MONTHYEARML24248A0902024-08-28028 August 2024 Steam Generator Inspection Call ML24192A0012024-07-0606 July 2024 (E-Mail) Palisades Nuclear Plant - Plant - Draft Request for Additional Information: Palisades Operating TS License Amendment Request - June 6, 2024 ML24187A1332024-07-0505 July 2024 LTR-24-0069 Emailed Response Regarding Palisades Restart Project ML24192A1472024-06-28028 June 2024 Email - Palisades Nuclear Plant - Draft Request for Additional Information: Palisades Administrative TS License Amendment Request - June 28, 2024 ML24192A1672024-06-28028 June 2024 Restart - NRC Request for Additional Information - EP ORO Coordination - June 28, 2024 ML24135A3542024-05-20020 May 2024 NRC Response to Jody Flynn of Michigan Regarding Statements Made About Holtec in the April 25, 2024 Peekskill Herald Article: Holtec Playing Fast and Loose with Taxpayers Money by Tina Volz-Bongar (Docket 50-255) ML24141A0862024-05-16016 May 2024 Notification of NRC Activities Regarding Palisades Restart ML24170A8812024-05-15015 May 2024 NRR E-mail Capture - Post Acceptance/Abeyance Process for the 10 CFR 2.206 Petition on Palisades Misuse of Decommissioning Trust Fund ML24032A2442024-02-0101 February 2024 OEDO-24-00011 - 10 CFR 2.206 Petition Holtec Misuse Decommissioning Fund- Email to Petitioner ML24005A1262024-01-0505 January 2024 Permanently Defueled Emergency Plan Implementation Notification ML23055A1532023-02-24024 February 2023 Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22343A1902022-12-0909 December 2022 Acceptance Review: Palisades Proposed Exemption from 10 CFR 140.11 (a)(4) Primary and Secondary Liability Insurance ML22343A2282022-12-0909 December 2022 Acceptance Review: Palisades Proposed Exemption from 10 CFR 50.54(w)(1) - Onsite Property Damage Insurance ML22284A0502022-10-0707 October 2022 Acceptance Review: License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML22227A0092022-08-12012 August 2022 Acceptance Review: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme (L-2022-LLA-0099) ML22227A0082022-08-12012 August 2022 Acceptance Review: Exemption Request from 10CFR50.47(b), 10 CFR 50.47(c)(2), and 10 CFR Part 50, Appendix E, Section IV ML22179A0752022-06-28028 June 2022 E-mail from Entergy Dated June 28, 2022, Notification of Palisades and Big Rock Point License Transfer (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) ML22159A2672022-06-0202 June 2022 Answers to Your Questions on Palisades ML22159A2652022-05-0303 May 2022 Questions Asked at Palisades Plant Performance Public Meeting April 26, 2022 ML21328A0062021-11-18018 November 2021 NRR E-mail Capture - (External_Sender) State of Michigan Response - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments ML22208A1052021-11-16016 November 2021 NRR E-mail Capture - (External_Sender) State of Michigan Response - Palisades - Preparation for Issuance of Final Environmental Assessment and Finding of No Significant Impact Holtec Exemption Request to Use Dtf ML21309A5152021-11-0505 November 2021 NRR E-mail Capture - Palisades Nuclear Plant - Preparation for Issuance of Final Environmental Assessment and Finding of No Significant Impact Holtec Exemption Request to Use Dtf ML21309A2982021-11-0505 November 2021 NRR E-mail Capture - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments ML21209A9802021-07-28028 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Rescission of Interim Compensatory Measure from Order EA-02-026 ML21189A2462021-07-0606 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Proposed Partial Exemption from Record Retention Requirements ML21189A0432021-07-0606 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Permanently Defueled Technical Specifications ML21054A1822021-02-23023 February 2021 NRR E-mail Capture - Regarding Public Comment on Palisades Request for Relief RR 5-8 ML21028A4092021-01-27027 January 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Holtec Exemption Request from 10CFR50.82(a)(8)(i)(A) and 10CFR50.75(h)(1)(iv) ML21028A0552021-01-27027 January 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of License Transfer Application ML21007A3752021-01-0707 January 2021 NRR E-mail Capture - Regarding Public Comment on Palisades Nuclear Plant License Transfer (Sierra Club Nuclear Free Michigan) ML21054A1812021-01-0606 January 2021 NRR E-mail Capture - (External_Sender) Regarding Public Comment on Palisades Request for Relief RR 5-8 ML20275A3432020-10-0101 October 2020 Verbal Authorization for Proposed Alternative (RR 5-8) Reactor Vessel Closure Head Penetration Repairs ML20272A0112020-09-26026 September 2020 Request for Additional Information - Palisades Relief Request RR 5-8 (Proposed Alternative) for Reactor Pressure Vessel Head Penetration Repairs ML20262G9622020-09-17017 September 2020 Acknowledgement to Mr. Muhich e-mail, Dated September 15, 2020 (e-mail) ML20241A1802020-08-27027 August 2020 NRR E-mail Capture - Palisades Nuclear Plant- Upcoming Steam Generator Tube Inservice Inspection ML20162A4522020-04-0808 April 2020 Lake Mich Level Correspondence with Ipotter ML19344C7162019-08-25025 August 2019 Response from NEIMA Local Community Advisory Board Questionnaire 08-25-2019 C Ferry ML19344C8072019-08-16016 August 2019 Scanned Response 09-29-2019 I Potter ML19226A2932019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Re License Amendment Request to Adopt TSTF-425, Revision 3 for the Palisades Nuclear Plant ML19226A2922019-08-0505 August 2019 NRR E-mail Capture - Draft Request for Additional Information for Palisades License Amendment Request to Adopt TSTF-425 ML19122A4852019-04-29029 April 2019 NRR E-mail Capture - Request for Additional Information for Palisades License Amendment Request to Revise License Conditions Related to NFPA 805 