Acceptance of Supplemental Information to Support Increased Enrichment and Burnup and Revised Schedule for Review of Framatomes TR ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of Apollo
ML24067A242
Person / Time
Site: 99902041
Issue date: 03/22/2024
From: Ngola Otto
Licensing Processes Branch
To: Elliott G
Framatome
References
EPID L-2022-TOP-0038
Download: ML24067A242 (1)


Text

March 22, 2024 Gayle Elliott, Director Licensing and Regulatory Affairs Framatome Inc.

3315 Old Forest Road Lynchburg, VA 24501

SUBJECT:

THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE OF SUPPLEMENTAL INFORMATION TO SUPPORT INCREASED ENRICHMENT AND BURNUP AND REVISED SCHEDULE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10350P, REVISION 0, FRAMATOME METHODOLOGY FOR BOILING WATER REACTORS:

EVALUATION AND VALIDATION OF APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038)

Dear Gayle Elliott:

By letter dated February 21, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24057A358), Framatome, Inc. (Framatome) submitted supplemental information to Topical Report (TR) ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B, for U.S. Nuclear Regulatory Commission (NRC) staffs review. The supplemental information supports increased enrichment and burnup for boiling water reactor fuels. The NRC staff had agreed to consider the supplement information as part of the ongoing review of ANP-10350P, Revision 0, in discussions with Framatome representatives during a partially closed meeting held on February 21, 2023 (ADAMS Accession No. ML23053A259).

The NRC staff have found that the supplemental information is sufficient to begin its detailed technical safety review of the new information in combination with the initial June 30, 2022, ANP-10350P, Revision 0, submittal (ADAMS Package Accession No. ML22186A071). Below are discussions and the NRC staffs rationale for planned schedule revisions and level of effort increases to accommodate review of the supplemental information and the overall TR. Based on the information provided in your submittal, the NRC staff plans to conduct an audit by end of May 2024, issue Requests for Additional Information (RAIs) by July 2024, the draft safety evaluation (SE) by February 28, 2025, and final SE by May 30, 2025, as annotated in the enclosed schedule. The draft SE completion date assumes 60 days for RAI responses, but will be adjusted, if necessary, to accommodate any delays in the responses. The enclosed schedule provides dates for the initial planned, actual, and revised milestones for the overall review.

Additionally, the NRC staff estimates that it will require an increase of approximately 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> to the current 900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> that was planned for the initial June 30, 2022, submittal, for a total of 1400 hours0.0162 days <br />0.389 hours <br />0.00231 weeks <br />5.327e-4 months <br /> to complete the safety review. The Advisory Committee on Reactor Safeguards

(ACRS) plans to review this TR, and as such, subcommittee and full committee meetings are estimated to occur in March 2025, and April 2025, respectively to facilitate this effort. The specific ACRS meeting dates will be confirmed and scheduled later.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff-hours will be billed accordingly.

If you have any questions regarding the TR review, please contact me at 301-415-6695 or via email at Ngola.Otto@nrc.gov.

Sincerely,

/RA/

Ngola A. Otto, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902041

Enclosure:

Initial Planned, Actual, and Revised Schedule with increased enrichment supplement Review

Enclosure Initial Planned, Actual, and Revised Schedule with Increased Enrichment Supplement Review Milestone Initial Planned Actual Revised Initial Submittal Jun. 30, 2022 Jun. 30, 2022 Acceptance Aug. 19, 2022 Aug. 22, 2022 Audit-1 Dec. 5-8, 2022 Dec. 5-8, 2022 Issued Requests for Additional Information (RAI) - Set #1 Jan. 26, 2023 Jan. 26, 2023 Issue RAIs - Set #2 Mar. 31, 2023 Apr. 14, 2023 Response to RAIs - Set #1 May 31, 2023 Jun. 30, 2023 Response to RAIs - Set #2 Jun. 30, 2023 Oct. 6, 2023 Increased Enrichment & Burnup Supplemental Information Dec. 2023 Feb. 21, 2024 Audit-2 May 2024 TBD Issue RAIs - Set #3 Jul. 2024 TBD Response to RAIs - Set #3 Sept. 2024 TBD Issue Draft SE Apr. 26, 2024 Feb. 28, 2025 ACRS Subcommittee Meeting Jun. 2024 Mar. 2025 ACRS Full Committee Meeting Jul. 2024 Apr. 2025 Issue Final SE Aug. 30, 2024 May 30, 2025

SUBJECT:

THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE OF SUPPLEMENTAL INFORMATION TO SUPPOERT INCREASED ENRICHMENT AND BURNUP AND REVISED SCHEDULE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10350P, REVISION 0, FRAMATOME METHODOLOGY FOR BOILING WATER REACTORS:

EVALUATION AND VALIDATION OF APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) DATED: MARCH 22, 2024 DISTRIBUTION:

PUBLIC RidsACRS_MailCTR Resource RidsNrrLADHarrison Resource RidsOgcMailCenter Resource RidsNrrDorlOd Resource RidsNrrDssSfnb Resource RidsNrrDorlLlpb Resource RidsResOd Resource RidsNrrDss Resource KHeller, NRR ASmith, NRR ACollier, NRR GGeorge, NRR SKrepel, NRR NOtto, NRR JDonoghue, NRR MJRoss-Lee, NRR YDiazSanabria, NRR BPham, NRR ADAMS Accession Number: ML24067A242

  • via email OFFICE NRR/DORL/LLPB/PM* NRR/DORL/LLPB/LA* NRR/DSS/SFNB/BC*

NRR/DORL/LLPB/BC*

NAME Notto DHarrison SKrepel GGeorge DATE 03/18/2024 03/19/2024 03/20/2024 03/21/2024 OFFICE NRR/DORL/LLPB/PM NAME Notto DATE 03/22/2024 OFFICIAL RECORD COPY