NL-04-094, Supplemental Response to Request for Additional Information Security Plan Sections 1-19

From kanterella
Jump to navigation Jump to search

Supplemental Response to Request for Additional Information Security Plan Sections 1-19
ML042190319
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/04/2004
From: Dacimo F
Entergy Nuclear Northeast
To:
Document Control Desk, NRC/FSME
References
EA-03-086, NL-04-094, TAC MC2929, TAC MC2930
Download: ML042190319 (2)


Text

AEntergy Nuclear Northeast U- SAFEGUARDS INFORMATION Indian Point Energy Center 450 Broadway, GSB PRO. Box 249 Eny Buchanan, NY 10511-0249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration August 4, 2004 Indian Point Unit Nos. 1, 2, and 3 Docket Nos. 50-03, 50-247, and 50-286 NL-04-094 Document Control Desk U. S. Nuclear Regulatory Commission Mail Station O-P1-17 Washington, D.C. 20555-0001

SUBJECT:

Supplemental Response To Request For Additional Information Re: Indian Point Units 1, 2 and 3 Security Plan Sections 1-19 (TAC Nos. MC2929 and MC2930)

Reference:

1. Entergy letter to NRC, NL-04-082, "Response To Request For Additional Information Re: Indian Point Units 1, 2 and 3 Security Plan Sections 10-19 (TAC Nos. MC2929 and MC2930)," dated July 8, 2004.
2. Entergy letter to NRC, NL-04-085, 'Response To Request For Additional Information Re: Indian Point Units 1, 2 and 3 Security Plan Sections 1-9 (TAC Nos. MC2929 and MC2930)," dated July 14, 2004.

Dear Sir:

Entergy Nuclear Operations, Inc., (ENO) responded in References 1 and 2 to NRC letters dated June 16 and June 25, 2004 containing requests for additional information (RAls) regarding ENO's April 29, 2004 responses to Order EA-03-086. In the responses we noted that the plan was based on NEI-03-12, "Template for the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan" Revision 1, as approved by the staff in a letter from Roy P. Zimmerman to Steven D. Floyd dated June 10, 2004. ENO also stated that, where template language was involved, ENO would adopt revised language once agreement had been reached between the industry Security Working Group (SWG) licensee representatives and the staff. ENO is submitting revised responses in this letter to reflect agreements reached to date, to indicate where outstanding items still exist, and to docket changes agreed to in a teleconference with the NRC Staff on July 20, 2004.

Attachment 1 provides the supplemental response to the Reference 1 and 2 responses to NRC requests for additional information regarding Security Plan Sections 1-19.

This letter contains no new commitments. If you have any questions or require additional information, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.

SAFEGUARDS INFORMATION NOTICE: ATTACHMENT 1 CONTAINS "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF ATTACHMENT 1 FROM THIS LETTER, THIS LETTER BECOMES DECONTROLLED."

,s 11,0-6,

SAFEQUARDS INFORMATION Docket Nos. 50-03, 50-247, and 50-286 NL-04-094 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on August 4, 2004.

Fred R. Dacimo Site Vice President Indian Point Energy Center w/o attachments cc:

Mr. Samuel J. Collins Resident Inspectors' Office Regional Administrator-Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Indian Point Unit 3 475 Allendale Road P.O. Box 337 King of Prussia, Pennsylvania 19406-1415 Buchanan, NY 10511-0337 Mr. Patrick D. Milano, Sr. Project Manager Mr. Robert L. Fretz Project Directorate I Security Plan Review Team Division of Licensing Project Management Project Directorate II Office of Nuclear Reactor Regulation Division of Licensing Project Management U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Mail Stop O-8-C2 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Mail Stop 8-B2 Washington, D.C. 20555-0001 Mr. Michael K. Webb, Project Manager Resident Inspectors' Office Project Directorate IV U.S. Nuclear Regulatory Commission Division of Licensing Project Management Indian Point Unit 2 Office of Nuclear Reactor Regulation P.O. Box 59 U.S. Nuclear Regulatory Commission Buchanan, NY 10511-0059 Mail Stop 0-7-Dl Washington, D.C. 20555-0001 SAFEGUARDS INFORMATION NOTICE: ATTACHMENT 1 CONTAINS 'SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF ATTACHMENT I FROM THIS LETTER, THIS LETTER BECOMES "DECONTROLLED."