NL-04-097, Response to Request for Additional Information Re Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan

From kanterella
Jump to navigation Jump to search

Response to Request for Additional Information Re Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan
ML042310539
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/12/2004
From: Dacimo F
Entergy Nuclear Northeast
To:
Document Control Desk, NRC/FSME
References
NL-04-097, TAC MC2929, TAC MC2930
Download: ML042310539 (2)


Text

Entergy Nuclear Northeast Indian Point Energy Center SAFEGUARDS INFORMATION Enter 450 Broadway, GSB PRO. Box 249 Buchanan, NY 10511-0249 Tel 9147346700 Fred Dacimo Site Vice President Administration August 12,2004 Indian Point Unit Nos. 1,2, and 3 Docket Nos. 50-03,50-247, and 50-286 NL-04-097 Document Control Desk U. S. Nuclear Regulatory Commission Mail Station 0-P1 -17 Washington, D.C. 20555-0001

SUBJECT:

Response to Request For Additional Information Re: Indian Point Units 1, 2 and 3 Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan (TAC Nos. MC2929 and MC2930)

Reference:

1. NRC Letter to Entergy, Indian Point Nuclear Generating Station, Units 2 and 3 - Request For Additional Information Re: Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan (TAC Nos. MC2929 and MC2930),' dated July 23, 2004
2. Entergy Letter (NL-04-061) to NRC, Supplemental Response to the April 29,2003, Orders to Indian Point Units 2 and 3," dated June 1, 2004

Dear Sir:

Entergy Nuclear Operations, Inc., (ENO) is in receipt of the referenced letter containing requests for additional information (RAIs). In order to standardize our approach with the NRC-approved industry approach, ENO's April 29, 2004 responses to Order EA-03-086, as supplemented in Reference 2, were strictly based on NEt03-12, 'Template for the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan' Revision 1, as approved by the staff in a letter from Roy P. Zimmerman to Steven D. Floyd dated June 10, 2004.

In response to these NRC RAIs, ENO is using revised language reflecting agreement reached between the industry Security Working Group (SWG) licensee representatives and the staff. ENO proposes to provide revised Security Plans or replacement pages for each site that incorporate all of our RAI responses on a schedule to be determined with the staff.

Attachment I provides responses to the RAIs In Reference 1. This letter contains new commitments listed in . If you have any questions or require additional information, please contact Mr. Patric W.

Conroy, Manager, Licensing at (914) 734-6668.

SAFEGUARDS INFORMATION NOTICE: ATTACHMENT 1 CONTAINS 'SAFEGUARDS INFORMATIONW AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF ATTACHMENT 1 FROM THIS LETTER, THIS LETTER BECOMES 'DECONTROLLED.'

%01RoS

SAFEGUARDS INFORMATION Docket kos. 50-03, 50-247, and 50-286 NL-04-097 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on August 12, 2004.

Fred R. Dacimo Site Vice President Indian Point Energy Center wlo attachments cc:

Mr. Samuel J. Collins Resident Inspectors' Office Regional Administrator-Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Indian Point Unit 3 475 Allendale Road P.O. Box 337 lKng of Prussia, Pennsylvania 19406-1415 Buchanan, NY 10511-0337 Mr. Patrick D. Milano, Sr. Project Manager Mr. Robert L. Fretz Project Directorate I Security Plan Review Team Division of Ucensing Project Management Project Directorate II Office of Nuclear Reactor Regulation Dilslon of Licensing Project Management U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Mail Stop O-8-C2 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Mail Stop 8-B2 Washington, D.C. 20555-0001 Mr. Michael K. Webb, Project Manager Resident Inspectors' Office Project Directorate IV U.S. Nuclear Regulatory Commission Division of Licensing Project Management Indian Point Unit 2 Office of Nuclear Reactor Regulation P.O. Box 59 U.S. Nuclear Regulatory Commission Buchanan, NY 10511-0059 Mail Stop 0-7-DI Washington, D.C. 20555-0001 SAFEGUARDS INFORMATION NOTICE: ATTACHMENT I CONTAINS 'SAFEGUARDS INFORMATION AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF ATTACHMENT I FROM THIS LETTER, THIS LETTER BECOMES 'DECONTROLLED.'