RA-09-028, Physical Security Plan for Maine Yankee Independent Fuel Storage Installation

From kanterella
Jump to navigation Jump to search
Physical Security Plan for Maine Yankee Independent Fuel Storage Installation
ML092580473
Person / Time
Site: Maine Yankee
Issue date: 09/03/2009
From: Connell J
Maine Yankee Atomic Power Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
MN-09-012, RA-09-028
Download: ML092580473 (2)


Text

Maine Yanr~kee 321 OLD FERRY RD

  • WISCASSET, ME 04578-4922 SAFEGUARDS INFORMATION September 3, 2009 MN-09-012 RA-09-028 UNITED STATES NUCLEAR REGULARTORY COMMISSION Attention: Document Control Desk Washington, DC 20555

Reference:

(a) License No: DPR-36 (Docket Nos. 50-309,72-030)

(b) Maine Yankee Letter to USNRC, MN-09-003 - Submittal of Revised Maine Yankee ISFSI Security Plan under IOCFR50.90 dated February 3, 2009 (c) Maine Yankee Letter to USNRC, MN-09-006 - Maine Yankee MOUs with Local Law Enforcement Agencies dated February 27, 2009 (d) USNRC Letter to Maine Yankee - Maine Yankee Independent Fuel Storage Installation Security Plan Changes (TAC L24322) dated April 30, 2009

Subject:

Physical Security Plan for Maine Yankee Independent Fuel Storage Installation Gentlemen:

This letter informs the USNRC that in accordance with Reference (d), which was received in response to References (b) and (c), a complete reformatting and issuance of the Physical Security Plan for the Maine Yankee Independent Fuel Storage Installation has been implemented. The changes were approved and became effective on August 3, 2009. Since the entire Plan was reformatted and re-titled, it was issued as Revision 0.

Based on the overall evaluation of the changes made to the Physical Security Plan for the Maine Yankee Independent Spent Fuel Storage Installation, it has been determined that no physical security changes were made, and therefore the changes do not decrease the effectiveness of the Plan. Therefore the changes are being submitted under the provisions of 10 CFR 50.54(p)(2). Also, as required by 10 CFR 50.54(p)(2), a description of the changes is included as Attachment 1 to this letter.

DOCUMENT TRANSMITTED HEREWITH CONTAINS SAFEGUARDS INFORMATION. WHEN SEPERATED FROM ATTACHMENTS, THIS PAGE IS "DECONTROLLED" SAFEGUARDS INFORMATION

SAFEGUARDS INFORMATION If you have any questions, please contact me at (207)-882-1303 or at iconnell(Th3yankees.com.

Very truly y James Connell Vice President Attachments: 1 - Summary of Changes (Safeguards Information) 2 - Physical Security Plan for Maine Yankee Independent Fuel Storage Facility (Safeguards Information) cc w/o Attachments:

Mr. John Goshen, P.E., Project Manager, USNRC Mr. Samuel Collins, Administrator, USNRC Region I Mr. Mark Roberts, USNRC Region I Mr. Jay Hyland, P. E., State of Maine Mr. Pat Dostie, State of Maine Mr. Wayne Norton, VP, CNO, Maine Yankee Mr. Joe Fay, Esq, Maine Yankee DOCUMENT TRANSMITTED HEREWITH CONTAINS SAFEGUARDS INFORMATION. WHEN SEPERATED FROM ATTACHMENTS, THIS PAGE IS "DECONTROLLED" SAFEGUARDS INFORMATION