MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-080, .48(d)(2) Summary Report2019-09-26026 September 2019 .48(d)(2) Summary Report 2021-05-06
[Table view] Category:Report
MONTHYEARML22013A7062022-01-13013 January 2022 Investigation Report of LLRW Shipment Pursuant to 10 CFR 20, Appendix G ML21056A0782021-04-0707 April 2021 Final Environmental Assessment and Finding of No Significant Impact for Initial and Updated Decommissioning Funding Plans for Indian Point ISFSI (Docket: 72-51) NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement ML20309A5052020-11-0303 November 2020 Inspector Notes Cover Sheet ML20259A2172020-09-14014 September 2020 Commitment Change Summary Report ML20260H0722020-06-18018 June 2020 IP-RPT-14-00013, Revision 3, Indian Point Nuclear Generating Units 2 and 3, Consequences of a Postulated Fire and Explosion Following the Release of Natural Gas from the New Aim 42 Pipeline Near Ipec ML20122A1052020-05-27027 May 2020 Letter from Margaret M. Doane to John B. Rhodes, Chair and Executive Officer, Ny State Public Service Commission: Response to Ny State Public Service Commission Regarding Natural Gas Transmission Pipelines Near Indian Point Nuclear Power Pl ML20100F6352020-04-0808 April 2020 Expert Team Final Report NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML19252A3182019-09-0909 September 2019 Entergy to NRC, IPEC Weekly Sturgeon Monitoring Report for Week of Sept 2, 2019 NL-19-061, Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements2019-06-13013 June 2019 Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements ML19114A0742019-04-22022 April 2019 Entergy to NRC, IPEC Weekly Sturgeon Monitoring Report for Week of April 15, 2019 NL-19-012, Request for Approval of a Certified Fuel Handler Training and Retraining Program2019-04-15015 April 2019 Request for Approval of a Certified Fuel Handler Training and Retraining Program NL-18-0506, Failure to Observe the Certificate of Compliance Condition of the 8-120B Cask Pre-Shipment Leak Test2018-04-16016 April 2018 Failure to Observe the Certificate of Compliance Condition of the 8-120B Cask Pre-Shipment Leak Test NL-18-021, Indian Point, Unit 2, Fracture Mechanics Assessment of Embedded Flaw Repair Acceptability2018-04-0606 April 2018 Indian Point, Unit 2, Fracture Mechanics Assessment of Embedded Flaw Repair Acceptability ML18098A0882018-04-0606 April 2018 Fracture Mechanics Assessment of Embedded Flaw Repair Acceptability NL-20-066, Engineering Report IP-RPT-11-00032, Revision 5, Licensing Report on the Inter-Unit Transfer of Spent Nuclear Fuel at the Indian Point Energy Center2017-12-19019 December 2017 Engineering Report IP-RPT-11-00032, Revision 5, Licensing Report on the Inter-Unit Transfer of Spent Nuclear Fuel at the Indian Point Energy Center ML17349A1562017-12-0808 December 2017 Risk Impact of One-Time Extending the ILRT Interval Associated with the Proposed Technical Specification Changes ML17279A2472017-10-0606 October 2017 2017 Annual Assessment Meeting Written Comments Compilation ML17222A2392017-10-0404 October 2017 NRC Response to Request for Deferral of Actions Related to Beyond-Design-Basis Seismic and Flooding Hazard Reevaluations ML17289A6552017-10-0202 October 2017 Attachment 6 to NL-17-115, Revised HI-2094289, Licensing Report on the Inter-Unit Transfer of Spent Fuel at the Energy Center, Revision 9 NL-17-122, Transmittal of 10 CFR 50.59(d)(2) Summary Report, March 26, 2015 to May 18,20172017-09-28028 September 2017 Transmittal of 10 CFR 50.59(d)(2) Summary Report, March 26, 2015 to May 18,2017 ML17096A2122017-03-23023 March 2017 Entergy Engineering Report No. IP-RPT-16-00078, Indian Point RAI CLI-16-07 SAMA Cost-Benefit Sensitivities Rev. 1 (March 23, 2017) NL-17-020, License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan2017-02-0606 February 2017 License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan ML17096A2112017-01-0404 January 2017 