MONTHYEARNRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-23-0017, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2023-04-28028 April 2023 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-23-0025, Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2023-04-28028 April 2023 Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-23-0018, Annual Non-Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Non-Radiological Environmental Operating Report NRC-23-0024, Levels and Sources of Property Insurance Coverage2023-04-0303 April 2023 Levels and Sources of Property Insurance Coverage NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0011, License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis2023-03-0707 March 2023 License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0051, DTE Electric Company - Guarantee of Payment of Deferred Premiums2022-11-29029 November 2022 DTE Electric Company - Guarantee of Payment of Deferred Premiums NRC-22-0052, Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 20222022-11-17017 November 2022 Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 2022 NRC-22-0046, Submittal of Biennial Review of the Fermi 1 Safety Analysis Report2022-11-14014 November 2022 Submittal of Biennial Review of the Fermi 1 Safety Analysis Report NRC-22-0041, Evacuation Time Estimate Report2022-10-0505 October 2022 Evacuation Time Estimate Report NRC-22-0033, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20222022-08-29029 August 2022 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2022 NRC-22-0030, Inservice Inspection Summary Report2022-08-10010 August 2022 Inservice Inspection Summary Report NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-22-0022, Annual Non-Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Non-Radiological Environmental Operating Report NRC-22-0021, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-22-0020, Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring2022-04-28028 April 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring NRC-22-0003, Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2022-04-26026 April 2022 Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-22-0019, Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance2022-04-0404 April 2022 Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report 2024-01-12
[Table view] |
Text
Vito A. Kaminskas Site Vice President DTE Energy Company 6400 N. Dixie Highway, Newport, MI 48166 Tel: 734.586.6515 Fax: 734.586.4172 Email: kaminskasv@dteenergy.com
. DTE Energy-10 CFR 20.1703(b)
April 10, 2015 NRC- 15-0046 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) DTE Electric Company, NRC-I15-0019, "Request for Use of MURUROA Supplied, Air Suits Models MTH2 &V4F 1 and the MURUROA BLU Suit Systems," February 12, 2015 (ML15043A782)
- 3) U.S. Nuclear Regulatory Commission, "Fermi 2- Supplemental Information Needed for Acceptance of Request for Use of MURUROA Supplied Air Suits Models MTH2 & V4F 1 and the MURUROA BLU Suit Systems (TAC NO. MF5742)," March 30, 2015 (ML15084A069)
Subject:
Response to NRC Request for Supplemental Information Needed for Acceptance of Request for Use of MURUROA Supplied Air Suits In Reference 2, DTE Electric Company (DTE) submitted a request for authorization for use of the M`URUROA supplied air suits, Models MTH2 and V4F 1, and the MURUROA BLU Suit Systems, which have not been tested or certified by the National Institute for Occupational Safety and Health (NIOSH). In Reference 3, the U.S.
Nuclear Regulatory Commission (NRC) requested that DTE provide supplemental information needed to complete their acceptance review of the request. The enclosure to this letter provides the requested supplemental information.
Ao00 KJ (.7
USNRC NRC- 15-0046 Page 2 This letter contains no new commitments. Should you have any questions or require additional information, please contact Mr. Christopher Robinson, Licensing Manager at (734) 586-5076.
Sincerely,
Enclosure:
Response to Request for Supplemental Information cc: Director, Office of Nuclear Reactor Regulation NRC Project Manager NRC Resident Office Reactor Projects Chief, Branch 5, Region III Regional Administrator, Region III Michigan Public Service Commission, Regulated Energy Division (kindschl@michigan.gov)
Enclosure to NRC-15-0046 Response to Request for Supplemental Information
Enclosure to NRC- 15-0046 Page 1 Response to Request for Supplemental Information
Background
On February 12, 2015, DTE Electric Company (DTE) submitted a request for authorization for use of the MURUROA supplied air suits, Models MTH2 and V4F 1, and the MURUROA BLU Suit Systems, which have not been tested or certified by the National Institute for Occupational Safety and Health (NIOSH). On March 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) requested that DTE provide additional information regarding the minimum supplied inlet air pressure to the MTH2 and V4F1 suits or revise the scope of the application regarding inlet air pressure to the suits. NRC requested that DTE "provide reliable test information that demonstrates that the MTH2 and V4F 1 will provide adequate air pressure to the suits sufficient to meet the minimum air flow and [carbon dioxide] C02 build up limits of the [European Union]
EU certification standard" or "revise the scope of the application to be within the test data provided."
Response
In accordance with NRC's request, DTE is revising the scope of the application to be within the test data provided regarding inlet air pressure to the MTH2 and V4FI suits. This change complies with the manufacturer's instructions. This change will revise the first paragraph on Page 4 of Reference 2, Enclosure 1, Section 1.2.2 to state:
Air hoses of any length can be used, but air shall be supplied to the suits at 85 PSI (6 bar). A regulator at the inlet is used to adjust the airflow. To ensure user safety, the regulator cannot shut off the air supply. There are two patented exhaust valves on the back of the suit, one behind the neck and one at the lower back. The exhaust valves prevent any aspiration of contaminants if supplied air is lost.
The last paragraph in Reference 2, Enclosure 1, Section 1.2.4 on page 5 will be revised to state:
DTE will follow the manufacturer's instructions for use ensuring that the minimum operating air pressure and airflow is being supplied to the suit prior to working in them, specifically ensuring that the minimum pressure will be monitored during regular use. Air hoses of any length can be used, but air shall be supplied to the MURUROA MTH2 and V4F1 at 85 PSI (6 bar). A regulator at the inlet can adjust the air flow. To ensure user safety, the regulator cannot shut off the air supply. The maximum noise level is kept between 76 decibels (dB) at maximum air flow and 58 dB at minimum air flow.