public for comment in a local meeting to be held in the vicinity of the reactor site.

Ninety days following submittal and NRC receipt of the PSDAR, the licensee may begin to perform major decommissioning activities under a modified 10 CFR §50.59 procedure, i.e., without specific NRC approval.

Major activities are defined as any activity that results in permanent removal of major radioactive components, permanently modifies the structure of the containment, or results in dismantling components (for shipment) containing GTCC, as defined by 10 CFR §61. Major components are further defined as comprising the reactor vessel and internals, large bore reactor recirculation system piping, and other large components that are radioactive. The NRC includes the following additional criteria for use of the §50.59 process in decommissioning. The proposed activity must not:

foreclose release of the site for possible unrestricted use, significantly increase decommissioning costs, cause any significant environmental impact, or violate the terms of the licensees existing license.

Existing operational technical specifications are reviewed and modified to reflect plant conditions and the safety concerns associated with permanent cessation of operations. The environmental impact associated with the planned decommissioning activities is also considered. Typically, a licensee will not be allowed to proceed if the consequences of a particular decommissioning activity are greater than that bounded by previously evaluated environmental assessments or impact statements. In this instance, the licensee would have to submit TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 4 of 14 a license amendment for the specific activity and update the environmental report.

The decommissioning program outlined in the PSDAR will be designed to accomplish the required tasks within the ALARA guidelines (as defined in 10 CFR §20) for protection of personnel from exposure to radiation hazards. It will also address the continued protection of the health and safety of the public and the environment during the dismantling activity. Consequently, with the development of the PSDAR, activity specifications, cost-benefit and safety analyses, and work packages and procedures, would be assembled to support the proposed decontamination and dismantling activities.

Site Preparations Following final plant shutdown, and in preparation for actual decommissioning activities, the following activities are initiated:

Characterization of the site and surrounding environs. This includes radiation surveys of work areas, major components (including the reactor vessel and its internals), internal piping, and primary shield cores.

Isolation of the spent fuel storage pool and fuel handling systems, such that decommissioning operations can commence on the balance of the plant. Decommissioning operations are scheduled around the fuel handling area to optimize the overall project schedule. The fuel is transferred to the ISFSI as it decays to the point that it meets the definition of standard fuel (DECON and SAFSTOR alternatives), or the DOE (Delayed DECON). Consequently, it is assumed that the fuel pool remains operational for approximately five and one-half years following the cessation of operations.

Specification of transport and disposal requirements for activated materials and/or hazardous materials, including shielding and waste stabilization.

Development of procedures for occupational exposure control, control and release of liquid and gaseous effluent, processing of radwaste (including dry-active waste, resins, filter media, metallic and non-metallic components generated in decommissioning), site security and emergency programs, and industrial safety.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 5 of 14 2.1.2 Period 2 - Decommissioning Operations This period includes the physical decommissioning activities associated with the removal and disposal of contaminated and activated components and structures, including the successful amendment of the 10 CFR §50 operating license (releasing the site, exclusive of the ISFSI).

Significant decommissioning activities in this phase include:

Construction of temporary facilities and/or modification of existing facilities to support dismantling activities. This may include a centralized processing area to facilitate equipment removal and component preparations for off-site disposal.

Reconfiguration and modification of site structures and facilities as needed to support decommissioning operations. This may include the upgrading of roads (on and off site) to facilitate hauling and transport. Modifications may be required to the containment structure to facilitate access of large/heavy equipment. Modifications may also be required to the refueling area of the reactor building to support the segmentation of the reactor vessel internals and component extraction.

Design and fabrication of temporary and permanent shielding to support removal and transportation activities, construction of contamination control envelopes, and the procurement of specialty tooling.

Procurement (lease or purchase) of shipping canisters, cask liners, and industrial packages.

Decontamination of components and piping systems as required to control (minimize) worker exposure.

Removal of piping and components no longer essential to support decommissioning operations.

Transfer of the steam separator and dryer assemblies to the dryer-separator pool for segmentation. Segmentation by weight and activity maximizes the loading of the shielded transport casks. The operations are conducted under water using remotely-operated tooling and contamination controls.

Disconnection of the control blades from the drives on the vessel lower head. Blades are transferred to the spent fuel pool for packaging.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 6 of 14 Disassembly, segmentation, and packaging of the core shroud and in-core guide tubes. Some of the material is expected to exceed Class C disposal requirements. As such, those segments are packaged in modified fuel storage canisters for geologic disposal.

Removal and segmentation of the remaining internals, fuel support castings, and core plate assembly.

Draining and decontamination of the reactor well and the permanent sealing of the spent fuel transfer gate. Installation of a shielded platform for segmentation of the reactor vessel. Cutting operations are performed in air using remotely operated equipment within a contamination control envelope, with the water level maintained just below the cut to minimize the working area dose rates. Sections are transferred to the dryer-separator pool for packaging and interim storage.

Disconnection of the control rod drives and instrumentation tubes from reactor vessel lower head. The lower reactor head and vessel support skirt are then segmented.

Removal of the reactor recirculation pumps. Exterior surfaces are decontaminated and openings covered. Components can serve as their own burial containers provided that all penetrations are properly sealed.

Demolition of the sacrificial shield activated concrete by controlled demolition.

At least two years prior to the anticipated date of license termination, an LTP is required. Submitted as a supplement to the Final Safety Analysis Report (FSAR) or its equivalent, the plan must include: a site characterization, description of the remaining dismantling activities, plans for site remediation, procedures for the final radiation survey, designation of the end use of the site, an updated cost estimate to complete the decommissioning, and any associated environmental concerns. The NRC will notice the receipt of the plan, make the plan available for public comment, and schedule a local meeting. LTP approval will be subject to any conditions and limitations as deemed appropriate by the Commission. The licensee may then commence with the final remediation of site facilities and services, including:

Removal of remaining plant systems and associated components as they become nonessential to the decommissioning program or worker TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 7 of 14 health and safety (e.g., waste collection and treatment systems, electrical power and ventilation systems).

Removal of the steel liners from the drywell, disposing of the activated and contaminated sections as radioactive waste. Removal of any activated/contaminated concrete.

Removal of the steel liners from the steam separator and dryer pool, reactor well and spent fuel storage pool.

Surveys of the decontaminated areas of the containment structures.

Removal of the contaminated equipment and material from the turbine and radwaste buildings, and any other contaminated facility.

Use radiation and contamination control techniques until radiation surveys indicate that the structures can be released for unrestricted access and conventional demolition. This activity may necessitate the dismantling and disposition of most of the systems and components (both clean and contaminated) located within these buildings. This activity will facilitate surface decontamination and subsequent verification surveys required prior to obtaining release for demolition.

Removal of the remaining components, equipment, and plant services in support of the area release survey(s).

Routing of material removed in the decontamination and dismantling to a central processing area. Material certified to be free of contamination is released for unrestricted disposition, e.g., as scrap, recycle, or general disposal. Contaminated material is characterized and segregated for additional off-site processing (disassembly, chemical cleaning, volume reduction, and waste treatment), and/or packaged for controlled disposal at a low-level radioactive waste disposal facility.

Incorporated into the LTP is the Final Survey Plan. This plan identifies the radiological surveys to be performed once the decontamination activities are completed and is developed using the guidance provided in the Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM).[21] This document incorporates the statistical approaches to survey design and data interpretation used by the EPA. It also identifies commercially available instrumentation and procedures for conducting radiological surveys. Use of this guidance ensures that the surveys are conducted in a manner that provides a high degree of confidence that applicable NRC criteria are satisfied. Once the survey is TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 8 of 14 complete, the results are provided to the NRC in a format that can be verified. The NRC then reviews and evaluates the information, performs an independent confirmation of radiological site conditions, and makes a determination on the requested change to the operating license (that would release the property, exclusive of the ISFSI, for unrestricted use).

The NRC will amend the operating license if it determines that site remediation has been performed in accordance with the LTP, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release.

2.1.3 Period 3 - Site Restoration Following completion of decommissioning operations, site restoration activities will begin. Efficient removal of the contaminated materials and verification that residual radionuclide concentrations are below the NRC limits will result in substantial damage to many of the structures.

Although performed in a controlled and safe manner, blasting, coring, drilling, scarification (surface removal), and the other decontamination activities will substantially degrade power block structures including the reactor, turbine and radwaste buildings. Under certain circumstances, verifying that subsurface radionuclide concentrations meet NRC site release requirements will require removal of grade slabs and lower floors, potentially weakening footings and structural supports.

This removal activity will be necessary for those facilities and plant areas where historical records, when available, indicate the potential for radionuclides having been present in the soil, where system failures have been recorded, or where it is required to confirm that subsurface process and drain lines were not breached over the operating life of the station.

Prompt dismantling of site structures is likely the most appropriate and cost-effective option. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures with a work force already mobilized on site is more efficient than if the process were deferred. Site facilities quickly degrade without maintenance, adding additional expense and creating potential hazards to the public as well as to future workers. Abandonment creates a breeding ground for vermin infestation as well as other biological hazards.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 9 of 14 This cost study presumes that non-essential structures and site facilities are dismantled as a continuation of the decommissioning activity.

Foundations and exterior walls are removed to a nominal depth of three feet below grade. The three-foot depth allows for the placement of gravel for drainage, as well as topsoil, so that vegetation can be established for erosion control. Site areas affected by the dismantling activities are restored and the plant area graded as required to prevent ponding and inhibit the refloating of subsurface materials.

Concrete rubble produced by demolition activities is processed to remove rebar and miscellaneous embedments. The processed material is then used on site to backfill voids. Excess materials are trucked to an off-site area for disposal as construction debris.

2.1.4 ISFSI Operations and Decommissioning The ISFSI will continue to operate under a general license (10 CFR §50) following the amendment of the operating license to release the adjacent (power block) property. Assuming the DOE starts accepting fuel from Oyster Creek in 2034, transfer of spent fuel from the ISFSI is anticipated to continue through the year 2036.

At the conclusion of the spent fuel transfer process, the ISFSI will be decommissioned. The existing design for the ISFSI is based upon the use of a multi-purpose canister and a concrete horizontal module for pad storage. For purposes of this cost analysis, it is assumed that the concrete and steel in several of the modules will have low levels of neutron activation. These modules will be designated for controlled disposal. The remaining modules will be dismantled using conventional techniques for the demolition of reinforced concrete. The concrete storage pad will then be removed, and the area graded and landscaped to conform to the surrounding environment.

The NRC will terminate the §50 license when it determines that the remediation of the ISFSI has been performed in accordance with an ISFSI license termination plan and that the final radiation survey and associated documentation demonstrate that the facility is suitable for release. Once the requirements are satisfied, the NRC can terminate the license for the ISFSI.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 10 of 14 2.2 SAFSTOR AND DELAYED DECOMMISSIONING The NRC defines SAFSTOR as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use." The facility is left intact (during the dormancy period), with structures maintained in a sound condition. Systems not required to operate in support of the spent fuel pool or site surveillance and security are drained, de-energized, and secured. Minimal cleaning/removal of loose contamination and/or fixation and sealing of remaining contamination are performed. Access to contaminated areas is secured to provide controlled access for inspection and maintenance.

The engineering and planning requirements are similar to those for the DECON alternative, although a shorter time period is expected for these activities due to the more limited work scope. Site preparations are also similar to those for the DECON alternative. However, with the exception of the required radiation surveys and site characterizations, the mobilization and preparation of site facilities is less extensive.

The following discussion is appropriate for both the SAFSTOR and Delayed DECON scenarios, the primary differences being in the storage methods for the spent fuel and the length of the dormancy period. Spent fuel is continued to be stored in the wet storage pool for the Delayed DECON scenario until such time that the transfer to a DOE facility can be completed, i.e., the ISFSI is not used to offload the pool. Decommissioning operations are assumed to begin once the transfer is complete. By contrast, all of the fuel remaining in the storage pool after the minimum required cooling period is relocated to the ISFSI in the SAFSTOR scenario and the pool emptied. The nuclear unit remains in storage after fuel transfer operations are completed, with decommissioning operations initiated such that the license is terminated within the required 60-year time period. In both scenarios, the spent fuel is transferred from the ISFSI to the DOE between the years 2034 and 2036.

2.2.1 Period 1 - Preparations Preparations for long-term storage include the planning for permanent defueling of the reactor, revision of technical specifications appropriate to the operating conditions and requirements, a characterization of the facility and major components, and the development of the PSDAR.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 11 of 14 The process of placing the plant in safe-storage includes, but is not limited to, the following activities:

Isolation of the spent fuel storage services and fuel handling systems located in the reactor building so that safe-storage operations may commence on the balance of the plant. This activity may be carried out by plant personnel in accordance with existing operating technical specifications. Activities are scheduled around the fuel handling systems to the greatest extent possible.

Draining and de-energizing of the non-contaminated systems not required to support continued site operations or maintenance.

Disposing of contaminated filter elements and resin beds not required for processing wastes from layup activities for future operations.

Draining of the reactor vessel, with the internals left in place and the vessel head secured.

Draining and de-energizing non-essential, contaminated systems with decontamination as required for future maintenance and inspection.

Preparing lighting and alarm systems whose continued use is required; de-energizing portions of fire protection, electric power, and HVAC systems whose continued use is not required.

Cleaning of the loose surface contamination from building access pathways.

Performing an interim radiation survey of plant, posting warning signs where appropriate.

Erecting physical barriers and/or securing all access to radioactive or contaminated areas, except as required for inspection and maintenance.

Installing security and surveillance monitoring equipment and relocating security fence around secured structures, as required.

2.2.2 Period 2 - Dormancy The second phase identified by the NRC in its rule addresses licensed activities during a storage period and is applicable to the dormancy phases of the deferred decommissioning alternatives. Dormancy activities include a 24-hour security force, preventive and corrective TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 12 of 14 maintenance on security systems, area lighting, general building maintenance, heating and ventilation of buildings, routine radiological inspections of contaminated structures, maintenance of structural integrity, and a site environmental and radiation monitoring program.

Resident maintenance personnel perform equipment maintenance, inspection activities, routine services to maintain safe conditions, adequate lighting, heating, and ventilation, and periodic preventive maintenance on essential site services.

An environmental surveillance program is carried out during the dormancy period to ensure that releases of radioactive material to the environment are prevented and/or detected and controlled. Appropriate emergency procedures are established and initiated for potential releases that exceed prescribed limits. The environmental surveillance program constitutes an abbreviated version of the program in effect during normal plant operations.

Security during the dormancy period is conducted primarily to prevent unauthorized entry and to protect the public from the consequences of their own actions. The security fence, sensors, alarms, and other surveillance equipment provide security. Fire and radiation alarms are also monitored and maintained. While remote surveillance is an option, it does not offer the immediate response time of a physical presence.

The transfer of the spent fuel to a DOE facility continues during this period until complete.

After an optional period of storage (such that license terminations are accomplished within 60 years of final shutdown), it is required that the licensee submit applications to terminate the license, along with an LTP (described in Section 2.1.2), thereby initiating the third phase.

2.2.3 Periods 3 and 4 - Delayed Decommissioning Prior to the commencement of decommissioning operations, preparations are undertaken to reactivate site services and prepare for decommissioning. Preparations include engineering and planning, a detailed site characterization, and the assembly of a decommissioning management organization. Final planning for activities and the writing of activity specifications and detailed procedures are also initiated at this time.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 13 of 14 Much of the work in developing a termination plan is relevant to the development of the detailed engineering plans and procedures. The activities associated with this phase and the follow-on decontamination and dismantling processes are detailed in Sections 2.1.1 and 2.1.2. The primary difference between the sequences anticipated for the DECON and deferred scenarios is the absence, in the latter, of any constraint on the availability of the fuel storage facilities located within the reactor building for decommissioning.

Variations in the length of the dormancy period are expected to have little effect upon the quantities of radioactive wastes generated from system and structure removal operations. Given the levels of radioactivity and spectrum of radionuclides expected from fifty years of plant operation, no plant process system identified as being contaminated upon final shutdown will become releasable due to the decay period alone, i.e., there is no significant reduction in the waste generated from the decommissioning activities. However, due to the lower activity levels, a greater percentage of the waste volume can be designated for off-site processing and recovery.

The delay in decommissioning also yields lower working area radiation levels. As such, the estimates for the delayed scenarios incorporate reduced ALARA controls for the lower occupational exposure potential.

Although the initial radiation levels due to 60Co will decrease during the dormancy period, the internal components of the reactor vessel will still exhibit sufficiently high radiation dose rates to require remote sectioning under water due to the presence of long-lived radionuclides such as 94Nb, 59Ni, and 63Ni. Therefore, the dismantling procedures described for the DECON alternative would still be employed during SAFSTOR scenario. Portions of the sacrificial shield will still be radioactive due to the presence of activated trace elements with long half-lives (152Eu and 154Eu). Decontamination will require controlled removal and disposal. It is assumed that radioactive corrosion products on inner surfaces of piping and components will not have decayed to levels that will permit unrestricted use or allow conventional removal.

These systems and components will be surveyed as they are removed and disposed of in accordance with the existing radioactive release criteria.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 2, Page 14 of 14 2.2.4 Period 5 - Site Restoration Following completion of decommissioning operations, site-restoration activities can begin. If the site structures are to be dismantled, dismantling as a continuation of the decommissioning process is clearly the most appropriate and cost-effective option, as described in Section 2.1.3. The basis for the dismantling cost in the SAFSTOR scenario is consistent with that described for DECON, presuming the removal of structures and site facilities to a nominal depth of three feet below grade and the limited restoration of the site.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 1 of 21

3. COST ESTIMATE The cost estimates prepared for decommissioning Oyster Creek consider the unique features of the site, including the NSSS, power generation systems, support services, site buildings, and ancillary facilities. The basis of the estimates, including the sources of information relied upon, the estimating methodology employed, site-specific considerations, and other pertinent assumptions, is described in this section.

3.1 BASIS OF ESTIMATE The estimates were developed with site-specific, technical information developed in an evaluation prepared for Exelon in 2008-09. The information was reviewed for the current analysis and updated as deemed appropriate.

The site-specific considerations and assumptions used in the previous evaluation were also revisited. Modifications were incorporated where new information was available or experience from ongoing decommissioning programs provided viable alternatives or improved processes.

3.2 METHODOLOGY The methodology used to develop the estimates follows the basic approach originally presented in the AIF/NESP-036 study report, "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates,"[22] and the DOE "Decommissioning Handbook."[23] These documents present a unit factor method for estimating decommissioning activity costs, which simplifies the estimating calculations. Unit factors for concrete removal ($/cubic yard), steel removal ($/ton), and cutting costs ($/inch) were developed using local labor rates. The activity-dependent costs were estimated with the item quantities (cubic yards and tons), developed from plant drawings and inventory documents. Removal rates and material costs for the conventional disposition of components and structures relied upon information available in the industry publication, "Building Construction Cost Data," published by R.S. Means.[24]

This analysis reflects lessons learned from TLGs involvement in the Shippingport Station Decommissioning Project, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells, and associated facilities, completed in 1997. In addition, the planning and engineering for the Pathfinder, Shoreham, Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Oyster Creek, Connecticut Yankee, and San TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 2 of 21 Onofre-1 nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.

The unit factor method provides a demonstrable basis for establishing reliable cost estimates. The detail provided in the unit factors, including activity duration, labor costs (by craft), and equipment and consumable costs, ensures that essential elements have not been omitted. Appendix A presents the detailed development of a typical unit factor. Appendix B provides the values contained within one set of factors developed for this analysis.

Work Difficulty Factors WDFs were assigned to each area, commensurate with the inefficiencies associated with working in confined, hazardous environments. The ranges used for the WDFs are as follows:

Access Factor 0% to 50%

Respiratory Protection Factor 0% to 25%

Radiation/ALARA Factor 0% to 100%

Protective Clothing Factor 0% to 50%

Work Break Factor 8.33%

These factors and their associated range of values were developed in conjunction with the Atomic Industrial Forums Guideline Study. The factors (and their suggested application) are discussed in more detail in Appendix F.

Scheduling Program Durations The unit factors, adjusted by the WDFs as described above, are applied against the inventory of materials to be removed in the radiologically controlled areas.

The resulting man-hours, or crew-hours, are used in the development of the decommissioning program schedule, using resource loading and event sequencing considerations. The scheduling of conventional removal and dismantling activities are based upon productivity information available from the "Building Construction Cost Data" publication.

An area-by-area activity duration critical path was used to develop the total decommissioning program schedule. The unit cost factors, adjusted for WDFs as described above, were applied against the inventory of materials to be removed in each defined work area. Each work area was assessed for the most efficient number of workers/crews for the decommissioning activities. These TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 3 of 21 adjusted unit cost factors were applied against the available manpower so that an overall duration for removal of components and piping from each work area could be calculated. Work area identification is consistent with the Survey Tracking Number (STN) system utilized by GPUs radiological services group in the 1997 timeframe. An index of the GPU STNs is provided in Appendix G.

The program schedule is used to determine the period-dependent costs for program management, administration, field engineering, equipment rental, contracted services, etc. The study relies upon regional or site-specific salary and wage rates for the personnel associated with the intended program.

3.3 FINANCIAL COMPONENTS OF THE COST MODEL TLGs proprietary decommissioning cost model, DECCER, produces a number of distinct cost elements. These direct expenditures, however, do not comprise the total cost to accomplish the project goal, i.e., license termination and site restoration.

Inherent in any cost estimate that does not rely on historical data is the inability to specify the precise source of costs imposed by factors such as tool breakage, accidents, illnesses, weather delays, and labor stoppages. In the DECCER cost model, contingency fulfills this role. Contingency is added to each line item to account for costs that are difficult or impossible to develop analytically. Such costs are historically inevitable over the duration of a job of this magnitude; therefore, this cost analysis includes funds to cover these types of expenses.

3.3.1 Contingency The activity- and period-dependent costs are combined to develop the total decommissioning cost. A contingency is then applied on a line-item basis, using one or more of the contingency types listed in the AIF/NESP-036 study. "Contingencies" are defined in the American Association of Cost Engineers Project and Cost Engineers' Handbook[25]

as "specific provision for unforeseeable elements of cost within the defined project scope; particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur." The cost elements in this analysis are based upon ideal conditions and maximum efficiency; therefore, consistent with industry practice, a contingency factor has been applied. In the AIF/NESP-036 study, the types of unforeseeable events that are likely to occur in decommissioning are discussed and TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 4 of 21 guidelines are provided for percentage contingency in each category. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.

The use and role of contingency within decommissioning estimates is not a safety factor issue. Safety factors provide additional security and address situations that may never occur. Contingency funds are expected to be fully expended throughout the program. They also provide assurance that sufficient funding is available to accomplish the intended tasks. An estimate without contingency, or from which contingency has been removed, can disrupt the orderly progression of events and jeopardize a successful conclusion to the decommissioning process.

For example, the most technologically challenging task in decommissioning a commercial nuclear station is the disposition of the reactor vessel and internal components, now highly radioactive after a lifetime of exposure to core activity. The disposition of these components forms the basis of the critical path (schedule) for decommissioning operations. Cost and schedule are interdependent, and any deviation in schedule has a significant impact on cost for performing a specific activity.

Disposition of the reactor vessel internals involves the underwater cutting of complex components that are highly radioactive. Costs are based upon optimum segmentation, handling, and packaging scenarios.

The schedule is primarily dependent upon the turnaround time for the heavily shielded shipping casks, including preparation, loading, and decontamination of the containers for transport. The number of casks required is a function of the pieces generated in the segmentation activity, a value calculated on optimum performance of the tooling employed in cutting the various subassemblies. The expected optimization, however, may not be achieved, resulting in delays and additional program costs. For this reason, contingency must be included to mitigate the consequences of the expected inefficiencies inherent in this complex activity, along with related concerns associated with the operation of highly specialized tooling, field conditions, and water clarity.

Contingency funds are an integral part of the total cost to complete the decommissioning process. Exclusion of this component puts at risk a TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 5 of 21 successful completion of the intended tasks and, potentially, subsequent related activities. For this study, TLG examined the major activity-related problems (decontamination, segmentation, equipment handling, packaging, transport, and waste disposal) that necessitate a contingency. Individual activity contingencies ranged from 10% to 75%,

depending on the degree of difficulty judged to be appropriate from TLGs actual decommissioning experience. The contingency values used in this study are as follows:

Decontamination 50%

Contaminated Component Removal 25%

Contaminated Component Packaging 10%

Contaminated Component Transport 15%

Low-Level Radioactive Waste Disposal 25%

Reactor Segmentation 75%

NSSS Component Removal 25%

Reactor Waste Packaging 25%

Reactor Waste Transport 25%

Reactor Vessel Component Disposal 50%

GTCC Disposal 15%

Non-Radioactive Component Removal 15%

Heavy Equipment and Tooling 15%

Supplies 25%

Engineering 15%

Energy 15%

Characterization and Termination Surveys 30%

Construction 15%

Taxes and Fees 10%

Insurance 10%

Staffing 15%

Spent Fuel Storage (Dry) Modules 15%

Spent Fuel Transfer Costs 15%

Operations and Maintenance Expenses 15%

The contingency values are applied to the appropriate components of the estimates on a line-item basis. A composite value is then reported at the end of each estimate. For example, the composite contingency value TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 6 of 21 reported for the DECON alternative is 18.3%. Values for the other alternatives are delineated within their respective detailed cost tables in Appendices D and E.

3.3.2 Financial Risk In addition to the routine uncertainties addressed by contingency, another cost element that is sometimes necessary to consider when bounding decommissioning costs relates to uncertainty, or risk.

Examples can include changes in work scope, pricing, job performance, and other variations that could conceivably, but not necessarily, occur.

Consideration is sometimes necessary to generate a level of confidence in the estimate, within a range of probabilities. TLG considers these types of costs under the broad term financial risk. Included within the category of financial risk are:

Transition activities and costs: ancillary expenses associated with eliminating 50% to 80% of the site labor force shortly after the cessation of plant operations, added cost for worker separation packages throughout the decommissioning program, national or company-mandated retraining, and retention incentives for key personnel.

Delays in approval of the decommissioning plan due to intervention, public participation in local community meetings, legal challenges, and national and local hearings.

Changes in the project work scope from the baseline estimate, involving the discovery of unexpected levels of contaminants, contamination in places not previously expected, contaminated soil previously undiscovered (either radioactive or hazardous material contamination), variations in plant inventory or configuration not indicated by the as-built drawings.

Regulatory changes (e.g., affecting worker health and safety, site release criteria, waste transportation, and disposal).

Policy decisions altering national commitments (e.g., in the ability to accommodate certain waste forms for disposition or in the timetable for such, for example, in the start and rate of acceptance of spent fuel by the DOE).

Pricing changes for basic inputs, such as labor, energy, materials, and burial.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 7 of 21 This cost study, however, does not add any additional cost to the estimate for financial risk since there is insufficient historical data from which to project future liabilities. Consequently, the areas of uncertainty or risk are revisited periodically and addressed through repeated revisions or updates of the base estimate.

3.4 SITE-SPECIFIC CONSIDERATIONS There are a number of site-specific considerations that affect the method for dismantling and removal of equipment from the site and the degree of restoration required. The cost impacts of the considerations identified below are included in this cost study.

3.4.1 Spent Fuel Management The cost to dispose of spent fuel generated from plant operations is not reflected within the estimates to decommission the Oyster Creek site.

Ultimate disposition of the spent fuel is within the province of the DOEs Waste Management System, as defined by the NWPA. As such, the disposal cost is financed by a 1 mill/kWhr surcharge paid into the DOEs waste fund during operations. However, the NRC requires licensees to establish a program to manage and provide funding for the management of all irradiated fuel at the reactors until title of the fuel is transferred to the Secretary of Energy. This funding requirement is fulfilled through inclusion of certain high-level waste cost elements within the estimate, as described below.

The total inventory of assemblies that will require handling during decommissioning is based upon several assumptions. The pickup of commercial fuel is assumed to begin in the year 2025. The maximum rate at which the fuel is removed from the commercial sites is based upon an annual capacity at the geologic repository of 3,000 metric tons of uranium (MTU). Any delay in the startup of the repository or decrease in the rate of acceptance will correspondingly prolong the transfer process and result in the fuel remaining at the site longer.

In all three scenarios, the existing ISFSI will continue to operate for the fifteen years following final shutdown. Assuming that the DOE commences repository operation in 2025, all fuel is projected to be removed from the Oyster Creek site by the year 2036.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 8 of 21 Operation and maintenance costs for the storage facilities are included within the estimates and address the cost for staffing the facilities, as well as security, insurance, and licensing fees. Costs are also provided for the final disposition of the facilities once the transfer is complete.

Repository Startup Operation of the DOEs yet-to-be constructed geologic repository is contingent upon the review and approval of the facilitys license application by the NRC, the successful resolution of pending litigation, and the development of a national transportation system. With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that could result in an interim storage facility being available by 2025.

Spent Fuel Management Model The Exelon nuclear fleet consists of 26 units at 14 sites in Illinois, Pennsylvania, New Jersey, New York and Maryland, including the inactive units at Dresden, Peach Bottom and Zion (Zion is still included in the spent fuel analysis model since the fuel transfer to DOE will be done as part of the Exelon allocation). The ability to complete the decommissioning of these units, particularly for the DECON and Delayed DECON alternatives, is highly dependent upon when the DOE is assumed to remove spent fuel from the sites.

The DOE's repository program assumes that spent fuel will be accepted for disposal from the nation's commercial nuclear plants in the order (the "queue") in which it was removed from service ("oldest fuel first"). A computer model developed by Exelon Nuclear was used to determine when the DOE would provide allocations in the queue for removal of spent fuel from the individual sites. Repository operations were based upon annual industry-wide receipt of 400 Metric Tons Heavy Metal (MTHM) in the first year of operation, a total of 3,800 MTHM in years 2 through 4 and 3,000 MTHM for year 5 and beyond.[26]

ISFSIs are constructed as necessary to maintain full-core discharge capability at the individual sites. Once the DOE begins repository operations, spent fuel shipments are managed across the fleet to optimize spent fuel storage.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 9 of 21 Canister Design The design and capacity of future cask acquisitions for the ISFSI is based upon the NUHOMS system, with a 61-fuel assembly capacity.

The DOE is assumed to provide the MPC for fuel transferred directly from the pool to the DOE at no cost to the owner.

Canister Loading and Transfer The cost for the labor to load/transport the spent fuel from the pool to the ISFSI pad is based upon Exelon experience. For estimating purposes, 50% of this cost is used to estimate the cost to transfer the fuel from the ISFSI to the DOE.

Operations and Maintenance Annual costs (excluding labor) of approximately $763,000 and $90,000 are used for operation and maintenance of the spent fuel pool and the ISFSI, respectively.

ISFSI Design Considerations A multi-purpose (storage and transport) dry shielded storage canister with a horizontal, reinforced concrete storage module is used as a basis for the cost analysis. The final core off load, equivalent to 10 modules, is assumed to have some level of neutron-induced activation as a result of the long-term storage of the fuel (i.e., to levels exceeding free-release limits). The ten modules are disposed of at a licensed facility. The cost of the disposition of this material, as well as the demolition of the ISFSI facility, is included in the estimate.

3.4.2 Reactor Vessel and Internal Components The NSSS (reactor vessel and reactor recirculation system components) will be decontaminated using chemical agents prior to the start of cutting operations (for DECON alternative only). A decontamination factor (average reduction) of 10 is assumed for the process.

The reactor pressure vessel and internal components are segmented for disposal in shielded, reusable transportation casks. Segmentation is performed in the dryer-separator pool, where a turntable and remote cutter are installed. The vessel is segmented in place, using a mast-TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 10 of 21 mounted cutter supported off the lower head and directed from a shielded work platform installed overhead in the reactor cavity.

Transportation cask specifications and transportation regulations will dictate segmentation and packaging methodology.

The dismantling of the reactor internals will generate radioactive waste considered unsuitable for shallow land disposal (i.e., GTCC). Although the material is not classified as high-level waste, the DOE has indicated it will accept this waste for disposal at the future high-level waste repository.[27] However, the DOE has not been forthcoming with an acceptance criteria or disposition schedule for this material, and numerous questions remain as to the ultimate disposal cost and waste form requirements. As such, for purposes of this study, the GTCC has been packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel. It is not anticipated that the DOE would accept this waste prior to completing the transfer of spent fuel.

Therefore, until such time the DOE is ready to accept GTCC waste, it is reasonable to assume that this material would remain in storage at the Oyster Creek site.

Intact disposal of the reactor vessel and internal components can provide savings in cost and worker exposure by eliminating the complex segmentation requirements, isolation of the GTCC material, and transport/storage of the resulting waste packages. Portland General Electric (PGE) was able to dispose of the Trojan reactor as an intact package. However, its location on the Columbia River simplified the transportation analysis since:

the reactor package could be secured to the transport vehicle for the entire journey, i.e., the package was not lifted during transport, there were no man-made or natural terrain features between the plant site and the disposal location that could produce a large drop, and transport speeds were very low, limited by the overland transport vehicle and the river barge.

As a member of the Northwest Compact, PGE had a site available for disposal of the package - the US Ecology facility in Washington State.

The characteristics of this arid site proved favorable in demonstrating compliance with land disposal regulations.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 11 of 21 It is not known whether this option will be available when Oyster Creek ceases operation. Future viability of this option will depend upon the ultimate location of the disposal site, as well as the disposal site licensees ability to accept highly radioactive packages and effectively isolate them from the environment. Additionally, with BWRs, the diameter of the reactor vessel may severely limit overland transport.

Consequently, the study assumes the reactor vessel will require segmentation, as a bounding condition.

3.4.3 Primary System Components Reactor recirculation piping is cut from the reactor vessel once the water level in the vessel (used for personnel shielding during dismantling and cutting operations in and around the vessel) is dropped below the nozzle zone. The piping is boxed and transported by shielded van. The reactor recirculation pumps and motors are lifted out intact, packaged, and transported for processing and/or disposal.

3.4.4 Main Turbine and Condenser The main turbine will be dismantled using conventional maintenance procedures. The turbine rotors and shafts will be removed to a laydown area. The lower turbine casings will be removed from their anchors by controlled demolition. The main condensers will also be disassembled and moved to a laydown area. Material is then prepared for transportation to an off-site recycling facility where it will be surveyed and designated for either decontamination or volume reduction, conventional disposal, or controlled disposal. Components will be packaged and readied for transport in accordance with the intended disposition.

3.4.5 Transportation Methods Contaminated piping, components, and structural material other than the highly activated reactor vessel and internal components will qualify as LSA-I, II or III or Surface Contaminated Object, SCO-I or II, as described in Title 49.[28] The contaminated material will be packaged in Industrial Packages (IP-1, IP-2, or IP-3, as defined in subpart 173.411) for transport unless demonstrated to qualify as their own shipping containers. The reactor vessel and internal components are expected to be transported as Type B, in accordance with §71. It is conceivable that the reactor, due to its limited specific activity, could qualify as LSA-II or TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 12 of 21 III. However, the high radiation levels on the outer surface would require that additional shielding be incorporated within the packaging so as to attenuate the dose to levels acceptable for transport.

Transport of the highly activated metal, produced in the segmentation of the reactor vessels and internal components, will be by shielded truck cask. Cask shipments may exceed 95,000 pounds, including vessel segment(s), supplementary shielding, cask tie-downs, and tractor-trailer. The maximum level of activity per shipment assumed permissible was based upon the license limits of the available shielded transport casks. The segmentation scheme for the vessel and internal segments is designed to meet these limits.

The transport of large intact components (e.g., large heat exchangers and other oversized components) will be by a combination of truck, rail, and/or multi-wheeled transporter. Truck transport costs were estimated using published tariffs from Tri-State Motor Transit.[29]

3.4.6 Low-Level Radioactive Waste Disposal To the greatest extent practical, metallic material generated in the decontamination and dismantling processes is treated to reduce the total volume requiring controlled disposal. The treated material, meeting the regulatory and/or site release criterion, is released as scrap, requiring no further cost consideration. Conditioning and recovery of the waste stream is performed off site at a licensed processing center.

The mass of radioactive waste generated during the various decommissioning activities is reported by line item in Appendices C, D and E, and summarized in Section 5. The Section 5 waste summaries are consistent with 10 CFR §61 classifications. Commercially available steel containers are used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations. The waste volumes are calculated on the exterior package dimensions for containerized material or a dimensional calculation for components serving as their own waste containers.

The more highly activated reactor components are transported in reusable, shielded truck casks with disposable liners. In calculating disposal costs, the burial fees are applied against the liner volume, with surcharges added for the special handling requirements and the TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 13 of 21 radiological characteristics of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste), where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.