Entergy Engineering Report No. IP-RPT-16-00077, Indian Point RAI CLI-16-07 MACCS2 Sensitivities, Rev. 0 (Jan 4, 2017) NL-16-109, HI-2094289, Licensing Report on the Inter-Unit Transfer of Spent Fuel at the Indian Point Energy Center.2016-09-19019 September 2016 HI-2094289, Licensing Report on the Inter-Unit Transfer of Spent Fuel at the Indian Point Energy Center. ML16280A2282016-09-19019 September 2016 Indian Point 2 Technical Requirements Manual NL-16-109, Indian Point 2 Technical Requirements Manual2016-09-19019 September 2016 Indian Point 2 Technical Requirements Manual ML16250A2762016-09-13013 September 2016 Evaluation of Impacts to Proposed Critical Habitat for the Atlantic Sturgeon for Indian Point Nuclear Generating Units 2 and 3 Proposed License Renewal NL-16-083, Post Accident Monitoring (PAM) Report for an Inoperable Containment Area Radiation Monitor (R-26) High Range, Indian Point Unit Number 32016-08-0101 August 2016 Post Accident Monitoring (PAM) Report for an Inoperable Containment Area Radiation Monitor (R-26) High Range, Indian Point Unit Number 3 ML18115A0592016-06-28028 June 2016 After Action Report/Improvement Plan, Drill Date June 28, 2016 ML16028A2952016-01-29029 January 2016 10 CFR 71.95 Notification Associated with the Failure to Observe Certificate of Compliance Condition of the 8-120B Secondary Lid Test Port Configuration PLA-7414, Redacted - Susquehanna, Units 1 and 2 - Submittal of 10 CFR 71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 91682015-11-19019 November 2015 Redacted - Susquehanna, Units 1 and 2 - Submittal of 10 CFR 71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 9168 ML15321A4542015-11-13013 November 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask JAFP-15-0129, Submittal of 10 CFR 71.95 Report Involving 8-120B Cask2015-11-0606 November 2015 Submittal of 10 CFR 71.95 Report Involving 8-120B Cask NL-15-2010, E.I. Hatch - Submits 10 CFR 71.95 Report on Non-Conformance Involving Radwaste Cask 8-120B2015-11-0202 November 2015 E.I. Hatch - Submits 10 CFR 71.95 Report on Non-Conformance Involving Radwaste Cask 8-120B NLS2015128, Submittal of 10 CFR 71.95 Report Involving Energysolutions Certificate of Compliance No. 91682015-10-29029 October 2015 Submittal of 10 CFR 71.95 Report Involving Energysolutions Certificate of Compliance No. 9168 ZS-2015-0156, Zionsolutions, LLC - Submittal of 10 CFR 71.95 Report on the 8-120B Cask2015-10-26026 October 2015 Zionsolutions, LLC - Submittal of 10 CFR 71.95 Report on the 8-120B Cask ML15313A1642015-10-0808 October 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask ML17052A2662015-10-0202 October 2015 Sturgeon Mobile Tracking for the New Ny Bridge at Tappan Zee NL-15-128, Submittal of 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments Implemented Between 04/01/2013 and 03/25/2015, And/Or Utilized in Support of the UFSAR Update2015-09-28028 September 2015 Submittal of 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments Implemented Between 04/01/2013 and 03/25/2015, And/Or Utilized in Support of the UFSAR Update NL-15-118, Post Accident Monitoring (PAM) Report for an Inoperable Reactor Vessel Level Indication System (RVLIS) Train B, Indian Point Unit 32015-09-0303 September 2015 Post Accident Monitoring (PAM) Report for an Inoperable Reactor Vessel Level Indication System (RVLIS) Train B, Indian Point Unit 3 ML15259A3422015-08-24024 August 2015 10 CFR 71.95 Report Evaluation Form; Submitted by Fenok, Erwin Resin Solutions, North Anna Power Stations, Et Al DCL-15-102, 10 CFR 71.95 Report Regarding Energy Solutions' Model 8-120B Shipping Cask2015-08-24024 August 2015 10 CFR 71.95 Report Regarding Energy Solutions' Model 8-120B Shipping Cask NL-15-1461, Submittal of 10 CFR 71.95 Report on Potential Issues Involving Radwaste Cask 8-120B2015-08-21021 August 2015 Submittal of 10 CFR 71.95 Report on Potential Issues Involving Radwaste Cask 8-120B PLA-7374, Submittal