Maine Yankee - Decommissioning Funding Assurance Status Report - 10 CFR 50.75
ML090830191
Person / Time
Site: Maine Yankee
Issue date: 03/16/2009
From: Pizzella C M
Maine Yankee Atomic Power Co
To:
Document Control Desk, NRC/FSME
References
CMP-09-002, MN-09-007, RA-09-008
Download: ML090830191 (4)


Text

'-I MAINE YANKEE 321 OLD FERRY ROAD, WISCASSET, ME 04578 Carla M. Pizzella Treasurer March 16, 2009 CMP-09-002 MN-09-007 RA-09-008 UNITED STATES NUCLEAR REGULATORY COMMISSION Attention:

Document Control Desk Washington, DC 20555 860-267-6426 x 304 Phone 860-267-3911 Fax

Reference:

(a) License No. DPR-36 (Docket No. 50-309)(b) Letter: M. B. Sellman to USNRC; Certifications of Permanent Cessation of Power Operation and Permanent Removal of Fuel From the Reactor; MN-97-89, dated August 7, 1997 (c) License Amendment No. 172 to Facility Operating License No.DPR-36, Maine Yankee Atomic Power Station dated September 30, 2005 (d) USNRC Regulatory Issue Summary (RIS) 2001-07, REV 1

Subject:

Decommissioning Funding Assurance Status Report -10 CFR 50.75 Gentlemen:

In reference (b), Maine Yankee informed the USNRC that the Board of Directors of Maine Yankee had decided to permanently cease operations at the Maine Yankee plant and that fuel had been permanently removed from the reactor. In accordance with 10 CFR 50.82(a)(2) the certifications in the letter modified the Maine Yankee license to permanently withdraw Maine Yankee's authority to operate the reactor. In 1998, Maine Yankee commenced decommissioning the power plant that was subsequently released from the Part 50 license in September 2005. In Reference (c), the NRC amended the Maine Yankee license, releasing most of the formerly licensed land for unrestricted use, shrinking the licensed land to the ISFSI only.In accordance with the requirements of 10 CFR 50.75, direction provided by the NRC staff on March 24, 2006 and recent RIS 2001-07, Rev 1 regulatory clarification, Maine Yankee hereby submits its report on the status of decommissioning funding for the year ending December 31, 2008 for Maine Yankee. Attachment 1 provides the requested information.

If you have any questions please contact me at 860-267-6426 x304.Very truly yours, Carla M. Pizzella Treasurer~A~-A~5~D

(

Enclosure:

Maine Yankee -"NRC Decommissioning Funding Status Report -December 31, 2008" c: Mr. E. Cobey, Chief, Decommissioning Branch, Region 1 Mr. S. J. Collins, NRC Regional Administrator, Region 1 Mr. P. J. Dostie,. State of Maine Mr. J. Goshen, NRC Project Manager, Maine Yankee Plant Mr. J. Hyland, State of Maine Attachment I to MY RA-09-008 and MN-09-007, page 1 of 2 NRC Decommissioning Funding Status Report Maine Yankee (Status as of 12131108)1. The amount of decommissioning funds estimated to be required pursuant tolO CFR 50.75(b) and (c).2. The amount accumulated at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (e)(1)(ii).

3. Schedule of the annual amounts remaining to be collected including amounts beyond those required in 10 CFR 50.75 (e) (1) (i).$123.9 million 1$90.8 million 2 None 4. The assumptions used regarding escalation of the decommissioning cost estimate, rates of earnings on decommissioning funds, and rates of other factors used in funding projections are: Annual escalation rate 2.50% (2009-2023) 5.5% (reduced in last few years)Annual after-tax earnings rate on decommissioning trust funds Other factors assumed None'Since the original power plant has been decommissioned and the license amended, the only remaining decommissioning as defined by the NRC in 10 CFR 50.75 is decontamination and dismantlement of the ISFSI once the fuel is removed. The Site-Specific Cost Estimate for future costs beyond 2008 is $123.9 million (in 2008 dollars) and includes the current estimate for spent fuel management costs i.e. Long-term ISFSI operations through 2023 ($110.6 million) and D&D of the ISFSI ($13.3 million).2 This accrued market value balance includes amounts in the Decommissioning Trust for all decommissioning costs including site restoration and long-term spent fuel storage as well as decommissioning as defined in 10 CFR 50.75. Since the original power plant has been decommissioned and the license amended, the only remaining decommissioning is decontamination and dismantlement of the ISFSI (estimated at $9.7 million of the current market value balance) once the fuel is removed.

Attachment I to MY RA-09-008 and MN-09-007, page 2 of 2 NRC Decommissioning Funding Status Report Maine Yankee (Status as of 12131/08)5. Any contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(ii)(A)

Maine Yankee has collected funds through its power contracts and-amendatory agreements under FERC regulation.

The power contracts, additional power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of Maine Yankee, including future decommissioning costs. Such contracts have been filed with FERC.6. Any modifications to a licensee's current method of providing financial assurance occurring since the last submitted report. None 7. Any material changes to trust agreements.

None