Letter Sequence Acceptance Review |
|---|
EPID:L-2022-TOP-0038, Request for Review and Approval of ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (Open) |
|
MONTHYEARML22186A0252022-06-30030 June 2022 Request for Review and Approval of ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: Request ML22230D0252022-08-22022 August 2022 Completeness Determination for Framatome Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of AP0LL02-A/ARTEMIS-B - Form 898 Project stage: Other ML22319A1782022-11-25025 November 2022 December 5-8, 2022, Regulatory Audit Plan for Framatome Inc. Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B - Letter - Project stage: Other ML23010A0022023-01-20020 January 2023 Report for December 5-8, 2022 Audit Regrding Framatome Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (Letter) Project stage: Other ML23018A1532023-01-26026 January 2023 1st Set of Request for Additional Information Regarding Framatome Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of Apollo2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - Letter Project stage: RAI ML23048A0892023-02-16016 February 2023 February 21, 2023 Meeting Proprietary Presentation for ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Topical Report (Affidavit) Project stage: Meeting ML23052A0742023-02-21021 February 2023 February 21, 2023 Meeting Closed Session Presentation for ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Topical Report (Non-Proprietary) (Slides) Project stage: Meeting ML23053A2592023-02-23023 February 2023 Summary of February 21, 2023, Partially Closed Meeting with Framatome Inc. and U.S. Nuclear Regulatory Commission for Topical Report, ANP-10350P, Rev. 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2 Project stage: Meeting ML23094A1802023-04-14014 April 2023 Second Set of Request for Additional Information Regarding Framatome Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of Apollo2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - Letter Project stage: RAI ML23205A0602023-07-24024 July 2023 Withholding Determination Re Response to Request for Additional Information for Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: RAI ML23205A0642023-07-24024 July 2023 Withholding Determination Regarding RAI Response for TR, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: RAI PMNS20230982, Closed Meeting with the NRC and Framatome Regarding Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B2023-08-31031 August 2023 Closed Meeting with the NRC and Framatome Regarding Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: Request ML23258A1302023-09-19019 September 2023 Summary of September 13, 2023 Closed Meeting with Framatome & the NRC on Topical Report, Anp 10350P, Rev 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS B Project stage: Meeting ML24067A2422024-03-22022 March 2024 Acceptance of Supplemental Information to Support Increased Enrichment and Burnup and Revised Schedule for Review of Framatomes TR ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of Apollo Project stage: Acceptance Review ML24135A1682024-05-20020 May 2024 May 28-30, 2024, Regulatory Audit Plan for Framatome Inc. Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of Apollo2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - Letter Project stage: Other ML24225A2502024-08-21021 August 2024 Report for May 28-30, 2024 Audit Regarding Framatome Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B - Supplement (Redacted) Project stage: Other ML24226B2232024-08-21021 August 2024 Report for May 28-30, 2024 Audit Regarding Framatome Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B - Supplement (Letter) Project stage: Other PMNS20241522, Closed Meeting with the Nuclear Regulatory Commission Staff and Framatome Inc. (Framatome) on Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B2025-01-0303 January 2025 Closed Meeting with the Nuclear Regulatory Commission Staff and Framatome Inc. (Framatome) on Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: Request ML25022A3032025-01-28028 January 2025 Summary of Closed Meeting with Framatome, Inc., and the U.S. Nuclear Regulatory Commission on Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B Project stage: Meeting ML25024A1272025-01-28028 January 2025 Withholding Determination for January 16, 2025, Proprietary Meeting Presentation on the Topical Report ANP-10350P, Rev. 0, Framatome Methodology for Bwrs: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - NRC 897 Project stage: Meeting ML25052A0832025-04-0707 April 2025 Draft Safety Evaluation for Framatome Topical Report ANP-10350P, Revision 0 (EPID L-2022-TOP-0038) - Letter Project stage: Draft Approval ML25052A0562025-04-18018 April 2025 Draft Safety Evaluation for Framatome Topical Report ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - Safety Evaluation - Non-Proprietary Project stage: Draft Approval ML25323A0972025-10-0808 October 2025 Verification for Approved Framatome Topical Report, ANP-10350P-A, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) (Topical Report Verification - Form 896) Project stage: Other ML25323A0962025-11-20020 November 2025 Verification for Approved Framatome Topical Report, ANP-10350P-A, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) (Transmittal) Project stage: Other ML25324A1122025-11-24024 November 2025 Withholding Determination Regarding Publication of Framatome Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - E-mail Project stage: Other ML25324A1132025-11-24024 November 2025 Withholding Determination Regarding Publication of Framatome Topical Report, ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) - NRC 897 Project stage: Other 2023-08-31
[Table View] |
Text
March 22, 2024 Gayle Elliott, Director Licensing and Regulatory Affairs Framatome Inc.