of 10 CFR71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 91682015-08-20020 August 2015 Submittal of 10 CFR71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 9168 NRC-15-0085, Submittal of 10 CFR 71.95 Report on the 8-120B Shipping Cask2015-08-19019 August 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Shipping Cask ZS-2015-0131, Zionsolutions, LLC - Submittal of10 CFR 71.95 Report on the 8-120B Cask2015-08-18018 August 2015 Zionsolutions, LLC - Submittal of10 CFR 71.95 Report on the 8-120B Cask ML15246A1452015-08-11011 August 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask NL-15-099, Submittal of 2014 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2015-07-30030 July 2015 Submittal of 2014 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report 2022-01-13
[Table view] Category:Miscellaneous
MONTHYEARML22013A7062022-01-13013 January 2022 Investigation Report of LLRW Shipment Pursuant to 10 CFR 20, Appendix G ML20260H0722020-06-18018 June 2020 IP-RPT-14-00013, Revision 3, Indian Point Nuclear Generating Units 2 and 3, Consequences of a Postulated Fire and Explosion Following the Release of Natural Gas from the New Aim 42 Pipeline Near Ipec ML20122A1052020-05-27027 May 2020 Letter from Margaret M. Doane to John B. Rhodes, Chair and Executive Officer, Ny State Public Service Commission: Response to Ny State Public Service Commission Regarding Natural Gas Transmission Pipelines Near Indian Point Nuclear Power Pl NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML19252A3182019-09-0909 September 2019 Entergy to NRC, IPEC Weekly Sturgeon Monitoring Report for Week of Sept 2, 2019 NL-19-061, Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements2019-06-13013 June 2019 Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements ML19114A0742019-04-22022 April 2019 Entergy to NRC, IPEC Weekly Sturgeon Monitoring Report for Week of April 15, 2019 NL-19-012, Request for Approval of a Certified Fuel Handler Training and Retraining Program2019-04-15015 April 2019 Request for Approval of a Certified Fuel Handler Training and Retraining Program NL-18-0506, Failure to Observe the Certificate of Compliance Condition of the 8-120B Cask Pre-Shipment Leak Test2018-04-16016 April 2018 Failure to Observe the Certificate of Compliance Condition of the 8-120B Cask Pre-Shipment Leak Test ML17279A2472017-10-0606 October 2017 2017 Annual Assessment Meeting Written Comments Compilation ML17222A2392017-10-0404 October 2017 NRC Response to Request for Deferral of Actions Related to Beyond-Design-Basis Seismic and Flooding Hazard Reevaluations NL-17-020, License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan2017-02-0606 February 2017 License Renewal Application - Revisions to Reactor Vessel Internals Aging Management Program and Inspection Plan NL-16-083, Post Accident Monitoring (PAM) Report for an Inoperable Containment Area Radiation Monitor (R-26) High Range, Indian Point Unit Number 32016-08-0101 August 2016 Post Accident Monitoring (PAM) Report for an Inoperable Containment Area Radiation Monitor (R-26) High Range, Indian Point Unit Number 3 ML16028A2952016-01-29029 January 2016 10 CFR 71.95 Notification Associated with the Failure to Observe Certificate of Compliance Condition of the 8-120B Secondary Lid Test Port Configuration PLA-7414, Redacted - Susquehanna, Units 1 and 2 - Submittal of 10 CFR 71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 91682015-11-19019 November 2015 Redacted - Susquehanna, Units 1 and 2 - Submittal of 10 CFR 71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 9168 ML15321A4542015-11-13013 November 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask JAFP-15-0129, Submittal of 10 CFR 71.95 Report Involving 8-120B Cask2015-11-0606 November 2015 Submittal of 10 CFR 71.95 Report Involving 8-120B Cask NLS2015128, Submittal of 10 CFR 71.95 Report Involving Energysolutions Certificate of Compliance No. 