Technical Requirements Manual, Rev. 12 for Section 2
ML22363A101
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 12/09/2022
From:
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2022-17545
Download: ML22363A101 (1)


Text

J.Jt::L.

  • v::, I .{.V.,{,.,{,

I Page 1 of 2

  • MANUAL HARD COPY DISTRIBUTION DOCUMENT TRANSMITTAL 2022-17545 USER INFORMATION:

GERLACH*ROSEY M EMPL#: 028401 CA#: 0363 Address: NUCSA2 Phone#: 542-3194 TRANSMITTAL INFORMATION:

TO: GERLACH*ROSEY M 12/09/2022 LOCATION: USNRC FROM: NUCLEAR RECORDS DOCUMENT CONTROL CENTER (NUCSA-2)

THE FOLLOWING CH,ANGES HAVE OCCURRED TO THE HARDCOPY OR ELECTRONIC MANUAL ASSIGNED TO YOU. HARDCOPY USERS MUST ENSURE THE DOCUMENTS PROVIDED MATCH THE INFORMATION ON THIS TRANSMITTAL. WHEN REPLACING THIS MATERIAL IN YOUR HARDCOPY MANUAL, ENSURE THE UPDATE DOCUMENT ID IS THE SAME DOCUMENT ID YOU'RE REMOVING FROM YOUR MANUAL. TOOLS OM THE HUMAN PERFORMANCE TOOL BAG SHOULD BE UTILIZED TO ELIMINATE THE CHANCE OF

  • RORS.

ATTENTION: "REPLACE" directions do not affect the Table of Contents, Therefore no TOC will be issued with the updated material.

TRM2 - TECHNICAL REQUIREMENTS MANUAL UNIT 2 REMOVE MANUAL TABLE OF CONTENTS DATE: 12/05/2022 ADD MANUAL TABLE OF CONTENTS DATE: 12/.08/2022 CATEGORY: DOCUMENTS TYPE: TRM2

Page 2 of 2

  • ID: TEXT 2.2 REMOVE: REV:11 ADD: REV: 12 I

ANY DISCREPANCIES WITH THE MATERIAL PROVIDED, CONTACT DCS@ X3171 OR X3194 FOR ASSISTANCE. UPDATES FOR HARDCOPY MANUALS WILL BE DISTRIBUTED WITHIN 3 DAYS IN ACCORDANCE WITH DEPARTMENT PROCEDURES. PLEASE MAKE AI::,L CHANGES AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX UPON COMPLETION OF UPDATES. FOR ELECTRONIC MANUAL USERS, ELECTRONICALLY REVIEW THE APPROPRIATE DOCUMENTS AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX .

SSES MANUAL Manual Name: TRM2

. anual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 Table Of Contents Issue Date: 12/0 8/2022 Procedure Name Rev Issue Date Change ID Change Number TEXT LOES 99 01/03/2019

Title:

LIST OF EFFECTIVE SECTIONS TEXT TOC 27 03/05/2019

Title:

TABLE OF CONTENTS TEXT 1.1 0 11/19 /2002

Title:

USE AND APPLICATION DEFINITIONS TEXT 2.1 1 02/04/2005

Title:

PLANT PROGRAMS AND SETPOINTS PLANT P TEXT 2.2 12

Title:

PLANT PROGRAMS AND TEXT 3.0 8

Title:

APPLICABILITY OPERATION (TRO) APPLICABILITY TEXT 3. 1 .1 11/09 /2007

Title:

REACTIVITY C ANTICIPATED TRANSIENT WITHOUT SCRAM ALTERNATE ROD INJECTION TEXT 3.1.2 11/19 /2002 SYSTEMS CONTROL ROD DRIVE (CRD.) HOUSING SUPPORT TEXT 3. 1. 3 5 12/18/2017

Title:

REACTIVITY CONTROL SYSTEMS CONTROL ROD BLOCK INSTRUMENTATION TEXT 3.1.4 1 10/12 /2020

Title:

REACTIVITY CONTROL SYSTEMS CONTROL ROD SCRAM ACCUMULATORS INSTRUMENTATION AND CHECK VALVE TEXT 3.2.1 19 03/31/2021

Title:

CORE OPERATING LIMITS REPORT (COLR)

Page 1 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2 Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT 3.3.1 0 11/19/2002

Title:

INSTR1]MENTATION RADIATION MONITORING INSTRUMENI'ATION TEXT 3.3.2 3 03/31/2011

Title:

INSTRUMENTATION SEISMIC MONITORING INSTRUMENTATION TEXT 3.3.3 2 11/09/2007

Title:

INSTRUMENTATION METEOROLOGICAL MONITORING INSTRUMENTATION TEXT 3.3.4 11 07/21/2017

Title:

INSTRUMENTATION TRM POST-ACCIDENT MONITORING INSTRUMENTATION TEXT 3.3.5 0 11/19/2002

Title:

INSTRUMENTATION THIS PAGE INTENTIONALLY LEFT BLANK

.'EXT 3. 3. 6 5 03/05/2019

Title:

INSTRUMENTATION TRM ISOLATION ACTUATION INSTRUMENTATION TEXT 3.3.7 4 01/17/2022

Title:

INSTRUMENTATION MAIN TURBINE OVERSPEED PROTECTION SYSTEM TEXT 3.3.8 1 10/22/2003

Title:

INTENTIONALLY LEFT BLANK TEXT 3.3.9 3 05/14/2009

Title:

INSTRUMENTATION LPRM UPSCALE ALARM INSTRUMENTATION TEXT 3.3.10 1 12/14/2004

Title:

INSTRUMENTATION REACTOR RECIRCULATION PUMP MG SET STOPS TEXT 3.3.11 1 10/22/2003

Title:

INSTRUMENTATION MVP ISOLATION INSTRUMENTATION TEXT 3.3.12 2 04/02/2019

Title:

WATER MONITORING INSTRUMENTATION Page 2 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2

.Ianual

Title:

TECHN"ICAL REQUIREMENTS MANUAL UNIT 2

)

TEXT 3.4.1 1 04/26/2006

Title:

REACTOR COOLANT SYSTEM REACTOR COOLANT SYSTEM CHEMISTRY TEXT 3.4.2 1 04/16/2009

Title:

INTENTIONALLY LEFT BLANK TEXT 3.4.3 1 11/09/2007

Title:

REACTOR COOLANT SYSTEM REACTOR COOLANT SYSTEM (RCS)

TEXT 3.4.4 2 ' 05/14/2009

Title:

REACTOR COOLANT SYSTEM REACTOR RECIRCULATION FLOW AND ROD LINE LIMIT TEXT 3.4.5 1 0_4/26/2006

Title:

REACTOR COOLANT SYSTEM REACTOR VESSEL MATERIALS

._'EXT 3. 4. 6 1 04/25/2013 (

Title:

REACTOR RECIRCULATION SINGLE LOOP OPERATION SLO FLOW RATE RESTRICTION TEXT 3.5.1 2 03/05/2019

Title:

ECCS RPV'WATER INVENTORY CONTROL AND RCIC SYSTEM ADS MANUAL INHIBIT TEXT 3.5.2 2 03/05/2019

Title:

ECCS RPV WATER.INVENTORY CONTROL AND RCIC SYSTEM ECCS RPV WATER INVENTORY CONTROL AND RCIC MONITORING INSTRUMENTATION TEXT 3.5.3 1 03/05/2019

Title:

ECCS RPV WATER INVENTORY CONTROL AND RCIC SYSTEM LONG TERM NITROGEN SUPPLY TO ADS TEXT 3.6.1 0 11/19/2002

Title:

CONTAINMENT VENTING OR PURGING TEXT 3.6.2 01/03/2019

Title:

SUPPRESSION CHAMBER TO DRYWELL VACUUM BREAKER POSITION INDICATION TEXT 3 6 3 0 11/19/2002

  • Tit~e: CONTAINMENT SUPPRESSION POOL ALARM INSTRUMENTATION Page 3 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2 Ianual

Title:

TECHNICAL REQUIREMENI'S MANOAL DNIT 2 TEXT 3.6.4 0 11/19/2002

Title:

CONTAINMENT PRIMARY CONTAINMENT CLOSED SYSTEM BOUNDARIES TEXT 3.7.1 0 11/19/2002

Title:

PLANT SYSTEMS EMERGENCY SERVICE WATER SYSTEM (ESW) SHOTOOWN TEXT 3.7.2 0 11/19/2002

Title:

PLANT SYSTEMS filTIMATE HEAT SINK (UHS) AND GROUND WATER LEVEL J--

TEXT 3.7.3.l 7 04/21/2022

Title:

PLANT SYSTEMS FIRE SUPPRESSION WATER SUPPLY SYSTEM TEXT 3.7.3.2 3 04/16/2009

Title:

PLANT SYSTEMS SPRAY AND SPRINKLER SYSTEMS

.'EXT 3 . 7 . 3 . 3 4

Title:

PLANT SYSTEMS CO2 SYSTEMS TEXT 3.7.3.4 2 05/16/2016 04/16/2009 r

Title:

PLANT SYSTEMS HALON SYSTEMS TEXT 3.7.3.5 2 04/16/2009

Title:

PLANT SYSTEMS FIRE HOSE STATIONS I

TEXT 3.7.3.6 2 04/16/2009

Title:

PLANT SYSTEMS YARD FIRE HYDRANTS AND HYDRANT HOSE HOUSES TEXT 3.7.3.7 1 04/26/2006

Title:

PLANT SYSTEMS FIRE RATED ASSEMBLIES TEXT 3.7.3.8 15 08/02/2021

Title:

PLANT SYSTEMS FIRE DETECTION INSTRUMENTATION . (

TEXT 3.7.4 1 04/26/2006

Title:

PLANT SYSTEMS SOLID RADWASTE SYSTEM Page 4 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2

  • Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT* 3 . 7 . 5 . 1 1 03/05/2015

Title:

PLANT SYSTEMS MAIN CONDENSER OFFGAS HYDROGEN MONITOR TEXT 3.7.5.2 0 11/19/2002

Title:

PLANT SYSTEMS MAIN CONDENSER OFFGAS EXPLOSIVE GAS MIXTURE TEXT 3.7.5.3 1 04/26/2006

Title:

PLANT SYSTEMS LIQUID HOLDUP TANKS TEXT 3.7.6 3 06/04/2012

Title:

PLANT SYSTEMS ESSW PUMPHOUSE VENTILATION TEXT 3.7.7 2 09/05/2008

Title:

PLANT SYSTEMS MAIN CONDENSER OFFGAS PRETREATMENT LOGARITHMIC RADIATION MONITORING INSTRUMENTATION

  • .'EXT 3. 7. 8 9 03/05/2015

Title:

PLANT SYSTEMS SNOBBERS TEXT 3.7.9 2 03/05/2019

Title:

PLANT SYSTEMS CONTROL STRUCTlJRB HVAC

)

TEXT 3.7.10 2 04/29/2014

Title:

PLANT SYSTEMS SPENT FUEL STORAGE POOLS (SFSPS)

TEXT 3.7.11 2 11/01/2018 ,

Title:

PLANT SYSTEMS TEXT 3.8.1 4 08/02/2021

Title:

ELECTRICAL POWER PRIMARY CONTAINMENT PENETRATION CONDUCTOR OVERCURRENT PROTECTIVE DEVICES TEXT 3.8.2.1 2 11/09/2007

Title:

ELECTRICAL POWER MOTOR OPERATED VALVES (MOV) THERMAL OVERLOAD PROTECTION -

CONTINUOUS TEXT 3.8.2.2 3 06/23/2021

Title:

ELECTRICAL POWER MOTOR OPERATED VALVES (MOV) THERMAL OVERLOAD PROTECTION -

AUTOMATIC Page 5 of 15 Report Date: 12/08/22

SSES MANUAL Manual Na.me:

TRM2 Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL TINIT 2 TEXT 3.8.3 4 01/28/2020

Title:

ELECTRICAL POWER DIESEL GENERATOR (DG) MAINTENANCE ACTIVITIES TEXT 3.8.4 1 02/04/2005

)

Title:

ELECTRICAL POWER 24 VDC ELECTRICAL SUBSYSTEM/"'

TEXT 3.8.5 1 11/14/2013

Title:

ELECTRICAL POWER DEGRADED VOLTAGE PROTECTION TEXT 3.8.6 3 03/05/2019

Title:

ELECTRICAL POWER EMERGENCY SWITCHGEAR ROOM COOLING TEXT 3.8.7 3 02/25/2021

Title:

BATTERY MAINTENANCE AND MONITORING PROGRAM

.L'EXT 3. 9 .1 0

Title:

REFUELING OPERATIONS DECAY TIME TEXT 3.9.2 0 11/19/2002 11/19/2002

Title:

REFUELING OPERATIONS COMMUNICATIONS TEXT 3.9.3 1 03/12/2019

Title:

REFUELING OPERATIONS REFUELING PLATFORM TEXT 3.10.1 1 04/26/2006

Title:

MISCELLANEOUS SEALED SOURCE CONTAMINATION TEXT 3.10.2 1 04/09/20'07

Title:

MISCELLANEOUS SHOTDOWN MARGIN TEST RPS INSTRUMENTATION TEXT 3.10.3 4 10/05/2022

Title:

MISCELLANEOUS INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

TEXT 3.10.4 2 04/17/2009

Title:

INTENTIONALLY LEFT BLANK Page 6 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2

.Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT 3.11.1.1 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS LIQUID EFFLUENTS CONCENTRATION TEXT 3 . 11. 1. 2 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS LIQUID EFFLUENTS DOSE TEXT 3 . 11 . 1 . 3 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS LIQUID WASTE TREATMENT SYSTEM TEXT 3.11.1.4 2 10/09/2012

Title:

RADIOACTIVE EFFLUENTS LIQUID RADWASTE EFFLUENT MONITORING INSTRUMENTATION TEXT 3 . 11 . 1. 5 3 03/05/2015

Title:

RADIOACTIVE EFFLUENTS :RADIOACTIVE LIQUID PROCESS MONITORING INSTRUMENTATION

  • *'EXT r3 .11.2 .1 4 03/12/2019

Title:

RADIOACTIVE EFFLUENTS DOSE RATE TEXT 3 . 11. 2 . 2 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS DOSE - NOBLE GASES TEXT 3 . 11. 2 . 3 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS DOSE - IODINE, TRITIUM, AND RADIONUCLIDES IN PARTICULATE FORM TEXT 3.11.2.4 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS GASEOUS RADWASTE TREATMENT SYSTEM TEXT 3.11.2.5 4 07/03/2013

Title:

RADIOACTIVE EFFLUENTS VENTILATION EXHAUST TREATMENT SYSTEM TEXT 3.11.2.6 8 07/21/2017

Title:

RADIOACTIVE EFFLUENTS RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION TEXT 3.11.3 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS TOTAL DOSE

~

Page 7 of 15 Report Date: 12/08/22

SSES MANUAL

\

Manual Name: TRM2 ra.nual

Title:

TECHNICAL REQUIREMENTS MANOAL UNIT 2 TEXT 3 . 11. 4 . 1 5 01/03/2022

Title:

RADIOACTIVE EFFLUENTS MONITORING PROGRAM TEXT 3 . 11. 4 . 2 2 04/26/2006

Title:

RADIOACTIVE EFFLUENTS LAND USE CENSUS TEXT 3 . 11. 4 . 3 1 04/26/2006

Title:

RADIOACTIVE EFFLUENTS INTERLABORATORY COMPARISON PROGRAM TEXT 3.12.1 . 0 11/19/2002

Title:

LOADS CONTROL PROGRAM CRANE TRAVEL.SPENT FUEL STORAGE POOL TEXT 3.12.2 4 04/17/2008

Title:

LOADS CONTROL PROGRAM HEAVY LOADS REQUIREMENT*s

.'EXT 3 .12. 3 0 11/19/2002

Title:

LOADS CONTROL PROGRAM LIGHT LOADS REQUIREMENTS TEXT 4.1 0 09/27/2003

Title:

ADMINISTRATIVE CONTROLS ORGANIZATION TEXT 4.2 1 01/03/2019

Title:

ADMINISTRATIVE CONTROLS REPORTABLE EVENT ACTION TEXT 4.3 1 01/03/2019

Title:

ADMINISTRATIVE CONTROLS SAFETY LIMIT VIOLATION TEXT 4.4 1 12/18/2008

Title:

ADMINISTRATIVE CONTROLS PROCEDURES & PROGRAMS TEXT 4.5 1 07/01/2021

Title:

ADMINISTRATIVE CONTROLS REPORTING REQUIREMENTS TEXT 4.6 0 09/27/2003

Title:

ADMINISTRATIVE CONTROLS RADIATION PROTECTION PROGRAM Page 8 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name I TRM2

.Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT 4.7 0 09/27/2003

Title:

ADMINISTRATIVE CONTROLS TRAINING TEXT B3.0 7 03/18/2021

Title:

APPLICABILITY BASES TECHNICAL REQUIREMENT FOR OPERATION (TRO) APPLICABILITY TEXT B3 .1.1 2_ 04/29/2014

Title:

REACTIVITY CONTROL SYSTEM BASES ANTICIPATED TRANSIENT WITHOUT SCRAM ALTERNATE ROD INJECTION (ATWS-ARI) INSTRUMENTATION TEXT B3.l.2 0 11/19/2002