3315 Old Forest Road Lynchburg, VA 24501
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE OF SUPPLEMENTAL INFORMATION TO SUPPORT INCREASED ENRICHMENT AND BURNUP AND REVISED SCHEDULE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10350P, REVISION 0, FRAMATOME METHODOLOGY FOR BOILING WATER REACTORS:
EVALUATION AND VALIDATION OF APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038)
Dear Gayle Elliott:
By letter dated February 21, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24057A358), Framatome, Inc. (Framatome) submitted supplemental information to Topical Report (TR) ANP-10350P, Revision 0, Framatome Methodology for Boiling Water Reactors: Evaluation and Validation of APOLLO2-A/ARTEMIS-B, for U.S. Nuclear Regulatory Commission (NRC) staffs review. The supplemental information supports increased enrichment and burnup for boiling water reactor fuels. The NRC staff had agreed to consider the supplement information as part of the ongoing review of ANP-10350P, Revision 0, in discussions with Framatome representatives during a partially closed meeting held on February 21, 2023 (ADAMS Accession No. ML23053A259).
The NRC staff have found that the supplemental information is sufficient to begin its detailed technical safety review of the new information in combination with the initial June 30, 2022, ANP-10350P, Revision 0, submittal (ADAMS Package Accession No. ML22186A071). Below are discussions and the NRC staffs rationale for planned schedule revisions and level of effort increases to accommodate review of the supplemental information and the overall TR. Based on the information provided in your submittal, the NRC staff plans to conduct an audit by end of May 2024, issue Requests for Additional Information (RAIs) by July 2024, the draft safety evaluation (SE) by February 28, 2025, and final SE by May 30, 2025, as annotated in the enclosed schedule. The draft SE completion date assumes 60 days for RAI responses, but will be adjusted, if necessary, to accommodate any delays in the responses. The enclosed schedule provides dates for the initial planned, actual, and revised milestones for the overall review.
Additionally, the NRC staff estimates that it will require an increase of approximately 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> to the current 900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> that was planned for the initial June 30, 2022, submittal, for a total of 1400 hours0.0162 days <br />0.389 hours <br />0.00231 weeks <br />5.327e-4 months <br /> to complete the safety review. The Advisory Committee on Reactor Safeguards
(ACRS) plans to review this TR, and as such, subcommittee and full committee meetings are estimated to occur in March 2025, and April 2025, respectively to facilitate this effort. The specific ACRS meeting dates will be confirmed and scheduled later.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff-hours will be billed accordingly.
If you have any questions regarding the TR review, please contact me at 301-415-6695 or via email at Ngola.Otto@nrc.gov.
Sincerely,
/RA/
Ngola A. Otto, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902041
Enclosure:
Initial Planned, Actual, and Revised Schedule with increased enrichment supplement Review
Enclosure Initial Planned, Actual, and Revised Schedule with Increased Enrichment Supplement Review Milestone Initial Planned Actual Revised Initial Submittal Jun. 30, 2022 Jun. 30, 2022 Acceptance Aug. 19, 2022 Aug. 22, 2022 Audit-1 Dec. 5-8, 2022 Dec. 5-8, 2022 Issued Requests for Additional Information (RAI) - Set #1 Jan. 26, 2023 Jan. 26, 2023 Issue RAIs - Set #2 Mar. 31, 2023 Apr. 14, 2023 Response to RAIs - Set #1 May 31, 2023 Jun. 30, 2023 Response to RAIs - Set #2 Jun. 30, 2023 Oct. 6, 2023 Increased Enrichment & Burnup Supplemental Information Dec. 2023 Feb. 21, 2024 Audit-2 May 2024 TBD Issue RAIs - Set #3 Jul. 2024 TBD Response to RAIs - Set #3 Sept. 2024 TBD Issue Draft SE Apr. 26, 2024 Feb. 28, 2025 ACRS Subcommittee Meeting Jun. 2024 Mar. 2025 ACRS Full Committee Meeting Jul. 2024 Apr. 2025 Issue Final SE Aug. 30, 2024 May 30, 2025
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS ACCEPTANCE OF SUPPLEMENTAL INFORMATION TO SUPPOERT INCREASED ENRICHMENT AND BURNUP AND REVISED SCHEDULE FOR THE REVIEW OF FRAMATOMES TOPICAL REPORT, ANP-10350P, REVISION 0, FRAMATOME METHODOLOGY FOR BOILING WATER REACTORS:
EVALUATION AND VALIDATION OF APOLLO2-A/ARTEMIS-B (EPID L-2022-TOP-0038) DATED: MARCH 22, 2024 DISTRIBUTION:
PUBLIC RidsACRS_MailCTR Resource RidsNrrLADHarrison Resource RidsOgcMailCenter Resource RidsNrrDorlOd Resource RidsNrrDssSfnb Resource RidsNrrDorlLlpb Resource RidsResOd Resource RidsNrrDss Resource KHeller, NRR ASmith, NRR ACollier, NRR GGeorge, NRR SKrepel, NRR NOtto, NRR JDonoghue, NRR MJRoss-Lee, NRR YDiazSanabria, NRR BPham, NRR ADAMS Accession Number: ML24067A242
- via email OFFICE NRR/DORL/LLPB/PM* NRR/DORL/LLPB/LA* NRR/DSS/SFNB/BC*
NRR/DORL/LLPB/BC*
NAME Notto DHarrison SKrepel GGeorge DATE 03/18/2024 03/19/2024 03/20/2024 03/21/2024 OFFICE NRR/DORL/LLPB/PM NAME Notto DATE 03/22/2024 OFFICIAL RECORD COPY