91682015-10-29029 October 2015 Submittal of 10 CFR 71.95 Report Involving Energysolutions Certificate of Compliance No. 9168 ZS-2015-0156, Zionsolutions, LLC - Submittal of 10 CFR 71.95 Report on the 8-120B Cask2015-10-26026 October 2015 Zionsolutions, LLC - Submittal of 10 CFR 71.95 Report on the 8-120B Cask ML15313A1642015-10-0808 October 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask NL-15-128, Submittal of 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments Implemented Between 04/01/2013 and 03/25/2015, And/Or Utilized in Support of the UFSAR Update2015-09-28028 September 2015 Submittal of 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments Implemented Between 04/01/2013 and 03/25/2015, And/Or Utilized in Support of the UFSAR Update NL-15-118, Post Accident Monitoring (PAM) Report for an Inoperable Reactor Vessel Level Indication System (RVLIS) Train B, Indian Point Unit 32015-09-0303 September 2015 Post Accident Monitoring (PAM) Report for an Inoperable Reactor Vessel Level Indication System (RVLIS) Train B, Indian Point Unit 3 ML15259A3422015-08-24024 August 2015 10 CFR 71.95 Report Evaluation Form; Submitted by Fenok, Erwin Resin Solutions, North Anna Power Stations, Et Al DCL-15-102, 10 CFR 71.95 Report Regarding Energy Solutions' Model 8-120B Shipping Cask2015-08-24024 August 2015 10 CFR 71.95 Report Regarding Energy Solutions' Model 8-120B Shipping Cask NL-15-1461, Submittal of 10 CFR 71.95 Report on Potential Issues Involving Radwaste Cask 8-120B2015-08-21021 August 2015 Submittal of 10 CFR 71.95 Report on Potential Issues Involving Radwaste Cask 8-120B PLA-7374, Submittal of 10 CFR71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 91682015-08-20020 August 2015 Submittal of 10 CFR71.95 Report Regarding Energy Solutions 8-120B Cask Certificate of Compliance 9168 NRC-15-0085, Submittal of 10 CFR 71.95 Report on the 8-120B Shipping Cask2015-08-19019 August 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Shipping Cask ZS-2015-0131, Zionsolutions, LLC - Submittal of10 CFR 71.95 Report on the 8-120B Cask2015-08-18018 August 2015 Zionsolutions, LLC - Submittal of10 CFR 71.95 Report on the 8-120B Cask ML15246A1452015-08-11011 August 2015 Submittal of 10 CFR 71.95 Report on the 8-120B Cask NL-15-099, Submittal of 2014 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2015-07-30030 July 2015 Submittal of 2014 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-15-072, 2015 Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements2015-06-18018 June 2015 2015 Form OAR-1 Owners Activity Report for Inservice Inspection and Repairs and Replacements NL-15-030, Revised 10 C.F.R. 50.59 Safety Evaluation and Supporting Analyses Prepared in Response to the Algonquin Incremental Market Natural Gas Project2015-04-0808 April 2015 Revised 10 C.F.R. 50.59 Safety Evaluation and Supporting Analyses Prepared in Response to the Algonquin Incremental Market Natural Gas Project NL-15-013, Re-Submittal of Netco Report NET-300067-01, Criticality Safety Analysis of the Indian Point Unit 2 Spent Fuel Pool with Credit for Inserted Neutron Absorber Panels, for NRC Review and Approval2015-01-28028 January 2015 Re-Submittal of Netco Report NET-300067-01, Criticality Safety Analysis of the Indian Point Unit 2 Spent Fuel Pool with Credit for Inserted Neutron Absorber Panels, for NRC Review and Approval NL-14-152, Entergy'S Expedited Seismic Evaluation Process Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights From...2014-12-22022 December 2014 Entergy'S Expedited Seismic Evaluation Process Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights From... ML14329A1952014-11-0404 November 2014 NET-300067-01, Rev. 0, Criticality Safety Analysis of the Indian Point Unit 2 Spent Fuel Pool with Credit for Inserted Neutron Absorber Panels NL-14-115, 10 CFR 50.59(d)(2) Summary Report for Indian Point, Units 1 and 2 April 1, 2012 to March 19, 20142014-09-18018 