Modifications ML19095A6572019-04-0505 April 2019 NRR E-mail Capture - Acceptance for Review of Application to Revise the Palisades Nuclear Plant License Renewed Facility Operation License Regarding Full Compliance Implementation Date for the Fire Protection Program ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML19059A0292019-02-27027 February 2019 NRR E-mail Capture - Acceptance Review Results for License Amendment Request to Adopt TSTF-529, Revision 4, Clarify Use and Application Rules, for Entergy Fleet ML19009A5392019-01-0909 January 2019 NRR E-mail Capture - Request for Additional Information for Palisades License Amendment Request to Revise Emergency Diesel Generator Degraded Voltage Surveillance Requirement 3.3.5.2a ML19009A5382018-12-12012 December 2018 NRR E-mail Capture - Draft Request for Additional Information for Palisades License Amendment Request to Revise Emergency Diesel Generator Degraded Voltage Surveillance Requirement 3.3.5.2a ML18337A1382018-11-30030 November 2018 NRR E-mail Capture - Request for Additional Information Related to Palisades Relief Request Number RR 5-7 ML18337A1352018-11-30030 November 2018 NRR E-mail Capture - Acceptance for Review of Application to Revise the Palisades Nuclear Plant License Renewed Facility Operation License Regarding Changes to the Fire Protection Plan ML18337A1402018-11-29029 November 2018 NRR E-mail Capture - Draft Request for Additional Information Related to Palisades Relief Request 5-7 ML18184A2402018-07-0303 July 2018 NRR E-mail Capture - Acceptance for Review of Application to Revise Technical Specification Surveillance Requirement 3.3.5.2a for the Diesel Generator Undervoltage Start 2024-08-28
[Table view] |
Text
From: Justin Poole (He/Him)
To: James Miksa; Amy Filbrandt
Subject:
Steam Generator Outage Call Date: Wednesday, August 28, 2024 2:09:00 PM
Jim/Amy,
Inservice inspections of steam generator tubes play a vital role in assuring SG tube integrity. A telephone conference call has been arranged with members of your staff to discuss the ongoing results of the steam generator tube inspections to be conducted during the upcoming inspection at Palisades Nuclear Plant. This call will occur after the majority of the tubes have been inspected, but before the steam generator inspection activities have been completed.
Below is a list of discussion points to facilitate this call.
The NRC staff will document a publicly available summary of the conference call, including any material that you provide to the NRC staff in support of the call.
Should you have any questions you can contact me.
Justin C. Poole Project Manager Palisades Restart NRR/DORL/LPL 3 U.S. Nuclear Regulatory Commission (301)415-2048
STEAM GENERATOR TUBE INSPECTION DISCUSSION POINTS
The following discussion points have been prepared to facilitate the conference call arranged with the licensee to discuss the results of the steam generator tube inspections to be conducted during the upcoming steam generator inspection. This conference call is scheduled to occur towards the end of the planned SG tube inspections, but before the unit completes the inspections and repairs.
The NRC staff plans to document a publicly available summary of the conference call, as well as any material that is provided in support of the call.
- 1. Discuss any trends in the amount of primary-to-secondary leakage observed during the most recently completed cycle.
- 2. Discuss whether any secondary side pressure tests were performed during the outage and the associated results.
- 3. Discuss any exceptions taken to the industry guidelines.
- 4. For each steam generator, provide a description of the inspections performed including the areas examined and the probes used (e.g., dents/dings, sleeves, expansion-transition, U-bends with a rotating probe), the scope of the inspection (e.g., 100% of dents/dings greater than 5 volts and a 20% sample between 2 and 5 volts), and the expansion criteria.
- 5. For each area examined (e.g., tube supports, dent/dings, sleeves, etc.), provide the following:
A summary of the number of indications identified to date for each degradation mode (e.g., number of circumferential primary water stress corrosion cracking indications at the expansion transition).
For the most significant indications in each area, provide an estimate of the severity of the indication (e.g., voltage, depth, and length of the indication), including whether tube integrity (structural and accident induced leakage integrity) was maintained during the previous operating cycle. In addition, discuss any analyses performed specifically for the most significant indications to demonstrate tube integrity.
- 6. Describe repair/plugging plans.
- 7. Describe in-situ pressure test and tube pull plans and results (as applicable and if available).
- 8. Discuss the following regarding loose parts:
The inspections performed to detect loose parts.
A description of any loose parts detected and their location within the SG (including the source or nature of the loose part, if known).
If the loose parts were removed from the SG.
Indications of tube damage associated with the loose parts.
- 9. Discuss the scope and results of any secondary side inspection and maintenance activities (e.g., in-bundle visual inspections, feedring inspections, sludge lancing, assessing deposit loading, etc.).
- 10. Discuss any unexpected or unusual results.
- 11. Provide the schedule for steam generator-related activities during the remainder of the current outage.
- 12. Discuss any actions taken or plans for obtaining water samples or deposit samples (e.g., sludge pile, tube scale, etc.) to evaluate potential detrimental chemistry conditions or contaminants (e.g., chlorides, sulfates, Pb) during the plant shutdown.