Disposal fees are calculated using current disposal agreements, with surcharges added for the highly activated components, for example, generated in the segmentation of the reactor vessel. The majority of the material generated from the decontamination and dismantling activities (approximately 94% for the DECON alternative) is Class A waste. The disposal cost for this material is based upon Exelons current agreement with EnergySolutions for its disposal facility in Clive, Utah. Another 5%

of the total volume (also Class A) is assumed to be sent to the Barnwell facility.

Since the EnergySolutions facility is not able to accept the higher activity waste (Class B and C) generated in the decontamination of the reactor vessel and segmentation of the components closest to the core, the cost of disposal of this material (approximately 1% of the total volume) was based upon Exelons rates for the Barnwell facility.

Material exceeding Class C limits (limited to material closest to the reactor core and comprising less than 0.4% of the total waste volume) is generally not suitable for shallow-land disposal. This material is packaged in the same multipurpose canisters used for spent fuel storage/transport.

3.4.7 Site Conditions Following Decommissioning The NRC will terminate (or amend) the site license when it determines that site remediation has been performed in accordance with the license termination plan, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release. The NRCs involvement in the decommissioning process will end at this point. Building codes and environmental regulations will dictate the next step in the decommissioning process, as well as the owners own future plans for the site.

Non-essential structures or buildings severely damaged in decontamination process are removed to a nominal depth of three feet below grade. Concrete rubble generated from demolition activities is processed and made available as clean fill. The excavations will be TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 14 of 21 regraded such that the power block area will have a final contour consistent with adjacent surroundings.

The estimates include the remediation of contaminated soil. This assumption may be affected by continued plant operations and/or future regulatory actions, such as the development of site-specific release criteria.

3.5 ASSUMPTIONS The following are the major assumptions made in the development of the estimates for decommissioning the site.

3.5.1 Estimating Basis The study follows the principles of ALARA through the use of work duration adjustment factors. These factors address the impact of activities such as radiological protection instruction, mock-up training, and the use of respiratory protection and protective clothing. The factors lengthen a task's duration, increasing costs and lengthening the overall schedule. ALARA planning is considered in the costs for engineering and planning, and in the development of activity specifications and detailed procedures. Changes to worker exposure limits may impact the decommissioning cost and project schedule.

3.5.2 Labor Costs The craft labor required to decontaminate and dismantle the nuclear unit will be acquired through standard site contracting practices. The current cost of labor at the site is used as an estimating basis. Costs for site administration, operations, construction, and maintenance personnel are based upon average salary information provided by Exelon or from comparable industry information.

Exelon will hire a Decommissioning Operations Contractor (DOC) to manage the decommissioning. The owner will provide site security, radiological health and safety, quality assurance and overall site administration during the decommissioning and demolition phases.

Contract personnel will provide engineering services (e.g., for preparing the activity specifications, work procedures, activation, and structural analyses) under the direction of Exelon.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 15 of 21 3.5.3 Design Conditions Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 137Cs, 90Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major NSSS components to be shipped under current transportation regulations and disposal requirements.

The curie contents of the vessel and internals at final shutdown are derived from those listed in NUREG/CR-3474.[30] Actual estimates are derived from the curie/gram values contained therein and adjusted for the different mass of the Oyster Creek components, projected operating life, and different periods of decay. Additional short-lived isotopes were derived from NUREG/CR-0130[31] and NUREG/CR-0672,[32] and benchmarked to the long-lived values from NUREG/CR-3474.

The disposal cost for the control blades removed from the vessel with the final core load is included within the estimates. Control blade residence time in the reactor is assumed to be controlled such that the blades do not become GTCC material. Disposition of any blades stored in the pool from operations is considered an operating expense and therefore not accounted for in the estimates.

Activation of the reactor building structure is confined to the sacrificial shield. More extensive activation (at very low levels) of the interior structures within containment has been detected at several reactors and their owners have elected to dispose of the affected material at a controlled facility rather than reuse the material as fill on site or send it to a landfill. The ultimate disposition of the material removed from the reactor building will depend upon the site release criteria selected, as well as the designated end use for the site.

3.5.4 General Transition Activities Existing warehouses will be cleared of non-essential material and remain for use by Exelon and its subcontractors. The plants operating staff will perform the following activities at no additional cost or credit to the project during the transition period:

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 16 of 21 Drain and collect fuel oils, lubricating oils, and transformer oils for recycle and/or sale.

Drain and collect acids, caustics, and other chemical stores for recycle and/or sale.

Processes operating waste inventories, i.e., the estimates do not address the disposition of any legacy wastes; the disposal of operating wastes during this initial period is not considered a decommissioning expense.

Scrap and Salvage The existing plant equipment is considered obsolete and suitable for scrap as deadweight quantities only. Exelon will make economically reasonable efforts to salvage equipment following final plant shutdown.

However, dismantling techniques assumed by TLG for equipment in this analysis are not consistent with removal techniques required for salvage (resale) of equipment. Experience has indicated that some buyers wanted equipment stripped down to very specific requirements before they would consider purchase. This required expensive rework after the equipment had been removed from its installed location. Since placing a salvage value on this machinery and equipment would be speculative, and the value would be small in comparison to the overall decommissioning expenses, this analysis does not attempt to quantify the possible salvage value that an owner may realize based upon those efforts.

It is assumed, for purposes of this analysis, that any value received from the sale of scrap generated in the dismantling process would be more than offset by the on-site processing costs. The dismantling techniques assumed in the decommissioning estimates do not include the additional cost for size reduction and preparation to meet furnace ready conditions. For example, the recovery of copper from electrical cabling may require the removal and disposition of any contaminated insulation, an added expense. With a volatile market, the potential profit margin in scrap recovery is highly speculative, regardless of the ability to free release this material. This assumption is an implicit recognition of scrap value in the disposal of clean metallic waste at no additional cost to the project.

Furniture, tools, mobile equipment such as forklifts, trucks, bulldozers, and other property will be removed at no cost or credit to the TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 17 of 21 decommissioning project. Disposition may include relocation to other facilities. Spare parts will also be made available for alternative use.

Energy For estimating purposes, the plant is assumed to be de-energized, with the exception of those facilities associated with spent fuel storage.

Replacement power costs are used for the cost of energy consumption during decommissioning for tooling, lighting, ventilation, and essential services.

Insurance Costs for continuing coverage (nuclear liability and property insurance) following cessation of plant operations and during decommissioning are included and based upon current operating premiums. Reductions in premiums throughout the decommissioning process are based upon guidance provided by Exelon.

Taxes Property taxes are included for all decommissioning periods. Exelon provided a schedule estimate of decreasing tax payments against the current tax assessment. These reductions continue until reaching a minimum property tax payment of $1,000,000 per year; this level is maintained for the balance of the decommissioning program.

Site Modifications The perimeter fence and in-plant security barriers will be moved, as appropriate, to conform to the Site Security Plan in force during the various stages of the project.

3.6 COST ESTIMATE

SUMMARY

A schedule of expenditures for each scenario is provided in Tables 3.1 through 3.3. Decommissioning costs are reported in the year of projected expenditure; however, the values are provided in thousands of 2011 dollars. Costs are not inflated, escalated, or discounted over the period of expenditure. The annual expenditures are based upon the detailed activity costs reported in Appendices C through E, along with the schedules discussed in Section 4.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 18 of 21 TABLE 3.1 SCHEDULE OF ANNUAL EXPENDITURES DECON (thousands, 2011 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total 2019 183 31 6 0 33 253 2020 67,261 11,335 2,224 171 12,325 93,317 2021 91,003 33,530 3,257 23,107 23,596 174,493 2022 72,012 28,519 1,990 19,168 10,341 132,031 2023 65,797 16,924 1,654 7,004 6,212 97,590 2024 65,977 16,970 1,659 7,023 6,229 97,858 2025 56,731 12,363 1,265 7,231 5,923 83,514 2026 43,173 4,761 654 3,612 4,295 56,495 2027 30,669 8,697 273 8 2,576 42,222 2028 23,269 8,525 174 0 2,380 34,348 2029 4,961 0 0 0 2,160 7,121 2030 4,961 0 0 0 2,160 7,121 2031 4,961 0 0 0 2,160 7,121 2032 4,974 0 0 0 2,166 7,140 2033 4,961 0 0 0 2,160 7,121 2034 5,104 431 0 0 2,160 7,696 2035 6,254 3,881 0 0 2,160 12,296 2036 6,268 4,431 0 0 7,270 17,970 2037 5,205 1,423 0 1,745 3,699 12,072 2038 823 318 0 239 553 1,933 Total 564,548 152,139 13,156 69,307 100,560 899,710 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 19 of 21 TABLE 3.2 SCHEDULE OF ANNUAL EXPENDITURES DELAYED DECON (thousands, 2011 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total 2019 145 3 6 0 14 169 2020 53,387 1,323 2,212 61 5,558 62,541 2021 39,896 5,087 1,311 1,431 17,624 65,349 2022 14,347 421 441 16 3,444 18,670 2023 14,347 421 441 16 3,444 18,670 2024 14,386 422 442 16 3,454 18,721 2025 14,347 421 441 16 3,444 18,670 2026 14,347 421 441 16 3,444 18,670 2027 14,347 421 441 16 3,444 18,670 2028 14,386 422 442 16 3,454 18,721 2029 14,347 421 441 16 3,444 18,670 2030 14,347 421 441 16 3,444 18,670 2031 14,347 421 441 16 3,444 18,670 2032 14,386 422 442 16 3,454 18,721 2033 14,347 421 441 16 3,444 18,670 2034 14,635 1,284 441 16 3,444 19,820 2035 16,935 8,184 441 16 3,444 29,020 2036 10,376 5,185 282 10 2,853 18,706 2037 43,703 1,677 2,206 62 2,405 50,053 2038 72,058 20,567 2,151 12,377 9,501 116,654 2039 64,149 18,163 1,928 15,255 10,942 110,437 2040 69,899 11,292 1,659 14,964 8,065 105,878 2041 37,097 4,114 528 1,497 2,750 45,986 2042 24,040 10,850 221 0 1,466 36,576 2043 9,748 4,399 89 0 594 14,831 Total 628,351 97,188 18,772 45,886 110,021 900,219 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 20 of 21 TABLE 3.3 SCHEDULE OF ANNUAL EXPENDITURES SAFSTOR (thousands, 2011 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total 2019 154 29 6 0 31 220 2020 56,552 10,816 2,212 61 11,522 81,162 2021 43,052 14,555 1,311 1,431 17,909 78,258 2022 17,503 9,889 441 16 4,006 31,856 2023 17,503 9,889 441 16 4,006 31,856 2024 17,551 9,916 442 16 4,017 31,943 2025 12,065 5,054 330 12 3,244 20,704 2026 6,716 297 221 8 2,494 9,735 2027 6,716 297 221 8 2,494 9,735 2028 6,734 298 221 8 2,500 9,762 2029 6,716 297 221 8 2,494 9,735 2030 6,716 297 221 8 2,494 9,735 2031 6,716 297 221 8 2,494 9,735 2032 6,734 298 221 8 2,500 9,762 2033 6,716 297 221 8 2,494 9,735 2034 6,859 729 221 8 2,494 10,310 2035 8,009 4,179 221 8 2,494 14,910 2036 8,020 4,180 221 8 2,500 14,928 2037 3,809 291 221 7 2,314 6,641 2038 3,809 291 221 7 2,314 6,641 2039 3,809 291 221 7 2,314 6,641 2040 3,819 291 221 7 2,321 6,660 2041 3,809 291 221 7 2,314 6,641 2042 3,809 291 221 7 2,314 6,641 2043 3,809 291 221 7 2,314 6,641 2044 3,819 291 221 7 2,321 6,660 2045 3,809 291 221 7 2,314 6,641 2046 3,809 291 221 7 2,314 6,641 2047 3,809 291 221 7 2,314 6,641 2048 3,819 291 221 7 2,321 6,660 2049 3,809 291 221 7 2,314 6,641 2050 3,809 291 221 7 2,314 6,641 2051 3,809 291 221 7 2,314 6,641 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 3, Page 21 of 21 TABLE 3.3 (continued)

SCHEDULE OF ANNUAL EXPENDITURES SAFSTOR (thousands, 2011 dollars)

Equipment &

Year Labor Materials Energy Burial Other Total 2052 3,819 291 221 7 2,321 6,660 2053 3,809 291 221 7 2,314 6,641 2054 3,809 291 221 7 2,314 6,641 2055 3,809 291 221 7 2,314 6,641 2056 3,819 291 221 7 2,321 6,660 2057 3,809 291 221 7 2,314 6,641 2058 3,809 291 221 7 2,314 6,641 2059 3,809 291 221 7 2,314 6,641 2060 3,819 291 221 7 2,321 6,660 2061 3,809 291 221 7 2,314 6,641 2062 3,809 291 221 7 2,314 6,641 2063 3,809 291 221 7 2,314 6,641 2064 3,819 291 221 7 2,321 6,660 2065 3,809 291 221 7 2,314 6,641 2066 3,809 291 221 7 2,314 6,641 2067 3,809 291 221 7 2,314 6,641 2068 3,819 291 221 7 2,321 6,660 2069 3,809 291 221 7 2,314 6,641 2070 3,809 291 221 7 2,314 6,641 2071 3,809 291 221 7 2,314 6,641 2072 3,819 291 221 7 2,321 6,660 2073 3,809 291 221 7 2,314 6,641 2074 3,809 291 221 7 2,314 6,641 2075 30,732 1,197 1,564 27 2,369 35,889 2076 66,971 14,501 2,192 7,539 6,228 97,430 2077 64,064 22,408 1,990 15,841 11,863 116,165 2078 70,697 11,640 1,654 14,860 8,226 107,078 2079 43,969 4,266 736 3,649 3,750 56,370 2080 24,106 10,909 221 0 1,470 36,706 2081 13,173 5,961 121 0 803 20,058 Total 699,563 153,545 24,479 43,832 194,895 1,116,314 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 1 of 7

4. SCHEDULE ESTIMATE The schedules for the decommissioning scenarios considered in this study follow the sequence presented in the AIF/NESP-036 study, with minor changes to reflect recent experience and site-specific constraints. In addition, the scheduling has been revised to reflect the spent fuel management plans described in Section 3.4.1.

A schedule or sequence of activities is presented in Figure 4.1 for the DECON decommissioning alternative. The schedule is also representative of the work activities identified in the delayed dismantling scenarios, absent any spent fuel constraints. The scheduling sequence assumes that fuel is removed from the spent fuel pool within the first five and one-half years after operations cease. The key activities listed in the schedule do not reflect a one-to-one correspondence with those activities in the cost tables, but reflect dividing some activities for clarity and combining others for convenience. The schedule was prepared using the "Microsoft Project 2010" computer software.[33]

4.1 SCHEDULE ESTIMATE ASSUMPTIONS The schedule reflects the results of a precedence network developed for the site decommissioning activities, i.e., a PERT (Program Evaluation and Review Technique) Software Package. The work activity durations used in the precedence network reflect the actual man-hour estimates from the cost tables, adjusted by stretching certain activities over their slack range and shifting the start and end dates of others. The following assumptions were made in the development of the DECON decommissioning schedule:

The reactor building is isolated until such time that all spent fuel has been discharged from the storage pool to the DOE. Decontamination and dismantling of the storage pool is initiated once the transfer of spent fuel to the DOE is complete.

All work (except vessel and internals removal) is performed during an 8-hour workday, 5 days per week, with no overtime. There are eleven paid holidays per year.

Reactor and internals removal activities are performed by using separate crews for different activities working on different shifts, with a corresponding backshift charge for the second shift.

Multiple crews work parallel activities to the maximum extent possible, consistent with optimum efficiency, adequate access for cutting, removal TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 2 of 7 and laydown space, and with the stringent safety measures necessary during demolition of heavy components and structures.

For plant systems removal, the systems with the longest removal durations in areas on the critical path are considered to determine the duration of the activity.

4.2 PROJECT SCHEDULE The period-dependent costs presented in the detailed cost tables are based upon the durations developed in the schedule for decommissioning Oyster Creek. Durations are established between several milestones in each project period; these durations are used to establish a critical path for the entire project. In turn, the critical path duration for each period is used as the basis for determining the period-dependent costs. A second critical path is also shown for the spent fuel cooling period, which determines the release of the reactor building for final decontamination.

Project timelines are provided in Figures 4.2 through 4.4; the milestone dates are based on this same shutdown date. The start of decommissioning activities in the Delayed Decommissioning scenario is concurrent with the end of the fuel transfer activity (i.e., to an off-site DOE facility).

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 3 of 7 FIGURE 4.1 DECON ACTIVITY SCHEDULE TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 4 of 7 FIGURE 4.1 DECON ACTIVITY SCHEDULE (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 5 of 7 FIGURE 4.2 DECOMMISSIONING TIMELINE DECON (not to scale)

DECON (Shutdown December 31, 2019)

Pool and ISFSI Operations ISFSI Operations Period 1 Period 3 Transition and Period 2 Site ISFSI ISFSI Preparations Decommissioning Restoration Operations D&D 12/2019 07/2021 03/2027 10/2028 12/2036 03/2038 Spent Fuel Pool Empty 06/2025 ISFSI Empty TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 6 of 7 FIGURE 4.3 DECOMMISSIONING TIMELINE DELAYED DECON (not to scale)

Delayed DECON (Shutdown December 31, 2019)

Spent Fuel Storage Period 1 Period 3 Period 5 Transition and Period 2 Delayed Period 4 Site Preparations Dormancy Preparations Decommissioning Restoration 12/2019 06/2021 12/2036 07/2038 11/2041 05/2043 Spent Fuel Pool and ISFSI Empty TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 4, Page 7 of 7 FIGURE 4.4 DECOMMISSIONING TIMELINE SAFSTOR (not to scale)

SAFSTOR (Shutdown December 31, 2019)

Spent Fuel Storage Period 1 Period 3 Period 5 Transition and Period 2 Delayed Period 4 Site Preparations Dormancy Preparations Decommissioning Restoration 12/2019 06/2021 04/2075 10/2076 12/2079 07/2081 Spent Fuel Pool and ISFSI Empty 12/2036 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002 Rev. 4 Decommissioning Cost Analysis Section 5, Page 1 of 5

5. RADIOACTIVE WASTES The objectives of the decommissioning process are the removal of all radioactive material from the site that would restrict its future use and the termination of the NRC license(s). This currently requires the remediation of all radioactive material at the site in excess of applicable legal limits. Under the Atomic Energy Act,[34] the NRC is responsible for protecting the public from sources of ionizing radiation. Title 10 of the Code of Federal Regulations delineates the production, utilization, and disposal of radioactive materials and processes. In particular, §71 defines radioactive material as it pertains to packaging and transportation and §61 specifies its disposition.

Most of the materials being transported for controlled burial are categorized as Low Specific Activity (LSA) or Surface Contaminated Object (SCO) materials containing Type A quantities, as defined in 49 CFR §173-178. Shipping containers are required to be Industrial Packages (IP-1, IP-2 or IP-3, as defined in subpart 173.411). For this study, commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations.

The volumes of radioactive waste generated during the various decommissioning activities at the site is shown on a line-item basis in Appendices C, D, and E and summarized in Tables 5.1 through 5.3. The quantified waste volume summaries shown in these tables are consistent with §61 classifications. The volumes are calculated based on the exterior dimensions for containerized material and on the displaced volume of components serving as their own waste containers.

The reactor vessel and internals are categorized as large quantity shipments and, accordingly, will be shipped in reusable, shielded truck casks with disposable liners.

In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste),

where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.

No process system containing/handling radioactive substances at shutdown is presumed to meet material release criteria by decay alone, i.e., systems radioactive at shutdown will still be radioactive over the time period during which the decommissioning is accomplished, due to the presence of long-lived radionuclides.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002 Rev. 4 Decommissioning Cost Analysis Section 5, Page 2 of 5 While the dose rates decrease with time, radionuclides such as 137Cs will still control the disposition requirements.

The waste material generated in the decontamination and dismantling of Oyster Creek is primarily generated during Period 2 of the DECON alternative and Period 4 of the deferred alternatives. Material that is considered potentially contaminated when removed from the radiologically controlled area is sent to processing facilities in Tennessee for conditioning and disposal. Heavily contaminated components and activated materials are routed for controlled disposal. The disposal volumes reported in the tables reflect the savings resulting from reprocessing and recycling.

Disposal fees are calculated using current disposal agreements, with surcharges added for the highly activated components, for example, generated in the segmentation of the reactor vessel. The majority of the material generated from the decontamination and dismantling activities (approximately 94% for the DECON alternative) is Class A waste. The disposal cost for this material is based upon Exelons current agreement with EnergySolutions for its disposal facility in Clive, Utah. Another 5% of the total volume (also Class A) is assumed to be sent to the Barnwell facility.

Since the EnergySolutions facility is not able to accept the higher activity waste (Class B and C) generated in the decontamination of the reactor vessel and segmentation of the components closest to the core, the cost of disposal of this material (approximately 1% of the total volume) was based upon Exelons rates for the Barnwell facility.

A small quantity of material will be generated during the Oyster Creek decommissioning will not be considered suitable for near-surface disposal, and is assumed to be disposed of in a geologic repository, in a manner similar to that envisioned for spent fuel disposal. Such material, known as Greater-Than-Class-C or GTCC material, is estimated to require five spent fuel storage canisters (or the equivalent) to dispose of the most radioactive portions of the reactor vessel internals. The volume and weight reported in Tables 5.1 through 5.3 represent the packaged weight and volume of the spent fuel storage canisters.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002 Rev. 4 Decommissioning Cost Analysis Section 5, Page 3 of 5 TABLE 5.1 DECOMMISSIONING WASTE

SUMMARY

DECON Waste Volume Weight Class1 (cubic feet) (pounds)

Low-Level Radioactive Waste EnergySolutions (Clive, Utah)

Containerized A 123,335 6,922,273 Bulk A 262,559 20,911,740 Atlantic Compact (Barnwell, S.C.) A 21,081 2,114,319 B 2,413 274,227 C 918 61,980 Geologic Repository (Greater-than-Class C) >C 1,428 282,300 Total 411,735 30,566,839 Processed Waste (off-site) 401,427 17,169,570 Scrap Metal 48,668,000 1 Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55 2 Columns may not add due to rounding.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002 Rev. 4 Decommissioning Cost Analysis Section 5, Page 4 of 5 TABLE 5.2 DECOMMISSIONING WASTE

SUMMARY

DELAYED DECON Waste Volume Weight Class1 (cubic feet) (pounds)

Low-Level Radioactive Waste EnergySolutions (Clive, Utah)

Containerized A 50,941 2,824,673 Bulk A 241,514 19,067,090 Atlantic Compact (Barnwell, S.C.) A 20,169 1,948,021 B 1,002 109,390 C 470 53,730 Geologic Repository (Greater-than-Class C) >C 1,428 282,300 Total 315,523 24,285,204 Processed Waste (off-site) 470,429 19,975,460 Scrap Metal 48,584,000 1 Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55 2 Columns may not add due to rounding.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002 Rev. 4 Decommissioning Cost Analysis Section 5, Page 5 of 5 TABLE 5.3 DECOMMISSIONING WASTE

SUMMARY

SAFSTOR Waste Volume Weight Class1 (cubic feet) (pounds)

Low-Level Radioactive Waste EnergySolutions (Clive, Utah)

Containerized A 50,414 2,735,513 Bulk A 243,889 19,114,590 Atlantic Compact (Barnwell, S.C.) A 20,686 1,936,101 B 1,127 121,830 C 344 41,290 Geologic Repository (Greater-than-Class C) >C 1,428 282,300 Total 317,889 24,231,624 Processed Waste (off-site) 470,956 20,064,620 Scrap Metal 48,584,000 1 Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55 2 Columns may not add due to rounding.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 1 of 6

6. RESULTS The analysis to estimate the costs to decommission Oyster Creek relied upon the site-specific, technical information developed for a previous analysis prepared in 2008-09. While not an engineering study, the estimates provide Exelon with sufficient information to assess their financial obligations, as they pertain to the eventual decommissioning of the nuclear station.

The estimates described in this report are based on numerous fundamental assumptions, including regulatory requirements, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements. The decommissioning scenarios assume continued operation of the plants spent fuel pool for a minimum of five and one-half years following the cessation of operations for continued cooling of the assemblies.

The spent fuel is removed from the site within fifteen years of final shutdown.

The cost projected to promptly decommission (DECON) Oyster Creek is estimated to be $899.7 million. The majority of this cost (approximately 74.0%) is associated with the physical decontamination and dismantling of the nuclear unit so that the license can be terminated. Another 19.7% is associated with the management, interim storage, and eventual transfer of the spent fuel. The remaining 6.3% is for the demolition of the designated structures and limited restoration of the site.

The primary cost contributors, identified in Tables 6.1 through 6.3, are either labor-related or associated with the management and disposition of the radioactive waste.

Program management is the largest single contributor to the overall cost. The magnitude of the expense is a function of both the size of the organization required to manage the decommissioning, as well as the duration of the program. It is assumed, for purposes of this analysis, that Exelon will oversee the decommissioning program, using a DOC to manage the decommissioning labor force and the associated subcontractors. The size and composition of the management organization varies with the decommissioning phase and associated site activities.

However, once the operating license is terminated, the staff is substantially reduced for the conventional demolition and restoration of the site.

As described in this report, the spent fuel pool will remain operational for approximately five and one-half years following the cessation of operations (DECON alternative). The pool will be isolated and an independent spent fuel island created.

This will allow decommissioning operations to proceed in and around the pool area.

Within this approximately five and one-half-year period, the spent fuel will be transferred to the ISFSI.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 2 of 6 The cost for waste disposal includes only those costs associated with the controlled disposition of the low-level radioactive waste generated from decontamination and dismantling activities, including plant equipment and components, structural material, filters, resins and dry-active waste. As described in Section 5, disposal of the majority of the radioactive material is at EnergySolutions facility in Clive, Utah or some alternative facility. Highly activated components, requiring additional isolation from the environment, are packaged for geologic disposal. Disposal of these components is based upon a cost equivalent for spent fuel.

A significant portion of the metallic waste is designated for additional processing and treatment at an off-site facility. Processing reduces the volume of material requiring controlled disposal through such techniques and processes as survey and sorting, decontamination, and volume reduction. The material that cannot be unconditionally released is packaged for controlled disposal at one of the currently operating facilities. The cost identified in the summary table for processing is all-inclusive, incorporating the ultimate disposition of the material.

Removal costs reflect the labor-intensive nature of the decommissioning process, as well as the management controls required to ensure a safe and successful program.

Decontamination and packaging costs also have a large labor component that is based upon labor cost data supplied by Exelon. Non-radiological demolition is a natural extension of the decommissioning process. The methods employed in decontamination and dismantling are generally destructive and indiscriminate in inflicting collateral damage. With a work force mobilized to support decommissioning operations, non-radiological demolition can be an integrated activity and a logical expansion of the work being performed in the process of terminating the operating license. Prompt demolition reduces future liabilities and can be more cost effective than deferral, due to the deterioration of the facilities (and therefore the working conditions) with time.

The reported cost for transport includes the tariffs and surcharges associated with moving large components and/or overweight shielded casks overland, as well as the general expense, e.g., labor and fuel, of transporting material to the destinations identified in this report. For purposes of this analysis, material is primarily moved overland by truck.

Decontamination is used to reduce the plants radiation fields and minimize worker exposure. Slightly contaminated material or material located within a contaminated area is sent to an off-site processing center, i.e., this analysis does not assume that contaminated plant components and equipment can be decontaminated for uncontrolled release in-situ. Centralized processing centers have proven to be a TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 3 of 6 more economical means of handling the large volumes of material produced in the dismantling of a nuclear unit.

License termination survey costs are associated with the labor intensive and complex activity of verifying that contamination has been removed from the site to the levels specified by the regulating agency. This process involves a systematic survey of all remaining plant surface areas and surrounding environs, sampling, isotopic analysis, and documentation of the findings. The status of any plant components and materials not removed in the decommissioning process will also require confirmation and will add to the expense of surveying the facilities alone.

The remaining costs include allocations for heavy equipment and temporary services, as well as for other expenses such as regulatory fees and the premiums for nuclear insurance. While site operating costs are greatly reduced following the final cessation of plant operations, certain administrative functions do need to be maintained either at a basic functional or regulatory level.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 4 of 6 TABLE 6.1

SUMMARY

OF DECOMMISSIONING COST ELEMENTS DECON (thousands of 2011 dollars)

Cost Element Cost Percentage Decontamination 22,297 2.5%

Removal 148,522 16.5%

Packaging 22,786 2.5%

Transportation 17,598 2.0%

Waste Disposal 64,400 7.2%

Off-site Waste Processing 10,024 1.1%

Program Management [1] 417,042 46.4%

Spent Fuel Pool Isolation 11,822 1.3%

Spent Fuel - Direct Expenditures [2] 100,110 11.1%

Insurance and Regulatory Fees 20,929 2.3%

Energy 13,156 1.5%

Characterization and Licensing Surveys 19,885 2.2%

Property Taxes 21,212 2.4%

Miscellaneous Equipment 6,800 0.8%

Site O&M 3,127 0.3%

Total [3] 899,710 100.0%

Cost Element Cost Percentage License Termination 665,975 74.0%

Spent Fuel Management 177,146 19.7%

Site Restoration 56,589 6.3%

Total [3] 899,710 100.0%

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 5 of 6 TABLE 6.2

SUMMARY

OF DECOMMISSIONING COST ELEMENTS DELAYED DECON (thousands of 2011 dollars)

Cost Element Cost Percentage Decontamination 23,573 2.6%

Removal 134,505 14.9%

Packaging 17,207 1.9%

Transportation 13,288 1.5%

Waste Disposal 39,463 4.4%

Off-site Waste Processing 11,541 1.3%

Program Management [1] 501,758 55.7%

Spent Fuel Pool Isolation 11,822 1.3%

Spent Fuel - Direct Expenditures [2] 37,454 4.2%

Insurance and Regulatory Fees 25,123 2.8%

Energy 18,772 2.1%

Characterization and Licensing Surveys 21,402 2.4%

Property Taxes 25,586 2.8%

Miscellaneous Equipment 10,399 1.2%

Site O&M 8,327 0.9%

Total [3] 900,219 100.0%

Cost Element Cost Percentage License Termination 541,703 60.2%

Spent Fuel Management 299,125 33.2%

Site Restoration 59,390 6.6%

Total [3] 900,219 100.0%

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 6, Page 6 of 6 TABLE 6.3

SUMMARY

OF DECOMMISSIONING COST ELEMENTS SAFSTOR (thousands of 2011 dollars)

Cost Element Cost Percentage Decontamination 23,321 2.1%

Removal 137,788 12.3%

Packaging 16,136 1.4%

Transportation 11,848 1.1%

Waste Disposal 37,361 3.3%

Off-site Waste Processing 11,589 1.0%

Program Management [1] 556,588 49.9%

Spent Fuel Pool Isolation 11,822 1.1%

Spent Fuel - Direct Expenditures [2] 96,744 8.7%

Insurance and Regulatory Fees 57,478 5.1%

Energy 24,479 2.2%

Characterization and Licensing Surveys 21,402 1.9%

Property Taxes 68,922 6.2%

Miscellaneous Equipment 18,942 1.7%

Site O&M 21,895 2.0%

Total [3] 1,116,314 100.0%

Cost Element Cost Percentage License Termination 873,828 78.3%

Spent Fuel Management 183,117 16.4%

Site Restoration 59,369 5.3%

Total [3] 1,116,314 100.0%

[1] Includes engineering and security costs

[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/transfer/spent fuel pool O&M and EP fees

[3] Columns may not add due to rounding TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 7, Page 1 of 3

7. REFERENCES 1 Decommissioning Cost Analysis for the Oyster Creek Nuclear Generating Station, Document No. E16-1555-010, Rev. 1, TLG Services, Inc., March 2009
2. U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988
3. U.S. Nuclear Regulatory Commission, Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors," October 2003
4. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, Radiological Criteria for License Termination
5. U.S. Code of Federal Regulations, Title 10, Parts 20 and 50, Entombment Options for Power Reactors, Advanced Notice of Proposed Rulemaking, Federal Register Volume 66, Number 200, October 16, 2001
6. U.S. Code of Federal Regulations, Title 10, Parts 2, 50 and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61 (p 39278 et seq.), July 29, 1996
7. Nuclear Waste Policy Act of 1982, 42 U.S. Code 10101, et seq.

http://pbadupws.nrc.gov/docs/ML1327/ML13274A489.pdf#page=419

8. Blue Ribbon Commission on Americas Nuclear Future Charter, http://cybercemetery.unt.edu/archive/brc/20120620215336/http://brc.gov/index.p hp?q=page/charter
9. Blue Ribbon Commission on Americas Nuclear Future, Report to the Secretary of Energy, http://www.brc.gov/sites/default/files/documents

/brc_finalreport_jan2012.pdf, p. 32, January 2012

10. Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste, U.S. DOE, January 11, 2013 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 7, Page 2 of 3

7. REFERENCES (continued)
11. United States Court of Appeals for the District of Columbia Circuit, In Re:

Aiken County, Et Al., August 2013, http://www.cadc.uscourts.gov/internet/opinions.nsf/BAE0CF34F762EBD9852 57BC6004DEB18/$file/11-1271-1451347.pdf

12. U.S. Code of Federal Regulations, Title 10, Part 961.11, Article IV -

Responsibilities of the Parties, B. DOE Responsibilities, 5.(a) DOE shall issue an annual acceptance priority ranking for receipt of SNF and/or HLW at the DOE repository. This priority ranking shall be based on the age of SNF and/or HLW as calculated from the date of discharge of such materials from the civilian nuclear power reactor. The oldest fuel or waste will have the highest priority for acceptance

13. U.S. Code of Federal Regulations, Title 10, Part 72, Subpart K, General License for Storage of Spent Fuel at Power Reactor Sites
14. Low-Level Radioactive Waste Policy, Public Law 96-573, 1980
15. Low-Level Radioactive Waste Policy Amendments Act of 1985, Public Law 99-240, January 15, 1986
16. U.S. Code of Federal Regulations, Title 10, Part 61, Licensing Requirements for Land Disposal of Radioactive Waste
17. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, Radiological Criteria for License Termination, Federal Register, Volume 62, Number 139 (p 39058 et seq.), July 21, 1997
18. Establishment of Cleanup Levels for CERCLA Sites with Radioactive Contamination, EPA Memorandum OSWER No. 9200.4-18, August 22, 1997
19. U.S. Code of Federal Regulations, Title 40, Part 141.16, Maximum contaminant levels for beta particle and photon radioactivity from man-made radionuclides in community water systems TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 7, Page 3 of 3

7. REFERENCES (continued)
20. Memorandum of Understanding Between the Environmental Protection Agency and the Nuclear Regulatory Commission: Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites, OSWER 9295.8-06a, October 9, 2002
21. Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM),

NUREG/CR-1575, Rev. 1, EPA 402-R-97-016, Rev. 1, August 2000

22. T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986
23. W.J. Manion and T.S. LaGuardia, "Decommissioning Handbook," U.S.

Department of Energy, DOE/EV/10128-1, November 1980

24. "Building Construction Cost Data 2011," Robert Snow Means Company, Inc.,

Kingston, Massachusetts

25. Project and Cost Engineers Handbook, Second Edition, p. 239, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, 1984
26. Civilian Radioactive Waste Management System Waste Acceptance System Requirements Document, Revision 5, ICN01 (DOE/RW-0351) effective March 10, 2008
27. "Strategy for Management and Disposal of Greater-Than-Class C Low-Level Radioactive Waste, Federal Register Volume 60, Number 48 (p 13424 et seq.),

March 1995

28. U.S. Department of Transportation, Title 49 of the Code of Federal Regulations, "Transportation," Parts 173 through 178, 1996
29. Tri-State Motor Transit Company, published tariffs, Interstate Commerce Commission (ICC), Docket No. MC-427719 Rules Tariff, March 2004, Radioactive Materials Tariff, February 2011 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Section 7, Page 4 of 3

7. REFERENCES (continued)
30. J.C. Evans et al., "Long-Lived Activation Products in Reactor Materials" NUREG/CR-3474, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. August 1984
31. R.I. Smith, G.J. Konzek, W.E. Kennedy, Jr., "Technology, Safety and Costs of Decommissioning a Reference Pressurized Water Reactor Power Station,"

NUREG/CR-0130 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1978

32. H.D. Oak, et al., "Technology, Safety and Costs of Decommissioning a Reference Boiling Water Reactor Power Station," NUREG/CR-0672 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1980
33. "Microsoft Project 2010," Microsoft Corporation, Redmond, WA, 2003
34. Atomic Energy Act of 1954, (68 Stat. 919)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix A, Page 1 of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix A, Page 2 of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT Example: Unit Factor for Removal of Contaminated Heat Exchanger < 3,000 lbs.