September 2014 10 CFR 50.59(d)(2) Summary Report for Indian Point, Units 1 and 2 April 1, 2012 to March 19, 2014 ML15166A0702014-08-31031 August 2014 Algonquin Incremental Market (Aim) Project, Phase 2 Acoustic Survey for Indiana Bats (Myotis Sodalis) and Northern Long-Eared Bats (Myotis Septentrionalis), August 2014 NL-14-110, Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ZS-2014-0271, Zionsolutions' 10 CFR 71.95 Report of Non-Compliance with Certificate of Compliance No. 9168, Revision No. 20 - Cask 8-120B2014-08-18018 August 2014 Zionsolutions' 10 CFR 71.95 Report of Non-Compliance with Certificate of Compliance No. 9168, Revision No. 20 - Cask 8-120B ML14141A5402014-05-0909 May 2014 Supplemental Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML14071A1832014-04-0101 April 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident NL-14-043, Entergy Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima.2014-03-31031 March 2014 Entergy Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima. NL-14-042, Entergy Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi.2014-03-31031 March 2014 Entergy Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi. ML14071A1982014-03-20020 March 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident ML14015A4172014-01-30030 January 2014 Staff Summary of the Steam Generator Tube Inservice Inspections for the Spring 2013 Refueling Outage ML14304A7512013-12-13013 December 2013 Unit 3 Coastal Zone Management Act Consistency Certification, Vol. II of III, Supplemental Information Regarding NYSDEC Record, Part 8 of 9 NL-13-133, 10 CFR 71.95 Report on Failure to Observe Certificate of Compliance Conditions for Radwaste Model 8-120B Cask Vent Port Leak Test Hold Time2013-10-0202 October 2013 10 CFR 71.95 Report on Failure to Observe Certificate of Compliance Conditions for Radwaste Model 8-120B Cask Vent Port Leak Test Hold Time DCL-13-094, and Humboldt Bay Power Plant, 10 CFR 71.95 Reports Regarding Energysolutions' Model 8-120B Shipping Cask2013-09-30030 September 2013 and Humboldt Bay Power Plant, 10 CFR 71.95 Reports Regarding Energysolutions' Model 8-120B Shipping Cask L-2013-258, 10 CFR 71.95 - Cask 8-120B - 60 Day Report2013-09-16016 September 2013 10 CFR 71.95 - Cask 8-120B - 60 Day Report NRC-13-0052, CFR 71.95 Report - Failure to Observe Certificate of Compliance Conditions for the 8-120B Vent Port Leak Test Hold Time2013-09-0909 September 2013 CFR 71.95 Report - Failure to Observe Certificate of Compliance Conditions for the 8-120B Vent Port Leak Test Hold Time 2022-01-13
[Table view] |
Text
a ~'En tergy Enteray Nuclear Northeast Indian Point Energy Center 450 Broaday, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249 Tel (914) 254-6700 John A. Ventosa Site Vice President Administration NL-13-133 October 2, 2013 ATTN: Docket Control Desk Mr. Mark Lombard Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Subject:
10 CFR 71.95 Report on Failure to Observe Certificate of Compliance Conditions for Radwaste Model 8-120B Cask Vent Port Leak Test Hold Time Indian Point Units Nos. 2 and 3 Docket No. 50-3, 50-247 and 50-286 DPR-5, DPR-26 and DPR-64
Dear Sir:
Entergy Nuclear Operations Inc. (ENO) hereby submits this report pursuant to 10 CFR 71.95(a)(3) regarding potential instances in which the conditions of approval in Certificate of Compliance (CoC) #9168 for the EnergySoultions Model 8-120B cask may not have been observed in making shipments from the Indian Point Energy Center (IPEC). The potential condition involves a discrepancy in the cask vent port seal air pressure drop test hold time between EnergySolutions test procedure TR-TP-002 and the Safety Analysis Report (SAR) for the Model 8-120B cask (20 minute hold time per the test procedure, versus 60 minutes required by the SAR supporting the CoC). This condition was recorded in the Entergy Corrective Action Program as Condition Report CR-IP2-2013-03672.
