NLS2003028, BWRVIP-25 Rim Hold Down Bolt Inspection Deferral

From kanterella
Jump to navigation Jump to search
BWRVIP-25 Rim Hold Down Bolt Inspection Deferral
ML030850116
Person / Time
Site: Cooper Entergy icon.png
Issue date: 03/19/2003
From: Coyle M
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NLS2003028
Download: ML030850116 (3)


Text

".."-

N Nebraska Public Power District Nebraska's Energy Leader NLS2003028 March 19, 2003 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

BWRVIP-25 Rim Hold-Down Bolt Inspection Deferral Cooper Nuclear Station, NRC Docket No. 50-298, DPR-46

References:

1. "BWR Vessel and Internals Project BWR Core Plate Inspection and Flaw Evaluation Guidelines (BWRVIP-25)," EPRI TR-107284, December 1996.
2. Letter to U.S. Nuclear Regulatory Commission from David Wilson (Nebraska Public Power District) dated March 28, 2002, "Boiling Water Reactor Vessel and Internals Project (BWRVIP) Program Issues" (NLS2002039).

The purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) that the Nebraska Public Power District (NPPD) will be unable to perform a BWRVIP inspection during the current refueling outage (RFO). Reference 1 recommends an EVT-1 examination of the rim hold-down bolts from below the core plate. This examination has not been performed to date due to access restrictions encountered during a normal refueling outage. In Reference 2, NPPD committed to develop and implement an alternative examination during RFO2 1. However, the commitment also contained the provision that if the subject alternative examination could not be developed, then both the NRC and the BWRVIP would be notified. An adequate alternative examination is not possible at this time. The BWRVIP has been notified of the inability of NPPD to perform the recommended EVT-1 examination. An Engineering Evaluation has been performed that justifies deferral of this examination until RF023. This is a generic industry issue that the BWRVIP is addressing. Following this resolution, NPPD will implement the final BWRVIP recommendations regarding this inspection. This letter satisfies the Reference 2 commitment to also notify the NRC.

Should you have any questions concerning this matter, please contact Mr. Paul Fleming at (402) 825-2774.

Sincerely, chael T. Coyle I Site Vice President

/wrv Cooper Nuclear Station J4D P.O. Box 98/Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 http //www nppd corn

NLS2003028 Page 2 of 2 cc: Regional Administrator USNRC - Region IV Senior Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident Inspector USNRC NPG Distribution Records

B 4 ATTACHMENT 3 LIST OF NRC COMMITMENTS Correspondence No: NLS2003028 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the NL&S Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.

COMMITMENT COMMITTED DATE OR OUTAGE Following this resolution [by the BWRVIP], NPPD will implement the final BWRVIP N/A recommendations regarding this [BWRVIP-25 Rim Hold-Down Bolt] inspection.