1. SCOPE Heat exchangers weighing < 3,000 lbs. will be removed in one piece using a crane or small hoist. They will be disconnected from the inlet and outlet piping. The heat exchanger will be sent to the waste processing area.
2. CALCULATIONS Activity Critical Act Activity Duration Duration ID Description (minutes) (minutes)*

a Remove insulation 60 (b) b Mount pipe cutters 60 60 c Install contamination controls 20 (b) d Disconnect inlet and outlet lines 60 60 e Cap openings 20 (d) f Rig for removal 30 30 g Unbolt from mounts 30 30 h Remove contamination controls 15 15 i Remove, wrap, send to waste processing area 60 60 Totals (Activity/Critical) 355 255 Duration adjustment(s):

+ Respiratory protection adjustment (25% of critical duration) 64

+ Radiation/ALARA adjustment (30% of critical duration) 77 Adjusted work duration 396

+ Protective clothing adjustment (30% of adjusted duration) 119 Productive work duration 515

+ Work break adjustment (8.33 % of productive duration) 43 Total work duration (minutes) 558

      • Total duration = 9.300 hr ***
  • Alpha designators indicate activities that can be performed in parallel TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix A, Page 3 of 4 APPENDIX A (Continued)

3. LABOR REQUIRED Duration Rate Crew Number (Hours) ($/hr) Cost Laborers 3.00 9.300 50.59 1,411.46 Craftsmen 2.00 9.300 72.91 1,356.13 Foreman 1.00 9.300 77.72 722.80 General Foreman 0.25 9.300 83.77 194.77 Fire Watch 0.05 9.300 50.59 23.52 Health Physics Technician 1.00 9.300 56.70 527.31 Total labor cost $4,235.99
4. EQUIPMENT & CONSUMABLES COSTS Equipment Costs none Consumables/Materials Costs Blotting paper 50 @ $0.58/sq ft [1] $29.00 Tarpaulin, oil resistant, fire retardant 50 @ $0.43/sq ft [2] $21.50 Gas torch consumables 1 @ $11.07 x 1 /hr [3] $11.07 Subtotal cost of equipment and materials $61.57 Overhead & profit on equipment and materials @ 17.00 % $10.47 Total costs, equipment & material $72.04 TOTAL COST:

Removal of contaminated heat exchanger <3000 pounds: $4,308.03 Total labor cost: $4,235.99 Total equipment/material costs: $72.04 Total craft labor man-hours required per unit: 67.89 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix A, Page 4 of 4

5. NOTES AND REFERENCES Work difficulty factors were developed in conjunction with the Atomic Industrial Forums (now NEI) program to standardize nuclear decommissioning cost estimates and are delineated in Volume 1, Chapter 5 of the Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.

References for equipment & consumables costs:

1. www.mcmaster.com online catalog, McMaster Carr Spill Control (7193T88)
2. R.S. Means (2011) Division 01 56, Section 13.60-0600, page 20
3. R.S. Means (2011) Division 01 54 33, Section 40-6360, page 664 Material and consumable costs were adjusted using the regional indices for Forked River, New Jersey.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 1 of 7 APPENDIX B UNIT COST FACTOR LISTING (DECON: Power Block Structures Only)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 2 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Removal of clean instrument and sampling tubing, $/linear foot 0.58 Removal of clean pipe 0.25 to 2 inches diameter, $/linear foot 6.04 Removal of clean pipe >2 to 4 inches diameter, $/linear foot 8.74 Removal of clean pipe >4 to 8 inches diameter, $/linear foot 17.42 Removal of clean pipe >8 to 14 inches diameter, $/linear foot 33.29 Removal of clean pipe >14 to 20 inches diameter, $/linear foot 43.19 Removal of clean pipe >20 to 36 inches diameter, $/linear foot 63.57 Removal of clean pipe >36 inches diameter, $/linear foot 75.57 Removal of clean valve >2 to 4 inches 115.38 Removal of clean valve >4 to 8 inches 174.18 Removal of clean valve >8 to 14 inches 332.93 Removal of clean valve >14 to 20 inches 431.87 Removal of clean valve >20 to 36 inches 635.66 Removal of clean valve >36 inches 755.68 Removal of clean pipe hanger for small bore piping 36.93 Removal of clean pipe hanger for large bore piping 132.67 Removal of clean pump, <300 pound 291.70 Removal of clean pump, 300-1000 pound 820.63 Removal of clean pump, 1000-10,000 pound 3,242.22 Removal of clean pump, >10,000 pound 6,262.89 Removal of clean pump motor, 300-1000 pound 345.82 Removal of clean pump motor, 1000-10,000 pound 1,351.36 Removal of clean pump motor, >10,000 pound 3,040.55 Removal of clean heat exchanger <3000 pound 1,740.87 Removal of clean heat exchanger >3000 pound 4,371.81 Removal of clean feedwater heater/deaerator 12,325.01 Removal of clean moisture separator/reheater 25,340.92 Removal of clean tank, <300 gallons 375.45 Removal of clean tank, 300-3000 gallon 1,187.89 Removal of clean tank, >3000 gallons, $/square foot surface area 10.04 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 3 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Removal of clean electrical equipment, <300 pound 160.20 Removal of clean electrical equipment, 300-1000 pound 563.03 Removal of clean electrical equipment, 1000-10,000 pound 1,126.06 Removal of clean electrical equipment, >10,000 pound 2,696.17 Removal of clean electrical transformer < 30 tons 1,872.46 Removal of clean electrical transformer > 30 tons 5,392.33 Removal of clean standby diesel generator, <100 kW 1,912.54 Removal of clean standby diesel generator, 100 kW to 1 MW 4,268.93 Removal of clean standby diesel generator, >1 MW 8,837.56 Removal of clean electrical cable tray, $/linear foot 14.90 Removal of clean electrical conduit, $/linear foot 6.50 Removal of clean mechanical equipment, <300 pound 160.20 Removal of clean mechanical equipment, 300-1000 pound 563.03 Removal of clean mechanical equipment, 1000-10,000 pound 1,126.06 Removal of clean mechanical equipment, >10,000 pound 2,696.17 Removal of clean HVAC equipment, <300 pound 193.70 Removal of clean HVAC equipment, 300-1000 pound 676.53 Removal of clean HVAC equipment, 1000-10,000 pound 1,348.30 Removal of clean HVAC equipment, >10,000 pound 2,696.17 Removal of clean HVAC ductwork, $/pound 0.61 Removal of contaminated instrument and sampling tubing, $/linear foot 1.52 Removal of contaminated pipe 0.25 to 2 inches diameter, $/linear foot 22.14 Removal of contaminated pipe >2 to 4 inches diameter, $/linear foot 37.12 Removal of contaminated pipe >4 to 8 inches diameter, $/linear foot 60.02 Removal of contaminated pipe >8 to 14 inches diameter, $/linear foot 115.23 Removal of contaminated pipe >14 to 20 inches diameter, $/linear foot 137.67 Removal of contaminated pipe >20 to 36 inches diameter, $/linear foot 189.97 Removal of contaminated pipe >36 inches diameter, $/linear foot 225.52 Removal of contaminated valve >2 to 4 inches 453.26 Removal of contaminated valve >4 to 8 inches 534.38 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 4 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Removal of contaminated valve >8 to 14 inches 1,093.21 Removal of contaminated valve >14 to 20 inches 1,384.29 Removal of contaminated valve >20 to 36 inches 1,840.57 Removal of contaminated valve >36 inches 2,196.14 Removal of contaminated pipe hanger for small bore piping 143.96 Removal of contaminated pipe hanger for large bore piping 474.77 Removal of contaminated pump, <300 pound 940.71 Removal of contaminated pump, 300-1000 pound 2,195.08 Removal of contaminated pump, 1000-10,000 pound 7,271.71 Removal of contaminated pump, >10,000 pound 17,655.09 Removal of contaminated pump motor, 300-1000 pound 953.80 Removal of contaminated pump motor, 1000-10,000 pound 2,961.81 Removal of contaminated pump motor, >10,000 pound 6,664.50 Removal of contaminated heat exchanger <3000 pound 4,308.03 Removal of contaminated heat exchanger >3000 pound 12,499.36 Removal of contaminated feedwater heater/deaerator 31,262.00 Removal of contaminated moisture separator/reheater 68,239.01 Removal of contaminated tank, <300 gallons 1,566.16 Removal of contaminated tank, >300 gallons, $/square foot 31.54 Removal of contaminated electrical equipment, <300 pound 731.65 Removal of contaminated electrical equipment, 300-1000 pound 1,791.81 Removal of contaminated electrical equipment, 1000-10,000 pound 3,442.77 Removal of contaminated electrical equipment, >10,000 pound 6,950.88 Removal of contaminated electrical cable tray, $/linear foot 35.67 Removal of contaminated electrical conduit, $/linear foot 18.17 Removal of contaminated mechanical equipment, <300 pound 820.17 Removal of contaminated mechanical equipment, 300-1000 pound 2,015.63 Removal of contaminated mechanical equipment, 1000-10,000 pound 3,872.06 Removal of contaminated mechanical equipment, >10,000 pound 6,950.88 Removal of contaminated HVAC equipment, <300 pound 820.17 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 5 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Removal of contaminated HVAC equipment, 300-1000 pound 2,015.63 Removal of contaminated HVAC equipment, 1000-10,000 pound 3,872.06 Removal of contaminated HVAC equipment, >10,000 pound 6,950.88 Removal of contaminated HVAC ductwork, $/pound 2.10 Removal/plasma arc cut of contaminated thin metal components, $/linear in. 4.02 Additional decontamination of surface by washing, $/square foot 8.21 Additional decontamination of surfaces by hydrolasing, $/square foot 37.06 Decontamination rig hook up and flush, $/ 250 foot length 6,904.99 Chemical flush of components/systems, $/gallon 18.43 Removal of clean standard reinforced concrete, $/cubic yard 163.02 Removal of grade slab concrete, $/cubic yard 215.45 Removal of clean concrete floors, $/cubic yard 414.96 Removal of sections of clean concrete floors, $/cubic yard 1,258.40 Removal of clean heavily rein concrete w/#9 rebar, $/cubic yard 270.73 Removal of contaminated heavily rein concrete w/#9 rebar, $/cubic yard 2,113.63 Removal of clean heavily rein concrete w/#18 rebar, $/cubic yard 342.28 Removal of contaminated heavily rein concrete w/#18 rebar, $/cubic yard 2,787.73 Removal heavily rein concrete w/#18 rebar & steel embedments, $/cubic yard 533.01 Removal of below-grade suspended floors, $/cubic yard 414.96 Removal of clean monolithic concrete structures, $/cubic yard 1,054.73 Removal of contaminated monolithic concrete structures, $/cubic yard 2,101.37 Removal of clean foundation concrete, $/cubic yard 826.68 Removal of contaminated foundation concrete, $/cubic yard 1,955.13 Explosive demolition of bulk concrete, $/cubic yard 36.25 Removal of clean hollow masonry block wall, $/cubic yard 107.84 Removal of contaminated hollow masonry block wall, $/cubic yard 299.44 Removal of clean solid masonry block wall, $/cubic yard 107.84 Removal of contaminated solid masonry block wall, $/cubic yard 299.44 Backfill of below-grade voids, $/cubic yard 33.82 Removal of subterranean tunnels/voids, $/linear foot 130.49 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 6 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Placement of concrete for below-grade voids, $/cubic yard 137.69 Excavation of clean material, $/cubic yard 3.67 Excavation of contaminated material, $/cubic yard 39.90 Removal of clean concrete rubble (tipping fee included), $/cubic yard 25.95 Removal of contaminated concrete rubble, $/cubic yard 27.45 Removal of building by volume, $/cubic foot 0.35 Removal of clean building metal siding, $/square foot 1.32 Removal of contaminated building metal siding, $/square foot 3.80 Removal of standard asphalt roofing, $/square foot 2.71 Removal of transite panels, $/square foot 2.51 Scarifying contaminated concrete surfaces (drill & spall), $/square foot 12.37 Scabbling contaminated concrete floors, $/square foot 7.46 Scabbling contaminated concrete walls, $/square foot 20.05 Scabbling contaminated ceilings, $/square foot 68.73 Scabbling structural steel, $/square foot 6.27 Removal of clean overhead crane/monorail < 10 ton capacity 798.67 Removal of contaminated overhead crane/monorail < 10 ton capacity 1,870.00 Removal of clean overhead crane/monorail >10-50 ton capacity 1,916.79 Removal of contaminated overhead crane/monorail >10-50 ton capacity 4,471.00 Removal of polar crane > 50 ton capacity 8,055.49 Removal of gantry crane > 50 ton capacity 33,702.09 Removal of structural steel, $/pound 0.25 Removal of clean steel floor grating, $/square foot 5.75 Removal of contaminated steel floor grating, $/square foot 13.56 Removal of clean free standing steel liner, $/square foot 15.05 Removal of contaminated free standing steel liner, $/square foot 36.48 Removal of clean concrete-anchored steel liner, $/square foot 7.52 Removal of contaminated concrete-anchored steel liner, $/square foot 42.43 Placement of scaffolding in clean areas, $/square foot 18.75 Placement of scaffolding in contaminated areas, $/square foot 27.59 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix B, Page 7 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit Landscaping with topsoil, $/acre 30,563.66 Cost of CPC B-88 LSA box & preparation for use 2,267.67 Cost of CPC B-25 LSA box & preparation for use 2,077.38 Cost of CPC B-12V 12 gauge LSA box & preparation for use 1,691.68 Cost of CPC B-144 LSA box & preparation for use 11,450.82 Cost of LSA drum & preparation for use 219.29 Cost of cask liner for CNSI 8 120A cask (resins) 8,414.66 Cost of cask liner for CNSI 8 120A cask (filters) 8,795.03 Decontamination of surfaces with vacuuming, $/square foot 0.90 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 1 of 16 APPENDIX C DETAILED COST ANALYSIS DECON TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 2 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 1a Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 Prepare preliminary decommissioning cost 156 23 179 179 1,300 1a.1.2 Notification of Cessation of Operations a 1a.1.3 Remove fuel & source material n/a 1a.1.4 Notification of Permanent Defueling a 1a.1.5 Deactivate plant systems & process waste a 1a.1.6 Prepare and submit PSDAR 239 36 275 275 2,000 1a.1.7 Review plant dwgs & specs. 550 83 633 633 4,600 1a.1.8 Perform detailed rad survey a 1a.1.9 Estimate byproduct inventory 120 18 138 138 1,000 1a.1.10 End product description 120 18 138 138 1,000 1a.1.11 Detailed byproduct inventory 156 23 179 179 1,300 1a.1.12 Define major work sequence 897 135 1,032 1,032 7,500 1a.1.13 Perform SER and EA 371 56 427 427 3,100 1a.1.14 Perform SiteSpecific Cost Study 598 90 688 688 5,000 1a.1.15 Prepare/submit License Termination Plan 490 74 564 564 4,096 1a.1.16 Receive NRC approval of termination plan a Activity Specifications 1a.1.17.1 Plant & temporary facilities 589 88 677 609 68 4,920 1a.1.17.2 Plant systems 499 75 573 516 57 4,167 1a.1.17.3 NSSS Decontamination Flush 60 9 69 69 500 1a.1.17.4 Reactor internals 850 127 977 977 7,100 1a.1.17.5 Reactor vessel 778 117 894 894 6,500 1a.1.17.6 Sacrificial shield 60 9 69 69 500 1a.1.17.7 Moisture separators/reheaters 120 18 138 138 1,000 1a.1.17.8 Reinforced concrete 191 29 220 110 110 1,600 1a.1.17.9 Main Turbine 250 37 287 287 2,088 1a.1.17.10 Main Condensers 250 37 287 287 2,088 1a.1.17.11 Pressure suppression structure 239 36 275 275 2,000 1a.1.17.12 Drywell 191 29 220 220 1,600 1a.1.17.13 Plant structures & buildings 373 56 429 215 215 3,120 1a.1.17.14 Waste management 550 83 633 633 4,600 1a.1.17.15 Facility & site closeout 108 16 124 62 62 900 1a.1.17 Total 5,107 766 5,873 5,361 512 42,683 Planning & Site Preparations 1a.1.18 Prepare dismantling sequence 287 43 330 330 2,400 1a.1.19 Plant prep. & temp. svces 2,800 420 3,220 3,220 1a.1.20 Design water cleanup system 168 25 193 193 1,400 1a.1.21 Rigging/Cont. Cntrl Envlps/tooling/etc. 2,200 330 2,530 2,530 1a.1.22 Procure casks/liners & containers 147 22 169 169 1,230 1a.1 Subtotal Period 1a Activity Costs 14,406 2,161 16,566 16,055 512 78,609 Period 1a Additional Costs 1a.2.1 ISFSI Expansion 6,000 900 6,900 6,900 1a.2 Subtotal Period 1a Additional Costs 6,000 900 6,900 6,900 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 3 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,978 1,647 12,624 12,624 1a.3 Subtotal Period 1a Collateral Costs 10,978 1,647 12,624 12,624 Period 1a PeriodDependent Costs 1a.4.1 Insurance 2,227 223 2,450 2,450 1a.4.2 Property taxes 1a.4.3 Health physics supplies 469 117 586 586 1a.4.4 Heavy equipment rental 462 69 531 531 1a.4.5 Disposal of DAW generated 14 10 35 12 70 70 610 12,190 20 1a.4.6 Plant energy budget 1,918 288 2,206 2,206 1a.4.7 NRC Fees 769 77 846 846 1a.4.8 Emergency Planning Fees 564 56 621 621 1a.4.9 Site O&M Costs 309 46 355 355 1a.4.10 Spent Fuel Pool O&M 763 114 878 878 1a.4.11 ISFSI Operating Costs 89 13 103 103 1a.4.12 Security Staff Cost 8,441 1,266 9,707 9,707 157,471 1a.4.13 Utility Staff Cost 33,041 4,956 37,997 37,997 423,400 1a.4 Subtotal Period 1a PeriodDependent Costs 931 14 10 35 48,122 7,238 56,350 54,749 1,601 610 12,190 20 580,871 1a.0 TOTAL PERIOD 1a COST 931 14 10 35 79,506 11,946 92,441 70,804 21,126 512 610 12,190 20 659,480 PERIOD 1b Decommissioning Preparations Period 1b Direct Decommissioning Activities Detailed Work Procedures 1b.1.1.1 Plant systems 566 85 651 586 65 4,733 1b.1.1.2 NSSS Decontamination Flush 120 18 138 138 1,000 1b.1.1.3 Reactor internals 479 72 550 550 4,000 1b.1.1.4 Remaining buildings 162 24 186 46 139 1,350 1b.1.1.5 CRD housings & NIs 120 18 138 138 1,000 1b.1.1.6 Incore instrumentation 120 18 138 138 1,000 1b.1.1.7 Removal primary containment 239 36 275 275 2,000 1b.1.1.8 Reactor vessel 434 65 499 499 3,630 1b.1.1.9 Facility closeout 144 22 165 83 83 1,200 1b.1.1.10 Sacrificial shield 144 22 165 165 1,200 1b.1.1.11 Reinforced concrete 120 18 138 69 69 1,000 1b.1.1.12 Main Turbine 249 37 286 286 2,080 1b.1.1.13 Main Condensers 250 37 287 287 2,088 1b.1.1.14 Moisture separators & reheaters 239 36 275 275 2,000 1b.1.1.15 Radwaste building 327 49 376 338 38 2,730 1b.1.1.16 Reactor building 327 49 376 338 38 2,730 1b.1.1 Total 4,037 606 4,643 4,212 431 33,741 1b.1.2 Decon NSSS 1,105 552 1,657 1,657 1,067 1b.1 Subtotal Period 1b Activity Costs 1,105 4,037 1,158 6,300 5,869 431 1,067 33,741 Period 1b Additional Costs 1b.2.1 Spent fuel pool isolation 10,280 1,542 11,822 11,822 1b.2.2 Site Characterization 4,986 1,496 6,482 6,482 27,140 9,952 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 4 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 1b Additional Costs (continued) 1b.2.3 Disposition of Liquid RCRA Waste (not Lead) 17 529 135 680 680 2,019 115,076 1b.2.4 Disposition of PCB Soil RCRA Waste (not Lead) 1,362 1,450 567 3,378 3,378 27,000 3,240,000 1b.2.5 Disposition Of Lead Inventory 26 756 117 899 899 328 232,673 1b.2.6 Asbestos Remediation 12,217 2 279 1,030 3,354 16,883 16,883 19,193 249,515 150,230 1b.2 Subtotal Period 1b Additional Costs 12,217 2 1,684 756 3,009 15,266 7,211 40,144 40,144 328 48,212 3,837,264 177,370 9,952 Period 1b Collateral Costs 1b.3.1 Decon equipment 902 135 1,037 1,037 1b.3.2 DOC staff relocation expenses 1,124 169 1,292 1,292 1b.3.3 Process decommissioning water waste 71 31 85 153 90 430 430 449 26,940 88 1b.3.4 Process decommissioning chemical flush waste 3 101 373 5,544 1,454 7,475 7,475 1,495 159,317 280 1b.3.5 Small tool allowance 186 28 213 213 1b.3.6 Pipe cutting equipment 1,100 165 1,265 1,265 1b.3.7 Decon rig 1,500 225 1,725 1,725 1b.3.8 Spent Fuel Capital and Transfer 5,564 835 6,399 6,399 1b.3 Subtotal Period 1b Collateral Costs 2,476 1,286 132 458 5,698 6,688 3,100 19,837 13,438 6,399 449 1,495 186,257 367 Period 1b PeriodDependent Costs 1b.4.1 Decon supplies 28 7 35 35 1b.4.2 Insurance 849 85 934 934 1b.4.3 Property taxes 1,221 122 1,343 1,343 1b.4.4 Health physics supplies 920 230 1,150 1,150 1b.4.5 Heavy equipment rental 234 35 269 269 1b.4.6 Disposal of DAW generated 8 6 21 7 42 42 362 7,234 12 1b.4.7 Plant energy budget 1,944 292 2,236 2,236 1b.4.8 NRC Fees 390 39 429 429 1b.4.9 Emergency Planning Fees 286 29 315 315 1b.4.10 Site O&M Costs 157 24 180 180 1b.4.11 Spent Fuel Pool O&M 387 58 445 445 1b.4.12 ISFSI Operating Costs 45 7 52 52 1b.4.13 Security Staff Cost 4,278 642 4,920 4,920 79,814 1b.4.14 DOC Staff Cost 5,599 840 6,439 6,439 64,486 1b.4.15 Utility Staff Cost 16,820 2,523 19,343 19,343 215,657 1b.4 Subtotal Period 1b PeriodDependent Costs 28 1,154 8 6 21 31,977 4,938 38,132 37,320 812 362 7,234 12 359,957 1b.0 TOTAL PERIOD 1b COST 3,609 14,657 142 2,148 756 8,727 57,968 16,406 104,413 96,772 7,210 431 328 49,023 1,495 4,030,755 178,816 403,650 PERIOD 1 TOTALS 3,609 15,588 156 2,158 756 8,762 137,473 28,352 196,854 167,576 28,336 943 328 49,633 1,495 4,042,945 178,836 1,063,130 PERIOD 2a Large Component Removal Period 2a Direct Decommissioning Activities Nuclear Steam Supply System Removal 2a.1.1.2 Recirculation Pumps & Motors 52 122 41 141 8 216 137 717 717 107 1,053 196,350 2,938 2a.1.1.3 CRDMs & NIs Removal 199 179 523 183 137 258 1,478 1,478 5,179 112,850 5,509 2a.1.1.4 Reactor Vessel Internals 163 3,054 7,122 2,158 11,058 244 10,257 34,055 34,055 1,252 918 918 309,830 26,675 1,199 2a.1.1.5 Reactor Vessel 98 6,613 2,130 1,718 2,333 244 7,174 20,310 20,310 14,674 1,573,112 26,675 1,199 2a.1.1 Totals 511 9,968 9,816 4,200 8 13,743 488 17,826 56,561 56,561 107 22,159 918 918 2,192,142 61,797 2,398 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 5 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Removal of Major Equipment 2a.1.2 Main Turbine/Generator 374 1,869 451 1,622 263 657 5,236 5,236 76,676 3,843 3,668,086 5,691 2a.1.3 Main Condensers 1,125 1,297 313 1,125 183 672 4,714 4,714 53,200 2,666 2,545,038 17,138 Disposal of Plant Systems New Radwaste Building System Components 2a.1.7.1 7EB 114 185 12 11 4 32 114 471 471 215 462 34,932 4,350 2a.1.7.2 N2G 13 0 0 1 1 4 18 18 40 8 2,090 202 2a.1.7.3 N2P 27 1 2 6 1 8 46 46 324 14 13,964 411 2a.1.7.4 N3A 77 5 4 5 10 23 123 123 237 140 17,648 1,160 2a.1.7.5 N3D 91 3 3 8 5 26 136 136 419 72 21,112 1,440 2a.1.7.6 N3I 19 0 0 0 1 5 26 26 19 12 1,460 308 2a.1.7.7 N3N 113 5 4 6 9 33 169 169 288 138 19,541 1,744 2a.1.7.8 N3P 29 2 2 2 4 9 47 47 118 53 7,792 439 2a.1.7.9 N3Q 20 0 1 1 1 5 28 28 67 12 3,381 309 2a.1.7.10 N3R 19 1 1 1 2 6 30 30 62 30 4,242 299 2a.1.7.11 N3S 29 1 1 3 2 8 44 44 158 25 7,828 454 2a.1.7.12 N3T 17 1 0 1 1 5 25 25 42 14 2,501 276 2a.1.7.13 N3U 126 20 18 6 55 51 275 275 317 801 58,171 1,957 2a.1.7.14 N3W 130 22 20 6 60 53 291 291 333 872 62,848 2,026 2a.1.7.15 N3Y 235 22 25 42 50 83 457 457 2,216 724 131,007 3,647 2a.1.7.16 N51 22 32 1 1 4 2 20 83 83 213 22 9,918 832 2a.1.7.17 N52 15 26 2 2 1 6 16 69 69 68 88 7,641 640 2a.1.7.18 N53 22 40 4 4 3 11 25 110 110 144 165 14,952 962 2a.1.7.19 N54 5 19 1 1 1 3 8 38 38 27 44 3,559 367 2a.1.7.20 N55 82 3 3 6 5 23 123 123 336 68 17,502 1,300 2a.1.7.21 N56 109 7 7 9 15 34 181 181 481 220 32,049 1,597 2a.1.7.22 N5A 38 48 2 3 4 5 34 135 135 226 81 13,609 1,321 2a.1.7.23 N5B 28 45 1 2 5 1 27 109 109 286 18 12,631 1,110 2a.1.7.24 N5C 20 2 1 1 3 6 33 33 49 49 4,789 304 2a.1.7.25 N5D 31 2 2 1 5 10 51 51 75 67 6,878 484 2a.1.7.26 N5E 21 2 1 1 4 7 35 35 49 52 4,983 317 2a.1.7.27 N5F 30 2 2 1 6 10 51 51 51 80 6,642 464 2a.1.7.28 N5G 1 15 0 0 0 1 5 23 23 23 15 1,797 242 2a.1.7.29 N5H 12 1 1 0 2 4 20 20 1 29 1,704 194 2a.1.7.30 N5I 10 18 1 1 0 2 10 42 42 26 22 2,322 442 2a.1.7.31 N5J 13 1 1 2 2 4 23 23 99 28 5,599 212 2a.1.7.32 N5K 17 1 1 1 1 5 25 25 56 16 3,223 256 2a.1.7.33 N5N 32 1 1 2 1 9 45 45 125 15 5,947 494 2a.1.7.34 N5O 81 4 4 11 5 24 130 130 579 80 28,042 1,264 2a.1.7.35 N5P 30 3 3 2 8 11 57 57 121 115 11,189 487 2a.1.7.36 N5Q 30 3 3 2 7 10 56 56 121 114 11,082 480 2a.1.7.37 N5S 72 8 12 38 11 29 171 171 2,012 159 90,750 1,167 2a.1.7.38 N5T 65 68 4 5 9 10 54 216 216 482 146 27,568 2,004 2a.1.7.39 N5U 65 69 4 5 9 10 55 217 217 483 147 27,630 2,019 2a.1.7.40 N5Y 16 27 1 1 2 3 16 66 66 124 44 7,504 653 2a.1.7.41 N5Z 16 27 1 1 2 3 16 66 66 124 44 7,504 653 2a.1.7.42 PPA 85 3 4 9 6 25 133 133 468 91 24,149 1,308 2a.1.7 Totals 417 2,230 161 163 223 368 932 4,494 4,494 11,707 5,395 779,680 40,595 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 6 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Old Radwaste Building System Components 2a.1.8.1 7BA 92 4 4 6 10 27 143 143 317 140 20,810 1,436 2a.1.8.2 7DA 54 6 6 1 18 20 105 105 56 263 17,183 836 2a.1.8.3 7FA 2 25 2 3 3 6 10 51 51 148 93 11,278 415 2a.1.8.4 PBA 114 170 18 16 10 46 117 493 493 544 688 60,422 4,293 2a.1.8.5 PDA 12 60 2 3 5 6 24 112 112 277 83 15,938 1,107 2a.1.8.6 PMA 14 1 1 1 1 4 21 21 32 18 2,350 217 2a.1.8.7 PRA 92 3 5 15 5 28 148 148 763 78 35,407 1,455 2a.1.8.8 PTK / PTP 15 0 0 1 0 4 20 20 28 1 1,211 232 2a.1.8 Totals 128 522 37 38 41 93 233 1,091 1,091 2,166 1,364 164,599 9,991 Turbine Building System Components 2a.1.9.1 7CA 182 298 34 30 22 81 197 842 842 1,163 1,174 113,971 6,303 2a.1.9.2 TB2 1,081 82 93 170 177 362 1,965 1,965 8,921 2,579 508,624 16,709 2a.1.9.3 TB23 5 0 0 1 0 1 8 8 40 1 1,711 83 2a.1.9.4 TB38 16 1 1 1 3 5 28 28 75 42 5,430 230 2a.1.9.5 TC2 1,753 373 399 524 919 844 4,813 4,813 27,433 13,399 1,873,979 27,653 2a.1.9.6 TE2 186 23 27 51 50 73 410 410 2,649 730 149,011 2,845 2a.1.9.7 TEE 365 13 22 72 19 111 603 603 3,794 277 169,779 5,611 2a.1.9.8 TEG 26 1 1 2 3 8 41 41 89 43 6,078 382 2a.1.9.9 TP2 192 17 19 40 34 67 368 368 2,092 490 112,797 2,999 2a.1.9.10 TP3 126 14 14 10 37 46 248 248 546 561 53,095 2,029 2a.1.9.11 TPE 115 15 13 8 36 42 229 229 408 541 46,636 1,789 2a.1.9 Totals 182 4,162 573 620 901 1,360 1,757 9,554 9,554 47,212 19,838 3,041,110 66,633 2a.1.12 Scaffolding in support of decommissioning 1,076 27 7 22 8 278 1,419 1,419 1,057 112 53,901 19,311 2a.1 Subtotal Period 2a Activity Costs 1,237 19,457 13,779 5,792 3,944 16,018 488 22,355 83,070 83,070 192,124 55,377 918 918 12,444,560 221,157 2,398 Period 2a Collateral Costs 2a.3.1 Process decommissioning water waste 161 72 195 352 205 985 985 1,031 61,862 201 2a.3.2 Process decommissioning chemical flush waste 1 26 97 235 76 435 435 388 41,295 73 2a.3.3 Small tool allowance 269 40 309 278 31 2a.3.4 Spent Fuel