The enclosed notification from the certificate holder EnergySolutions provides the information related to the condition, as required by 10 CFR 71.95(a)(3), and is applicable to the use of the 8-120B cask at IPEC. The enclosed report dated August 14, 2013, was developed by the certificate holder EnergySolutions and filed with the NRC. Entergy records show that IPEC Units 1, 2 and 3 made a total of 14 class B shipments using the 8-120B cask since 2001 which are listed in Attachment 1. During those shipments the vendor leak test procedure was required to be performed and would have resulted in a vent port seal test of 20 minutes rather than the 60 minutes required by the cask's SAR. EnergySolutions has revised the procedure to include a 60 minute test of the vent port seal.
Docket Nos. 50-3, 50-247 & 50-286 NL-13-133 Page 2 of 2 Entergy is making no commitments in this letter. Should you have any questions regarding this matter, please contact Mr. Robert Walpole, Manager, Licensing, Indian Point Energy Center at (914) 254-6710.
Sincerely yours, JAV/cbr
Enclosure:
EnergySolutions 10 CFR 71.95 Report on the 8-120B Cask dated August 14, 2013 : List of IPEC Units 1, 2 and 3 Class B Shipments Using the 8-120B Cask cc: Document Control Desk U.S. Nuclear Regulatory Commission Mr. William M. Dean, Regional Administrator, NRC Region 1 Mr. Douglas Pickett, Senior Project Manager, NRC NRR DORL Mr. Stephen Giebel, Senior Project Manager, NRC FSME DWMEP DURLD Ms. Bridget Frymire, NYS Department of Public Service Resident Inspector's Office Indian Point Energy Center U.S. Nuclear Regulatory Commission
Docket Nos. 50-3, 50-247 & 50-286 NL-13-133 Enclosure EnergySolutions 10 CFR 71.95 Report on the 8-120B Cask dated August 14, 2013
ENERGYSOLUTIONS August 14, 2013 CD13-0232 Mark Lombard, Director Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington DC.20555-0001 ATTN: Document Control Desk
Subject:
10 CFR 71.95 Report on the 8-120B Cask
Dear Mr. Lombard:
EnergySolutions hereby submits the attached report providing the information required by 10 CFRT71.95(a)(3) for instances in which the conditions of approval in the Certificate of Compliance for the 8-120B Cask (Certificate of Compliance #9168) may not have been observed in making certain shipments. The circumstances described in this report are applicable to all licensed users of the cask.
If you have any questions regarding this submittal, please contact me at 801-649-2109.
Sincer Daniel B. Shr.um Senior Vice President, Regulatory Affairs EnergySolutions
Attachment:
Failure to Observe Certificate of Compliance Conditions for the 8-120B Vent Port Leak Test Hold Time cc: Michele Sampson, Chief Thermal and Containment Branch Pierre M. Saverot Licensing Branch 423 West 300 South, Suite 200 - Salt Lake City, UT 84101 www.energysolutions.com
EN ERGYSOLUTIONY Failure to Observe Certificate of Compliance Conditions for the 8-120B Vent Port Leak Test Hold Time August 14, 2013
- 1) Abstract This report provides the information required by 10 CFR 71.95(a)(3) for instances in which the conditions of approval in the Certificate of Compliance for the 8-120B Cask (Certificate of Compliance #9168) may not have been observed in making certain shipments. The circumstances described in this report are applicable to all licensed users of the cask.
