Revised Technical Specification Pages (Clean Pages)
ML24158A525
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/06/2024
From:
Ameren Missouri, Union Electric Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML24158A521 List:
References
ULNRC-06880
Download: ML24158A525 (1)


Text

Attachment 2 Revised Technical Specification Pages (Clean Pages) 2 Pages

Definitions I.1 1.1 Definitions (continued)

DOSE EQUIVALENT XE-133 DOSE EQUIVALENT XE-133 shall be that concentration of Xe-I 33 (microcuries per gram) that alone would produce the same acute dose to the whole body as the combined activities of noble gas nuclides Kr-85m, Kr-87, Kr-88, Xe-133m, Xe-133, Xe-135m, Xe-I35, and Xe-I38 actually present.

If a specific noble gas nuclide is not detected, it should be assumed to be present at the minimum detectable activity.

The determination of DOSE EQUIVALENT XE-I 33 shall be performed using the effective dose conversion factors for air submersion listed in Table 111.1 of EPA Federal Guidance Report No. I 2, 98, External Exposure to Radionuclides in Air, Water, and Soil, 1993.

ENGINEERED SAFETY The ESF RESPONSE TIME shall be that time interval from FEATURE (ESF) RESPONSE when the monitored parameter exceeds its ESF actuation TIME setpoint at the channel sensor until the ESF equipment is capable of performing its safety function (i.e., the valves travel to their required positions, pump discharge pressures reach their required values, etcj. Times shall include diesel generator starting and sequence loading delays, where applicable. The response time may be measured by means of any series of sequential, overlapping, or total steps so that the entire response time is measured. In lieu of measurement, response time may be verified for selected components provided that the components and methodology for verification have been previously reviewed and approved by the NRC or the components have been evaluated in accordance with an NRC approved methodology.

INSERVICE TESTING The INSERVICE TESTING PROGRAM is the licensee PROGRAM program that fulfills the requirements of 10 CFR 50.55a(f).

LEAKAGE LEAKAGE shall be:

a. Identified LEAKAGE I

. LEAKAGE, such as that from pump seals or valve packing (except reactor coolant pump (RCP) seal water leakoff), that is captured and conducted to collection systems or a sump or collecting tank;

2. LEAKAGE into the containment atmosphere from sources that are both specifically located and known either not to interfere with the operation of leakage detection systems or not to be pressure boundary LEAKAGE; or (continued)

CALLAWAY PLANT 1.1-3 Amendment

Definitions I.1 1.1 Definitions (continued)

PHYSICS TESTS PHYSICS TESTS shall be those tests performed to measure the fundamental nuclear characteristics of the reactor core and related instrumentation. These tests are:

a. Described in Chapter 14 ofthe FSAR;
b. Authorized under the provisions of I 0 CFR 50.59; or
c. Otherwise approved by the Nuclear Regulatory Commission.

PRESSURE AND The PTLR is the unit specific document that provides the TEMPERATURE LIMITS reactor vessel pressure and temperature limits, including REPORT (PTLR) heatup and REPORT (PTLR) cooldown rates, the power operated relief valve (PORV) lift settings, and the Cold Overpressure Mitigation System (COMS) arming temperature, for the current reactor vessel fluence period. These pressure and temperature limits shall be determined for each fluence period in accordance with Specification 5.6.6.

QUADRANT POWER QPTR shall be the ratio of the maximum upper excore TILT RATIO (QPTR) detector calibrated output to the average of the upper excore detector calibrated outputs, or the ratio of the maximum lower excore detector calibrated output to the average of the lower excore detector calibrated outputs, whichever is greater.

RATED THERMAL POWER RTP shall be a total reactor core heat transfer rate to the (RTP) reactor coolant of 3565 MWt.

REACTOR TRIP SYSTEM The RTS RESPONSE TIME shall be that time interval from (RTS) RESPONSE TIME when the monitored parameter exceeds its RTS trip setpoint at the channel sensor until loss of stationary gripper coil voltage. The response time may be measured by means of any series of sequential, overlapping, or total steps so that the entire response time is measured. In lieu of measurement, response time may be verified for selected components provided that the components and methodology for verification have been previously reviewed and approved by the NRC or the components have been evaluated in accordance with an NRC approved methodology.

(continued)

CALLAWAY PLANT 1.1-5 Amendment