Capital and Transfer 13,835 2,075 15,910 15,910 2a.3 Subtotal Period 2a Collateral Costs 162 269 98 291 587 13,835 2,397 17,639 1,698 15,910 31 1,419 103,157 274 Period 2a PeriodDependent Costs 2a.4.1 Decon supplies 69 17 87 87 2a.4.2 Insurance 1,684 168 1,852 1,852 2a.4.3 Property taxes 2,422 242 2,665 2,398 266 2a.4.4 Health physics supplies 1,567 392 1,958 1,958 2a.4.5 Heavy equipment rental 2,533 380 2,913 2,913 2a.4.6 Disposal of DAW generated 102 72 253 84 511 511 4,416 88,314 144 2a.4.7 Plant energy budget 2,296 344 2,641 2,641 2a.4.8 NRC Fees 904 90 994 994 2a.4.9 Site O&M Costs 390 58 448 448 2a.4.10 Spent Fuel Pool O&M 962 144 1,106 1,106 2a.4.11 ISFSI Operating Costs 113 17 130 130 2a.4.12 Security Staff Cost 8,959 1,344 10,303 10,303 166,257 2a.4.13 DOC Staff Cost 17,165 2,575 19,740 19,740 199,771 2a.4.14 Utility Staff Cost 29,498 4,425 33,923 33,923 371,943 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 7 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 2a.4 Subtotal Period 2a PeriodDependent Costs 69 4,099 102 72 253 64,394 10,282 79,270 77,768 1,236 266 4,416 88,314 144 737,971 2a.0 TOTAL PERIOD 2a COST 1,469 23,825 13,979 6,156 3,944 16,857 78,716 35,034 179,979 162,536 17,146 297 192,124 61,211 918 918 12,636,030 221,574 740,369 PERIOD 2b Site Decontamination Period 2b Direct Decommissioning Activities New Radwaste Building System Components 2b.1.3.1 N38 194 12 11 19 23 60 319 319 1,005 337 59,967 2,944 2b.1.3.2 N48 99 4 4 8 7 29 151 151 406 107 22,600 1,507 2b.1.3.3 N4A 15 34 3 3 2 9 19 85 85 109 127 11,494 701 2b.1.3.4 N4B 12 32 3 3 2 7 17 76 76 98 109 10,011 669 2b.1.3.5 N4D 101 7 5 4 15 31 163 163 210 217 20,822 1,539 2b.1.3.6 N4E 8 0 0 0 0 2 10 10 11 5 736 121 2b.1.3.7 N4F 21 1 1 1 3 7 34 34 51 41 4,416 330 2b.1.3.8 N4H 25 2 2 4 3 8 44 44 187 49 10,386 417 2b.1.3.9 N4K 27 2 1 2 3 8 43 43 129 41 7,565 417 2b.1.3.10 N4L 40 1 1 3 3 11 59 59 135 37 7,564 628 2b.1.3.11 N5R 87 3 5 18 4 27 144 144 967 53 42,284 1,364 2b.1.3.12 N5V 65 68 7 7 6 19 57 230 230 309 295 28,625 2,009 2b.1.3.13 N5W 11 0 0 0 0 3 13 13 9 0 405 169 2b.1.3.14 N5X 84 85 3 4 15 3 67 262 262 786 48 34,564 2,536 2b.1.3 Totals 176 831 47 50 84 100 346 1,633 1,633 4,412 1,465 261,438 15,352 Old Radwaste Building System Components 2b.1.4.1 ORW Pre D&D Desludge and Decon 229 34 263 263 3,197 2b.1.4.2 PRD 17 0 1 3 0 5 26 26 143 6 6,156 274 2b.1.4.3 PSB 157 7 9 18 15 48 253 253 950 214 50,690 2,440 2b.1.4.4 PTA 43 3 3 5 6 14 74 74 276 82 15,879 686 2b.1.4.5 PUA 233 15 13 16 32 72 381 381 860 459 61,058 3,599 2b.1.4.6 PUU 157 12 15 28 27 54 292 292 1,441 413 80,833 2,504 2b.1.4.7 PVA 9 0 0 0 0 2 12 12 12 1 524 148 2b.1.4.8 UAB 338 8 13 41 13 97 510 510 2,148 188 97,655 5,225 2b.1.4.9 UAS 233 7 12 41 8 69 369 369 2,128 128 93,445 3,622 2b.1.4 Totals 1,417 51 65 152 100 394 2,180 2,180 7,959 1,490 406,240 21,696 Turbine Building System Components 2b.1.5.1 TD2 67 4 4 5 9 21 110 110 241 130 17,177 1,004 2b.1.5.2 TF2 364 51 64 154 95 152 879 879 8,047 1,384 405,420 5,629 2b.1.5.3 TFG 26 1 1 3 1 7 39 39 134 14 6,251 414 2b.1.5.4 TG2 264 42 55 114 95 119 689 689 5,957 1,383 320,296 4,199 2b.1.5.5 TH2 515 120 130 138 324 262 1,490 1,490 7,240 4,729 562,006 8,167 2b.1.5.6 TKA 24 1 1 1 2 7 34 34 47 24 3,253 350 2b.1.5.7 TL2 112 11 9 7 24 37 199 199 358 344 34,042 1,692 2b.1.5.8 TMA 68 6 7 13 12 24 129 129 690 178 38,125 1,051 2b.1.5.9 TN2 359 31 36 62 70 125 683 683 3,260 1,023 190,382 5,575 2b.1.5.10 TO2 194 29 223 223 3,221 2b.1.5.11 TOA 99 4 6 18 6 30 162 162 917 84 42,017 1,497 2b.1.5.12 TOCR 74 5 9 30 6 26 150 150 1,590 87 69,536 1,062 2b.1.5.13 TOR 72 6 7 14 13 25 137 137 717 185 39,614 1,139 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 8 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Turbine Building System Components (continued) 2b.1.5.14 TOV 19 0 1 2 0 5 28 28 90 6 4,042 293 2b.1.5.15 TOW 115 8 14 45 12 42 236 236 2,346 181 105,569 1,765 2b.1.5.16 TOX / TOY 32 1 1 2 1 9 46 46 106 16 5,216 488 2b.1.5.17 TS2 225 29 33 52 69 89 496 496 2,704 1,009 167,033 3,439 2b.1.5.18 TTA 67 6 7 13 13 24 130 130 675 194 38,390 1,085 2b.1.5.19 TU2 210 9 13 35 16 65 347 347 1,825 234 87,369 3,270 2b.1.5 Totals 2,906 334 395 705 769 1,098 6,207 5,984 223 36,944 11,206 2,135,738 45,340 Augmented Offgas System Components 2b.1.6.1 AY8 161 13 14 20 33 55 297 297 1,044 475 69,386 2,486 2b.1.6.2 AYA 34 3 4 7 8 12 69 69 384 110 21,817 527 2b.1.6.3 AYB 32 2 2 4 4 10 53 53 208 51 11,355 504 2b.1.6.4 AYC 82 4 6 17 7 26 141 141 899 97 41,912 1,279 2b.1.6.5 AYE 28 2 1 1 4 8 44 44 43 52 4,754 428 2b.1.6.6 AZ8 61 4 4 9 7 19 104 104 492 103 25,832 941 2b.1.6.7 AZA 14 1 0 0 1 4 20 20 24 15 1,797 215 2b.1.6.8 AZC 117 4 6 20 6 35 188 188 1,046 86 47,345 1,791 2b.1.6.9 AZD 20 1 1 1 2 6 30 30 40 31 3,402 307 2b.1.6.10 AZE 19 1 1 1 2 5 29 29 39 27 3,151 295 2b.1.6.11 AZF 17 1 1 1 2 5 27 27 65 22 3,914 274 2b.1.6.12 AZI 33 1 2 6 1 10 54 54 322 19 14,113 526 2b.1.6 Totals 618 36 43 88 75 196 1,056 1,056 4,607 1,088 248,777 9,574 Miscellaneous System Components 2b.1.7.1 BAA 295 19 23 50 38 96 520 520 2,608 547 136,965 4,556 2b.1.7.2 BBA 100 6 11 39 9 35 200 200 2,039 124 89,851 1,559 2b.1.7.3 BDA 12 0 0 0 0 3 17 17 21 5 1,132 190 2b.1.7.4 CAA 694 27 52 185 32 220 1,211 1,211 9,683 489 419,874 10,902 2b.1.7.5 DAA 72 3 3 5 6 21 110 110 277 86 16,118 1,145 2b.1.7.6 DAC 172 5 7 21 8 50 263 263 1,094 117 51,066 2,672 2b.1.7.7 DGB 82 12 94 94 1,336 2b.1.7.8 DOT 14 2 16 16 223 2b.1.7.9 DPH 95 14 109 109 1,527 2b.1.7.10 DWF 22 3 25 25 360 2b.1.7.11 FWP 127 19 146 146 2,018 2b.1.7.12 INTAKE STRUCTURE 199 30 229 229 3,218 2b.1.7.13 MAA 142 11 13 19 27 48 260 260 1,013 392 63,370 2,192 2b.1.7.14 MBA 51 3 3 6 7 16 87 87 290 107 17,813 769 2b.1.7.15 MBS / MBT 38 1 1 1 2 10 54 54 71 32 4,701 577 2b.1.7.16 MS 40 6 46 46 676 2b.1.7.17 NMB ROOF 20 3 22 22 312 2b.1.7.18 OB 292 44 336 336 4,806 2b.1.7.19 PTB 43 6 49 49 688 2b.1.7.20 RSF ROOF 29 0 1 3 1 8 42 42 166 8 7,167 452 2b.1.7.21 UYARD 1,807 46 52 81 110 504 2,599 2,599 4,250 1,645 263,340 21,795 2b.1.7.22 WAA 166 8 10 17 19 51 271 271 878 275 51,268 2,492 2b.1.7.23 WHS 19 3 22 22 318 2b.1.7.24 YARD AREAS 351 53 404 404 5,688 2b.1.7.25 YDA / YFA / YLA 2 0 0 0 0 1 3 3 18 1 796 30 2b.1.7 Totals 4,885 130 176 428 258 1,259 7,136 5,637 1,500 22,409 3,827 1,123,463 70,499 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 9 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 2b.1.8 Scaffolding in support of decommissioning 1,345 34 9 28 10 348 1,774 1,774 1,321 140 67,377 24,139 Decontamination of Site Buildings 2b.1.9.1 New Radwaste Building Systems Removal 0 167 103 156 0 233 134 794 794 6 4,340 382,187 2,526 2b.1.9.2 Old Radwaste Building Systems Removal 0 4 11 17 0 25 11 68 68 6 461 40,787 73 2b.1.9.3 Turbine Building Systems Removal 469 249 376 561 339 1,993 1,993 10,447 919,350 6,185 2b.1.9.4 Augmented Off Gas Decon 40 258 30 45 1 67 112 554 554 45 1,256 112,340 4,323 2b.1.9.5 LLRW Storage Decon 23 83 18 27 41 48 240 240 758 66,660 1,490 2b.1.9.6 Miscellaneous Buildings Decon 22 110 18 27 40 54 271 271 745 65,556 1,886 2b.1.9.7 New Radwaste Building Decon 105 980 115 175 4 259 401 2,040 2,040 235 4,829 434,128 15,639 2b.1.9.8 Old Radwaste Building Decon 912 474 718 3 1,070 651 3,828 3,828 152 19,923 1,759,171 10,889 2b.1.9.9 Stack/Exhaust Tunnels Remove & Decon 170 1,105 72 110 163 426 2,046 2,046 3,043 267,756 18,826 2b.1.9.10 Turbine Building 0ft Decon 150 1,123 113 171 22 251 459 2,288 2,288 1,144 4,660 454,804 18,446 2b.1.9.11 Turbine Building 23ft Decon 105 797 86 130 21 190 330 1,660 1,660 1,109 3,527 353,718 13,021 2b.1.9.12 Turbine Building 46ft Decon 65 276 51 77 115 147 731 731 2,146 188,826 4,839 2b.1.9.13 Drywell Decon 5 814 458 523 1,263 646 3,707 3,707 19,950 1,351,210 11,073 2b.1.9.14 Drywell Liner Removal 2,320 1,335 74 105 422 71 1,598 5,924 5,924 22,108 1,022 956,216 53,760 2b.1.9.15 RB0 Torus Removal 3,110 1,531 110 156 626 105 2,092 7,728 7,728 32,774 1,515 1,417,560 67,988 2b.1.9.16 Reactor Building Systems Removal 7 18 27 40 17 108 108 736 64,800 111 2b.1.9.17 Reactor Building 19ft Decon 65 504 51 78 39 108 208 1,053 1,053 2,052 1,994 255,644 8,152 2b.1.9.18 Reactor Building 119ft Decon 513 655 27 40 30 54 447 1,765 1,765 1,563 980 147,532 17,352 2b.1.9.19 Reactor Building 23ft Decon 48 288 38 57 85 130 647 647 1,591 140,034 4,847 2b.1.9.20 Reactor Building 51ft Decon 53 302 42 64 95 140 696 696 1,775 156,192 5,106 2b.1.9.21 Reactor Building 75ft Decon 18 161 14 21 32 62 308 308 594 52,272 2,605 2b.1.9 Totals 6,811 11,882 2,171 3,100 1,168 4,867 8,450 38,448 38,448 61,196 86,292 9,586,742 269,137 2b.1 Subtotal Period 2b Activity Costs 6,987 23,884 2,804 3,839 2,653 6,178 12,090 58,435 56,712 1,723 138,847 105,508 13,829,770 455,736 Period 2b Additional Costs 2b.2.1 Contaminated Soil Removal 111 2 500 5,702 1,529 7,844 7,844 106,200 8,071,193 834 2b.2 Subtotal Period 2b Additional Costs 111 2 500 5,702 1,529 7,844 7,844 106,200 8,071,193 834 Period 2b Collateral Costs 2b.3.1 Process decommissioning water waste 171 79 213 386 222 1,072 1,072 1,130 67,806 220 2b.3.2 Process decommissioning chemical flush waste 0 1 5 12 4 22 22 20 2,118 4 2b.3.3 Small tool allowance 527 79 606 606 2b.3.4 Decommissioning Equipment Disposition 155 49 127 44 53 427 427 6,000 635 305,961 88 2b.3.5 Spent Fuel Capital and Transfer 30,040 4,506 34,546 34,546 2b.3 Subtotal Period 2b Collateral Costs 171 527 236 267 127 441 30,040 4,864 36,673 2,126 34,546 6,000 1,785 375,885 312 Period 2b PeriodDependent Costs 2b.4.1 Decon supplies 1,864 466 2,330 2,330 2b.4.2 Insurance 1,700 170 1,870 1,870 2b.4.3 Property taxes 2,963 296 3,260 3,260 2b.4.4 Health physics supplies 3,279 820 4,099 4,099 2b.4.5 Heavy equipment rental 5,456 818 6,274 6,274 2b.4.6 Disposal of DAW generated 184 130 456 152 923 923 7,979 159,584 260 2b.4.7 Plant energy budget 3,937 591 4,528 4,528 2b.4.8 NRC Fees 1,963 196 2,160 2,160 2b.4.9 Site O&M Costs 846 127 973 973 2b.4.10 Spent Fuel Pool O&M 2,089 313 2,402 2,402 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 10 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 2b PeriodDependent Costs (continued) 2b.4.11 Liquid Radwaste Processing Equipment/Services 530 80 610 610 2b.4.12 ISFSI Operating Costs 245 37 282 282 2b.4.13 Security Staff Cost 19,457 2,919 22,375 22,375 361,067 2b.4.14 DOC Staff Cost 35,864 5,380 41,244 41,244 416,726 2b.4.15 Utility Staff Cost 61,585 9,238 70,823 70,823 773,511 2b.4 Subtotal Period 2b PeriodDependent Costs 1,864 8,735 184 130 456 131,180 21,602 164,152 161,468 2,684 7,979 159,584 260 1,551,304 2b.0 TOTAL PERIOD 2b COST 9,022 33,257 3,226 4,736 2,780 12,778 161,220 40,085 267,104 228,151 37,230 1,723 144,847 221,472 22,436,440 457,143 1,551,304 PERIOD 2d Decontamination Following Wet Fuel Storage Period 2d Direct Decommissioning Activities 2d.1.1 Remove spent fuel racks 608 64 142 226 744 554 2,338 2,338 10,858 615,095 1,071 Disposal of Plant Systems Drywell System Components 2d.1.2.1 IAA/IAC 471 380 288 232 79 704 582 2,737 2,737 4,134 10,243 749,934 7,409 2d.1.2.2 IBA 113 189 27 25 8 76 131 570 570 438 1,113 80,901 3,998 2d.1.2.3 ICA 165 303 50 42 21 123 203 907 907 1,098 1,789 146,198 6,483 2d.1.2.4 IEA 78 16 16 10 47 37 205 205 498 687 59,174 1,354 2d.1.2.5 RC6 74 2 3 7 4 21 111 111 373 58 18,457 1,134 2d.1.2 Totals 749 1,024 384 319 125 955 974 4,529 4,529 6,541 13,891 1,054,664 20,378 Reactor Building System Components 2d.1.3.1 RB1 228 14 18 38 29 74 400 400 2,009 419 105,353 3,451 2d.1.3.2 RBB 119 7 9 20 14 38 208 208 1,062 211 55,076 1,828 2d.1.3.3 RBC 122 8 10 23 17 40 220 220 1,203 243 62,657 1,882 2d.1.3.4 RBE 160 9 10 21 17 50 267 267 1,094 249 58,612 2,475 2d.1.3.5 RBF 135 20 18 8 53 53 288 288 441 774 61,571 2,161 2d.1.3.6 RBO 590 45 70 185 90 213 1,193 1,193 9,702 1,312 468,326 9,941 2d.1.3.7 RBS 274 37 39 37 99 108 594 594 1,923 1,445 159,975 4,412 2d.1.3.8 RBSW 135 4 7 24 5 40 214 214 1,258 73 55,258 2,080 2d.1.3.9 RC1/RC3 5 0 0 0 0 1 6 6 14 1 583 73 2d.1.3.10 RC7 90 8 9 15 18 32 172 172 797 266 47,464 1,323 2d.1.3.11 RCA 53 5 4 1 12 17 92 92 77 170 12,751 829 2d.1.3.12 RCB 79 4 4 7 9 24 128 128 374 137 22,891 1,211 2d.1.3.13 RCD 397 23 28 61 45 126 680 680 3,212 659 167,841 6,084 2d.1.3.14 RCG 76 9 10 15 22 29 161 161 761 322 49,171 1,207 2d.1.3.15 RCJ 83 4 5 9 9 25 135 135 468 129 26,309 1,281 2d.1.3.16 RCM 123 12 13 19 29 44 239 239 987 425 64,171 1,941 2d.1.3.17 RCN 272 17 17 29 36 86 456 456 1,510 517 90,705 4,175 2d.1.3.18 RCS 98 20 18 7 56 44 243 243 342 814 60,078 1,557 2d.1.3.19 RCT 63 4 4 6 9 20 107 107 306 137 20,185 977 2d.1.3.20 RD8 98 77 74 24 225 103 601 601 1,250 3,286 236,914 1,680 2d.1.3.21 RDM 54 3 2 4 5 16 83 83 186 71 11,617 806 2d.1.3.22 REC 244 11 14 30 23 74 396 396 1,571 331 82,567 3,681 2d.1.3.23 REF 113 28 24 8 75 54 302 302 422 1,086 78,740 1,775 2d.1.3.24 REH/REI 136 7 9 21 15 43 230 230 1,078 212 55,804 2,109 2d.1.3.25 REL 241 25 28 44 59 88 486 486 2,281 866 141,749 3,766 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 11 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Reactor Building System Components (continued) 2d.1.3.26 REM 64 3 4 8 6 20 105 105 439 85 22,669 994 2d.1.3.27 REO 138 27 27 15 77 63 346 346 773 1,121 94,897 2,207 2d.1.3.28 REQ 190 20 18 15 49 67 359 359 774 717 72,168 2,993 2d.1.3.29 RER 28 64 6 5 2 16 36 158 158 94 238 17,349 1,350 2d.1.3.30 RET 18 48 2 2 3 3 23 99 99 147 50 8,803 1,062 2d.1.3.31 REW 32 1 1 2 1 9 46 46 129 15 6,094 498 2d.1.3.32 REX 35 1 1 3 1 10 51 51 147 16 6,875 550 2d.1.3.33 REY 40 2 2 2 5 12 63 63 107 73 8,463 619 2d.1.3.34 RFB 180 10 12 25 19 56 303 303 1,295 283 68,684 2,813 2d.1.3.35 RFC 39 119 15 11 4 33 62 283 283 185 483 35,025 2,413 2d.1.3.36 RFF 126 6 7 14 12 38 202 202 728 169 39,127 1,945 2d.1.3.37 RFH 171 32 26 7 79 71 386 386 386 1,156 81,383 2,669 2d.1.3.38 RFJ 149 29 25 7 77 64 352 352 386 1,128 79,658 2,339 2d.1.3.39 RFL 96 3 4 13 3 28 147 147 702 45 31,087 1,528 2d.1.3.40 RFN 130 6 7 18 11 39 211 211 942 153 46,967 2,023 2d.1.3.41 RFQ 189 5 6 15 10 53 278 278 777 142 39,606 2,842 2d.1.3.42 RGC 100 3 4 11 5 29 152 152 580 75 27,852 1,562 2d.1.3.43 RGD 282 41 45 49 110 116 642 642 2,567 1,600 194,860 4,497 2d.1.3.44 RGI 60 1 2 7 2 17 90 90 388 23 17,054 956 2d.1.3.45 RGL 70 3 4 9 5 21 112 112 474 71 23,263 1,105 2d.1.3.46 RGP 32 1 1 4 1 9 48 48 221 14 9,781 495 2d.1.3.47 RGR 214 10 12 24 21 65 346 346 1,278 306 69,247 3,298 2d.1.3.48 RGU 96 2 3 9 4 27 142 142 473 63 22,804 1,504 2d.1.3.49 RH1 57 2 2 5 3 16 86 86 280 51 14,241 877 2d.1.3.50 RH2 42 3 4 8 6 14 77 77 441 94 23,218 659 2d.1.3.51 RH3 / RH4 / RH6 142 5 5 8 9 40 210 210 444 130 25,468 2,168 2d.1.3.52 RHA 14 32 2 2 1 6 17 74 74 41 93 6,930 703 2d.1.3.53 RHJ 51 1 2 5 3 14 75 75 239 37 11,796 788 2d.1.3.54 RHL 33 1 1 2 2 9 48 48 92 25 5,176 498 2d.1.3.55 RHX 61 3 3 7 5 18 97 97 349 79 18,642 934 2d.1.3.56 RHY 55 1 2 7 2 16 82 82 343 23 15,246 863 2d.1.3.57 RMCC 98 6 7 15 13 32 170 170 771 187 41,956 1,476 2d.1.3 Totals 99 7,184 650 702 980 1,571 2,556 13,742 13,742 51,322 22,900 3,382,757 113,936 Miscellaneous System Components 2d.1.8.1 GAA / GCA 23 3 26 26 368 2d.1.8 Totals 23 3 26 26 368 Decontamination of Site Buildings 2d.1.9.1 Reactor Building 91ft Decon 38 251 30 46 68 109 542 542 1,267 111,534 4,179 2d.1.9 Totals 38 251 30 46 68 109 542 542 1,267 111,534 4,179 2d.1.10 Scaffolding in support of decommissioning 269 7 2 6 2 70 355 355 264 28 13,475 4,828 2d.1 Subtotal Period 2d Activity Costs 1,494 8,815 1,213 1,294 1,110 3,340 4,266 21,532 21,506 26 58,127 48,944 5,177,526 144,759 Period 2d Additional Costs 2d.2.1 License Termination Survey Planning 1,948 584 2,532 2,532 12,480 2d.2 Subtotal Period 2d Additional Costs 1,948 584 2,532 2,532 12,480 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 12 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 2d Collateral Costs 2d.3.1 Process decommissioning water waste 63 29 79 144 82 397 397 420 25,229 82 2d.3.2 Process decommissioning chemical flush waste 4 116 429 1,041 338 1,927 1,927 1,718 183,018 321 2d.3.3 Small tool allowance 168 25 193 193 2d.3.4 Decommissioning Equipment Disposition 155 49 127 44 53 427 427 6,000 635 305,961 88 2d.3 Subtotal Period 2d Collateral Costs 66 168 300 557 127 1,228 498 2,945 2,945 6,000 2,773 514,208 492 Period 2d PeriodDependent Costs 2d.4.1 Decon supplies 110 28 138 138 2d.4.2 Insurance 566 57 622 622 2d.4.3 Property taxes 986 99 1,084 1,084 2d.4.4 Health physics supplies 1,051 263 1,314 1,314 2d.4.5 Heavy equipment rental 1,966 295 2,261 2,261 2d.4.6 Disposal of DAW generated 71 50 175 58 355 355 3,067 61,346 100 2d.4.7 Plant energy budget 757 114 870 870 2d.4.8 NRC Fees 707 71 778 778 2d.4.9 Site O&M Costs 305 46 351 351 2d.4.10 Liquid Radwaste Processing Equipment/Services 382 57 440 440 2d.4.11 ISFSI Operating Costs 88 13 101 101 2d.4.12 Security Staff Cost 3,793 569 4,363 4,363 68,400 2d.4.13 DOC Staff Cost 8,929 1,339 10,268 10,268 102,857 2d.4.14 Utility Staff Cost 16,312 2,447 18,759 18,759 196,457 2d.4 Subtotal Period 2d PeriodDependent Costs 110 3,017 71 50 175 32,826 5,455 41,704 41,603 101 3,067 61,346 100 367,714 2d.0 TOTAL PERIOD 2d COST 1,671 12,000 1,583 1,901 1,237 4,744 34,773 10,803 68,713 68,585 101 26 64,127 54,784 5,753,080 145,351 380,194 PERIOD 2f License Termination Period 2f Direct Decommissioning Activities 2f.1.1 ORISE confirmatory survey 161 48 210 210 2f.1.2 Terminate license a 2f.1 Subtotal Period 2f Activity Costs 161 48 210 210 Period 2f Additional Costs 2f.2.1 License Termination Survey 8,201 2,460 10,661 10,661 118,801 6,240 2f.2 Subtotal Period 2f Additional Costs 8,201 2,460 10,661 10,661 118,801 6,240 Period 2f Collateral Costs 2f.3.1 DOC staff relocation expenses 1,124 169 1,292 1,292 2f.3 Subtotal Period 2f Collateral Costs 1,124 169 1,292 1,292 Period 2f PeriodDependent Costs 2f.4.1 Insurance 432 43 475 475 2f.4.2 Property taxes 753 75 828 828 2f.4.3 Health physics supplies 805 201 1,006 1,006 2f.4.4 Disposal of DAW generated 8 6 20 7 41 41 355 7,097 12 2f.4.5 Plant energy budget 289 43 332 332 2f.4.6 NRC Fees 579 58 637 637 2f.4.7 Site O&M Costs 233 35 268 268 2f.4.8 ISFSI Operating Costs 67 10 78 78 2f.4.9 Security Staff Cost 2,836 425 3,262 3,262 51,071 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 13 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 2f PeriodDependent Costs (continued) 2f.4.10 DOC Staff Cost 5,156 773 5,929 5,929 57,357 2f.4.11 Utility Staff Cost 7,221 1,083 8,304 8,304 80,929 2f.4 Subtotal Period 2f PeriodDependent Costs 805 8 6 20 17,567 2,755 21,160 21,083 78 355 7,097 12 189,357 2f.0 TOTAL PERIOD 2f COST 805 8 6 20 27,053 5,432 33,324 33,246 78 355 7,097 118,812 195,597 PERIOD 2 TOTALS 12,162 69,886 18,796 12,799 7,960 34,399 301,763 91,353 549,119 492,518 54,555 2,046 401,099 337,822 918 918 40,832,640 942,880 2,867,465 PERIOD 3b Site Restoration Period 3b Direct Decommissioning Activities Demolition of Remaining Site Buildings 3b.1.1.1 Stack/Exhaust Tunnels Remove & Decon 1,038 156 1,193 1,193 1,911 3b.1.1.2 Administration Building 506 76 582 582 6,477 3b.1.1.3 Augmented Off Gas Building 338 51 388 388 3,399 3b.1.1.4 Chlorination Building 32 5 36 36 407 3b.1.1.5 Diesel Generator Building 137 21 157 157 1,268 3b.1.1.6 Dilution Structure 178 27 205 205 1,758 3b.1.1.7 Domestic Water Facility 11 2 12 12 147 3b.1.1.8 Fire Pump House 4 1 5 5 54 3b.1.1.9 Fresh Water Pump House 22 3 26 26 293 3b.1.1.10 Heating Boiler House 41 6 48 48 546 3b.1.1.11 Intake Structure 632 95 727 727 6,322 3b.1.1.12 Low Level Radwaste Storage 444 67 511 511 5,435 3b.1.1.13 Machine Shop 226 34 260 260 2,858 3b.1.1.14 Main Gate Security 101 15 116 116 1,059 3b.1.1.15 Maintenance Building 326 49 375 375 4,274 3b.1.1.16 Materials Warehouse 879 132 1,011 1,011 8,908 3b.1.1.17 Miscellaneous Structures 617 93 710 710 6,565 3b.1.1.18 New Radwaste Building 745 112 857 857 8,009 3b.1.1.19 New Sample Pump House 9 1 11 11 128 3b.1.1.20 Office Building 374 56 430 430 4,459 3b.1.1.21 Old Radwaste Building 680 102 782 782 6,852 3b.1.1.22 Plant Engineering 170 25 195 195 1,784 3b.1.1.23 Pretreatment Building 31 5 35 35 420 3b.1.1.24 Reactor Building 6,127 919 7,046 7,046 61,454 3b.1.1.25 Sample Pool 15 2 18 18 180 3b.1.1.26 Security Modifications 1,256 188 1,444 1,444 10,330 3b.1.1.27 Site Emergency Building 316 47 363 363 3,285 3b.1.1.28 Tank Pads & Misc. Yard 772 116 887 887 8,326 3b.1.1.29 Turbine Building 4,209 631 4,840 4,840 41,424 3b.1.1.30 Turbine Pedestal 574 86 660 660 5,050 3b.1.1 Totals 20,808 3,121 23,929 23,929 203,381 Site Closeout Activities 3b.1.2 Remove Rubble 798 120 917 917 4,211 3b.1.3 Grade & landscape site 634 95 729 729 1,304 3b.1.4 Final report to NRC 187 28 215 215 1,560 3b.1 Subtotal Period 3b Activity Costs 22,240 187 3,364 25,790 215 25,576 208,896 1,560 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 14 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 3b Additional Costs 3b.2.1 Concrete Crushing 756 9 115 880 880 3,219 3b.2.2 Install Cofferdams Intake & Dilution 975 146 1,122 1,122 8,296 3b.2 Subtotal Period 3b Additional Costs 1,732 9 261 2,002 2,002 11,516 Period 3b Collateral Costs 3b.3.1 Small tool allowance 264 40 304 304 3b.3 Subtotal Period 3b Collateral Costs 264 40 304 304 Period 3b PeriodDependent Costs 3b.4.1 Insurance 891 89 980 980 3b.4.2 Property taxes 1,552 155 1,708 1,708 3b.4.3 Heavy equipment rental 4,438 666 5,104 5,104 3b.4.4 Plant energy budget 298 45 343 343 3b.4.5 NRC ISFSI Fees 334 33 368 368 3b.4.6 ISFSI Operating Costs 139 21 160 160 3b.4.7 Site O&M Cost 480 72 552 552 3b.4.8 Security Staff Cost 5,848 877 6,725 0 5,649 1,076 105,300 3b.4.9 DOC Staff Cost 10,204 1,531 11,735 11,735 110,160 3b.4.10 Utility Staff Cost 7,702 1,155 8,857 0 1,949 6,909 88,290 3b.4 Subtotal Period 3b PeriodDependent Costs 4,438 27,449 4,644 36,531 0 10,813 25,718 303,750 3b.0 TOTAL PERIOD 3b COST 28,674 27,644 8,309 64,627 215 10,813 53,600 220,412 305,310 PERIOD 3c Fuel Storage Operations/Shipping Period 3c Direct Decommissioning Activities Period 3c Collateral Costs 3c.3.1 Spent Fuel Capital and Transfer 9,500 1,425 10,925 10,925 3c.3 Subtotal Period 3c Collateral Costs 9,500 1,425 10,925 10,925 Period 3c PeriodDependent Costs 3c.4.1 Insurance 4,691 469 5,160 5,160 3c.4.2 Property taxes 8,175 818 8,993 8,993 3c.4.4 NRC ISFSI Fees 2,432 243 2,675 2,675 3c.4.5 ISFSI Operating Costs 732 110 842 842 3c.4.6 Security Staff Cost 25,904 3,886 29,790 29,790 460,697 3c.4.7 Utility Staff Cost 9,385 1,408 10,793 10,793 115,174 3c.4 Subtotal Period 3c PeriodDependent Costs 51,319 6,933 58,252 58,252 575,871 3c.0 TOTAL PERIOD 3c COST 60,819 8,358 69,177 69,177 575,871 PERIOD 3d GTCC shipping Period 3d Direct Decommissioning Activities Nuclear Steam Supply System Removal 3d.1.1.1 Vessel & Internals GTCC Disposal 500 4,450 717 5,667 5,667 1,428 282,300 3d.1.1 Totals 500 4,450 717 5,667 5,667 1,428 282,300 3d.1 Subtotal Period 3d Activity Costs 500 4,450 717 5,667 5,667 1,428 282,300 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 15 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 3d PeriodDependent Costs 3d.4.1 Insurance 22 2 24 24 3d.4.2 Property taxes 38 4 42 42 3d.4.4 ISFSI Operating Costs 3 1 4 4 3d.4.5 Security Staff Cost 121 18 140 140 2,160 3d.4.6 Utility Staff Cost 44 7 51 51 540 3d.4 Subtotal Period 3d PeriodDependent Costs 229 31 261 261 2,700 3d.0 TOTAL PERIOD 3d COST 500 4,450 229 749 5,928 5,667 261 1,428 282,300 2,700 PERIOD 3e ISFSI Decontamination Period 3e Direct Decommissioning Activities Period 3e Additional Costs 3e.2.1 ISFSI License Termination 2,690 1,587 1,411 1,281 6,969 6,969 19,521 2,578,520 3e.2.2 ISFSI License Termination Cascading Costs 1,517 536 308 2,362 2,362 3e.2 Subtotal Period 3e Additional Costs 4,207 1,587 1,947 1,589 9,330 9,330 19,521 2,578,520 Period 3e Collateral Costs 3e.3.1 Small tool allowance 54 8 63 63 3e.3 Subtotal Period 3e Collateral Costs 54 8 63 63 Period 3e PeriodDependent Costs 3e.4.1 Insurance 652 65 717 717 3e.4.2 Property taxes 1,136 114 1,250 1,250 3e.4.4 Security Staff Cost 966 145 1,111 1,111 17,193 3e.4.5 Utility Staff Cost 1,091 164 1,255 1,255 13,043 3e.4 Subtotal Period 3e PeriodDependent Costs 3,845 487 4,333 4,333 30,236 3e.0 TOTAL PERIOD 3e COST 4,262 1,587 5,792 2,084 13,726 13,726 19,521 2,578,520 30,236 PERIOD 3f ISFSI Site Restoration Period 3f Direct Decommissioning Activities Period 3f Additional Costs 3f.2.1 ISFSI Site Restoration 144 6 22 172 172 3f.2 Subtotal Period 3f Additional Costs 144 6 22 172 172 Period 3f Collateral Costs 3f.3.1 Small tool allowance 1 0 1 1 3f.3 Subtotal Period 3f Collateral Costs 1 0 1 1 Period 3f PeriodDependent Costs 3f.4.2 Property taxes 36 4 39 39 3f.4.4 Security Staff Cost 30 5 35 35 539 3f.4.5 Utility Staff Cost 28 4 32 32 334 3f.4 Subtotal Period 3f PeriodDependent Costs 94 12 106 106 873 3f.0 TOTAL PERIOD 3f COST 144 100 35 279 279 873 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix C, Page 16 of 16 Table C Oyster Creek Nuclear Generating Station DECON Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:27:38 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 3 TOTALS 33,080 500 6,037 94,585 19,535 153,737 5,882 94,255 53,600 19,521 1,428 2,860,820 220,412 914,990 TOTAL COST TO DECOMMISSION 15,771 118,554 19,453 14,957 8,717 49,198 533,821 139,240 899,710 665,975 177,146 56,589 401,427 406,975 2,413 918 1,428 47,736,400 1,342,127 4,845,585 TOTAL COST TO DECOMMISSION WITH 18.31% CONTINGENCY: $899,710 thousands of 2011 dollars TOTAL NRC LICENSE TERMINATION COST IS 74.02% OR: $665,975 thousands of 2011 dollars SPENT FUEL MANAGEMENT COST IS 19.69% OR: $177,146 thousands of 2011 dollars NONNUCLEAR DEMOLITION COST IS 6.29% OR: $56,589 thousands of 2011 dollars TOTAL LOWLEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC): 410,307 cubic feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED: 1,428 cubic feet TOTAL SCRAP METAL REMOVED: 24,334 tons TOTAL CRAFT LABOR REQUIREMENTS: 1,342,127 manhours End Notes:

n/a indicates that this activity not charged as decommissioning expense.

a indicates that this activity performed by decommissioning staff.

0 indicates that this value is less than 0.5 but is nonzero.

a cell containing " " indicates a zero value TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 1 of 17 APPENDIX D DETAILED COST ANALYSIS DELAYED DECON TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 2 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 1a Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 SAFSTOR site characterization survey 434 130 564 564 1a.1.2 Prepare preliminary decommissioning cost 156 23 179 179 1,300 1a.1.3 Notification of Cessation of Operations a 1a.1.4 Remove fuel & source material n/a 1a.1.5 Notification of Permanent Defueling a 1a.1.6 Deactivate plant systems & process waste a 1a.1.7 Prepare and submit PSDAR 239 36 275 275 2,000 1a.1.8 Review plant dwgs & specs. 156 23 179 179 1,300 1a.1.9 Perform detailed rad survey a 1a.1.10 Estimate byproduct inventory 120 18 138 138 1,000 1a.1.11 End product description 120 18 138 138 1,000 1a.1.12 Detailed byproduct inventory 179 27 206 206 1,500 1a.1.13 Define major work sequence 120 18 138 138 1,000 1a.1.14 Perform SER and EA 371 56 427 427 3,100 1a.1.15 Perform SiteSpecific Cost Study 598 90 688 688 5,000 Activity Specifications 1a.1.16.1 Prepare plant and facilities for SAFSTOR 589 88 677 677 4,920 1a.1.16.2 Plant systems 499 75 573 573 4,167 1a.1.16.3 Plant structures and buildings 373 56 429 429 3,120 1a.1.16.4 Waste management 239 36 275 275 2,000 1a.1.16.5 Facility and site dormancy 239 36 275 275 2,000 1a.1.16 Total 1,939 291 2,230 2,230 16,207 Detailed Work Procedures 1a.1.17.1 Plant systems 142 21 163 163 1,183 1a.1.17.2 Facility closeout & dormancy 144 22 165 165 1,200 1a.1.17 Total 285 43 328 328 2,383 1a.1.18 Procure vacuum drying system 12 2 14 14 100 1a.1.19 Drain/deenergize noncont. systems a 1a.1.20 Drain & dry NSSS a 1a.1.21 Drain/deenergize contaminated systems a 1a.1.22 Decon/secure contaminated systems a 1a.1 Subtotal Period 1a Activity Costs 4,728 774 5,503 5,503 35,890 Period 1a PeriodDependent Costs 1a.4.1 Insurance 2,227 223 2,450 2,450 1a.4.2 Property taxes 1a.4.3 Health physics supplies 469 117 586 586 1a.4.4 Heavy equipment rental 462 69 531 531 1a.4.5 Disposal of DAW generated 14 10 35 12 70 70 610 12,190 20 1a.4.6 Plant energy budget 1,918 288 2,206 2,206 1a.4.7 NRC Fees 769 77 846 846 1a.4.8 Emergency Planning Fees 564 56 621 621 1a.4.9 Site O&M Costs 309 46 355 355 1a.4.10 Spent Fuel Pool O&M 763 114 878 878 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 3 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 1a PeriodDependent Costs (continued) 1a.4.11 ISFSI Operating Costs 89 13 103 103 1a.4.12 Security Staff Cost 8,441 1,266 9,707 9,707 157,471 1a.4.13 Utility Staff Cost 33,041 4,956 37,997 37,997 423,400 1a.4 Subtotal Period 1a PeriodDependent Costs 931 14 10 35 48,122 7,238 56,350 54,749 1,601 610 12,190 20 580,871 1a.0 TOTAL PERIOD 1a COST 931 14 10 35 52,851 8,013 61,853 60,252 1,601 610 12,190 20 616,761 PERIOD 1b SAFSTOR Limited DECON Activities Period 1b Direct Decommissioning Activities Decontamination of Site Buildings 1b.1.1.1 New Radwaste Building Systems Removal 0 0 0 0 1 1b.1.1.2 Old Radwaste Building Systems Removal 0 0 0 0 1 1b.1.1.3 Augmented Off Gas Decon 2 1 3 3 33 1b.1.1.4 Stack/Exhaust Tunnels Remove & Decon 54 27 81 81 849 1b.1.1.5 Turbine Building 0ft Decon 10 5 15 15 137 1b.1.1.6 Drywell Liner Removal 2,063 1,031 3,094 3,094 28,819 1b.1.1.7 RB0 Torus Removal 2,765 1,383 4,148 4,148 38,634 1b.1.1.8 Reactor Building 19ft Decon 7 3 10 10 96 1b.1.1.9 Reactor Building 119ft Decon 429 215 644 644 5,996 1b.1.1 Totals 5,330 2,665 7,996 7,996 74,565 1b.1 Subtotal Period 1b Activity Costs 5,330 2,665 7,996 7,996 74,565 Period 1b Additional Costs 1b.2.1 Spent fuel pool isolation 10,280 1,542 11,822 11,822 1b.2 Subtotal Period 1b Additional Costs 10,280 1,542 11,822 11,822 Period 1b Collateral Costs 1b.3.1 Decon equipment 902 135 1,037 1,037 1b.3.2 Process decommissioning water waste 288 127 343 620 363 1,742 1,742 1,817 109,041 354 1b.3.4 Small tool allowance 100 15 115 115 1b.3 Subtotal Period 1b Collateral Costs 1,190 100 127 343 620 514 2,894 2,894 1,817 109,041 354 Period 1b PeriodDependent Costs 1b.4.1 Decon supplies 1,056 264 1,320 1,320 1b.4.2 Insurance 418 42 459 459 1b.4.3 Property taxes 601 60 661 661 1b.4.4 Health physics supplies 442 111 553 553 1b.4.5 Heavy equipment rental 115 17 132 132 1b.4.6 Disposal of DAW generated 4 3 9 3 19 19 164 3,277 5 1b.4.7 Plant energy budget 478 72 550 550 1b.4.8 NRC Fees 192 19 211 211 1b.4.9 Emergency Planning Fees 141 14 155 155 1b.4.10 Site O&M Costs 77 12 89 89 1b.4.11 Spent Fuel Pool O&M 190 29 219 219 1b.4.12 ISFSI Operating Costs 22 3 26 26 1b.4.13 Security Staff Cost 2,104 316 2,420 2,420 39,260 1b.4.14 Utility Staff Cost 8,238 1,236 9,473 9,473 105,560 1b.4 Subtotal Period 1b PeriodDependent Costs 1,056 558 4 3 9 12,461 2,196 16,286 15,887 399 164 3,277 5 144,820 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 4 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 1b.0 TOTAL PERIOD 1b COST 7,576 658 131 346 630 22,740 6,917 38,998 38,599 399 1,981 112,319 74,925 144,820 PERIOD 1c Preparations for SAFSTOR Dormancy Period 1c Direct Decommissioning Activities 1c.1.1 Prepare support equipment for storage 489 73 562 562 3,000 1c.1.2 Install containment pressure equal. lines 51 8 59 59 700 1c.1.3 Interim survey prior to dormancy 733 220 953 953 12,166 1c.1.4 Secure building accesses a 1c.1.5 Prepare & submit interim report 70 10 80 80 583 1c.1 Subtotal Period 1c Activity Costs 540 803 311 1,654 1,654 15,866 583 Period 1c Collateral Costs 1c.3.1 Process decommissioning water waste 238 105 284 513 300 1,440 1,440 1,503 90,169 293 1c.3.3 Small tool allowance 5 1 6 6 1c.3 Subtotal Period 1c Collateral Costs 238 5 105 284 513 301 1,446 1,446 1,503 90,169 293 Period 1c PeriodDependent Costs 1c.4.1 Insurance 418 42 459 459 1c.4.2 Property taxes 601 60 661 661 1c.4.3 Health physics supplies 187 47 234 234 1c.4.4 Heavy equipment rental 115 17 132 132 1c.4.5 Disposal of DAW generated 4 2 9 3 18 18 152 3,039 5 1c.4.6 Plant energy budget 478 72 550 550 1c.4.7 NRC Fees 192 19 211 211 1c.4.8 Emergency Planning Fees 141 14 155 155 1c.4.9 Site O&M Costs 77 12 89 89 1c.4.10 Spent Fuel Pool O&M 190 29 219 219 1c.4.11 ISFSI Operating Costs 22 3 26 26 1c.4.12 Security Staff Cost 2,104 316 2,420 2,420 39,260 1c.4.13 Utility Staff Cost 8,238 1,236 9,473 9,473 105,560 1c.4 Subtotal Period 1c PeriodDependent Costs 302 4 2 9 12,461 1,869 14,646 14,247 399 152 3,039 5 144,820 1c.0 TOTAL PERIOD 1c COST 238 847 109 286 522 13,263 2,481 17,746 17,346 399 1,655 93,209 16,164 145,403 PERIOD 1 TOTALS 7,813 2,435 254 642 1,186 88,855 17,411 118,597 116,197 2,400 4,246 217,718 91,109 906,985 PERIOD 2a SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1 Quarterly Inspection a 2a.1.2 Semiannual environmental survey a 2a.1.3 Prepare reports a 2a.1.4 Bituminous roof replacement 722 108 830 830 2a.1.5 Maintenance supplies 1,992 498 2,490 2,490 2a.1 Subtotal Period 2a Activity Costs 2,714 606 3,321 3,321 Period 2a Collateral Costs 2a.3.1 Spent Fuel Capital and Transfer 12,250 1,838 14,088 14,088 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 5 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 2a.3 Subtotal Period 2a Collateral Costs 12,250 1,838 14,088 14,088 Period 2a PeriodDependent Costs 2a.4.1 Insurance 9,568 957 10,524 10,524 2a.4.2 Property taxes 14,904 1,490 16,395 16,395 2a.4.3 Health physics supplies 2,778 694 3,472 3,472 2a.4.4 Disposal of DAW generated 78 55 194 65 393 393 3,398 67,952 111 2a.4.5 Plant energy budget 5,665 850 6,515 6,515 2a.4.6 NRC ISFSI Fees 420 42 462 462 2a.4.7 NRC Fees 3,254 325 3,580 3,580 2a.4.8 Site O&M Costs 4,565 685 5,249 5,249 2a.4.9 Spent Fuel Pool O&M 11,270 1,690 12,960 12,960 2a.4.10 ISFSI Operating Costs 1,321 198 1,519 1,519 2a.4.11 Security Staff Cost 88,917 13,338 102,255 102,255 1,640,100 2a.4.12 Utility Staff Cost 94,837 14,226 109,063 109,063 1,216,600 2a.4 Subtotal Period 2a PeriodDependent Costs 2,778 78 55 194 234,720 34,560 272,386 7,444 264,941 3,398 67,952 111 2,856,700 2a.0 TOTAL PERIOD 2a COST 2,778 78 55 194 249,684 37,004 289,794 10,765 279,029 3,398 67,952 111 2,856,700 PERIOD 2b SAFSTOR Dormancy with Dry Spent Fuel Storage Period 2b Direct Decommissioning Activities 2b.1.1 Quarterly Inspection a 2b.1.2 Semiannual environmental survey a 2b.1.3 Prepare reports a 2b.1.4 Bituminous roof replacement 37 5 42 42 2b.1.5 Maintenance supplies 101 25 126 126 2b.1 Subtotal Period 2b Activity Costs 137 31 168 168 Period 2b Collateral Costs 2b.3.1 Spent Fuel Capital and Transfer 3,375 506 3,881 3,881 2b.3 Subtotal Period 2b Collateral Costs 3,375 506 3,881 3,881 Period 2b PeriodDependent Costs 2b.4.1 Insurance 429 43 472 472 2b.4.2 Property taxes 747 75 822 822 2b.4.3 Health physics supplies 68 17 85 85 2b.4.4 Disposal of DAW generated 2 1 5 2 10 10 83 1,653 3 2b.4.5 Plant energy budget 143 22 165 165 2b.4.6 NRC ISFSI Fees 139 14 153 153 2b.4.7 NRC Fees 165 16 181 181 2b.4.8 Site O&M Costs 231 35 266 266 2b.4.9 ISFSI Operating Costs 67 10 77 77 2b.4.10 Security Staff Cost 2,368 355 2,724 2,724 42,120 2b.4.11 Utility Staff Cost 1,975 296 2,272 2,272 24,960 2b.4 Subtotal Period 2b PeriodDependent Costs 68 2 1 5 6,266 884 7,227 276 6,950 83 1,653 3 67,080 2b.0 TOTAL PERIOD 2b COST 68 2 1 5 9,778 1,421 11,276 444 10,832 83 1,653 3 67,080 PERIOD 2 TOTALS 2,846 80 57 199 259,463 38,425 301,070 11,209 289,860 3,480 69,605 114 2,923,780 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 6 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 3a Reactivate Site Following SAFSTOR Dormancy Period 3a Direct Decommissioning Activities 3a.1.1 Prepare preliminary decommissioning cost 156 23 179 179 1,300 3a.1.2 Review plant dwgs & specs. 550 83 633 633 4,600 3a.1.3 Perform detailed rad survey a 3a.1.4 End product description 120 18 138 138 1,000 3a.1.5 Detailed byproduct inventory 156 23 179 179 1,300 3a.1.6 Define major work sequence 897 135 1,032 1,032 7,500 3a.1.7 Perform SER and EA 371 56 427 427 3,100 3a.1.8 Perform SiteSpecific Cost Study 598 90 688 688 5,000 3a.1.9 Prepare/submit License Termination Plan 490 74 564 564 4,096 3a.1.10 Receive NRC approval of termination plan a Activity Specifications 3a.1.11.1 Reactivate plant & temporary facilities 882 132 1,014 913 101 7,370 3a.1.11.2 Plant systems 499 75 573 516 57 4,167 3a.1.11.3 Reactor internals 850 127 977 977 7,100 3a.1.11.4 Reactor vessel 778 117 894 894 6,500 3a.1.11.5 Sacrificial shield 60 9 69 69 500 3a.1.11.6 Moisture separators/reheaters 120 18 138 138 1,000 3a.1.11.7 Reinforced concrete 191 29 220 110 110 1,600 3a.1.11.8 Main Turbine 250 37 287 287 2,088 3a.1.11.9 Main Condensers 250 37 287 287 2,088 3a.1.11.10 Pressure suppression structure 239 36 275 275 2,000 3a.1.11.11 Drywell 191 29 220 220 1,600 3a.1.11.12 Plant structures & buildings 373 56 429 215 215 3,120 3a.1.11.13 Waste management 550 83 633 633 4,600 3a.1.11.14 Facility & site closeout 108 16 124 62 62 900 3a.1.11 Total 5,340 801 6,141 5,596 545 44,633 Planning & Site Preparations 3a.1.12 Prepare dismantling sequence 287 43 330 330 2,400 3a.1.13 Plant prep. & temp. svces 2,800 420 3,220 3,220 3a.1.14 Design water cleanup system 168 25 193 193 1,400 3a.1.15 Rigging/Cont. Cntrl Envlps/tooling/etc. 2,200 330 2,530 2,530 3a.1.16 Procure casks/liners & containers 147 22 169 169 1,230 3a.1 Subtotal Period 3a Activity Costs 14,280 2,142 16,422 15,876 545 77,559 Period 3a PeriodDependent Costs 3a.4.1 Insurance 573 57 631 631 3a.4.2 Property taxes 999 100 1,099 1,099 3a.4.3 Health physics supplies 410 102 512 512 3a.4.4 Heavy equipment rental 462 69 531 531 3a.4.5 Disposal of DAW generated 12 8 29 10 59 59 514 10,287 17 3a.4.6 Plant energy budget 1,918 288 2,206 2,206 3a.4.7 NRC Fees 272 27 299 299 3a.4.8 Site O&M Costs 309 46 355 355 3a.4.9 Security Staff Cost 3,629 544 4,173 4,173 65,179 3a.4.10 Utility Staff Cost 20,498 3,075 23,573 23,573 258,629 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 7 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 3a.4 Subtotal Period 3a PeriodDependent Costs 872 12 8 29 28,199 4,319 33,440 33,440 514 10,287 17 323,807 3a.0 TOTAL PERIOD 3a COST 872 12 8 29 42,479 6,461 49,861 49,316 545 514 10,287 17 401,366 PERIOD 3b Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems 566 85 651 586 65 4,733 3b.1.1.2 Reactor internals 479 72 550 550 4,000 3b.1.1.3 Remaining buildings 162 24 186 46 139 1,350 3b.1.1.4 CRD housings & NIs 120 18 138 138 1,000 3b.1.1.5 Incore instrumentation 120 18 138 138 1,000 3b.1.1.6 Removal primary containment 239 36 275 275 2,000 3b.1.1.7 Reactor vessel 434 65 499 499 3,630 3b.1.1.8 Facility closeout 144 22 165 83 83 1,200 3b.1.1.9 Sacrificial shield 144 22 165 165 1,200 3b.1.1.10 Reinforced concrete 120 18 138 69 69 1,000 3b.1.1.11 Main Turbine 249 37 286 286 2,080 3b.1.1.12 Main Condensers 250 37 287 287 2,088 3b.1.1.13 Moisture separators & reheaters 239 36 275 275 2,000 3b.1.1.14 Radwaste building 327 49 376 338 38 2,730 3b.1.1.15 Reactor building 327 49 376 338 38 2,730 3b.1.1 Total 3,917 588 4,505 4,074 431 32,741 3b.1 Subtotal Period 3b Activity Costs 3,917 588 4,505 4,074 431 32,741 Period 3b Additional Costs 3b.2.1 Site Characterization 4,986 1,496 6,482 6,482 27,140 9,952 3b.2.2 Disposition of Liquid RCRA Waste (not Lead) 17 529 135 680 680 2,019 115,076 3b.2.3 Disposition of PCB Soil RCRA Waste (not Lead) 1,362 1,450 567 3,378 3,378 27,000 3,240,000 3b.2.4 Disposition of Lead Inventory 26 756 117 899 899 328 232,673 3b.2.5 Asbestos Remediation 12,217 2 279 1,030 3,354 16,883 16,883 19,193 249,515 150,230 3b.2 Subtotal Period 3b Additional Costs 12,217 2 1,684 756 3,009 4,986 5,669 28,323 28,323 328 48,212 3,837,264 177,370 9,952 Period 3b Collateral Costs 3b.3.1 Decon equipment 902 135 1,037 1,037 3b.3.2 DOC staff relocation expenses 1,124 169 1,292 1,292 3b.3.3 Small tool allowance 184 28 211 211 3b.3.4 Pipe cutting equipment 1,100 165 1,265 1,265 3b.3 Subtotal Period 3b Collateral Costs 902 1,284 1,124 496 3,806 3,806 Period 3b PeriodDependent Costs 3b.4.1 Decon supplies 28 7 35 35 3b.4.2 Insurance 287 29 316 316 3b.4.3 Property taxes 501 50 551 551 3b.4.4 Health physics supplies 879 220 1,099 1,099 3b.4.5 Heavy equipment rental 232 35 266 266 3b.4.6 Disposal of DAW generated 7 5 17 6 34 34 292 5,834 10 3b.4.7 Plant energy budget 962 144 1,106 1,106 3b.4.8 NRC Fees 136 14 150 150 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 8 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 3b PeriodDependent Costs (continued) 3b.4.9 Site O&M Costs 155 23 178 178 3b.4.10 Security Staff Cost 1,819 273 2,092 2,092 32,679 3b.4.11 DOC Staff Cost 5,076 761 5,838 5,838 58,560 3b.4.12 Utility Staff Cost 10,277 1,542 11,819 11,819 129,669 3b.4 Subtotal Period 3b PeriodDependent Costs 28 1,111 7 5 17 19,214 3,103 23,484 23,484 292 5,834 10 220,907 3b.0 TOTAL PERIOD 3b COST 930 14,611 8 1,689 756 3,025 29,242 9,855 60,117 59,686 431 328 48,504 3,843,098 177,380 263,600 PERIOD 3 TOTALS 930 15,483 20 1,698 756 3,055 71,721 16,317 109,979 109,002 976 328 49,018 3,853,385 177,396 664,966 PERIOD 4a Large Component Removal Period 4a Direct Decommissioning Activities Nuclear Steam Supply System Removal 4a.1.1.2 Recirculation Pumps & Motors 10 108 41 136 8 216 112 632 632 107 1,053 196,350 2,156 4a.1.1.3 CRDMs & NIs Removal 40 179 523 141 137 172 1,190 1,190 5,179 112,850 3,338 4a.1.1.4 Reactor Vessel Internals 114 2,810 5,441 1,228 4,927 213 6,327 21,060 21,060 1,502 1,002 470 298,460 22,925 1,049 4a.1.1.5 Vessel & Internals GTCC Disposal 4,450 667 5,117 5,117 1,428 282,300 4a.1.1.6 Reactor Vessel 87 6,370 1,859 1,718 2,333 213 6,913 19,494 19,494 14,674 1,573,112 22,925 1,049 4a.1.1 Totals 251 9,467 7,864 3,222 8 12,062 427 14,192 47,492 47,492 107 22,409 1,002 470 1,428 2,463,072 51,345 2,098 Removal of Major Equipment 4a.1.2 Main Turbine/Generator 326 1,861 391 1,707 582 4,867 4,867 80,711 3,632,000 4,957 4a.1.3 Main Condensers 1,000 1,291 271 1,184 597 4,344 4,344 56,000 2,520,000 15,180 New Radwaste Building System Components 4a.1.7.1 7EB 162 9 9 7 23 49 259 259 362 334 33,679 2,492 4a.1.7.2 N2G 11 0 0 1 3 16 16 49 2,007 178 4a.1.7.3 N2P 24 1 1 6 7 40 40 341 13,830 357 4a.1.7.4 N3A 68 1 2 8 18 96 96 398 16,151 1,000 4a.1.7.5 N3D 81 1 2 10 22 115 115 501 20,362 1,263 4a.1.7.6 N3I 17 0 0 1 0 4 23 23 27 5 1,390 273 4a.1.7.7 N3N 101 1 2 9 27 139 139 447 18,140 1,529 4a.1.7.8 N3P 26 0 1 3 7 37 37 179 7,267 383 4a.1.7.9 N3Q 17 0 0 2 5 24 24 80 3,260 271 4a.1.7.10 N3R 17 0 0 2 5 24 24 97 3,934 261 4a.1.7.11 N3S 25 0 1 4 7 37 37 187 7,583 400 4a.1.7.12 N3T 16 0 0 1 4 21 21 58 2,357 243 4a.1.7.13 N3U 113 14 14 12 38 43 234 234 610 548 55,829 1,727 4a.1.7.14 N3W 117 16 15 12 41 45 247 247 643 604 60,369 1,792 4a.1.7.15 N3Y 208 5 13 58 63 348 348 3,054 124,028 3,179 4a.1.7.16 N51 28 0 1 5 8 42 42 239 9,707 433 4a.1.7.17 N52 23 1 1 2 3 7 38 38 121 43 7,290 353 4a.1.7.18 N53 35 2 3 5 5 11 61 61 248 75 14,268 541 4a.1.7.19 N54 17 1 1 1 2 5 26 26 46 28 3,435 260 4a.1.7.20 N55 73 1 2 8 20 104 104 414 16,809 1,137 4a.1.7.21 N56 97 1 3 14 27 143 143 734 29,828 1,389 4a.1.7.22 N5A 42 1 2 6 2 12 64 64 290 26 13,205 663 4a.1.7.23 N5B 39 1 1 6 11 58 58 307 12,485 621 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 9 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours New Radwaste Building System Components (continued) 4a.1.7.24 N5C 18 0 0 2 5 25 25 106 4,294 267 4a.1.7.25 N5D 28 0 1 3 8 39 39 152 6,190 426 4a.1.7.26 N5E 19 0 0 2 5 26 26 110 4,453 278 4a.1.7.27 N5F 27 2 1 2 3 8 43 43 91 45 6,294 408 4a.1.7.28 N5G 13 0 0 1 3 18 18 40 1,645 205 4a.1.7.29 N5H 11 1 1 0 2 3 18 18 5 26 1,667 172 4a.1.7.30 N5I 15 0 0 1 4 21 21 51 2,090 238 4a.1.7.31 N5J 12 0 1 3 3 19 19 131 5,328 187 4a.1.7.32 N5K 15 0 0 1 4 21 21 75 3,050 224 4a.1.7.33 N5N 28 0 1 3 8 39 39 143 5,803 433 4a.1.7.34 N5O 72 1 3 13 21 110 110 670 27,221 1,105 4a.1.7.35 N5P 26 2 2 3 4 9 46 46 183 62 10,822 420 4a.1.7.36 N5Q 26 2 2 3 4 8 46 46 182 61 10,719 414 4a.1.7.37 N5S 64 4 10 42 24 143 143 2,195 89,151 1,024 4a.1.7.38 N5T 59 2 3 12 3 18 97 97 606 40 26,812 930 4a.1.7.39 N5U 60 2 3 12 3 18 98 98 607 40 26,871 942 4a.1.7.40 N5Y 23 1 1 3 1 7 36 36 153 19 7,306 358 4a.1.7.41 N5Z 23 1 1 3 1 7 36 36 153 19 7,306 358 4a.1.7.42 PPA 75 1 3 11 21 110 110 572 23,240 1,139 4a.1.7 Totals 1,972 76 109 299 135 596 3,187 3,187 15,660 1,977 747,476 30,271 Old Radwaste Building System Components 4a.1.8.1 7BA 83 1 2 9 22 117 117 480 19,481 1,272 4a.1.8.2 7DA 48 5 5 2 14 17 92 92 122 206 16,640 738 4a.1.8.3 7FA 22 1 2 4 3 7 39 39 206 43 10,810 355 4a.1.8.4 PBA 147 12 12 17 26 49 263 263 893 388 57,934 2,324 4a.1.8.5 PDA 52 1 2 7 14 75 75 373 15,150 808 4a.1.8.6 PMA 12 0 0 1 3 17 17 54 2,174 190 4a.1.8.7 PRA 82 1 4 16 24 128 128 855 34,703 1,292 4a.1.8.8 PTK / PTP 13 0 0 1 3 17 17 30 1,199 202 4a.1.8 Totals 460 21 26 57 43 141 749 749 3,011 637 158,091 7,180 Turbine Building System Components 4a.1.9.1 7CA 260 21 22 33 46 87 468 468 1,755 663 108,906 4,017 4a.1.9.2 TB2 961 19 52 227 284 1,544 1,544 11,906 483,529 14,570 4a.1.9.3 TB23 5 0 0 1 1 8 8 42 1,699 83 4a.1.9.4 TB38 16 0 1 2 5 24 24 124 5,034 229 4a.1.9.5 TC2 1,562 70 188 820 549 3,190 3,190 42,978 1,745,363 23,871 4a.1.9.6 TE2 186 12 20 60 22 65 365 365 3,126 317 144,922 2,822 4a.1.9.7 TEE 320 7 18 79 95 519 519 4,115 167,126 4,871 4a.1.9.8 TEG 26 0 1 3 7 36 36 139 5,640 380 4a.1.9.9 TP2 170 4 12 51 52 289 289 2,659 107,977 2,613 4a.1.9.10 TP3 113 9 10 16 20 38 205 205 859 292 51,008 1,793 4a.1.9.11 TPE 102 10 10 12 23 36 193 193 647 335 45,003 1,572 4a.1.9 Totals 3,722 153 332 1,305 110 1,219 6,840 6,840 68,349 1,608 2,866,205 56,820 4a.1.12 Scaffolding in support of decommissioning 940 27 7 22 8 244 1,249 1,249 1,057 112 53,901 16,869 4a.1 Subtotal Period 4a Activity Costs 251 17,887 11,294 4,359 4,583 12,357 427 17,571 68,729 68,729 224,895 26,743 1,002 470 1,428 12,440,740 182,622 2,098 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 10 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 4a Collateral Costs 4a.3.1 Process decommissioning water waste 24 15 39 71 37 185 185 207 12,411 40 4a.3.3 Small tool allowance 223 33 257 231 26 4a.3 Subtotal Period 4a Collateral Costs 24 223 15 39 71 70 442 416 26 207 12,411 40 Period 4a PeriodDependent Costs 4a.4.1 Decon supplies 62 15 77 77 4a.4.2 Insurance 643 64 707 707 4a.4.3 Property taxes 1,120 112 1,232 1,109 123 4a.4.4 Health physics supplies 1,311 328 1,639 1,639 4a.4.5 Heavy equipment rental 2,252 338 2,590 2,590 4a.4.6 Disposal of DAW generated 85 60 212 71 428 428 3,704 74,073 121 4a.4.7 Plant energy budget 2,042 306 2,348 2,348 4a.4.8 NRC Fees 804 80 884 884 4a.4.9 Site O&M Costs 346 52 398 398 4a.4.10 Liquid Radwaste Processing Equipment/Services 434 65 499 499 4a.4.11 Security Staff Cost 4,066 610 4,676 4,676 73,036 4a.4.12 DOC Staff Cost 13,729 2,059 15,789 15,789 161,263 4a.4.13 Utility Staff Cost 23,178 3,477 26,654 26,654 292,143 4a.4 Subtotal Period 4a PeriodDependent Costs 62 3,563 85 60 212 46,362 7,578 57,922 57,799 123 3,704 74,073 121 526,441 4a.0 TOTAL PERIOD 4a COST 336 21,674 11,394 4,459 4,583 12,639 46,789 25,219 127,092 126,943 149 224,895 30,653 1,002 470 1,428 12,527,230 182,783 528,539 PERIOD 4b Site Decontamination Period 4b Direct Decommissioning Activities 4b.1.1 Remove spent fuel racks 545 64 142 226 744 523 2,243 2,243 10,858 615,095 1,071 Disposal of Plant Systems Drywell System Components 4b.1.2.1 IAA/IAC 329 218 191 136 527 285 1,685 1,685 7,111 7,660 723,932 5,700 4b.1.2.2 IBA 164 19 19 17 50 61 330 330 880 734 77,321 2,588 4b.1.2.3 ICA 263 36 32 35 79 99 543 543 1,841 1,148 140,037 4,149 4b.1.2.4 IEA 70 9 11 18 22 28 157 157 926 320 55,719 1,176 4b.1.2.5 RC6 65 1 2 8 18 95 95 440 17,889 989 4b.1.2 Totals 890 282 255 214 678 491 2,809 2,809 11,199 9,861 1,014,897 14,602 Reactor Building System Components 4b.1.3.1 RB1 202 4 11 48 60 324 324 2,495 101,308 2,991 4b.1.3.2 RBB 106 2 6 25 31 170 170 1,306 53,019 1,597 4b.1.3.3 RBC 108 2 6 28 33 178 178 1,485 60,294 1,647 4b.1.3.4 RBE 142 2 6 26 41 217 217 1,381 56,063 2,156 4b.1.3.5 RBF 121 14 14 14 35 45 244 244 740 516 59,235 1,909 4b.1.3.6 RBO 526 18 49 214 173 981 981 11,229 456,005 8,678 4b.1.3.7 RBS 247 22 27 53 50 88 486 486 2,757 727 153,183 3,897 4b.1.3.8 RBSW 135 2 6 26 39 207 207 1,343 54,558 2,077 4b.1.3.9 RC1/RC3 4 0 0 0 1 6 6 14 577 63 4b.1.3.10 RC7 90 2 5 21 27 145 145 1,106 44,917 1,311 4b.1.3.11 RCA 47 3 3 3 8 15 79 79 147 109 12,175 725 4b.1.3.12 RCB 69 2 3 10 2 20 105 105 501 28 21,917 1,051 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 11 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Reactor Building System Components (continued) 4b.1.3.13 RCD 352 7 17 76 103 555 555 3,974 161,384 5,318 4b.1.3.14 RCG 67 2 5 22 21 116 116 1,136 46,136 1,041 4b.1.3.15 RCJ 74 1 3 12 21 110 110 617 25,044 1,121 4b.1.3.16 RCM 109 2 6 28 33 179 179 1,481 60,136 1,694 4b.1.3.17 RCN 243 3 9 40 69 365 365 2,107 85,581 3,666 4b.1.3.18 RCS 87 15 14 12 38 37 204 204 636 561 57,657 1,365 4b.1.3.19 RCT 57 1 2 9 16 84 84 464 18,858 858 4b.1.3.20 RD8 87 66 66 36 189 91 535 535 1,861 2,761 231,971 1,484 4b.1.3.21 RDM 48 0 1 5 13 67 67 268 10,870 701 4b.1.3.22 REC 216 3 9 37 61 326 326 1,953 79,329 3,190 4b.1.3.23 REF 100 23 21 13 60 47 264 264 667 875 76,709 1,550 4b.1.3.24 REH/REI 121 2 6 25 35 189 189 1,325 53,806 1,846 4b.1.3.25 REL 215 5 14 63 66 364 364 3,286 133,445 3,285 4b.1.3.26 REM 57 1 2 10 16 87 87 538 21,846 868 4b.1.3.27 REO 122 21 22 21 57 53 296 296 1,115 827 92,099 1,930 4b.1.3.28 REQ 169 9 11 25 17 53 284 284 1,311 254 67,684 2,610 4b.1.3.29 RER 56 5 4 3 11 19 98 98 177 167 16,663 881 4b.1.3.30 RET 32 1 1 4 1 9 48 48 185 18 8,515 500 4b.1.3.31 REW 28 0 1 3 8 39 39 146 5,936 432 4b.1.3.32 REX 31 0 1 3 8 43 43 165 6,710 477 4b.1.3.33 REY 36 0 1 4 10 50 50 192 7,781 543 4b.1.3.34 RFB 159 3 7 31 46 246 246 1,622 65,859 2,449 4b.1.3.35 RFC 104 12 9 6 24 35 190 190 337 351 33,707 1,649 4b.1.3.36 RFF 111 2 4 18 31 166 166 923 37,469 1,696 4b.1.3.37 RFH 152 25 22 13 61 61 335 335 692 893 78,810 2,337 4b.1.3.38 RFJ 133 23 21 13 59 56 305 305 690 866 77,154 2,052 4b.1.3.39 RFL 85 1 3 14 24 128 128 754 30,625 1,337 4b.1.3.40 RFN 115 2 5 21 33 176 176 1,118 45,418 1,768 4b.1.3.41 RFQ 167 2 4 18 45 236 236 942 38,243 2,456 4b.1.3.42 RGC 89 1 3 13 25 130 130 667 27,107 1,368 4b.1.3.43 RGD 251 7 19 84 79 441 441 4,427 179,773 3,921 4b.1.3.44 RGI 53 1 2 8 15 78 78 414 16,826 835 4b.1.3.45 RGL 62 1 2 11 18 94 94 555 22,545 967 4b.1.3.46 RGP 29 0 1 5 8 43 43 238 9,661 437 4b.1.3.47 RGR 190 3 7 31 54 284 284 1,633 66,314 2,876 4b.1.3.48 RGU 85 1 2 10 23 121 121 547 22,199 1,312 4b.1.3.49 RH1 50 1 1 6 14 72 72 339 13,754 762 4b.1.3.50 RH2 37 1 2 10 11 62 62 550 22,340 572 4b.1.3.51 RH3 / RH4 / RH6 127 1 3 11 34 176 176 592 24,061 1,896 4b.1.3.52 RHA 21 1 2 2 4 7 36 36 83 57 6,596 326 4b.1.3.53 RHJ 45 0 1 5 12 64 64 282 11,443 687 4b.1.3.54 RHL 29 0 1 2 8 40 40 121 4,913 431 4b.1.3.55 RHX 54 1 2 8 15 80 80 440 17,877 814 4b.1.3.56 RHY 49 1 2 7 13 71 71 369 14,998 750 4b.1.3.57 RMCC 98 2 4 19 28 151 151 989 40,165 1,468 4b.1.3 Totals 6,397 332 482 1,287 618 2,053 11,170 11,170 67,430 9,010 3,249,269 98,630 New Radwaste Building System Components 4b.1.4.1 N38 173 2 6 27 48 256 256 1,392 56,536 2,566 4b.1.4.2 N48 88 1 2 10 24 125 125 530 21,506 1,308 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 12 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours New Radwaste Building System Components (continued) 4b.1.4.3 N4A 29 2 2 3 4 9 50 50 183 63 10,949 470 4b.1.4.4 N4B 28 2 2 3 4 9 46 46 162 53 9,549 442 4b.1.4.5 N4D 91 1 2 9 24 127 127 459 18,650 1,350 4b.1.4.6 N4E 7 0 0 0 2 9 9 17 687 107 4b.1.4.7 N4F 19 0 0 2 5 27 27 98 3,986 289 4b.1.4.8 N4H 22 1 1 4 2 7 38 38 217 23 10,137 364 4b.1.4.9 N4K 24 0 1 3 7 35 35 176 7,138 364 4b.1.4.10 N4L 35 0 1 3 10 49 49 177 7,195 553 4b.1.4.11 N5R 77 2 4 20 23 125 125 1,029 41,782 1,188 4b.1.4.12 N5V 59 4 5 9 10 20 107 107 482 146 27,568 934 4b.1.4.13 N5W 9 0 0 0 2 12 12 10 401 148 4b.1.4.14 N5X 74 1 4 16 22 116 116 842 34,176 1,155 4b.1.4 Totals 734 16 31 110 19 211 1,122 1,122 5,774 286 250,260 11,236 Old Radwaste Building System Components 4b.1.5.1 ORW Pre D&D Desludge and Decon 203 30 234 234 2,839 4b.1.5.2 PRD 15 0 1 3 4 23 23 151 6,112 245 4b.1.5.3 PSB 139 2 5 23 39 209 209 1,198 48,634 2,135 4b.1.5.4 PTA 39 1 2 7 11 59 59 371 15,084 601 4b.1.5.5 PUA 208 2 6 27 57 300 300 1,389 56,392 3,154 4b.1.5.6 PUU 141 5 10 35 5 44 239 239 1,825 83 78,582 2,225 4b.1.5.7 PVA 9 0 0 0 2 12 12 13 519 148 4b.1.5.8 UAB 304 4 10 45 85 448 448 2,367 96,117 4,649 4b.1.5.9 UAS 208 4 10 43 61 326 326 2,277 92,465 3,222 4b.1.5 Totals 1,268 18 44 183 5 334 1,851 1,851 9,590 83 393,904 19,219 Turbine Building System Components 4b.1.6.1 TD2 60 1 2 7 17 87 87 390 15,850 875 4b.1.6.2 TF2 324 16 42 184 117 683 683 9,646 391,743 4,891 4b.1.6.3 TFG 23 0 1 3 6 34 34 150 6,106 361 4b.1.6.4 TG2 236 12 33 144 87 513 513 7,564 307,179 3,660 4b.1.6.5 TH2 459 21 56 243 162 940 940 12,740 517,385 7,040 4b.1.6.6 TKA 24 0 0 1 6 32 32 74 2,996 348 4b.1.6.7 TL2 100 7 6 10 14 32 168 168 523 201 32,662 1,480 4b.1.6.8 TMA 61 1 4 17 18 102 102 895 36,367 921 4b.1.6.9 TN2 320 7 19 85 96 528 528 4,447 180,585 4,873 4b.1.6.10 TO2 170 26 196 196 2,826 4b.1.6.11 TOA 87 2 4 19 26 138 138 1,014 41,172 1,303 4b.1.6.12 TOCR 74 3 7 32 25 141 141 1,692 68,697 1,058 4b.1.6.13 TOR 65 2 4 18 20 107 107 931 37,795 994 4b.1.6.14 TOV 19 0 0 2 5 27 27 98 3,978 292 4b.1.6.15 TOW 103 4 11 49 35 202 202 2,557 103,857 1,547 4b.1.6.16 TOX / TOY 28 0 1 2 8 39 39 124 5,052 423 4b.1.6.17 TS2 201 6 17 74 64 362 362 3,875 157,362 2,995 4b.1.6.18 TTA 60 1 4 17 18 101 101 899 36,508 957 4b.1.6.19 TU2 185 3 9 40 54 292 292 2,096 85,139 2,856 4b.1.6 Totals 2,599 87 221 949 14 820 4,691 4,495 196 49,717 201 2,030,434 39,701 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 13 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Augmented Offgas System Components 4b.1.7.1 AY8 143 3 7 30 42 224 224 1,596 64,813 2,154 4b.1.7.2 AYA 30 1 2 10 9 53 53 512 20,775 459 4b.1.7.3 AYB 29 0 1 5 8 43 43 267 10,862 441 4b.1.7.4 AYC 73 2 4 19 22 120 120 1,012 41,078 1,127 4b.1.7.5 AYE 25 0 0 2 7 35 35 103 4,199 375 4b.1.7.6 AZ8 54 1 3 12 16 85 85 611 24,796 824 4b.1.7.7 AZA 12 0 0 1 3 17 17 40 1,638 188 4b.1.7.8 AZC 103 2 5 22 30 162 162 1,145 46,509 1,555 4b.1.7.9 AZD 17 0 0 1 5 24 24 75 3,063 267 4b.1.7.10 AZE 16 0 0 1 4 23 23 70 2,856 256 4b.1.7.11 AZF 15 0 0 2 4 22 22 90 3,672 239 4b.1.7.12 AZI 30 1 1 7 9 47 47 343 13,938 461 4b.1.7 Totals 547 10 26 112 158 853 853 5,865 238,198 8,345 Miscellaneous System Components 4b.1.8.1 BAA 262 5 14 62 77 421 421 3,241 131,602 3,979 4b.1.8.2 BBA 88 4 10 42 30 173 173 2,183 88,656 1,368 4b.1.8.3 BDA 11 0 0 1 3 14 14 27 1,083 167 4b.1.8.4 CAA 615 17 45 196 192 1,064 1,064 10,252 416,330 9,611 4b.1.8.5 DAA 64 1 2 7 17 91 91 376 15,277 1,005 4b.1.8.6 DAC 152 2 5 23 42 225 225 1,230 49,940 2,323 4b.1.8.7 DGB 82 12 94 94 1,336 4b.1.8.8 DOT 14 2 16 16 223 4b.1.8.9 DPH 95 14 109 109 1,527 4b.1.8.10 DWF 22 3 25 25 360 4b.1.8.11 FWP 127 19 146 146 2,018 4b.1.8.12 GAA / GCA 23 3 26 26 368 4b.1.8.13 INTAKE STRUCTURE 199 30 229 229 3,218 4b.1.8.14 MAA 127 2 6 28 37 200 200 1,469 59,650 1,920 4b.1.8.15 MBA 51 1 2 8 14 76 76 413 16,776 764 4b.1.8.16 MBS / MBT 38 0 0 2 10 50 50 108 4,371 575 4b.1.8.17 MS 40 6 46 46 676 4b.1.8.18 NMB ROOF 20 3 22 22 312 4b.1.8.19 OB 292 44 336 336 4,806 4b.1.8.20 PTB 43 6 49 49 688 4b.1.8.21 RSF ROOF 29 0 1 3 8 42 42 175 7,097 451 4b.1.8.22 UYARD 1,807 10 27 118 474 2,435 2,435 6,162 250,262 21,730 4b.1.8.23 WAA 166 2 5 23 46 242 242 1,197 48,603 2,479 4b.1.8.24 WHS 19 3 22 22 318 4b.1.8.25 YARD AREAS 408 61 470 470 6,583 4b.1.8.26 YDA / YFA / YLA 2 0 0 0 1 3 3 19 783 30 4b.1.8 Totals 4,796 44 117 513 1,159 6,629 5,037 1,592 26,851 1,090,429 68,833 4b.1.9 Scaffolding in support of decommissioning 1,410 41 11 34 11 366 1,873 1,873 1,586 168 80,852 25,304 Decontamination of Site Buildings 4b.1.10.1 New Radwaste Building Systems Removal 0 146 103 156 0 233 129 767 767 6 4,340 382,187 2,226 4b.1.10.2 Old Radwaste Building Systems Removal 0 4 11 17 0 25 11 67 67 6 461 40,787 66 4b.1.10.3 Turbine Building Systems Removal 419 249 376 561 326 1,931 1,931 10,447 919,350 5,562 4b.1.10.4 Augmented Off Gas Decon 19 117 15 23 1 34 52 261 261 45 629 57,149 1,961 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 14 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Decontamination of Site Buildings (continued) 4b.1.10.5 LLRW Storage Decon 10 36 9 14 20 22 112 112 379 33,330 653 4b.1.10.6 Miscellaneous Buildings Decon 10 48 9 13 20 25 126 126 372 32,778 831 4b.1.10.7 New Radwaste Building Decon 47 441 58 88 4 130 186 955 955 235 2,420 222,115 7,003 4b.1.10.8 Old Radwaste Building Decon 410 237 359 3 535 314 1,859 1,859 152 9,965 882,859 4,833 4b.1.10.9 Stack/Exhaust Tunnels Remove & Decon 103 494 36 55 82 207 977 977 1,521 133,878 8,806 4b.1.10.10 Turbine Building 0ft Decon 72 532 58 88 22 127 223 1,122 1,122 1,144 2,356 252,047 8,702 4b.1.10.11 Turbine Building 23ft Decon 47 381 44 68 21 97 161 818 818 1,109 1,789 200,730 6,140 4b.1.10.12 Turbine Building 46ft Decon 29 121 26 39 58 68 340 340 1,073 94,413 2,127 4b.1.10.13 Drywell Decon 4 727 395 513 1,006 552 3,198 3,198 16,964 1,290,650 9,848 4b.1.10.14 Drywell Liner Removal 2,063 1,197 74 105 422 71 1,435 5,366 5,366 22,108 1,022 956,216 47,924 4b.1.10.15 RB0 Torus Removal 2,765 1,375 110 156 626 105 1,881 7,017 7,017 32,774 1,515 1,417,560 60,646 4b.1.10.16 Reactor Building Systems Removal 6 18 27 40 17 107 107 736 64,800 101 4b.1.10.17 Reactor Building 19ft Decon 33 277 28 44 39 57 115 593 593 2,052 1,043 172,007 4,412 4b.1.10.18 Reactor Building 119ft Decon 442 537 16 24 30 29 372 1,450 1,450 1,563 526 107,572 14,581 4b.1.10.19 Reactor Building 23ft Decon 21 128 19 29 43 60 299 299 796 70,017 2,140 4b.1.10.20 Reactor Building 51ft Decon 24 133 21 32 48 64 322 322 887 78,096 2,253 4b.1.10.21 Reactor Building 75ft Decon 8 71 7 11 16 28 141 141 297 26,136 1,155 4b.1.10.22 Reactor Building 91ft Decon 17 111 15 23 34 50 250 250 634 55,770 1,847 4b.1.10 Totals 5,715 7,712 1,558 2,257 1,168 3,369 6,297 28,076 28,076 61,196 60,173 7,490,445 193,816 4b.1 Subtotal Period 4b Activity Costs 6,260 26,416 2,530 3,671 4,569 5,459 12,412 61,317 59,530 1,787 239,206 90,639 16,453,780 480,758 Period 4b Additional Costs 4b.2.1 ISFSI License Termination 1,563 1,587 1,411 999 5,560 5,560 19,521 2,578,520 4b.2.2 ISFSI License Termination Cascading Costs 778 247 154 1,179 1,179 4b.2.3 License Termination Survey Planning 1,948 584 2,532 2,532 12,480 4b.2.4 Contaminated Soil Removal 111 2 500 5,702 1,529 7,844 7,844 106,200 8,071,193 834 4b.2 Subtotal Period 4b Additional Costs 2,453 2 500 7,289 3,605 3,266 17,116 10,376 6,739 125,721 10,649,710 834 12,480 Period 4b Collateral Costs 4b.3.1 Process decommissioning water waste 52 33 88 159 82 414 414 466 27,948 91 4b.3.3 Small tool allowance 592 89 681 681 4b.3.4 Decommissioning Equipment Disposition 155 49 127 44 53 427 427 6,000 635 305,961 88 4b.3 Subtotal Period 4b Collateral Costs 52 592 188 137 127 203 224 1,521 1,521 6,000 1,101 333,910 179 Period 4b PeriodDependent Costs 4b.4.1 Decon supplies 1,124 281 1,404 1,404 4b.4.2 Insurance 850 85 935 935 4b.4.3 Property taxes 1,481 148 1,629 1,629 4b.4.4 Health physics supplies 2,768 692 3,460 3,460 4b.4.5 Heavy equipment rental 2,955 443 3,398 3,398 4b.4.6 Disposal of DAW generated 171 121 424 141 857 857 7,415 148,298 242 4b.4.7 Plant energy budget 2,132 320 2,452 2,452 4b.4.8 NRC Fees 1,063 106 1,170 1,170 4b.4.9 Site O&M Costs 458 69 527 527 4b.4.10 Liquid Radwaste Processing Equipment/Services 574 86 661 661 4b.4.11 Security Staff Cost 5,378 807 6,185 6,185 96,607 4b.4.12 DOC Staff Cost 17,703 2,655 20,358 20,358 207,126 4b.4.13 Utility Staff Cost 29,142 4,371 33,513 33,513 364,789 4b.4 Subtotal Period 4b PeriodDependent Costs 1,124 5,723 171 121 424 58,782 10,205 76,549 76,549 7,415 148,298 242 668,521 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 15 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 4b.0 TOTAL PERIOD 4b COST 7,435 35,184 2,891 4,429 4,696 13,374 62,387 26,106 156,503 147,976 6,739 1,787 245,206 224,875 27,585,700 482,012 681,001 PERIOD 4f License Termination Period 4f Direct Decommissioning Activities 4f.1.1 ORISE confirmatory survey 161 48 210 210 4f.1.2 Terminate license a 4f.1 Subtotal Period 4f Activity Costs 161 48 210 210 Period 4f Additional Costs 4f.2.1 License Termination Survey 8,201 2,460 10,661 10,661 118,801 6,240 4f.2 Subtotal Period 4f Additional Costs 8,201 2,460 10,661 10,661 118,801 6,240 Period 4f Collateral Costs 4f.3.1 DOC staff relocation expenses 1,124 169 1,292 1,292 4f.3 Subtotal Period 4f Collateral Costs 1,124 169 1,292 1,292 Period 4f PeriodDependent Costs 4f.4.2 Property taxes 753 75 828 828 4f.4.3 Health physics supplies 802 201 1,003 1,003 4f.4.4 Disposal of DAW generated 8 6 20 7 41 41 351 7,025 11 4f.4.5 Plant energy budget 289 43 332 332 4f.4.6 NRC Fees 579 58 637 637 4f.4.7 Site O&M Costs 233 35 268 268 4f.4.8 Security Staff Cost 1,087 163 1,250 1,250 18,857 4f.4.9 DOC Staff Cost 5,156 773 5,929 5,929 57,357 4f.4.10 Utility Staff Cost 6,703 1,005 7,708 7,708 74,643 4f.4 Subtotal Period 4f PeriodDependent Costs 802 8 6 20 14,800 2,361 17,997 17,997 351 7,025 11 150,857 4f.0 TOTAL PERIOD 4f COST 802 8 6 20 24,286 5,038 30,161 30,161 351 7,025 118,812 157,097 PERIOD 4 TOTALS 7,771 57,660 14,293 8,894 9,279 26,034 133,462 56,363 313,755 305,080 6,739 1,936 470,101 255,880 1,002 470 1,428 40,119,960 783,607 1,366,638 PERIOD 5b Site Restoration Period 5b Direct Decommissioning Activities Demolition of Remaining Site Buildings 5b.1.1.1 Stack/Exhaust Tunnels Remove & Decon 1,019 153 1,172 1,172 1,665 5b.1.1.2 Administration Building 506 76 582 582 6,477 5b.1.1.3 Augmented Off Gas Building 338 51 388 388 3,399 5b.1.1.4 Chlorination Building 32 5 36 36 407 5b.1.1.5 Diesel Generator Building 137 21 157 157 1,268 5b.1.1.6 Dilution Structure 178 27 205 205 1,758 5b.1.1.7 Domestic Water Facility 11 2 12 12 147 5b.1.1.8 Fire Pump House 4 1 5 5 54 5b.1.1.9 Fresh Water Pump House 22 3 26 26 293 5b.1.1.10 Heating Boiler House 41 6 48 48 546 5b.1.1.11 Intake Structure 632 95 727 727 6,322 5b.1.1.12 Low Level Radwaste Storage 444 67 511 511 5,435 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 16 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Demolition of Remaining Site Buildings (continued) 5b.1.1.13 Machine Shop 226 34 260 260 2,858 5b.1.1.14 Main Gate Security 101 15 116 116 1,059 5b.1.1.15 Maintenance Building 326 49 375 375 4,274 5b.1.1.16 Materials Warehouse 879 132 1,011 1,011 8,908 5b.1.1.17 Miscellaneous Structures 617 93 710 710 6,565 5b.1.1.18 New Radwaste Building 745 112 857 857 8,009 5b.1.1.19 New Sample Pump House 9 1 11 11 128 5b.1.1.20 Office Building 374 56 430 430 4,459 5b.1.1.21 Old Radwaste Building 680 102 782 782 6,852 5b.1.1.22 Plant Engineering 170 25 195 195 1,784 5b.1.1.23 Pretreatment Building 31 5 35 35 420 5b.1.1.24 Reactor Building 6,127 919 7,046 7,046 61,454 5b.1.1.25 Sample Pool 15 2 18 18 180 5b.1.1.26 Security Modifications 1,256 188 1,444 1,444 10,330 5b.1.1.27 Site Emergency Building 316 47 363 363 3,285 5b.1.1.28 Tank Pads & Misc. Yard 772 116 887 887 8,326 5b.1.1.29 Turbine Building 4,209 631 4,840 4,840 41,424 5b.1.1.30 Turbine Pedestal 574 86 660 660 5,050 5b.1.1 Totals 20,789 3,118 23,908 23,908 203,134 Site Closeout Activities 5b.1.2 Remove Rubble 798 120 917 917 4,211 5b.1.3 Grade & landscape site 634 95 729 729 1,304 5b.1.4 Final report to NRC 187 28 215 215 1,560 5b.1 Subtotal Period 5b Activity Costs 22,221 187 3,361 25,769 215 25,554 208,649 1,560 Period 5b Additional Costs 5b.2.1 Concrete Crushing 756 9 115 880 880 3,219 5b.2.2 Install Cofferdams Intake & Dilution 975 146 1,122 1,122 8,296 5b.2.3 ISFSI Site Restoration 103 6 16 126 126 5b.2 Subtotal Period 5b Additional Costs 1,835 15 278 2,128 126 2,002 11,516 Period 5b Collateral Costs 5b.3.1 Small tool allowance 265 40 305 305 5b.3 Subtotal Period 5b Collateral Costs 265 40 305 305 Period 5b PeriodDependent Costs 5b.4.2 Property taxes 1,552 155 1,708 1,708 5b.4.3 Heavy equipment rental 4,438 666 5,104 5,104 5b.4.4 Plant energy budget 298 45 343 343 5b.4.5 Site O&M Cost 480 72 552 552 5b.4.6 Security Staff Cost 2,242 336 2,578 2,578 38,880 5b.4.7 DOC Staff Cost 10,204 1,531 11,735 11,735 110,160 5b.4.8 Utility Staff Cost 5,737 861 6,598 6,598 63,180 5b.4 Subtotal Period 5b PeriodDependent Costs 4,438 20,514 3,665 28,617 28,617 212,220 5b.0 TOTAL PERIOD 5b COST 28,759 20,716 7,344 56,818 215 126 56,478 220,165 213,780 PERIOD 5 TOTALS 28,759 20,716 7,344 56,818 215 126 56,478 220,165 213,780 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix D, Page 17 of 17 Table D Oyster Creek Nuclear Generating Station Delayed DECON Decommissioning Cost Estimate (Thousands of 2011 Dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:40 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours TOTAL COST TO DECOMMISSION 16,514 107,183 14,647 11,290 10,035 30,474 574,216 135,859 900,219 541,703 299,125 59,390 470,429 312,624 1,002 470 1,428 44,260,660 1,272,391 6,076,148 TOTAL COST TO DECOMMISSION WITH 17.77% CONTINGENCY: $900,219 thousands of 2011 dollars TOTAL NRC LICENSE TERMINATION COST IS 60.17% OR: $541,703 thousands of 2011 dollars SPENT FUEL MANAGEMENT COST IS 33.23% OR: $299,125 thousands of 2011 dollars NONNUCLEAR DEMOLITION COST IS 6.6% OR: $59,390 thousands of 2011 dollars TOTAL LOWLEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC): 314,095 cubic feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED: 1,428 cubic feet TOTAL SCRAP METAL REMOVED: 24,292 tons TOTAL CRAFT LABOR REQUIREMENTS: 1,272,391 manhours End Notes:

n/a indicates that this activity not charged as decommissioning expense.

a indicates that this activity performed by decommissioning staff.

0 indicates that this value is less than 0.5 but is nonzero.

a cell containing " " indicates a zero value TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 1 of 18 APPENDIX E DETAILED COST ANALYSIS SAFSTOR TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 2 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 1a Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1 SAFSTOR site characterization survey 434 130 564 564 1a.1.2 Prepare preliminary decommissioning cost 156 23 179 179 1,300 1a.1.3 Notification of Cessation of Operations a 1a.1.4 Remove fuel & source material n/a 1a.1.5 Notification of Permanent Defueling a 1a.1.6 Deactivate plant systems & process waste a 1a.1.7 Prepare and submit PSDAR 239 36 275 275 2,000 1a.1.8 Review plant dwgs & specs. 156 23 179 179 1,300 1a.1.9 Perform detailed rad survey a 1a.1.10 Estimate byproduct inventory 120 18 138 138 1,000 1a.1.11 End product description 120 18 138 138 1,000 1a.1.12 Detailed byproduct inventory 179 27 206 206 1,500 1a.1.13 Define major work sequence 120 18 138 138 1,000 1a.1.14 Perform SER and EA 371 56 427 427 3,100 1a.1.15 Perform SiteSpecific Cost Study 598 90 688 688 5,000 Activity Specifications 1a.1.16.1 Prepare plant and facilities for SAFSTOR 589 88 677 677 4,920 1a.1.16.2 Plant systems 499 75 573 573 4,167 1a.1.16.3 Plant structures and buildings 373 56 429 429 3,120 1a.1.16.4 Waste management 239 36 275 275 2,000 1a.1.16.5 Facility and site dormancy 239 36 275 275 2,000 1a.1.16 Total 1,939 291 2,230 2,230 16,207 Detailed Work Procedures 1a.1.17.1 Plant systems 142 21 163 163 1,183 1a.1.17.2 Facility closeout & dormancy 144 22 165 165 1,200 1a.1.17 Total 285 43 328 328 2,383 1a.1.18 Procure vacuum drying system 12 2 14 14 100 1a.1.19 Drain/deenergize noncont. systems a 1a.1.20 Drain & dry NSSS a 1a.1.21 Drain/deenergize contaminated systems a 1a.1.22 Decon/secure contaminated systems a 1a.1 Subtotal Period 1a Activity Costs 4,728 774 5,503 5,503 35,890 Period 1a Additional Costs 1a.2.1 ISFSI Expansion 5,200 780 5,980 5,980 1a.2 Subtotal Period 1a Additional Costs 5,200 780 5,980 5,980 Period 1a Collateral Costs 1a.3.1 Spent Fuel Capital and Transfer 10,977 1,647 12,623 12,623 1a.3 Subtotal Period 1a Collateral Costs 10,977 1,647 12,623 12,623 Period 1a PeriodDependent Costs 1a.4.1 Insurance 2,227 223 2,450 2,450 1a.4.2 Property taxes 1a.4.3 Health physics supplies 469 117 586 586 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 3 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 1a PeriodDependent Costs (continued) 1a.4.4 Heavy equipment rental 462 69 531 531 1a.4.5 Disposal of DAW generated 14 10 35 12 70 70 610 12,190 20 1a.4.6 Plant energy budget 1,918 288 2,206 2,206 1a.4.7 NRC Fees 769 77 846 846 1a.4.8 Emergency Planning Fees 564 56 621 621 1a.4.9 Site O&M Costs 309 46 355 355 1a.4.10 Spent Fuel Pool O&M 763 114 878 878 1a.4.11 ISFSI Operating Costs 89 13 103 103 1a.4.12 Security Staff Cost 8,441 1,266 9,707 9,707 157,471 1a.4.13 Utility Staff Cost 33,041 4,956 37,997 37,997 423,400 1a.4 Subtotal Period 1a PeriodDependent Costs 931 14 10 35 48,122 7,238 56,350 54,749 1,601 610 12,190 20 580,871 1a.0 TOTAL PERIOD 1a COST 931 14 10 35 69,028 10,439 80,456 60,252 20,205 610 12,190 20 616,761 PERIOD 1b SAFSTOR Limited DECON Activities Period 1b Direct Decommissioning Activities Decontamination of Site Buildings 1b.1.1.1 New Radwaste Building Systems Removal 0 0 0 0 1 1b.1.1.2 Old Radwaste Building Systems Removal 0 0 0 0 1 1b.1.1.3 Augmented Off Gas Decon 2 1 3 3 33 1b.1.1.4 Stack/Exhaust Tunnels Remove & Decon 54 27 81 81 849 1b.1.1.5 Turbine Building 0ft Decon 10 5 15 15 137 1b.1.1.6 Drywell Liner Removal 2,063 1,031 3,094 3,094 28,819 1b.1.1.7 RB0 Torus Removal 2,765 1,383 4,148 4,148 38,634 1b.1.1.8 Reactor Building 19ft Decon 7 3 10 10 96 1b.1.1.9 Reactor Building 119ft Decon 429 215 644 644 5,996 1b.1.1 Totals 5,330 2,665 7,996 7,996 74,565 1b.1 Subtotal Period 1b Activity Costs 5,330 2,665 7,996 7,996 74,565 Period 1b Additional Costs 1b.2.1 Spent fuel pool isolation 10,280 1,542 11,822 11,822 1b.2 Subtotal Period 1b Additional Costs 10,280 1,542 11,822 11,822 Period 1b Collateral Costs 1b.3.1 Decon equipment 902 135 1,037 1,037 1b.3.2 Process decommissioning water waste 288 127 343 620 363 1,742 1,742 1,817 109,041 354 1b.3.4 Small tool allowance 100 15 115 115 1b.3.5 Spent Fuel Capital and Transfer 2,737 410 3,147 3,147 1b.3 Subtotal Period 1b Collateral Costs 1,190 100 127 343 620 2,737 924 6,042 2,894 3,147 1,817 109,041 354 Period 1b PeriodDependent Costs 1b.4.1 Decon supplies 1,056 264 1,320 1,320 1b.4.2 Insurance 418 42 459 459 1b.4.3 Property taxes 601 60 661 661 1b.4.4 Health physics supplies 442 111 553 553 1b.4.5 Heavy equipment rental 115 17 132 132 1b.4.6 Disposal of DAW generated 4 3 9 3 19 19 164 3,277 5 1b.4.7 Plant energy budget 478 72 550 550 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 4 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 1b PeriodDependent Costs (continued) 1b.4.8 NRC Fees 192 19 211 211 1b.4.9 Emergency Planning Fees 141 14 155 155 1b.4.10 Site O&M Costs 77 12 89 89 1b.4.11 Spent Fuel Pool O&M 190 29 219 219 1b.4.12 ISFSI Operating Costs 22 3 26 26 1b.4.13 Security Staff Cost 2,104 316 2,420 2,420 39,260 1b.4.14 Utility Staff Cost 8,238 1,236 9,473 9,473 105,560 1b.4 Subtotal Period 1b PeriodDependent Costs 1,056 558 4 3 9 12,461 2,196 16,286 15,887 399 164 3,277 5 144,820 1b.0 TOTAL PERIOD 1b COST 7,576 658 131 346 630 25,477 7,328 42,145 38,599 3,546 1,981 112,319 74,925 144,820 PERIOD 1c Preparations for SAFSTOR Dormancy Period 1c Direct Decommissioning Activities 1c.1.1 Prepare support equipment for storage 489 73 562 562 3,000 1c.1.2 Install containment pressure equal. lines 51 8 59 59 700 1c.1.3 Interim survey prior to dormancy 733 220 953 953 12,166 1c.1.4 Secure building accesses a 1c.1.5 Prepare & submit interim report 70 10 80 80 583 1c.1 Subtotal Period 1c Activity Costs 540 803 311 1,654 1,654 15,866 583 Period 1c Collateral Costs 1c.3.1 Process decommissioning water waste 238 105 284 513 300 1,440 1,440 1,503 90,169 293 1c.3.3 Small tool allowance 5 1 6 6 1c.3.4 Spent Fuel Capital and Transfer 2,737 410 3,147 3,147 1c.3 Subtotal Period 1c Collateral Costs 238 5 105 284 513 2,737 711 4,593 1,446 3,147 1,503 90,169 293 Period 1c PeriodDependent Costs 1c.4.1 Insurance 418 42 459 459 1c.4.2 Property taxes 601 60 661 661 1c.4.3 Health physics supplies 187 47 234 234 1c.4.4 Heavy equipment rental 115 17 132 132 1c.4.5 Disposal of DAW generated 4 2 9 3 18 18 152 3,039 5 1c.4.6 Plant energy budget 478 72 550 550 1c.4.7 NRC Fees 192 19 211 211 1c.4.8 Emergency Planning Fees 141 14 155 155 1c.4.9 Site O&M Costs 77 12 89 89 1c.4.10 Spent Fuel Pool O&M 190 29 219 219 1c.4.11 ISFSI Operating Costs 22 3 26 26 1c.4.12 Security Staff Cost 2,104 316 2,420 2,420 39,260 1c.4.13 Utility Staff Cost 8,238 1,236 9,473 9,473 105,560 1c.4 Subtotal Period 1c PeriodDependent Costs 302 4 2 9 12,461 1,869 14,646 14,247 399 152 3,039 5 144,820 1c.0 TOTAL PERIOD 1c COST 238 847 109 286 522 16,000 2,891 20,893 17,346 3,546 1,655 93,209 16,164 145,403 PERIOD 1 TOTALS 7,813 2,435 254 642 1,186 110,505 20,658 143,494 116,197 27,297 4,246 217,718 91,109 906,985 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 5 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 2a SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1 Quarterly Inspection a 2a.1.2 Semiannual environmental survey a 2a.1.3 Prepare reports a 2a.1.4 Bituminous roof replacement 196 29 225 225 2a.1.5 Maintenance supplies 540 135 675 675 2a.1 Subtotal Period 2a Activity Costs 736 164 901 901 Period 2a Collateral Costs 2a.3.1 Spent Fuel Capital and Transfer 43,967 6,595 50,562 50,562 2a.3 Subtotal Period 2a Collateral Costs 43,967 6,595 50,562 50,562 Period 2a PeriodDependent Costs 2a.4.1 Insurance 3,396 340 3,735 2,526 1,209 2a.4.2 Property taxes 5,402 540 5,943 4,403 1,540 2a.4.3 Health physics supplies 753 188 942 942 2a.4.4 Disposal of DAW generated 21 15 53 18 107 107 922 18,431 30 2a.4.5 Plant energy budget 1,537 230 1,767 884 884 2a.4.6 NRC Fees 883 88 971 971 2a.4.7 Site O&M Costs 1,238 186 1,424 1,424 2a.4.8 Spent Fuel Pool O&M 3,057 459 3,515 3,515 2a.4.9 ISFSI Operating Costs 358 54 412 412 2a.4.10 Security Staff Cost 24,118 3,618 27,736 8,574 19,162 444,866 2a.4.11 Utility Staff Cost 25,724 3,859 29,582 6,534 23,049 329,994 2a.4 Subtotal Period 2a PeriodDependent Costs 753 21 15 53 65,713 9,579 76,134 26,364 49,770 922 18,431 30 774,860 2a.0 TOTAL PERIOD 2a COST 753 21 15 53 110,416 16,338 127,597 27,264 100,332 922 18,431 30 774,860 PERIOD 2b SAFSTOR Dormancy with Dry Spent Fuel Storage Period 2b Direct Decommissioning Activities 2b.1.1 Quarterly Inspection a 2b.1.2 Semiannual environmental survey a 2b.1.3 Prepare reports a 2b.1.4 Bituminous roof replacement 563 84 647 647 2b.1.5 Maintenance supplies 1,553 388 1,941 1,941 2b.1 Subtotal Period 2b Activity Costs 2,115 473 2,588 2,588 Period 2b Collateral Costs 2b.3.1 Spent Fuel Capital and Transfer 9,500 1,425 10,925 10,925 2b.3 Subtotal Period 2b Collateral Costs 9,500 1,425 10,925 10,925 Period 2b PeriodDependent Costs 2b.4.1 Insurance 6,600 660 7,260 7,260 2b.4.2 Property taxes 11,502 1,150 12,652 12,652 2b.4.3 Health physics supplies 1,050 263 1,313 1,313 2b.4.4 Disposal of DAW generated 29 21 73 24 147 147 1,272 25,441 41 2b.4.5 Plant energy budget 2,208 331 2,539 2,539 2b.4.6 NRC ISFSI Fees 559 56 615 615 2b.4.7 NRC Fees 2,536 254 2,790 2,790 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 6 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 2b PeriodDependent Costs (continued) 2b.4.8 Site O&M Costs 3,558 534 4,091 4,091 2b.4.9 ISFSI Operating Costs 1,030 154 1,184 1,184 2b.4.10 Security Staff Cost 36,444 5,467 41,911 24,637 17,274 648,154 2b.4.11 Utility Staff Cost 30,398 4,560 34,958 18,774 16,184 384,091 2b.4 Subtotal Period 2b PeriodDependent Costs 1,050 29 21 73 94,835 13,452 109,460 74,203 35,258 1,272 25,441 41 1,032,246 2b.0 TOTAL PERIOD 2b COST 1,050 29 21 73 106,451 15,350 122,973 76,791 46,183 1,272 25,441 41 1,032,246 PERIOD 2c SAFSTOR Dormancy without Spent Fuel Storage Period 2c Direct Decommissioning Activities 2c.1.1 Quarterly Inspection a 2c.1.2 Semiannual environmental survey a 2c.1.3 Prepare reports a 2c.1.4 Bituminous roof replacement 1,875 281 2,156 2,156 2c.1.5 Maintenance supplies 5,174 1,293 6,467 6,467 2c.1 Subtotal Period 2c Activity Costs 7,049 1,575 8,624 8,624 Period 2c PeriodDependent Costs 2c.4.1 Insurance 21,991 2,199 24,190 24,190 2c.4.2 Property taxes 38,324 3,832 42,157 42,157 2c.4.3 Health physics supplies 3,291 823 4,114 4,114 2c.4.4 Disposal of DAW generated 90 64 223 74 451 451 3,904 78,074 127 2c.4.5 Plant energy budget 7,356 1,103 8,459 8,459 2c.4.6 NRC Fees 7,657 766 8,423 8,423 2c.4.7 Site O&M Costs 11,854 1,778 13,633 13,633 2c.4.8 Security Staff Cost 71,385 10,708 82,093 82,093 1,199,829 2c.4.9 Utility Staff Cost 54,396 8,159 62,556 62,556 699,900 2c.4 Subtotal Period 2c PeriodDependent Costs 3,291 90 64 223 212,964 29,443 246,076 246,076 3,904 78,074 127 1,899,729 2c.0 TOTAL PERIOD 2c COST 3,291 90 64 223 220,013 31,018 254,699 254,699 3,904 78,074 127 1,899,729 PERIOD 2 TOTALS 5,095 141 100 349 436,879 62,706 505,269 358,754 146,515 6,097 121,947 199 3,706,834 PERIOD 3a Reactivate Site Following SAFSTOR Dormancy Period 3a Direct Decommissioning Activities 3a.1.1 Prepare preliminary decommissioning cost 156 23 179 179 1,300 3a.1.2 Review plant dwgs & specs. 550 83 633 633 4,600 3a.1.3 Perform detailed rad survey a 3a.1.4 End product description 120 18 138 138 1,000 3a.1.5 Detailed byproduct inventory 156 23 179 179 1,300 3a.1.6 Define major work sequence 897 135 1,032 1,032 7,500 3a.1.7 Perform SER and EA 371 56 427 427 3,100 3a.1.8 Perform SiteSpecific Cost Study 598 90 688 688 5,000 3a.1.9 Prepare/submit License Termination Plan 490 74 564 564 4,096 3a.1.10 Receive NRC approval of termination plan a TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 7 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Activity Specifications 3a.1.11.1 Reactivate plant & temporary facilities 882 132 1,014 913 101 7,370 3a.1.11.2 Plant systems 499 75 573 516 57 4,167 3a.1.11.3 Reactor internals 850 127 977 977 7,100 3a.1.11.4 Reactor vessel 778 117 894 894 6,500 3a.1.11.5 Sacrificial shield 60 9 69 69 500 3a.1.11.6 Moisture separators/reheaters 120 18 138 138 1,000 3a.1.11.7 Reinforced concrete 191 29 220 110 110 1,600 3a.1.11.8 Main Turbine 250 37 287 287 2,088 3a.1.11.9 Main Condensers 250 37 287 287 2,088 3a.1.11.10 Pressure suppression structure 239 36 275 275 2,000 3a.1.11.11 Drywell 191 29 220 220 1,600 3a.1.11.12 Plant structures & buildings 373 56 429 215 215 3,120 3a.1.11.13 Waste management 550 83 633 633 4,600 3a.1.11.14 Facility & site closeout 108 16 124 62 62 900 3a.1.11 Total 5,340 801 6,141 5,596 545 44,633 Planning & Site Preparations 3a.1.12 Prepare dismantling sequence 287 43 330 330 2,400 3a.1.13 Plant prep. & temp. svces 2,800 420 3,220 3,220 3a.1.14 Design water cleanup system 168 25 193 193 1,400 3a.1.15 Rigging/Cont. Cntrl Envlps/tooling/etc. 2,200 330 2,530 2,530 3a.1.16 Procure casks/liners & containers 147 22 169 169 1,230 3a.1 Subtotal Period 3a Activity Costs 14,280 2,142 16,422 15,876 545 77,559 Period 3a PeriodDependent Costs 3a.4.1 Insurance 573 57 631 631 3a.4.2 Property taxes 999 100 1,099 1,099 3a.4.3 Health physics supplies 410 102 512 512 3a.4.4 Heavy equipment rental 462 69 531 531 3a.4.5 Disposal of DAW generated 12 8 29 10 59 59 514 10,287 17 3a.4.6 Plant energy budget 1,918 288 2,206 2,206 3a.4.7 NRC Fees 272 27 299 299 3a.4.8 Site O&M Costs 309 46 355 355 3a.4.9 Security Staff Cost 3,629 544 4,173 4,173 65,179 3a.4.10 Utility Staff Cost 20,498 3,075 23,573 23,573 258,629 3a.4 Subtotal Period 3a PeriodDependent Costs 872 12 8 29 28,199 4,319 33,440 33,440 514 10,287 17 323,807 3a.0 TOTAL PERIOD 3a COST 872 12 8 29 42,479 6,461 49,861 49,316 545 514 10,287 17 401,366 PERIOD 3b Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems 566 85 651 586 65 4,733 3b.1.1.2 Reactor internals 479 72 550 550 4,000 3b.1.1.3 Remaining buildings 162 24 186 46 139 1,350 3b.1.1.4 CRD housings & NIs 120 18 138 138 1,000 3b.1.1.5 Incore instrumentation 120 18 138 138 1,000 3b.1.1.6 Removal primary containment 239 36 275 275 2,000 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 8 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Detailed Work Procedures (continued) 3b.1.1.7 Reactor vessel 434 65 499 499 3,630 3b.1.1.8 Facility closeout 144 22 165 83 83 1,200 3b.1.1.9 Sacrificial shield 144 22 165 165 1,200 3b.1.1.10 Reinforced concrete 120 18 138 69 69 1,000 3b.1.1.11 Main Turbine 249 37 286 286 2,080 3b.1.1.12 Main Condensers 250 37 287 287 2,088 3b.1.1.13 Moisture separators & reheaters 239 36 275 275 2,000 3b.1.1.14 Radwaste building 327 49 376 338 38 2,730 3b.1.1.15 Reactor building 327 49 376 338 38 2,730 3b.1.1 Total 3,917 588 4,505 4,074 431 32,741 3b.1 Subtotal Period 3b Activity Costs 3,917 588 4,505 4,074 431 32,741 Period 3b Additional Costs 3b.2.1 Site Characterization 4,986 1,496 6,482 6,482 27,140 9,952 3b.2.2 Disposition of Liquid RCRA Waste (not Lead) 17 529 135 680 680 2,019 115,076 3b.2.3 Disposition of PCB Soil RCRA Waste (not Lead) 1,362 1,450 567 3,378 3,378 27,000 3,240,000 3b.2.4 Disposition of Lead Inventory 26 756 117 899 899 328 232,673 3b.2.5 Asbestos Remediation 12,217 2 279 1,030 3,354 16,883 16,883 19,193 249,515 150,230 3b.2 Subtotal Period 3b Additional Costs 12,217 2 1,684 756 3,009 4,986 5,669 28,323 28,323 328 48,212 3,837,264 177,370 9,952 Period 3b Collateral Costs 3b.3.1 Decon equipment 902 135 1,037 1,037 3b.3.2 DOC staff relocation expenses 1,124 169 1,292 1,292 3b.3.3 Small tool allowance 184 28 211 211 3b.3.4 Pipe cutting equipment 1,100 165 1,265 1,265 3b.3 Subtotal Period 3b Collateral Costs 902 1,284 1,124 496 3,806 3,806 Period 3b PeriodDependent Costs 3b.4.1 Decon supplies 28 7 35 35 3b.4.2 Insurance 287 29 316 316 3b.4.3 Property taxes 501 50 551 551 3b.4.4 Health physics supplies 879 220 1,099 1,099 3b.4.5 Heavy equipment rental 232 35 266 266 3b.4.6 Disposal of DAW generated 7 5 17 6 34 34 292 5,834 10 3b.4.7 Plant energy budget 962 144 1,106 1,106 3b.4.8 NRC Fees 136 14 150 150 3b.4.9 Site O&M Costs 155 23 178 178 3b.4.10 Security Staff Cost 1,819 273 2,092 2,092 32,679 3b.4.11 DOC Staff Cost 5,076 761 5,838 5,838 58,560 3b.4.12 Utility Staff Cost 10,277 1,542 11,819 11,819 129,669 3b.4 Subtotal Period 3b PeriodDependent Costs 28 1,111 7 5 17 19,214 3,103 23,484 23,484 292 5,834 10 220,907 3b.0 TOTAL PERIOD 3b COST 930 14,611 8 1,689 756 3,025 29,242 9,855 60,117 59,686 431 328 48,504 3,843,098 177,380 263,600 PERIOD 3 TOTALS 930 15,483 20 1,698 756 3,055 71,721 16,317 109,979 109,002 976 328 49,018 3,853,385 177,396 664,966 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 9 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours PERIOD 4a Large Component Removal Period 4a Direct Decommissioning Activities Nuclear Steam Supply System Removal 4a.1.1.2 Recirculation Pumps & Motors 10 108 41 79 50 108 83 480 480 633 527 196,350 2,156 4a.1.1.3 CRDMs & NIs Removal 40 179 523 141 137 172 1,190 1,190 5,179 112,850 3,338 4a.1.1.4 Reactor Vessel Internals 96 2,500 5,060 1,039 4,014 175 5,481 18,366 18,366 1,573 1,127 344 299,030 18,150 858 4a.1.1.5 Vessel & Internals GTCC Disposal 4,450 667 5,117 5,117 1,428 282,300 4a.1.1.6 Reactor Vessel 6,060 1,354 827 1,912 175 6,072 16,399 16,399 15,440 1,579,847 18,150 858 4a.1.1 Totals 146 8,846 6,979 2,086 50 10,620 349 12,475 41,551 41,551 633 22,720 1,127 344 1,428 2,470,377 41,795 1,716 Removal of Major Equipment 4a.1.2 Main Turbine/Generator 326 1,861 391 1,707 582 4,867 4,867 80,711 3,632,000 4,957 4a.1.3 Main Condensers 1,000 1,291 271 1,184 597 4,344 4,344 56,000 2,520,000 15,180 New Radwaste Building System Components 4a.1.7.1 7EB 162 9 9 7 23 49 259 259 362 334 33,679 2,492 4a.1.7.2 N2G 11 0 0 1 3 16 16 49 2,007 178 4a.1.7.3 N2P 24 1 1 6 7 40 40 341 13,830 357 4a.1.7.4 N3A 68 1 2 8 18 96 96 398 16,151 1,000 4a.1.7.5 N3D 81 1 2 10 22 115 115 501 20,362 1,263 4a.1.7.6 N3I 17 0 0 1 0 4 23 23 27 5 1,390 273 4a.1.7.7 N3N 101 1 2 9 27 139 139 447 18,140 1,529 4a.1.7.8 N3P 26 0 1 3 7 37 37 179 7,267 383 4a.1.7.9 N3Q 17 0 0 2 5 24 24 80 3,260 271 4a.1.7.10 N3R 17 0 0 2 5 24 24 97 3,934 261 4a.1.7.11 N3S 25 0 1 4 7 37 37 187 7,583 400 4a.1.7.12 N3T 16 0 0 1 4 21 21 58 2,357 243 4a.1.7.13 N3U 113 14 14 12 38 43 234 234 610 548 55,829 1,727 4a.1.7.14 N3W 117 16 15 12 41 45 247 247 643 604 60,369 1,792 4a.1.7.15 N3Y 208 5 13 58 63 348 348 3,054 124,028 3,179 4a.1.7.16 N51 28 0 1 5 8 42 42 239 9,707 433 4a.1.7.17 N52 23 1 1 2 3 7 38 38 121 43 7,290 353 4a.1.7.18 N53 35 2 3 5 5 11 61 61 248 75 14,268 541 4a.1.7.19 N54 17 1 1 1 2 5 26 26 46 28 3,435 260 4a.1.7.20 N55 73 1 2 8 20 104 104 414 16,809 1,137 4a.1.7.21 N56 97 1 3 14 27 143 143 734 29,828 1,389 4a.1.7.22 N5A 42 1 2 6 2 12 64 64 290 26 13,205 663 4a.1.7.23 N5B 39 1 1 6 11 58 58 307 12,485 621 4a.1.7.24 N5C 18 0 0 2 5 25 25 106 4,294 267 4a.1.7.25 N5D 28 0 1 3 8 39 39 152 6,190 426 4a.1.7.26 N5E 19 0 0 2 5 26 26 110 4,453 278 4a.1.7.27 N5F 27 2 1 2 3 8 43 43 91 45 6,294 408 4a.1.7.28 N5G 13 0 0 1 3 18 18 40 1,645 205 4a.1.7.29 N5H 11 1 1 0 2 3 18 18 5 26 1,667 172 4a.1.7.30 N5I 15 0 0 1 4 21 21 51 2,090 238 4a.1.7.31 N5J 12 0 1 3 3 19 19 131 5,328 187 4a.1.7.32 N5K 15 0 0 1 4 21 21 75 3,050 224 4a.1.7.33 N5N 28 0 1 3 8 39 39 143 5,803 433 4a.1.7.34 N5O 72 1 3 13 21 110 110 670 27,221 1,105 4a.1.7.35 N5P 26 2 2 3 4 9 46 46 183 62 10,822 420 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 10 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours New Radwaste Building System Components (continued) 4a.1.7.36 N5Q 26 2 2 3 4 8 46 46 182 61 10,719 414 4a.1.7.37 N5S 64 4 10 42 24 143 143 2,195 89,151 1,024 4a.1.7.38 N5T 59 2 3 12 3 18 97 97 606 40 26,812 930 4a.1.7.39 N5U 60 2 3 12 3 18 98 98 607 40 26,871 942 4a.1.7.40 N5Y 23 1 1 3 1 7 36 36 153 19 7,306 358 4a.1.7.41 N5Z 23 1 1 3 1 7 36 36 153 19 7,306 358 4a.1.7.42 PPA 75 1 3 11 21 110 110 572 23,240 1,139 4a.1.7 Totals 1,972 76 109 299 135 596 3,187 3,187 15,660 1,977 747,476 30,271 Old Radwaste Building System Components 4a.1.8.1 7BA 83 1 2 9 22 117 117 480 19,481 1,272 4a.1.8.2 7DA 48 5 5 2 14 17 92 92 122 206 16,640 738 4a.1.8.3 7FA 22 1 2 4 3 7 39 39 206 43 10,810 355 4a.1.8.4 PBA 147 12 12 17 26 49 263 263 893 388 57,934 2,324 4a.1.8.5 PDA 52 1 2 7 14 75 75 373 15,150 808 4a.1.8.6 PMA 12 0 0 1 3 17 17 54 2,174 190 4a.1.8.7 PRA 82 1 4 16 24 128 128 855 34,703 1,292 4a.1.8.8 PTK / PTP 13 0 0 1 3 17 17 30 1,199 202 4a.1.8 Totals 460 21 26 57 43 141 749 749 3,011 637 158,091 7,180 Turbine Building System Components 4a.1.9.1 7CA 260 21 22 33 46 87 468 468 1,755 663 108,906 4,017 4a.1.9.2 TB2 961 19 52 227 284 1,544 1,544 11,906 483,529 14,570 4a.1.9.3 TB23 5 0 0 1 1 8 8 42 1,699 83 4a.1.9.4 TB38 16 0 1 2 5 