EnergySolutions' air pressure drop test procedure TR-TP-002 describes a 20-minute hold time for the pre-shipment leak test of the cask vent port. The 8-120B Safety Analysis Report (SAR), however, specifies a hold time of 60 minutes for the leak test of the vent port; therefore the conditions of approval in the Certificate of Compliance may not necessarily have been observed in making shipments. TR-TP-002 is the basis for leak tests on all EnergySolutions shipments, as well as the suggested procedure content for most shipments by our authorized users.'
The 8-120B CoC requires the package to be prepared for shipment and operated in accordance with Chapter 7 of the SAR, and tested and maintained in accordance with Chapter 8 of the SAR. TR-TP-002 captures the applicable SAR requirements and provides further detail for the development of a shipper's operating procedure. Recently, an 8-120B cask user identified the hold time discrepancy between TR-TP-002 and the SAR (i.e., 20 versus 60 minutes). Based on a review of past revisions of CoCs, SARs, and cask handling procedures, it appears that this discrepancy has existed for approximately 12 years, spanning approximately 88 cask users and approximately 1,400 shipments.
Upon notification and after confirmation of the discrepancy, EnergySolutions revised TR-TP-002 to incorporate the SAR required 60-minute vent port leak test. This change to TR-TP-002 was communicated to all EnergySolutionsregistered cask users on June 13, 2013. The SAR requires pre-shipment leak testing of the vent port only when the port has been opened since the preceding vent port leak test. EnergySolutions issued a notice to registered cask users on July 2, 2013 to clarify this issue. Operation of a package vent port is infrequent. However some vent ports may have been opened during the past 12 years; and therefore the pre-shipment leak testing would have been required.
The licensing basis for the pre-shipment leak tests for all three of the 8-120B lid containment seals is a pressure drop calculation for the largest of the three seals (the primary lid seal).
The required hold time is therefore conservative for the two seals with smaller test volumes.
Because of the small size of the vent port seal test volume, EnergySolutions has determined that the 20-minute hold time meets the same criterion by which the 60-minute hold time was derived for the larger primary lid seal. In fact, in the case of the vent port leak test, the 20-minute hold time provides substantial margin for detecting any leakage from the vent port. It therefore follows that there is no safety significance associated with the condition.
Since registered users of the 8-120B package are licensees, these licensees would normally prepare and issue an approved procedure to control their pre-shipment activities.
ENERGYSOLUTIONS Furthermore, there is no continuing safety concern as new lids are required to be used after August 31, 2013 with different testing procedures.
Due to the long timeframe over which this condition has existed, the large number of 8-120B cask users, the many shipments that have occurred, the difficulty of determining which if any shipments may have been out of compliance, and the finding of no significant safety impact, EnergySolutions hereby submits this notification to summarize the issue as it applies to all 8-120B users. Because of the imminent rollout of new lids and related test procedures, no further corrective actions by certificate users are necessary to address this leak test procedure.
- 2) Narrative Description of the Event a) Status of Components All 8-120B components are operating normally.
b) Dates of Occurrences February 2001 to present.
c) Cause of Error Discrepancy between EnergySolutions air pressure drop test procedure TR-TP-002 and Chapter 8 of the 8-120B SAR.
d) Failure Mode, Mechanism, and Effects Not applicable; no 8-120B packaging components have failed.
e) Systems or Secondary Functions Affected Not applicable.
f) Method of Discovery of the Error The condition was identified by an 8-120B cask user.
- 3) Assessment of Safety Consequences There is nto safety consequence of performing the pre-shipment leak test of the 8-120B cask vent port using a 20-minute hold time versus the 60-minute hold time that is required by the 8-120B CoC. The required hold time varies in proportion to the test volume if the test pressure and acceptance criterion remain unchanged. Larger test volumes require longer hold times. The test volume includes the free volume of the space to be tested and the volume of the test manifold. For the original subject 8-120B lids, Section 4.4 of the July 2012 SAR Addendum shows the calculation basis for a 60-minute hold time. Only one calculation was presented for the large primary lid containment seal. Since the other seals have smaller test volumes, a 60-minute hold time was conservatively specified for all seals, including the vent port.