Title:

REACTIVITY CONTROL SYSTEM BASES CONTROL ROD DRIVE (CRD) HOUSING SUPPORT TEXT B3.l.3 4 12/18/2017

Title:

REACTIVITY CONTROL SYSTEM BASES CONTROL ROD BLOCK INSTRUMENTATION

  • .'EXT B3.l.4 1 10/12/2020

Title:

REACTIVITY CONTROL SYSTEM BASES CONTROL ROD SCRAM ACCUMOLATORS INSTRUMENTATION AND CHECK VALVE TEXT B3.2.l 0 11/19/2002

Title:

CORE OPERATING LIMITS BASES CORE OPERATING LIMITS REPORT (COLR)

TEXT B3.3.l 1 01/31/2014

Title:

INSTRUMENTATION BASES RADIATION MONITORING INSTRUMENTATION TEXT B3.3.2 2 03/31/2011

Title:

INSTRUMENTATION BASES SEISMIC MONITORING INSTRUMENTATION TEXT B3.3.3 2 11/09/2007

Title:

INSTRUMENTATION BASES METEOROLOGICAL MONITORING INSTRUMENTATION TEXT B3.3.4 7 07/21/2017

Title:

INSTRUMENTATION BASES TRM POST ACCIDENT MONITORING (PAM) INSTRUMENTATION TEXT B3 3 5 0 2 11/09/2007

  • Titl~: INSTRUMENTATION BASES THIS PAGE INTENTIONALLY LEFT BLANK Page 9 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2 Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 03/05/2019 TEXT B3.3.6 6

Title:

INSTRUMENTATION BASES TRM ISOLATION ACTUATION INSTRUMENTATION TEXT B3.3.7 4 01/17/2022

Title:

INSTRUMENTATION BASES MAIN TURBINE OVERSPEED PROTECTION SYSTEM TEXT B3.3.8 1 10/22/2003

Title:

INTENTIONALLY BLANK TEXT B3.3.9 4 01/03/2019

Title:

INSTRUMENTATION BASES LPRM UPSCALE ALARM INSTRUMENTATION TEXT B3 .. 3. 10 3 02/22/2012

Title:

INSTRUMENTATION BASES REACTOR RECIRCULATION PUMP MG SET STOPS

.'EXT B3. 3 .11 1 10/22/2003

Title:

INSTRUMENTATION BASES MVP ISOLATION INSTRUMENTATION TEXT B3.3.12 1 04/02/2019

Title:

WATER MONITORING INSTRUMENTATION TEXT B3.4.l 0 11/19/2002

Title:

REACTOR COOLANT SYSTEM BASES REACTOR COOLANT SYSTEM CHEMISTRY

/'

TEXT B3.4.2 1 04/16/2009

Title:

REACTOR COOLANT SYSTEM BASES STRUCTURAL INTEGRITY TEXT B3.4.3 1 11/09/2007

Title:

REACTOR COOLANT SYSTEM BASES HIGH/LOW PRESSURE INTERFACE LEAKAGE MONITOR TEXT B3.4.4 1 01/03/2019

Title:

REACTOR COOLANT SYSTEM BASES REACTOR RECIRCULATION FLOW AND ROD LINE LIMIT 11/19/2002 TEXT B3.4.5 0

Title:

REACTOR COOLANT SYSTEM BASES REACTOR VESSEL MATERIALS Page 10 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2

.Ianual Title1 TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT B3.4.6 2 01/03/2019

Title:

REACTOR RECIRCULATION SINGLE LOOP OPERATION SLO FLOW RATE RESTRICTION TEXT B3.5.l 2 03/17/2020

Title:

ECCS RPV WATER INVENTORY CONTROL AND RCIC SYSTEM ADS MANUAL INHIBIT TEXT B3.5.2 2 03/05/2019 Title1 ECCS RPV WATER INVENTORY CONTROL AND RCIC SYSTEM ECCS RPV WATER INVENTORY CONTROL AND RCIC MONITORING INSTRUMENTATION TEXT B3.5.3 2 03/05/2019

Title:

ECCS RPV WATER INVENTORY CONTROL AND RCIC SYSTEM LONG TERM NITROGEN SUPPLY TO ADS TEXT B3.6.l 0 11/19/2002

Title:

CONTAINMENT BASES VENTING OR PURGING

  • .'EXT B3 . 6 . 2 0 11/19/2002

Title:

CONTAINMENT BASES SUPPRESSION CHAMBER-TO-DRYWELL VACUUM BREAKER POSITION INDICATION TEXT B3.6.3 I 1 04/19/2007

Title:

CONTAINMENT BASES SUPPRESSION POOL ALARM INSTRUMENTATION TEXT B3.6.4 1 12/14/2004

Title:

CONTAINMENT BASES PRIMARY CONTAINMENT CLOSED SYSTEM BOUNDARIES TEXT B3.7.l 0 11/19/2002

Title:

PLANT SYSTEMS BASES EMERGENCY SERVICE WATER SYSTEM (SHOTDOWN)

TEXT B3.7.2 0 11/19/2002

Title:

PLANT SYSTEMS BASES ULTIMATE HEAT SINK (UHS) GROUND WATER LEVEL TEXT B3.7.3.l 4 02/16/2017

Title:

PLANT SYSTEMS BASES FIRE SUPPRESSION WATER SUPPLY SYSTEM TEXT B3.7.3.2 2 04/26/2006

Title:

PLANT SYSTEMS BASES SPRAY AND SPRINKLER SYSTEMS Page 11 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2 lanual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT B3.7.3.3 0 11/19/2002

Title:

PLANT SYSTEMS BASES CO2 SYSTEMS TEXT B3.7.3.4 3 06/19/2019

Title:

PLANT SYSTEMS BASES HALON SYSTEMS TEXT B3.7.3.5 1 04/26/2006

Title:

PLANT SYSTEMS BASES FIRE HOSE STATIONS TEXT B3.7.3.6 1 04/26/2006

Title:

PLANT SYSTEMS BASES YARD FIRE HYDRANTS AND HYDRANT HOSE HOUSES TEXT B3.7.3.7 0 11/19/2002

Title:

PLANT SYSTEMS BASES FIRE RATED ASSEMBLIES

_'EXT B3. 7. 3. 8 3 09/27/2012

Title:

PLANT SYSTEMS BASES FIRE DETECTION INSTRUMENTATION TEXT B3.7.4 0 11/19/2002

Title:

PLANT SYSTEMS BASES SOLID RADWASTE SYSTEM TEXT B3.7.5.l 0 11/19/2002

Title:

PLANT SYSTEMS BASES MAIN CONDENSER OFFGAS HYDROGEN MONITOR TEXT B3.7.5.2 0 11/19/2002

Title:

PLANT SYSTEMS BASES MAIN CONDENSER OFFGAS EXPLOSIVE GAS MIXTURE TEXT B3.7.5,3 0 11/19/2002

Title:

PLANT SYSTEMS BASES LIQUID HOLDUP TANKS TEXT B3.7.6 4 06/04/2013

Title:

PLANT SYSTEMS BASES ESSW PUMPHOUSE VENTILATION TEXT B3.7.7 2 01/31/2008

Title:

PLANT SYSTEMS BASES MAIN CONDENSER OFFGAS PRETREATMENT LOGARITHMIC RADIATION MONITORING INSTRUMENTATION Page 12 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2

.ranual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT B3.7.8 4 . 01/31/2014 J

Title:

PLANT SYSTEMS BASES SNUBBERS TEXT B3.7.9 3 03/05/2019

Title:

PLANT SYSTEMS BASES CONTROL STRUCTURE HVAC

(

TEXT B3.7.10 1 12/14/2004

Title:

PLANT SYSTEMS BASES SPENI' FUEL STORAGE POOLS TEXT B3.7.11 3 11/01/2018

Title:

STRUCTURAL INTEGRITY TEXT B3.8.1 2 03/10/2010

Title:

ELECTRICAL POWER BASES PRIMARY CONTAINMENT PENETRATION CONDUCTOR OVERCORRENT PROTECTIVE DEVICES

  • *'EXT B3 . 8 ." 2 . 1 0 11/19/2002

Title:

ELECTRICAL POWER BASES MOTOR OPERATED VALVES (MOV) THERMAL OVERLOAD PROTECTIO~ -

CONTINUOUS TEXT B3.8.2.2 2 06/23/2021

Title:

ELECTRICAL POWER BASES MOTOR OPERATED VALVES (MOV) THERMAL OVERLOAD PROTECTION -

AUTOMATIC TEXT B3.8.3 0 11/19/2002

Title:

.ELECTRICAL POWER BASES DIESEL GENERATOR (DG) MAINTENANCE ACTIVITIES TEXT B3.8.4 'O 11/19/2002

Title:

ELECTRICAL POWER BASES 24 VDC ELECTRICAL POWER,SUBSYSTEM TEXT B3.8.5 1 11/14/2013

Title:

ELECTRICAL POWER BASES DEGRADED VOLTAGE PROTECTION TEXT B3.8.6 4, 03/05/2019

Title:

ELECTRICAL POWER BASES EMERGENCY SWITCHGEAR ROOM COOLING TEXT B3.8.7 3 02/25/2021

Title:

BATTERY MAINTENANCE AND MONITORING PROGRAM Page 13 of 15 Report Date: 12/08/22

SSES MANUAL Manual Name: TRM2 Ianual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT B3.9.l 0 11/19/2002

Title:

REFUELING OPERATIONS BASES DECAY TIME TEXT B3.9.2 0 11/19/2002

Title:

REFUELING OPERATIONS BASES COMMUNICATIONS TEXT B3.9.3 1 03/12/2019

Title:

REFUELING *OPERATIONS BASES REFUELING PLATFORM TEXT B3.10.l 0 11/19/2002

Title:

MISCELLANEOUS BASES SEALED SOURCE CONTAMINATION TEXT B3.10.2 1 04/10/2007

Title:

MISCELLANEOUS BASES SHUTDOWN MARGIN TEST RPS INSTRUMENTATION

.'EXT B3 .10. 3 1

3 10/05/2022

Title:

MISCELLANEOUS BASES INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

TEXT B3 . 11 . 1. 1 05/10/2016

Title:

RADIOACTIVE EFFLUENTS BASES LIQUID EFFLUENTS CONCENTRATION TEXT B3 .11.1. 2 0 11/19/2002'

Title:

RADIOACTIVE EFFLUENTS BASES LIQUID EFFLUENTS DOSE TEXT B3 .11.1. 3 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES LIQUID WASTE TREATMENT SYSTEM TEXT B3. 11. 1. 4 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES LIQUID RADWASTE EFFLUENT MONITORING INSTRUMENTATION TEXT B3 .11.1. 5 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES RADIOACTIVE LIQUID PROCESS MONITORING INSTRUMENTATION TEXT B3 .11. 2 .1 1 12/14/2004

Title:

RADIOACTIVE EFFLUENTS BASES DOSE RATE Page 14 of 15 Report Date: 12/08/22

t SSES MANUAL Manual Name: TRM2

  • lanual

Title:

TECHNICAL REQUIREMENTS MANUAL UNIT 2 TEXT B3.ll.2.2 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES DOSE - NOBLE GASES TEXT B3.ll.2.3 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES DOSE - IODINE, TRITIUM, AND RADIONUCLIDES IN PARTICOLATES FORM TEXT B3 .11. 2. 4 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES GASEOUS RADWASTE TREATMENT SYSTEM TEXT B3 .11. 2. 5 5 07/03/2013

Title:

RADIOACTIVE EFFLUENTS BASES VENTILATION EXHAUST TREATMENT SYSTEM TEXT B3 .11. 2. 6 2 09/08/2016

Title:

RADIOACTIVE EFFLUENTS BASES RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION

  • *'EXT B3.ll.3 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES TOTAL DOSE TEXT B3.ll.4.l 6 01/03/2022

Title:

RADIOACTIVE EFFLUENTS BASES MONITORING PROGRAM TEXT B3.ll.4.2 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES LAND USE CENSUS TEXT B3.ll.4.3 0 11/19/2002

Title:

RADIOACTIVE EFFLUENTS BASES INTERLABORATORY COMPARISON PROGRAM TEXT B3.12.l 1 10/04/2007

Title:

LOADS CONTROL PROGRAM BASES CRANE TRAVEL-SPENT FUEL STORAGE POOL

";"\

TEXT B3.12.2 1 12/03/2010

Title:

LOADS CONTROL PROGRAM BASES HEAVY LOADS REQUIREMENTS TEXT B3.12.3 0 11/19/2002

Title:

LOADS CONTROL PROGRAM BASES LIGHT LOADS REQUIREMENTS Page 15 of 15 Report Dati: 12/08/22

Instrument Trip Setpoint Program Rev. 12 2.2

  • 2.0 2.2 PLANT PROGRAMS AND SETPOINTS Instrument Trip Setpoint Table The Instrument Trip Setpoint Limits in Table 2.2-1 are the Trip Setpoint value limits that were contained in the Instrumentation Setpoint tables for protection systems and other functions important to safety that were included in the scope of the original Standard Technical Specifications. Actual instrument setpoints are established utilizing the Allowable Values specified in the Technical Specifications .and Technical Requirements.