24 24 124 5,034 229 4a.1.9.5 TC2 1,562 70 188 820 549 3,190 3,190 42,978 1,745,363 23,871 4a.1.9.6 TE2 186 12 20 60 22 65 365 365 3,126 317 144,922 2,822 4a.1.9.7 TEE 320 7 18 79 95 519 519 4,115 167,126 4,871 4a.1.9.8 TEG 26 0 1 3 7 36 36 139 5,640 380 4a.1.9.9 TP2 170 4 12 51 52 289 289 2,659 107,977 2,613 4a.1.9.10 TP3 113 9 10 16 20 38 205 205 859 292 51,008 1,793 4a.1.9.11 TPE 102 10 10 12 23 36 193 193 647 335 45,003 1,572 4a.1.9 Totals 3,722 153 332 1,305 110 1,219 6,840 6,840 68,349 1,608 2,866,205 56,820 4a.1.12 Scaffolding in support of decommissioning 940 27 7 22 8 244 1,249 1,249 1,057 112 53,901 16,869 4a.1 Subtotal Period 4a Activity Costs 146 17,267 10,408 3,223 4,625 10,916 349 15,854 62,787 62,787 225,422 27,054 1,127 344 1,428 12,448,050 173,072 1,716 Period 4a Collateral Costs 4a.3.1 Process decommissioning water waste 6 7 19 35 15 83 83 102 6,149 20 4a.3.3 Small tool allowance 210 31 241 217 24 4a.3 Subtotal Period 4a Collateral Costs 6 210 7 19 35 47 324 300 24 102 6,149 20 Period 4a PeriodDependent Costs 4a.4.1 Decon supplies 52 13 65 65 4a.4.2 Insurance 539 54 593 593 4a.4.3 Property taxes 939 94 1,033 930 103 4a.4.4 Health physics supplies 1,186 297 1,483 1,483 4a.4.5 Heavy equipment rental 1,888 283 2,172 2,172 4a.4.6 Disposal of DAW generated 80 57 198 66 400 400 3,462 69,233 113 4a.4.7 Plant energy budget 1,712 257 1,969 1,969 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 11 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 4a PeriodDependent Costs (continued) 4a.4.8 NRC Fees 674 67 741 741 4a.4.9 Site O&M Costs 290 44 334 334 4a.4.10 Liquid Radwaste Processing Equipment/Services 364 55 419 419 4a.4.11 Security Staff Cost 3,410 511 3,921 3,921 61,250 4a.4.12 DOC Staff Cost 11,514 1,727 13,241 13,241 135,240 4a.4.13 Utility Staff Cost 19,437 2,916 22,353 22,353 245,000 4a.4 Subtotal Period 4a PeriodDependent Costs 52 3,075 80 57 198 38,880 6,383 48,724 48,621 103 3,462 69,233 113 441,490 4a.0 TOTAL PERIOD 4a COST 204 20,551 10,495 3,298 4,625 11,149 39,229 22,284 111,836 111,708 127 225,422 30,618 1,127 344 1,428 12,523,430 173,205 443,206 PERIOD 4b Site Decontamination Period 4b Direct Decommissioning Activities 4b.1.1 Remove spent fuel racks 545 64 142 226 744 523 2,243 2,243 10,858 615,095 1,071 Drywell System Components 4b.1.2.1 IAA/IAC 329 218 191 136 527 285 1,685 1,685 7,111 7,660 723,932 5,700 4b.1.2.2 IBA 164 19 19 17 50 61 330 330 880 734 77,321 2,588 4b.1.2.3 ICA 263 36 32 35 79 99 543 543 1,841 1,148 140,037 4,149 4b.1.2.4 IEA 70 9 11 18 22 28 157 157 926 320 55,719 1,176 4b.1.2.5 RC6 65 1 2 8 18 95 95 440 17,889 989 4b.1.2 Totals 890 282 255 214 678 491 2,809 2,809 11,199 9,861 1,014,897 14,602 Reactor Building System Components 4b.1.3.1 RB1 202 4 11 48 60 324 324 2,495 101,308 2,991 4b.1.3.2 RBB 106 2 6 25 31 170 170 1,306 53,019 1,597 4b.1.3.3 RBC 108 2 6 28 33 178 178 1,485 60,294 1,647 4b.1.3.4 RBE 142 2 6 26 41 217 217 1,381 56,063 2,156 4b.1.3.5 RBF 121 14 14 14 35 45 244 244 740 516 59,235 1,909 4b.1.3.6 RBO 526 18 49 214 173 981 981 11,229 456,005 8,678 4b.1.3.7 RBS 247 22 27 53 50 88 486 486 2,757 727 153,183 3,897 4b.1.3.8 RBSW 135 2 6 26 39 207 207 1,343 54,558 2,077 4b.1.3.9 RC1/RC3 4 0 0 0 1 6 6 14 577 63 4b.1.3.10 RC7 90 2 5 21 27 145 145 1,106 44,917 1,311 4b.1.3.11 RCA 47 3 3 3 8 15 79 79 147 109 12,175 725 4b.1.3.12 RCB 69 2 3 10 2 20 105 105 501 28 21,917 1,051 4b.1.3.13 RCD 352 7 17 76 103 555 555 3,974 161,384 5,318 4b.1.3.14 RCG 67 2 5 22 21 116 116 1,136 46,136 1,041 4b.1.3.15 RCJ 74 1 3 12 21 110 110 617 25,044 1,121 4b.1.3.16 RCM 109 2 6 28 33 179 179 1,481 60,136 1,694 4b.1.3.17 RCN 243 3 9 40 69 365 365 2,107 85,581 3,666 4b.1.3.18 RCS 87 15 14 12 38 37 204 204 636 561 57,657 1,365 4b.1.3.19 RCT 57 1 2 9 16 84 84 464 18,858 858 4b.1.3.20 RD8 87 66 66 36 189 91 535 535 1,861 2,761 231,971 1,484 4b.1.3.21 RDM 48 0 1 5 13 67 67 268 10,870 701 4b.1.3.22 REC 216 3 9 37 61 326 326 1,953 79,329 3,190 4b.1.3.23 REF 100 23 21 13 60 47 264 264 667 875 76,709 1,550 4b.1.3.24 REH/REI 121 2 6 25 35 189 189 1,325 53,806 1,846 4b.1.3.25 REL 215 5 14 63 66 364 364 3,286 133,445 3,285 4b.1.3.26 REM 57 1 2 10 16 87 87 538 21,846 868 4b.1.3.27 REO 122 21 22 21 57 53 296 296 1,115 827 92,099 1,930 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 12 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Reactor Building System Components (continued) 4b.1.3.28 REQ 169 9 11 25 17 53 284 284 1,311 254 67,684 2,610 4b.1.3.29 RER 56 5 4 3 11 19 98 98 177 167 16,663 881 4b.1.3.30 RET 32 1 1 4 1 9 48 48 185 18 8,515 500 4b.1.3.31 REW 28 0 1 3 8 39 39 146 5,936 432 4b.1.3.32 REX 31 0 1 3 8 43 43 165 6,710 477 4b.1.3.33 REY 36 0 1 4 10 50 50 192 7,781 543 4b.1.3.34 RFB 159 3 7 31 46 246 246 1,622 65,859 2,449 4b.1.3.35 RFC 104 12 9 6 24 35 190 190 337 351 33,707 1,649 4b.1.3.36 RFF 111 2 4 18 31 166 166 923 37,469 1,696 4b.1.3.37 RFH 152 25 22 13 61 61 335 335 692 893 78,810 2,337 4b.1.3.38 RFJ 133 23 21 13 59 56 305 305 690 866 77,154 2,052 4b.1.3.39 RFL 85 1 3 14 24 128 128 754 30,625 1,337 4b.1.3.40 RFN 115 2 5 21 33 176 176 1,118 45,418 1,768 4b.1.3.41 RFQ 167 2 4 18 45 236 236 942 38,243 2,456 4b.1.3.42 RGC 89 1 3 13 25 130 130 667 27,107 1,368 4b.1.3.43 RGD 251 7 19 84 79 441 441 4,427 179,773 3,921 4b.1.3.44 RGI 53 1 2 8 15 78 78 414 16,826 835 4b.1.3.45 RGL 62 1 2 11 18 94 94 555 22,545 967 4b.1.3.46 RGP 29 0 1 5 8 43 43 238 9,661 437 4b.1.3.47 RGR 190 3 7 31 54 284 284 1,633 66,314 2,876 4b.1.3.48 RGU 85 1 2 10 23 121 121 547 22,199 1,312 4b.1.3.49 RH1 50 1 1 6 14 72 72 339 13,754 762 4b.1.3.50 RH2 37 1 2 10 11 62 62 550 22,340 572 4b.1.3.51 RH3 / RH4 / RH6 127 1 3 11 34 176 176 592 24,061 1,896 4b.1.3.52 RHA 21 1 2 2 4 7 36 36 83 57 6,596 326 4b.1.3.53 RHJ 45 0 1 5 12 64 64 282 11,443 687 4b.1.3.54 RHL 29 0 1 2 8 40 40 121 4,913 431 4b.1.3.55 RHX 54 1 2 8 15 80 80 440 17,877 814 4b.1.3.56 RHY 49 1 2 7 13 71 71 369 14,998 750 4b.1.3.57 RMCC 98 2 4 19 28 151 151 989 40,165 1,468 4b.1.3 Totals 6,397 332 482 1,287 618 2,053 11,170 11,170 67,430 9,010 3,249,269 98,630 New Radwaste Building System Components 4b.1.4.1 N38 173 2 6 27 48 256 256 1,392 56,536 2,566 4b.1.4.2 N48 88 1 2 10 24 125 125 530 21,506 1,308 4b.1.4.3 N4A 29 2 2 3 4 9 50 50 183 63 10,949 470 4b.1.4.4 N4B 28 2 2 3 4 9 46 46 162 53 9,549 442 4b.1.4.5 N4D 91 1 2 9 24 127 127 459 18,650 1,350 4b.1.4.6 N4E 7 0 0 0 2 9 9 17 687 107 4b.1.4.7 N4F 19 0 0 2 5 27 27 98 3,986 289 4b.1.4.8 N4H 22 1 1 4 2 7 38 38 217 23 10,137 364 4b.1.4.9 N4K 24 0 1 3 7 35 35 176 7,138 364 4b.1.4.10 N4L 35 0 1 3 10 49 49 177 7,195 553 4b.1.4.11 N5R 77 2 4 20 23 125 125 1,029 41,782 1,188 4b.1.4.12 N5V 59 4 5 9 10 20 107 107 482 146 27,568 934 4b.1.4.13 N5W 9 0 0 0 2 12 12 10 401 148 4b.1.4.14 N5X 74 1 4 16 22 116 116 842 34,176 1,155 4b.1.4 Totals 734 16 31 110 19 211 1,122 1,122 5,774 286 250,260 11,236 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 13 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Old Radwaste Building System Components 4b.1.5.1 ORW Pre D&D Desludge and Decon 203 30 234 234 2,839 4b.1.5.2 PRD 15 0 1 3 4 23 23 151 6,112 245 4b.1.5.3 PSB 139 2 5 23 39 209 209 1,198 48,634 2,135 4b.1.5.4 PTA 39 1 2 7 11 59 59 371 15,084 601 4b.1.5.5 PUA 208 2 6 27 57 300 300 1,389 56,392 3,154 4b.1.5.6 PUU 141 5 10 35 5 44 239 239 1,825 83 78,582 2,225 4b.1.5.7 PVA 9 0 0 0 2 12 12 13 519 148 4b.1.5.8 UAB 304 4 10 45 85 448 448 2,367 96,117 4,649 4b.1.5.9 UAS 208 4 10 43 61 326 326 2,277 92,465 3,222 4b.1.5 Totals 1,268 18 44 183 5 334 1,851 1,851 9,590 83 393,904 19,219 Turbine Building System Components 4b.1.6.1 TD2 60 1 2 7 17 87 87 390 15,850 875 4b.1.6.2 TF2 324 16 42 184 117 683 683 9,646 391,743 4,891 4b.1.6.3 TFG 23 0 1 3 6 34 34 150 6,106 361 4b.1.6.4 TG2 236 12 33 144 87 513 513 7,564 307,179 3,660 4b.1.6.5 TH2 459 21 56 243 162 940 940 12,740 517,385 7,040 4b.1.6.6 TKA 24 0 0 1 6 32 32 74 2,996 348 4b.1.6.7 TL2 100 7 6 10 14 32 168 168 523 201 32,662 1,480 4b.1.6.8 TMA 61 1 4 17 18 102 102 895 36,367 921 4b.1.6.9 TN2 320 7 19 85 96 528 528 4,447 180,585 4,873 4b.1.6.10 TO2 170 26 196 196 2,826 4b.1.6.11 TOA 87 2 4 19 26 138 138 1,014 41,172 1,303 4b.1.6.12 TOCR 74 3 7 32 25 141 141 1,692 68,697 1,058 4b.1.6.13 TOR 65 2 4 18 20 107 107 931 37,795 994 4b.1.6.14 TOV 19 0 0 2 5 27 27 98 3,978 292 4b.1.6.15 TOW 103 4 11 49 35 202 202 2,557 103,857 1,547 4b.1.6.16 TOX / TOY 28 0 1 2 8 39 39 124 5,052 423 4b.1.6.17 TS2 201 6 17 74 64 362 362 3,875 157,362 2,995 4b.1.6.18 TTA 60 1 4 17 18 101 101 899 36,508 957 4b.1.6.19 TU2 185 3 9 40 54 292 292 2,096 85,139 2,856 4b.1.6 Totals 2,599 87 221 949 14 820 4,691 4,495 196 49,717 201 2,030,434 39,701 Augmented Offgas System Components 4b.1.7.1 AY8 143 3 7 30 42 224 224 1,596 64,813 2,154 4b.1.7.2 AYA 30 1 2 10 9 53 53 512 20,775 459 4b.1.7.3 AYB 29 0 1 5 8 43 43 267 10,862 441 4b.1.7.4 AYC 73 2 4 19 22 120 120 1,012 41,078 1,127 4b.1.7.5 AYE 25 0 0 2 7 35 35 103 4,199 375 4b.1.7.6 AZ8 54 1 3 12 16 85 85 611 24,796 824 4b.1.7.7 AZA 12 0 0 1 3 17 17 40 1,638 188 4b.1.7.8 AZC 103 2 5 22 30 162 162 1,145 46,509 1,555 4b.1.7.9 AZD 17 0 0 1 5 24 24 75 3,063 267 4b.1.7.10 AZE 16 0 0 1 4 23 23 70 2,856 256 4b.1.7.11 AZF 15 0 0 2 4 22 22 90 3,672 239 4b.1.7.12 AZI 30 1 1 7 9 47 47 343 13,938 461 4b.1.7 Totals 547 10 26 112 158 853 853 5,865 238,198 8,345 Miscellaneous System Components 4b.1.8.1 BAA 262 5 14 62 77 421 421 3,241 131,602 3,979 4b.1.8.2 BBA 88 4 10 42 30 173 173 2,183 88,656 1,368 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 14 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Miscellaneous System Components (continued) 4b.1.8.3 BDA 11 0 0 1 3 14 14 27 1,083 167 4b.1.8.4 CAA 615 17 45 196 192 1,064 1,064 10,252 416,330 9,611 4b.1.8.5 DAA 64 1 2 7 17 91 91 376 15,277 1,005 4b.1.8.6 DAC 152 2 5 23 42 225 225 1,230 49,940 2,323 4b.1.8.7 DGB 82 12 94 94 1,336 4b.1.8.8 DOT 14 2 16 16 223 4b.1.8.9 DPH 95 14 109 109 1,527 4b.1.8.10 DWF 22 3 25 25 360 4b.1.8.11 FWP 127 19 146 146 2,018 4b.1.8.12 GAA / GCA 23 3 26 26 368 4b.1.8.13 INTAKE STRUCTURE 199 30 229 229 3,218 4b.1.8.14 MAA 127 2 6 28 37 200 200 1,469 59,650 1,920 4b.1.8.15 MBA 51 1 2 8 14 76 76 413 16,776 764 4b.1.8.16 MBS / MBT 38 0 0 2 10 50 50 108 4,371 575 4b.1.8.17 MS 40 6 46 46 676 4b.1.8.18 NMB ROOF 20 3 22 22 312 4b.1.8.19 OB 292 44 336 336 4,806 4b.1.8.20 PTB 43 6 49 49 688 4b.1.8.21 RSF ROOF 29 0 1 3 8 42 42 175 7,097 451 4b.1.8.22 UYARD 1,807 10 27 118 474 2,435 2,435 6,162 250,262 21,730 4b.1.8.23 WAA 166 2 5 23 46 242 242 1,197 48,603 2,479 4b.1.8.24 WHS 19 3 22 22 318 4b.1.8.25 YARD AREAS 408 61 470 470 6,583 4b.1.8.26 YDA / YFA / YLA 2 0 0 0 1 3 3 19 783 30 4b.1.8 Totals 4,796 44 117 513 1,159 6,629 5,037 1,592 26,851 1,090,429 68,833 4b.1.9 Scaffolding in support of decommissioning 1,410 41 11 34 11 366 1,873 1,873 1,586 168 80,852 25,304 Decontamination of Site Buildings 4b.1.10.1 New Radwaste Building Systems Removal 0 146 103 156 0 233 129 767 767 6 4,340 382,187 2,226 4b.1.10.2 Old Radwaste Building Systems Removal 0 4 11 17 0 25 11 67 67 6 461 40,787 66 4b.1.10.3 Turbine Building Systems Removal 419 249 376 561 326 1,931 1,931 10,447 919,350 5,562 4b.1.10.4 Augmented Off Gas Decon 19 117 15 23 1 34 52 261 261 45 629 57,149 1,961 4b.1.10.5 LLRW Storage Decon 10 36 9 14 20 22 112 112 379 33,330 653 4b.1.10.6 Miscellaneous Buildings Decon 10 48 9 13 20 25 126 126 372 32,778 831 4b.1.10.7 New Radwaste Building Decon 47 441 58 88 4 130 186 955 955 235 2,420 222,115 7,003 4b.1.10.8 Old Radwaste Building Decon 410 237 359 3 535 314 1,859 1,859 152 9,965 882,859 4,833 4b.1.10.9 Stack/Exhaust Tunnels Remove & Decon 103 494 36 55 82 207 977 977 1,521 133,878 8,806 4b.1.10.10 Turbine Building 0ft Decon 72 532 58 88 22 127 223 1,122 1,122 1,144 2,356 252,047 8,702 4b.1.10.11 Turbine Building 23ft Decon 47 381 44 68 21 97 161 818 818 1,109 1,789 200,730 6,140 4b.1.10.12 Turbine Building 46ft Decon 29 121 26 39 58 68 340 340 1,073 94,413 2,127 4b.1.10.13 Drywell Decon 4 727 395 513 1,006 552 3,198 3,198 16,964 1,290,650 9,848 4b.1.10.14 Drywell Liner Removal 2,063 1,197 74 105 422 71 1,435 5,366 5,366 22,108 1,022 956,216 47,924 4b.1.10.15 RB0 Torus Removal 2,765 1,375 110 156 626 105 1,881 7,017 7,017 32,774 1,515 1,417,560 60,646 4b.1.10.16 Reactor Building Systems Removal 6 18 27 40 17 107 107 736 64,800 101 4b.1.10.17 Reactor Building 19ft Decon 33 277 28 44 39 57 115 593 593 2,052 1,043 172,007 4,412 4b.1.10.18 Reactor Building 119ft Decon 442 537 16 24 30 29 372 1,450 1,450 1,563 526 107,572 14,581 4b.1.10.19 Reactor Building 23ft Decon 21 128 19 29 43 60 299 299 796 70,017 2,140 4b.1.10.20 Reactor Building 51ft Decon 24 133 21 32 48 64 322 322 887 78,096 2,253 4b.1.10.21 Reactor Building 75ft Decon 8 71 7 11 16 28 141 141 297 26,136 1,155 4b.1.10.22 Reactor Building 91ft Decon 17 111 15 23 34 50 250 250 634 55,770 1,847 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 15 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours 4b.1.10 Totals 5,715 7,712 1,558 2,257 1,168 3,369 6,297 28,076 28,076 61,196 60,173 7,490,445 193,816 4b.1 Subtotal Period 4b Activity Costs 6,260 26,416 2,530 3,671 4,569 5,459 12,412 61,317 59,530 1,787 239,206 90,639 16,453,780 480,758 Period 4b Additional Costs 4b.2.1 ISFSI License Termination 2,577 1,587 1,411 1,253 6,827 6,827 19,521 2,578,520 4b.2.2 ISFSI License Termination Cascading Costs 1,480 524 301 2,305 2,305 4b.2.3 License Termination Survey Planning 1,948 584 2,532 2,532 12,480 4b.2.4 Contaminated Soil Removal 111 2 500 5,702 1,529 7,844 7,844 106,200 8,071,193 834 4b.2 Subtotal Period 4b Additional Costs 4,169 2 500 7,289 3,883 3,666 19,509 10,376 9,133 125,721 10,649,710 834 12,480 Period 4b Collateral Costs 4b.3.1 Process decommissioning water waste 15 18 47 85 38 202 202 250 14,985 49 4b.3.3 Small tool allowance 615 92 707 707 4b.3.4 Decommissioning Equipment Disposition 155 49 127 44 53 427 427 6,000 635 305,961 88 4b.3 Subtotal Period 4b Collateral Costs 15 615 172 96 127 129 182 1,336 1,336 6,000 885 320,946 137 Period 4b PeriodDependent Costs 4b.4.1 Decon supplies 1,124 281 1,404 1,404 4b.4.2 Insurance 850 85 935 935 4b.4.3 Property taxes 1,481 148 1,629 1,629 4b.4.4 Health physics supplies 2,768 692 3,460 3,460 4b.4.5 Heavy equipment rental 2,955 443 3,398 3,398 4b.4.6 Disposal of DAW generated 171 121 424 141 857 857 7,415 148,298 242 4b.4.7 Plant energy budget 2,132 320 2,452 2,452 4b.4.8 NRC Fees 1,063 106 1,170 1,170 4b.4.9 Site O&M Costs 458 69 527 527 4b.4.10 Liquid Radwaste Processing Equipment/Services 574 86 661 661 4b.4.11 Security Staff Cost 5,378 807 6,185 6,185 96,607 4b.4.12 DOC Staff Cost 17,703 2,655 20,358 20,358 207,126 4b.4.13 Utility Staff Cost 29,142 4,371 33,513 33,513 364,789 4b.4 Subtotal Period 4b PeriodDependent Costs 1,124 5,722 171 121 424 58,782 10,205 76,548 76,548 7,415 148,298 242 668,521 4b.0 TOTAL PERIOD 4b COST 7,398 36,922 2,876 4,388 4,696 13,301 62,664 26,465 158,711 147,791 9,133 1,787 245,206 224,659 27,572,740 481,970 681,001 PERIOD 4f License Termination Period 4f Direct Decommissioning Activities 4f.1.1 ORISE confirmatory survey 161 48 210 210 4f.1.2 Terminate license a 4f.1 Subtotal Period 4f Activity Costs 161 48 210 210 Period 4f Additional Costs 4f.2.1 License Termination Survey 8,201 2,460 10,661 10,661 118,801 6,240 4f.2 Subtotal Period 4f Additional Costs 8,201 2,460 10,661 10,661 118,801 6,240 Period 4f Collateral Costs 4f.3.1 DOC staff relocation expenses 1,124 169 1,292 1,292 4f.3 Subtotal Period 4f Collateral Costs 1,124 169 1,292 1,292 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 16 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Period 4f PeriodDependent Costs 4f.4.2 Property taxes 753 75 828 828 4f.4.3 Health physics supplies 802 201 1,003 1,003 4f.4.4 Disposal of DAW generated 8 6 20 7 41 41 351 7,025 11 4f.4.5 Plant energy budget 289 43 332 332 4f.4.6 NRC Fees 579 58 637 637 4f.4.7 Site O&M Costs 233 35 268 268 4f.4.8 Security Staff Cost 1,087 163 1,250 1,250 18,857 4f.4.9 DOC Staff Cost 5,156 773 5,929 5,929 57,357 4f.4.10 Utility Staff Cost 6,703 1,005 7,708 7,708 74,643 4f.4 Subtotal Period 4f PeriodDependent Costs 802 8 6 20 14,800 2,361 17,997 17,997 351 7,025 11 150,857 4f.0 TOTAL PERIOD 4f COST 802 8 6 20 24,286 5,038 30,161 30,161 351 7,025 118,812 157,097 PERIOD 4 TOTALS 7,602 58,275 13,379 7,693 9,321 24,469 126,180 53,787 300,707 289,660 9,133 1,915 470,628 255,628 1,127 344 1,428 40,103,200 773,987 1,281,305 PERIOD 5b Site Restoration Period 5b Direct Decommissioning Activities Demolition of Remaining Site Buildings 5b.1.1.1 Stack/Exhaust Tunnels Remove & Decon 1,019 153 1,172 1,172 1,665 5b.1.1.2 Administration Building 506 76 582 582 6,477 5b.1.1.3 Augmented Off Gas Building 338 51 388 388 3,399 5b.1.1.4 Chlorination Building 32 5 36 36 407 5b.1.1.5 Diesel Generator Building 137 21 157 157 1,268 5b.1.1.6 Dilution Structure 178 27 205 205 1,758 5b.1.1.7 Domestic Water Facility 11 2 12 12 147 5b.1.1.8 Fire Pump House 4 1 5 5 54 5b.1.1.9 Fresh Water Pump House 22 3 26 26 293 5b.1.1.10 Heating Boiler House 41 6 48 48 546 5b.1.1.11 Intake Structure 632 95 727 727 6,322 5b.1.1.12 Low Level Radwaste Storage 444 67 511 511 5,435 5b.1.1.13 Machine Shop 226 34 260 260 2,858 5b.1.1.14 Main Gate Security 101 15 116 116 1,059 5b.1.1.15 Maintenance Building 326 49 375 375 4,274 5b.1.1.16 Materials Warehouse 879 132 1,011 1,011 8,908 5b.1.1.17 Miscellaneous Structures 617 93 710 710 6,565 5b.1.1.18 New Radwaste Building 745 112 857 857 8,009 5b.1.1.19 New Sample Pump House 9 1 11 11 128 5b.1.1.20 Office Building 374 56 430 430 4,459 5b.1.1.21 Old Radwaste Building 680 102 782 782 6,852 5b.1.1.22 Plant Engineering 170 25 195 195 1,784 5b.1.1.23 Pretreatment Building 31 5 35 35 420 5b.1.1.24 Reactor Building 6,127 919 7,046 7,046 61,454 5b.1.1.25 Sample Pool 15 2 18 18 180 5b.1.1.26 Security Modifications 1,256 188 1,444 1,444 10,330 5b.1.1.27 Site Emergency Building 316 47 363 363 3,285 5b.1.1.28 Tank Pads & Misc. Yard 772 116 887 887 8,326 5b.1.1.29 Turbine Building 4,209 631 4,840 4,840 41,424 5b.1.1.30 Turbine Pedestal 574 86 660 660 5,050 5b.1.1 Totals 20,789 3,118 23,908 23,908 203,134 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 17 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours Site Closeout Activities 5b.1.2 Remove Rubble 798 120 917 917 4,211 5b.1.3 Grade & landscape site 634 95 729 729 1,304 5b.1.4 Final report to NRC 187 28 215 215 1,560 5b.1 Subtotal Period 5b Activity Costs 22,221 187 3,361 25,769 215 25,554 208,649 1,560 Period 5b Additional Costs 5b.2.1 Concrete Crushing 756 9 115 880 880 3,219 5b.2.2 Install Cofferdams Intake & Dilution 975 146 1,122 1,122 8,296 5b.2.3 ISFSI Site Restoration 144 6 22 172 172 5b.2 Subtotal Period 5b Additional Costs 1,875 15 284 2,174 172 2,002 11,516 Period 5b Collateral Costs 5b.3.1 Small tool allowance 265 40 305 305 5b.3 Subtotal Period 5b Collateral Costs 265 40 305 305 Period 5b PeriodDependent Costs 5b.4.2 Property taxes 1,552 155 1,708 1,708 5b.4.3 Heavy equipment rental 4,438 666 5,104 5,104 5b.4.4 Plant energy budget 298 45 343 343 5b.4.5 Site O&M Cost 480 72 552 552 5b.4.6 Security Staff Cost 2,242 336 2,578 2,578 38,880 5b.4.7 DOC Staff Cost 10,204 1,531 11,735 11,735 110,160 5b.4.8 Utility Staff Cost 5,737 861 6,598 6,598 63,180 5b.4 Subtotal Period 5b PeriodDependent Costs 4,438 20,514 3,665 28,617 28,617 212,220 5b.0 TOTAL PERIOD 5b COST 28,799 20,716 7,350 56,865 215 172 56,478 220,165 213,780 PERIOD 5 TOTALS 28,799 20,716 7,350 56,865 215 172 56,478 220,165 213,780 TOTAL COST TO DECOMMISSION 16,345 110,088 13,794 10,132 10,077 29,059 766,001 160,818 1,116,314 873,828 183,117 59,369 470,956 314,989 1,127 344 1,428 44,296,250 1,262,856 6,773,869 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix E, Page 18 of 18 Table E Oyster Creek Nuclear Generating Station SAFSTOR Decommissioning Cost Estimate (thousands of 2011 dollars)

Costs run: Tue, Dec 9, 2014 at 07:28:09 Off-Site LLRW NRC Spent Fuel Site Processed Burial Volumes Burial / Utility and Activity DECCER Version 2010.09.09a Decon Removal Packaging Transport Processing Disposal Other Total Total Lic. Term. Management Restoration Volume Class A Class B Class C GTCC Processed Craft Contractor Index Activity Description Cost Cost Costs Costs Costs Costs Costs Contingency Costs Costs Costs Costs Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt., Lbs. Manhours Manhours TOTAL COST TO DECOMMISSION WITH 16.83% CONTINGENCY: $1,116,314 thousands of 2011 dollars TOTAL NRC LICENSE TERMINATION COST IS 78.28% OR: $873,828 thousands of 2011 dollars SPENT FUEL MANAGEMENT COST IS 16.4% OR: $183,117 thousands of 2011 dollars NONNUCLEAR DEMOLITION COST IS 5.32% OR: $59,369 thousands of 2011 dollars TOTAL LOWLEVEL RADIOACTIVE WASTE VOLUME BURIED (EXCLUDING GTCC): 316,460 cubic feet TOTAL GREATER THAN CLASS C RADWASTE VOLUME GENERATED: 1,428 cubic feet TOTAL SCRAP METAL REMOVED: 24,292 tons TOTAL CRAFT LABOR REQUIREMENTS: 1,262,856 manhours End Notes:

n/a indicates that this activity not charged as decommissioning expense.

a indicates that this activity performed by decommissioning staff.