ENER*YSOLV77ONS The SAR test volume for the primary containment seal was 103.2 cc. For the pre-shipment vent port leak test, there is no safety impact from a 20-minute hold time provided that the test volume is less than or equal to the 20/60 times the primary containment seal test chamber volume, or (20/60)* 103.2 = 34.4 cc. The vent port test volume is equal to the combined volume of the test manifold (10 cc) plus a very small residual volume inside the vent port, which is less than 34.4 cc. Therefore, pre-shipment leak tests of the vent port performed using a 20-minute hold time are adequate to demonstrate compliance with maximum leak rate acceptance criteria, and there is no safety consequence from testing vent ports for 20 minutes instead of 60 minutes.
- 4) Planned Corrective Actions As noted above, upon notification and after confirmation of the discrepancy, EnergySolutions revised TR-TP-002 to incorporate the SAR required 60-minute vent port leak test and notified registered cask users of the change.
Beginning September 1, 2013, the 8-120B fleet will ship with a new lid design, authorized in the latest revision of the CoC. 2 Thereafter, the 8-120B cask may no longer be used with the old seals that were authorized in Revision No. 17 of the 8-120B CoC. Shipments with the new lids will be required to use the seals authorized in Revision 19 of the CoC. The EnergySolutions air pressure drop test procedure TR-TP-002 is being revised and reissued based on the requirements of Revision 19 of the 8-120B CoC. These revisions are reviewed and approved by the EnergySolutions Cask Licensing Manager to assure that they are compliant with the requirements of the CoC.
EnergySolutions also has initiated a lifecycle procedure for managing Type B casks to assure that CoC requirements flow through the design, fabrication,.and operational phases. This is a new procedure that also would identify existing inconsistencies and prevent future inconsistencies between the SAR and operating procedures. The procedure will be effective August 19, 2013.
The error in incorporating the revised 60-minute vent port leak rate criteria into TR-TP-002 raises a question as to whether there are other similar errors involving the flow-down of requirements into operating procedures. Accordingly, EnergySolutions plans to conduct a review of the 8-120B and other EnergySolutions Type B packagings to verify that CoC and SAR requirements have been accurately translated into the prescribed operating procedures.
If any such discrepancies are found, EnergySolutions will expand the scope of these reviews as necessary.
- 5) Previous Similar Events Involving the 8-120B No previous similar events have been identified.
2No shipments have been made using the new lids to date.
EN ERGYSOLUTIONS
- 6) Contact for Additional Information Dan Shrum EnergySolutions Senior Vice President, Regulatory Affairs (801) 649-2109
- 7) Extent of Exposure of Individuals to Radiation or Radioactive Materials None.
Docket Nos. 50-3, 50-247 & 50-286 NL-13-133 Attachment 1 Page 1 of 1 List of IPEC Units 1, 2 and 3 Class B Shipments Using the 8-120B Cask Units 1 & 2 Shipment Date Cask COC Cask Serial Number 8/2/2001 USA/9168/B (U) CNS 8-120 B - 1 8/9/2001 USA/9168/B (U) CNS 8-120 B - 1 8/28/2002 USA/9168/B (U) CNS 8-120 B - 2 2/3/2003 USA/9168/B (U) CNS 8-120 B - 2S 8/11/2003 USA/9168/B (U) CNS 8-120 B - 2S 9/2/2003 USA/9168/B (U) CNS 8-120 B - 1 2/7/2005 USA/9168/B (U) CNS 8-120 B - 2 10/12/2005 USA/9168/B (U) CNS 8-120 B - 2S 11/3/2005 USA/9168/B (U) CNS 8-120 B- 2 7/28/2006 USA/9168/B (U) CNS 8-120 B- 1 12/1/2006 USA/9168/B (U) CNS 8-120 B - 2S 11/1/2007 USA/9168/B (U) CNS 8-120 B - 2 9/10/2010 USA/9168/B (U) CNS 8-120 B - 2 Unit 3 Shipment Date Cask COC Cask Serial Number 8/20/2004 USA/9168/B (U) CNS 8-120 B - 1S