0 indicates that this value is less than 0.5 but is nonzero.

a cell containing " " indicates a zero value TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 1 of 12 APPENDIX F WORK DIFFICULTY FACTOR ADJUSTMENTS TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 2 of 12 GUIDELINES FOR APPLYING WORK DURATION ADJUSTMENT FACTORS TLG has historically applied work duration adjustment factors in determining unit cost factors to account for working in a radiologically controlled environment. In performing an area-by-area decommissioning estimate, the work duration factors are applied on an area basis based on the nominal area conditions. Where practical, areas are established based on similar working conditions.

The WDFs fall into five categories: access, respiratory protection, ALARA, protective clothing (PC), and work breaks. The guidelines of how these factors are assessed for each area is described below. Table F-1 details the WDFs used for each of the seven unit cost factor sets contained in the estimates. Table F-2 outlines the unit cost factors used for each area of the Oyster Creek plant.

1) Access Factor:

Controlling Variables:

Height of the component above the working floor Difficulty in working around the component (restricted access)

Source of Variable Information:

Estimators observation or judgment Plant drawings Range of Access Factor Adjustments:

0% - Components are accessible and located near a working level floor or platform 10% - Scaffolding (component less than <12 feet above floor) is required to access the majority of the components or the area around the components is congested.

20% - Scaffolding (component less than <12 feet above floor) is required to access the majority of the components and the area around the components is congested.

30% - Scaffolding (component between 12 - 20 feet above floor) is required to access the majority of the components or the area around the components are extremely congested.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 3 of 12 40% - Scaffolding (component between 20 - 45 feet above floor) is required to access the majority of the components).

50% - Scaffolding (component greater than 45 feet above floor) is required to access the majority of the components).

2) Respiratory Protection Factor:

Controlling Variables:

Component surface contamination levels (internal or external)

Type of work (potential to create an airborne problem)

General area surface contamination levels Site specific requirements for maintaining respirator qualifications (initial qualification, requalification, etc.)

Personal air sampler requirements Sources of Variable Information:

Radiation Work Permit Requirements Area Survey Maps Site Radiation Protection Program Manual Range of Respiratory Protection Factor Adjustments:

0% - Respiratory protection is not required (clean system or loose surface contamination has been removed).

25% - Respiratory protection is only required during limited segments of the work (i.e., physical cutting) 50% - Respiratory protection is continuously required while working on the component.

3) Radiation/ALARA Factor:

Controlling Variables:

Component contact dose rate General area dose rate Site specific requirements for maintaining radiation worker qualification (initial qualification, requalification, etc.)

Dosimetry requirements Sources of Variable Information:

Area Survey Maps Site Radiation Protection Program Manual Radiation Work Permit Requirements TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 4 of 12 Range of Radiation/ALARA Factor Adjustments:

(Note that surface contamination levels are principally accounted for in protective clothing requirements and respiratory protection requirements) 0% - The component is clean and is not located in a radiologically controlled area 10% - The component is located in a radiologically controlled area (General Area Radiation field < 2 .5 mrem/hr).

20% - The component is located in a radiologically controlled area (General Area Radiation field between 2. 5 to 15 mrem/hr).

40% - The component is located in a radiologically controlled area (General Area Radiation field between 16 and 99 mrem/hr).

100% - The component is located in a radiologically controlled area (General Area Radiation field > 100 mrem/hr).

4) Protective Clothing Factor:

Controlling Variables:

Component surface contamination levels (internal or external)

General area surface contamination levels Type of activity (wet/dry work, potential to create a surface contamination problem)

Site specific work schedule arrangements Sources of Variable Information:

Radiation Work Permit Requirements Area Survey Maps Site Radiation Protection Program Manual Range of Protective Clothing Factor Adjustments (alternate site-specific schedules may dictate alternate adjustments):

0% - The component is clean and is not located in a radiologically controlled area.

30% - The component is clean or contaminated and is located in a surface contamination controlled area. Work is to be completed in accordance with the requirements of an RWP, which specifies a single or double set of PCs, or PCs with plastics.

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 5 of 12 50% - The components is located in a surface contamination controlled area.

Work is to be completed in accordance with the requirements of an RWP, which specifies plastics in addition to double PCs for protective clothing.

100% - The component is located in a surface contamination controlled area.

Work is to be completed in accordance with the requirements of an RWP, which specifies double PCs and double plastics. (extremely wet or humid working environment).

5) Work Break Factor:

Controlling Variables:

Site specific work schedule arrangements Sources of Variable Information:

Typical site work schedule Range of Work Break Factor Adjustments:

8.33% - Workday schedule outlined in AIF/NESP-036 (alternate site-specific schedules may dictate alternate adjustments).

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 6 of 12 TABLE F-1 UNIT COST FACTOR SETS AND THEIR WORK DIFFICULTY ADJUSTMENT FACTORS DECON / Clean DECON / Contaminated Percentage Percentage UCF Set ID Access Resp. PCs ALARA Access Resp. PCs ALARA 1 10 0 0 10 10 0 0 10 2 20 0 30 10 20 0 30 10 3 20 25 30 30 20 25 30 30 4 30 25 50 30 30 25 50 30 5 50 25 50 40 50 25 50 40 6 30 25 50 100 30 25 50 100 7 20 0 0 0 20 25 30 30 SAFSTOR / Clean SAFSTOR / Contaminated Percentage Percentage UCF Set ID Access Resp. PCs ALARA Access Resp. PCs ALARA 1 10 0 0 10 10 0 0 10 2 20 0 30 10 20 0 30 10 3 20 25 30 10 20 25 30 10 4 30 25 50 10 30 25 50 10 5 50 25 50 10 50 25 50 10 6 30 25 50 10 30 25 50 10 7 20 0 0 0 20 25 30 10 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 7 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS AREA AREA DESCRIPTION UCF SET Drywell System Components IAA DRYWELL RECIRC LOOP 5 IAC DRYWELL EL. 13 - SUB PILE ROOM 5 ICA DRYWELL EL. 51 & 75' 5 IEA DRYWELL EL. 95 4 RC6 DRYWELL LABRYNTH 3 Reactor Building System Components RB1 REACTOR BUILDING - 19' GENERAL 3 RBB 19' NE 3 RBC 19' SE 3 RBE CRD SYSTEM PUMP ROOM 3 RBF REACTOR BUILDING EQUIPMENT DRAIN TANK ROOM 3 RBO 19' INSIDE TORUS 4 RBS TOP OF TORUS SEGMENT N/E 4 RBSW REACTOR BUILDING SWITCHGEAR ROOM 2 RC1 SOUTHEAST AIRLOCK 3 RC7 SW RAD MONITOR ENCLOSURE 2 RCA NORTH SCRAM DISCHARGE VOLUME 3 RCB LAUNDRY & LAB DRAIN TANKS/PUMPS 3 RCD NORTH BANK HCU's 3 RCG NORTH CONTAINMENT SPRAY HEAT EXCHANGERS 3 RCJ CRD SYSTEM FILTER/VALVING AREA 3 RCM SOUTH BANK CSS HEAT EXCHANGERS 3 RCN SOUTH BANK CONTROL ROD DRIVE MODULES 3 RCS SOUTH SCRAM DISCHARGE VOLUME (RCS15VM) 3 RCT REACTOR BUILDING EL.23 ALL AREAS GENERAL 3 RD8 RX33' SHUTDOWN COOLING RM GENERAL ALL AREAS 3 RDM TIP DRIVE ROOM WEST 3 REC CORE SPRAY BOOSTER PUMPS 3 REF SHUTDOWN COOLING HEAT EXCHANGER ROOM 1 REH NITROGEN COMPRESSOR AREA 3 REI REACTOR 51' TOOL CRIB 3 REL RBCCW HEAT EXCHANGER/PUMP AREA 3 REM SOUTHEAST ACCESS AREA 3 REO CLEANUP SYSTEM HEAT EXCHANGER ROOM 4 REQ CLEANUP SYSTEM PUMP AREA 3 RER CLEANUP SYSTEM VALVE NEST EL.64 5 RET CLEANUP FILTER SLUDGE PUMP HALLWAY 6 REW INSTRUMENT RACK RK01 3 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 8 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS (continued)

AREA AREA DESCRIPTION UCF SET Reactor Building System Components (continued)

REX INSTRUMENT RACK RK02 AREA 3 REY REACTOR BUILDING 51' GENERAL ALL AREAS 3 RFB SOUTH EAST GENERAL AREA (C.U. SURGE TANK) 3 RFC RWCU VALVE AISLE AND CONTROL AREA 5 RFF CLEANUP SYSTEM FILTER AID/PRECOAT TANK AREA 3 RFH OLD FUEL POOL HEAT EXCHANGERS & PUMPS AREA 3 RFJ ASFP HEAT EXCHANGERS/PUMPS AREA 3 RFL CONTROL ROD DRIVE REBUILD ROOM 3 RFN EMERGENCY CONDENSER VALVE AREA 3 RFQ REACTOR BUILDING 75' GENERAL ALL AREAS 3 RGC NORTHEAST ACCESS AREA 3 RGD "B" EMERGENCY CONDENSER NE01-B 3 RGI SOUTHEAST ACCESS AREA 3 RGL SOUTHWEST ACCESS AREA 3 RGP CLEANUP DEMINERALIZER VAULT (RGP16FM) 4 RGR LIQUID POISON TANK/PUMPS AREA 3 RGU REACTOR BUILDING EL.95 - GENERAL ALL AREAS 3 RH1 NORTH FLOOR AREA 3 RH2 WEST FLOOR AREA 3 RH3 RB EL119 ALL AREAS 3 RH4 REACTOR BUILDING CRANE 3 RH6 ELEVATOR CONTROL EQUIP AREA 3 RHA REACTOR CAVITY 6 RHJ CASK WASHDOWN / DECONTAMINATION AREA 3 RHL BRIDGE CRANE AND TRACKS 3 RHX SOUTH FLOOR AREA 3 RHY SOUTH EAST FLOOR AREA 3 RMCC REACTOR BUILDING MCC ROOM 2 New Radwaste Building System Components 7EB NRW TUNNEL GENERAL ALL AREAS 5 N2G NRW BUILDING GENERAL ALL ELEVATIONS 3 N2P NRW BUILDING PENTHOUSE 3 N38 NRW 23' GENERAL ALL AREAS 3 N3A NRW TRUCK BAY 3 N3D NEW RADWASTE FILL AISLE 4 N3I NRW #2 SUMP ROOM 4 N3N NRW SOUTH OPERATING GALLERY EAST 4 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 9 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS (continued)

AREA AREA DESCRIPTION UCF SET New Radwaste Building System Components (continued)

N3P NRW HIGH PURITY PUMP ROOM 3 N3Q NRW WC-P-1B WASTE CHEM PUMP ROOM 3 N3R NRW VALVE AREA WEST 3 N3S NRW WC-P-1A WASTE CHEM PUMP ROOM 4 N3T NRW #1 SUMP ROOM 4 N3U NRW CONCENTRATOR SKID ROOM 'A' 4 N3W NRW CONCENTRATOR SKID ROOM 'B' 4 N3Y NRW HEAT EXCHANGER BUILDING 3 N48 NRW 38' GENERAL ALL AREAS 3 N4A NRW 'A' HOLD-UP TANK SL-T-3A ROOM 5 N4B B' HOLD-UP TANK SL-T-3B ROOM 5 N4D LARGE CONTAINER FILL SKID ROOM SL-Y-6 4 N4E NRW LARGE CONTAINER FILL SKID ROOM 3 N4F CLW PROCESS AREA 4 N4H SPENT RESIN TRANSFER PIPING 4 N4K NRW SPENT RESIN VALVE GALLERY 4 N4L PIPE GALLERY WEST 4 N51 NRW HP-D-1A DEMINERALIZER ROOM 5 N52 NRW HP-F-2A RESIN TRAP ROOM 5 N53 NRW HP-D-1B DEMINERALIZER ROOM 5 N54 NRW HP-F-2B RESIN TRAP ROOM 5 N55 NRW MEZZANINE/VALVING AREA 4 N56 NRW 48-0 ELEVATION GENERAL ALL AREAS 3 N5A NRW "A" CONCENTRATED LIQUID WASTE TANK ROOM SL-T-1A 5 N5B NRW "B" CONCENTRATED LIQUID WASTE TANK ROOM SL-T-1B 5 N5C NRW CHEMICAL WASTE FILTER ROOM 1A 4 N5D NRW HIGH PURITY FILTER ROOM 1A 4 N5E NRW CHEMICAL WASTE FILTER ROOM 1B 4 N5F NRW HIGH PURITY FILTER ROOM 1B 4 N5G NRW CONCENTRATED LIQUID WASTE PUMP SL-P-1A ROOM 5 N5H NRW VALVE GALLERY EAST 4 N5I NRW CONCENTRATED LIQUID WASTE PUMP SL-P-1B ROOM 5 N5J NRW SAMPLE SINK AREA 3 N5K NRW NEUTRALIZATION FEED SKID AREA 3 N5N NRW LAUNDRY/DECON AREA 3 N5O NRW FILTER PRECOAT/BODY FEED ROOM 3 N5P NRW SL-T-2A SPENT RESIN TANK 5 N5Q NRW SL-T-2B SPENT RESIN TANK 5 N5R NRW CONTROL ROOM 3 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 10 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS (continued)

AREA AREA DESCRIPTION UCF SET New Radwaste Building System Components (continued)

N5S NRW BUILDING HVAC ROOM 3 N5T NRW CHEM WASTE/FLR DRAIN TANK ROOM WC-T-1A 5 N5U NRW CHEM WASTE/FLR DRAIN TANK ROOM WC-T-1B 5 N5V NRW CHEM WASTE/FLR DRAIN TANK ROOM WC-T-1C 5 N5W NRW CRANE BAY-STORAGE/LAYDOWN ROOM 3 N5X NRW HIGH PURITY TANK & ROOM 1A 5 N5Y NRW WC-D-1A DEMISTER ROOM 5 N5Z NRW WC-D-1B DEMISTER ROOM 5 PAA OLD RADWASTE BUILDING GENERAL ALL AREAS 3 Old Radwaste Building System Components 7BA 1-12 SUMP AREA GENERAL 4 7DA ORW TUNNEL GENERAL ALL AREAS 4 7FA ORW AIR FILTER ROOM 5 PBA ORW SMALL PUMP ROOM 5 PDA ORW 35' & 45' CENTRIFUGE AND HOPPER 5 PMA ORW OVERBOARD DISCHARGE MONITOR 3 PRA ORW ROOF GENERAL ALL AREAS 4 PRD ORW FUEL POOL FILTERS / KELLY BUILDING 4 PSB ORW CONTROL ROOM OPERATION AREA 3 PTA ORW COMPACTOR AREA 3 PTK ORW - NORTH ANNEX 3 PTP DRUM STORAGE AREA GENERAL 3 PUA ORW LARGE PUMP ROOM 4 PUU ORW INSIDE TANK ROOM GENERAL 4 PVA ORW NORTH ANNEX KELLY BUILDING 2 UAB ORW OUTSIDE TANKS & MOAT AREA 4 UAS ORW SURGE TANK & PUMP AREA 4 ORW ORW PRE D&D DESLUDGE AND DECON 4 Turbine Building System Components 7CA TURBINE TUNNEL GENERAL ALL AREAS 5 TB2 TURBINE BUILDING BASEMENT GENERAL ALL AREAS 3 TB23 TB23 HALLWAY AREA 1 TB38 TB38 HALLWAY AREA 1 TC2 CONDENSER BAY OVERHEAD GENERAL ALL AREAS 3 TD2 CONDENSER BAY DRAIN TANK PIT 3 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 11 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS (continued)

AREA AREA DESCRIPTION UCF SET Turbine Building System Components (continued)

TE2 SPARE EXCITER GENERAL ALL AREAS 2 TEE 4160 VOLT ROOM 3 TEG RCA EXIT 1 TF2 FEED PUMP ROOM GENERAL ALL AREAS 3 TFG OFF GAS SAMPLE AREA 3 TG2 CONDENSATE PUMP PIT 3 TH2 HEATER BAY AREA 3 TKA TB EAST AND WEST PASSAGEWAY 2 TL2 HI-LO CONDUCTIVITY ROOM 3 TMA MECHANICAL VACUUM PUMP ROOM 3 TN2 TB BASEMENT NORTH 3 TO2 OPERATING FLOOR 3 TOA HEATER BAY ROOF 3 TOCR/DCA TURBINE BUILDING CONTROL ROOM 1 TOR TURBINE BYPASS VALVE AREA 3 TOV CONTAMINATED INSTRUMENT SHOP EL.55-4 2 TOW EL.46-6 WEST ROOF AREA 3 TOX TURBINE RAGEMS II BUILDING 3 TOY TURBINE REPAIR OFFICE 3 TP2 CONDENSATE DEMINERALIZER AREA 3 TP3 CONDENSATE DEMINERALIZER TANK ROOM 4 TPE REGEN TANK ROOM ENTRANCE AREA 3 TS2 STEAM JET AIR EJECTOR ROOM 3 TTA TRUNNION ROOM GENERAL ALL AREAS 4 TU2 TB NORTH MEZZANINE 3 Augmented Offgas System Components AY8 AOG NORTH ACCESS AREA (AYFOGZI) 3 AYA RECOMBINER ROOM 'A' 3 AYB RECOMBINER ROOM 'B' 3 AYC CHARCOAL ADSORBER ROOM 3 AYE AOG PIPE TUNNEL & SUMP AREA 4 AZ8 REFRIGERATION EQOT AREA ALL AREAS 3 AZA HEPA FILTER ROOM 'A' 3 AZC AOG CONTROL ROOM AREA 3 AZD WATER REMOVAL TRAIN #1 ROOM 3 AZE WATER REMOVAL TRAIN #2 ROOM 3 AZF WATER REMOVAL TRAIN #3 ROOM 3 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix F, Page 12 of 12 TABLE F-2 OYSTER CREEK STN DESIGNATIONS AND ASSOCIATED UNIT COST FACTORS (continued)

AREA AREA DESCRIPTION UCF SET Augmented Offgas System Components (continued)

AZI AOG BUILDING HVAC ROOM 3 Miscellaneous System Components BAA BOILER HOUSE ALL AREAS 3 BBA STACK ALL AREAS 3 BDA RAGEMS I BUILDING 3 CAA CONDENSATE STORAGE TANK 3 DAA CHEMISTRY LA GENERAL ALL AREAS 3 DAC CABLE SPREADING ROOM EL.36-0 3 DGB DIESEL GENERATOR #1 & #2 W/ STORAGE TANK 1 DOT DIRTY OIL TANK 1 DPH14-6 DILUTION PUMP HOUSE 1 DPH6-0 DILUTION PUMP HOUSE 1 DWF DOMESTIC WATER FACILITY 1 FWP FRESH WATER PUMP HOUSE 1 GAA NORTH GUARD HOUSE AND PARKING LOT 1 GCA MAIN GATE SECURITY BUILDING AND PARKING LOT 1 MAA NMB ;HOT MACHINE SHOP 3 MBA NMB RWP OFFICE 2 MBS NMB HOT TOOL ROOM 2 MBT RESP MAINT FACILITY 2 MS23-6 MACHINE SHOP 1 MS34-6 HEALTH PHYSICS STORAGE AREA 1 MSROOF MACHINE SHOP ROOF 1 NMBROOF HOT MACHINE SHOP ROOF AREA 1 OB35-0 OFFICE BUILDING A/B BATTERY ROOM 1 OB46-6 OFFICE BUILDING 1 OBROOF OFFICE BUILDING ROOF 1 PTB23-6 PRETREATMENT BLDG 1 RSFROOF SERVICE HEAD ROOF 2 WAA LLRWSF 2 WHS CONTROL ROOM 1 YDA DRYWELL PROCESSING FACILITY 2 YFA YARD LAUNDRY TRAILER 2 YLA YARD RADWASTE SHIPPING CENTER 2 INTAKE STR INTAKE STRUCTURE 1 UYARD YARD 2 YARD AREAS YARD AREAS 1 TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 1 of 12 APPENDIX G WORK AREA DESIGNATION GPU SURVEY TRACKING NUMBER (STN) INDEX TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 2 of 12 GPU STN INDEX TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 3 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 4 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 5 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 6 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 7 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 8 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 9 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 10 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 11 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

Oyster Creek Nuclear Generating Station Document E16-1640-002, Rev. 4 Decommissioning Cost Analysis Appendix G, Page 12 of 12 GPU STN INDEX (continued)

TLG Services, Inc.

ATTACHMENT 2 SPENT FUEL MANAGEMENT PLAN FOR OYSTER CREEK NUCLEAR GENERATING STATION Spent Fuel Management Plan December 30, 2014 Page 1 of 3 ATTACHMENT 2 SPENT FUEL MANAGEMENT PLAN FOR OYSTER CREEK NUCLEAR GENERATING STATION

Background

Exelon Generation Company, LLC (Exelon) provided notice of its intention to permanently terminate operations at Oyster Creek Nuclear Generating Station (OCNGS) on December 31, 2019, pursuant to an Administrative Consent Order between Exelon and the New Jersey Department of Environmental Protection dated December 9, 2010.

A preliminary decommissioning cost estimate that evaluates three options for decommissioning OCNGS has been prepared. For the purpose of demonstrating the adequacy of funding to meet regulatory requirements, the SAFSTOR decommissioning option has been selected. This Spent Fuel Management Plan is similarly based on the SAFSTOR analysis, although the discussion below includes all three decommissioning options. Exelon has not made a final determination of the decommissioning approach for OCNGS. Exelon reserves the right to choose the ultimate decommissioning option in accordance with its business needs, recognizing that it needs to assure the chosen option meets U.S. Nuclear Regulatory Commission (NRC) requirements for decommissioning funding assurance.

There is an Independent Spent Fuel Storage Installation (ISFSI) on the OCNGS site operating under a NRC general license.

Spent Fuel Management Strategy The NRC requires (as discussed in 10 CFR 50.54(bb)) that licensees establish a program to manage and provide funding for the management of all irradiated fuel at the reactor following permanent cessation of operation of the reactor until title to the irradiated fuel and possession of the fuel is transferred to the Secretary of Energy for its ultimate disposal in a repository.

Pending transfer of the fuel to the U.S. Department of Energy (DOE), Exelon will store fuel on an interim basis in the storage pool and/or the ISFSI located at the OCNGS site.

A licensed ISFSI is currently operational at OCNGS. For the DECON and SAFSTOR scenarios, the ISFSI facility will be expanded to accommodate the inventory of spent fuel in the spent fuel pool at the conclusion of the required cooling period. Once the spent fuel pool is emptied of fuel, the reactor building can be either decontaminated and dismantled or prepared for long-term storage. In the delayed DECON scenario, the spent fuel pool and the existing ISFSI facility would remain operational and used for the interim storage of the fuel until such time as the DOE takes title and possession of the fuel. The balance of the facility will be placed in a SAFSTOR condition. In all three decommissioning scenarios, the existing ISFSI will continue to operate until such time of the transfer of spent fuel to the DOE is complete.

Assuming that the DOEs generator allocation/receipt schedules are based upon the oldest fuel receiving the highest priority and that the DOE begins removing spent fuel from commercial facilities in 2025 with an annual capacity of 3,000 metric tons of uranium, spent fuel is projected to remain at the OCNGS site for approximately 17 years after the termination of operations Spent Fuel Management Plan December 30, 2014 Page 2 of 3 (spent fuel is projected to be removed from the OCNGS site by the end of 2036). Any delay in transfer of fuel to DOE or decrease in the rate of acceptance will correspondingly prolong the transfer process and result in spent fuel remaining at the site longer than anticipated.

Operation and maintenance costs for the storage facilities (ISFSI and spent fuel pool) are reflected in the cost estimate and include the costs for staffing the facilities, maintenance of necessary operational requirements as well as security, insurance, and licensing fees. The estimate includes the costs to purchase, load, and transfer the fuel storage canisters to the ISFSI and to decommission the ISFSI for each decommissioning scenario.

A discussion of site-specific considerations for the management of spent fuel at OCNGS under each decommissioning scenario may be found in Section 3.4.1 of the Decommissioning Cost Estimate Report.

When OCNGS terminates operations in 2019, OCNGS will continue to comply with existing NRC licensing requirements, including the operation and maintenance of the systems and structures needed to support continued operation of the OCNGS spent fuel pool and ISFSI, as necessary, under the decommissioning scenario ultimately selected. In addition, OCNGS will also comply with applicable license termination requirements in accordance with 10 CFR 50.82, Termination of license, with respect to plant shutdown and post-shutdown activities, including seeking NRC approvals as appropriate for the continued storage of irradiated fuel until transfer of the fuel to the DOE is complete.

Cost Estimate and Funding For Spent Fuel Management Based on the SAFSTOR Decommissioning Option Annual costs for spent fuel management under the SAFSTOR scenario range from approximately $3.3 million to $26.9 million with a total cost of $188.5 million (2014 dollars).

As of November 30, 2014, the OCNGS decommissioning trust fund balance was $869.9 million.

At this time, there are no annual contributions to the fund and none are anticipated through the decommissioning period. To the extent that the trust fund balance exceeds costs required for radiological decommissioning, trust fund monies (subject to receipt of an exemption), in conjunction with EGC operating revenues, will be used to pay for spent fuel management costs.

An additional potential source of funding for OCNGS spent fuel management costs is the Settlement Agreement between Exelon and the DOE, under which the United States Government has agreed to reimburse Exelon for costs incurred attributable to DOEs failure to meet its contractual obligations for the transfer of spent fuel from OCNGS and other Exelon nuclear plants (Reference A).

NRC Approvals This Spent Fuel Management Plan contemplates potential withdrawals from the decommissioning trust for spent fuel management purposes. Prior to any such withdrawals, in accordance with 10 CFR 50.12, Specific exemptions, Exelon will make appropriate submittals seeking an exemption from the requirements of 10 CFR 50.82(a)(8)(i)(A) in order to use the decommissioning trust funds for spent fuel management expenses. Exelon will monitor the funding level of the decommissioning fund to ensure that spent fuel management withdrawals will not inhibit the ability of Exelon to complete radiological decommissioning.

Spent Fuel Management Plan December 30, 2014 Page 3 of 3 References A. Settlement Agreement between the U.S. Department of Energy and Exelon Generation Company, LLC (including Commonwealth Edison Company and AmerGen Energy Company), signed and executed August 5, 2004, as amended by the Addendum to the Settlement Agreement signed May 4, 2009.

ATTACHMENT 3 ANNUAL SAFSTOR DECOMMISSIONING COST CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION Decommissioning Cost Cash Flow December 30, 2014 Page 1 of 2 ATTACHMENT 3 ANNUAL SAFSTOR DECOMMISSIONING COST CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION (thousands of 2014 dollars)

Radiological ISFSI Decommissioning Spent Fuel Decommissioning Site Restoration Year Cost Management Cost Cost Cost Total Cost(a) 2019(b) 176 59 0 0 236 2020 65,146 21,625 0 0 86,771 2021 62,592 21,073 0 0 83,665 2022 7,277 26,780 0 0 34,057 2023 7,277 26,780 0 0 34,057 2024 7,297 26,853 0 0 34,150 2025 7,204 14,931 0 0 22,135 2026 7,133 3,275 0 0 10,408 2027 7,133 3,275 0 0 10,408 2028 7,152 3,284 0 0 10,436 2029 7,133 3,275 0 0 10,408 2030 7,133 3,275 0 0 10,408 2031 7,133 3,275 0 0 10,408 2032 7,152 3,284 0 0 10,436 2033 7,133 3,275 0 0 10,408 2034 7,133 3,890 0 0 11,023 2035 7,133 8,808 0 0 15,940 2036 7,152 8,808 0 0 15,960 2037 7,100 0 0 0 7,100 2038 7,100 0 0 0 7,100 2039 7,100 0 0 0 7,100 2040 7,120 0 0 0 7,120 2041 7,100 0 0 0 7,100 2042 7,100 0 0 0 7,100 2043 7,100 0 0 0 7,100 2044 7,120 0 0 0 7,120 2045 7,100 0 0 0 7,100 2046 7,100 0 0 0 7,100 2047 7,100 0 0 0 7,100 2048 7,120 0 0 0 7,120 2049 7,100 0 0 0 7,100 2050 7,100 0 0 0 7,100 2051 7,100 0 0 0 7,100 2052 7,120 0 0 0 7,120 2053 7,100 0 0 0 7,100 2054 7,100 0 0 0 7,100 (a)

Cash flows may not add due to rounding (b) 2019 costs are for decommissioning planning Decommissioning Cost Cash Flow December 30, 2014 Page 2 of 2 ATTACHMENT 3 ANNUAL SAFSTOR DECOMMISSIONING COST CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION (thousands of 2014 dollars)

(Continued)

Radiological ISFSI Decommissioning Spent Fuel Decommissioning Site Restoration Year Cost Management Cost Cost Cost Total Cost(a) 2055 7,100 0 0 0 7,100 2056 7,120 0 0 0 7,120 2057 7,100 0 0 0 7,100 2058 7,100 0 0 0 7,100 2059 7,100 0 0 0 7,100 2060 7,120 0 0 0 7,120 2061 7,100 0 0 0 7,100 2062 7,100 0 0 0 7,100 2063 7,100 0 0 0 7,100 2064 7,120 0 0 0 7,120 2065 7,100 0 0 0 7,100 2066 7,100 0 0 0 7,100 2067 7,100 0 0 0 7,100 2068 7,120 0 0 0 7,120 2069 7,100 0 0 0 7,100 2070 7,100 0 0 0 7,100 2071 7,100 0 0 0 7,100 2072 7,120 0 0 0 7,120 2073 7,100 0 0 0 7,100 2074 7,100 0 0 0 7,100 2075 37,974 0 0 395 38,369 2076 103,487 0 0 675 104,162 2077 122,204 396 1,174 418 124,192 2078 106,601 1,663 4,924 1,289 114,477 2079 58,238 406 1,201 421 60,266 2080 148 119 0 38,976 39,243 2081 81 65 0 21,298 21,444 Totals(a) 934,208 188,471 7,299 63,471 1,193,450 (a)

Cash flows may not add due to rounding

ATTACHMENT 4 ANNUAL SAFSTOR DECOMMISSIONING FUND CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION Decommissioning Fund Cash Flow December 30, 2014 Page 1 of 2 ATTACHMENT 4 ANNUAL SAFSTOR DECOMMISSIONING FUND CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION (thousands of dollars)

(a)

Total Cost BOY Trust BOY Trust Fund Trust Fund EOY Trust Year (2014 dollars) Fund Value Less Cost Earnings(c) Fund Value(b) 2019(d) 236 960,460 960,224 1,600 961,825 2020 86,771 961,825 875,054 17,501 892,555 2021 83,665 892,555 808,890 16,178 825,068 2022 34,057 825,068 791,011 15,820 806,831 2023 34,057 806,831 772,775 15,455 788,230 2024 34,150 788,230 754,080 15,082 769,162 2025 22,135 769,162 747,027 14,941 761,967 2026 10,408 761,967 751,559 15,031 766,591 2027 10,408 766,591 756,183 15,124 771,306 2028 10,436 771,306 760,870 15,217 776,087 2029 10,408 776,087 765,679 15,314 780,993 2030 10,408 780,993 770,585 15,412 785,997 2031 10,408 785,997 775,589 15,512 791,101 2032 10,436 791,101 780,664 15,613 796,278 2033 10,408 796,278 785,870 15,717 801,587 2034 11,023 801,587 790,564 15,811 806,376 2035 15,940 806,376 790,435 15,809 806,244 2036 15,960 806,244 790,284 15,806 806,090 2037 7,100 806,090 798,989 15,980 814,969 2038 7,100 814,969 807,869 16,157 824,026 2039 7,100 824,026 816,926 16,339 833,265 2040 7,120 833,265 826,145 16,523 842,668 2041 7,100 842,668 835,568 16,711 852,279 2042 7,100 852,279 845,179 16,904 862,082 2043 7,100 862,082 854,982 17,100 872,082 2044 7,120 872,082 864,962 17,299 882,261 2045 7,100 882,261 875,161 17,503 892,664 2046 7,100 892,664 885,564 17,711 903,275 2047 7,100 903,275 896,175 17,924 914,099 2048 7,120 914,099 906,979 18,140 925,119 2049 7,100 925,119 918,018 18,360 936,379 2050 7,100 936,379 929,278 18,586 947,864 2051 7,100 947,864 940,764 18,815 959,579 2052 7,120 959,579 952,459 19,049 971,509 2053 7,100 971,509 964,408 19,288 983,697 2054 7,100 983,697 976,596 19,532 996,128 (a)

Annual SAFSTOR decommissioning cost (radiological + spent fuel + ISFSI decommissioning + site restoration)

(b)

Cash flows may not add due to rounding (c)

A 2% annual real rate of return is used as allowed by 10 CFR 50.75(e)(1)(i)

(d)

The 2019 BOY Trust Fund Value is the value of the decommissioning trust prior to the 2019 decommissioning planning expenses Decommissioning Fund Cash Flow December 30, 2014 Page 2 of 2 ATTACHMENT 4 ANNUAL SAFSTOR DECOMMISSIONING FUND CASH FLOW FOR OYSTER CREEK NUCLEAR GENERATING STATION (thousands of dollars)

(Continued)

Total Cost(a) BOY Trust BOY Trust Fund Trust Fund EOY Trust (c)

Year (2014 dollars) Fund Value Less Cost Earnings Fund Value(b) 2055 7,100 996,128 989,028 19,781 1,008,809 2056 7,120 1,008,809 1,001,689 20,034 1,021,723 2057 7,100 1,021,723 1,014,622 20,292 1,034,915 2058 7,100 1,034,915 1,027,815 20,556 1,048,371 2059 7,100 1,048,371 1,041,271 20,825 1,062,096 2060 7,120 1,062,096 1,054,976 21,100 1,076,076 2061 7,100 1,076,076 1,068,976 21,380 1,090,355 2062 7,100 1,090,355 1,083,255 21,665 1,104,920 2063 7,100 1,104,920 1,097,820 21,956 1,119,776 2064 7,120 1,119,776 1,112,657 22,253 1,134,910 2065 7,100 1,134,910 1,127,810 22,556 1,150,366 2066 7,100 1,150,366 1,143,265 22,865 1,166,131 2067 7,100 1,166,131 1,159,031 23,181 1,182,211 2068 7,120 1,182,211 1,175,091 23,502 1,198,593 2069 7,100 1,198,593 1,191,493 23,830 1,215,323 2070 7,100 1,215,323 1,208,223 24,164 1,232,387 2071 7,100 1,232,387 1,225,287 24,506 1,249,793 2072 7,120 1,249,793 1,242,673 24,853 1,267,526 2073 7,100 1,267,526 1,260,426 25,209 1,285,635 2074 7,100 1,285,635 1,278,535 25,571 1,304,105 2075 38,369 1,304,105 1,265,736 25,315 1,291,051 2076 104,162 1,291,051 1,186,889 23,738 1,210,626 2077 124,192 1,210,626 1,086,435 21,729 1,108,163 2078 114,477 1,108,163 993,686 19,874 1,013,560 2079 60,266 1,013,560 953,294 19,066 972,360 2080 39,243 972,360 933,117 18,662 951,780 2081 21,444 951,780 930,336 18,607 948,942 (b)

Total 1,193,450 (a)

Annual SAFSTOR decommissioning cost (radiological + spent fuel + ISFSI decommissioning + site restoration)

(b)

Cash flows may not add due to rounding (c)

A 2% annual real rate of return is used as allowed by 10 CFR 50.75(e)(1)(i)