Allowable Values are established in the Reference LCOs and TROs identified in this Table. TRO references are enclosed in square brackets.

Instrumentation process setpoints for the listed subsystems and trip functions are set consistent with the Trip Setpoint Limit Column of Table 2.2-1. Actual setpoints are established in accordance with engineering procedures.

Alarm setpoints and other non-protection system tr~p settings as may be fourid in the Technical Specifications or in the Technical Requirements are not included in this table.

Reference:

MFP-QA-1220, Engineering Change Process Handbook

  • SUSQUEHANNA - UNIT 2 TRM /2.0-5

Instrument Trip Setpoint Program Rev. 12 2.2

  • TABLE 2.2-1 (Page 1 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO TRIP FUNCTION TRIP SETPOINT 2.2.1 Reactor Protection 2.2,1.1 3.3.1.1 Intermediate Range Monitor, Nei.!tror:r Flux -  ::; 120/125 divisions of full scale High 2.2.1.2 3.3.1.1 Average Power Range Monitor, Neutron  ::; 18% of RATED THERMAL POWER Flux - High (Setdown) 2.2.1.3 3.3.1.1 Average Power Range Monitor, Simulated 0.55 W + 58.7%

Thermal Power - High Two Loop Operation 2.2.1.4 3.3.1.1 Average Power Range Monitor, Simulated 0.55 0/v- l:!.W) + 58.7%(b)

Thermal Power - High Single Loop Operation 2.2.1.5 3.3.1.1 Average Power Range Monitor, Simulated  ::; 113.5% of RATED THERMAL Thermal Power - High flow Clamp POWER 2.2.1.6 3.3.1.1 Average Power Range Monitor, Neutron Flux -  ::; 118% of RATED THERMAL High PO'NER 2.2.1.7 3.3.1.1 Reactor Vessel Stearn Dome Pressure - High  ::; 1087 psig 2.2.1.8 3.3.1.1 Reactor Vessel Water Level - Low, Level 3  :?: 13.0 inches(a) 2.2.1.9 3.3.1.1 Main Steam Isolation Valve - Clos1:1re  ::; 10% closed 2.2.1.10 This Section Not Used 2.2.1.11 3.3.1.1 Drywell Pressure - High  ::; 1.72 psig 2.2.1.12 3.3.1.1 Scram Discharge Volume Water l:..evel -  ::; 65 gallons High - Level Transmitter 2.2.1.13 3.3.1.1 Scram Discharge Volume Water Level -  ::; 61 gallons High - Float $witch 2.2.1.14 3.3.1.1 T1:1rbine Stop Valve - Closure  :$; 5.5% closed 2.2.1.15 3.3.1.1 Turbine Control Valve Fast Closure, Trip  :?: 500 pslg Oil Pressure - Low (s) See Figure 2.2-1.

(bl For single loop operation, the value of l:!.W = 8.7.

SUSQUEHANNA - UNIT 2 TRM / 2.a-6

Instrument Trip Setpoint Program Rev. 12 2.2 TABLE 2.2-1, (Page 2 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO] TRIP FUNCTION TRIP SETPOINT 2.2.1.16 OPRM Instrumentation 2.2.1.16.1 3.3.1.1 Sp PBA Amplitude Trip See COLR - TRO 3.2 2.2.1.16.2 3.3.1.1 Np PBA Successive Confirn,atJon Count Trip See COLR - TRO 3 2 2.2.1.16.3 [3'.3.9] TOL (E) Period Tolerance 0.10 sec 2.2.1.16.4 [3.3.9] fc Conditioning Filter Cutoff F:requency 1.50 Hz 2.2.1.16:5 [3.3.9] Tmin Oscillation Period Lower Time Limit 1.00 sec 2.2.1.16.6 [3.3.9] Tmax Osallation Period Upper Time Limit 3.50 sec 2.2.1.16.7 [3.3.9] LPRMmin Minimum LRPMs/Cell Required for 2 Cell Operability 2.2.1.16.8 [3.3.9] S1 Peak Threshold Setpolnt/ABA & GRBA 1.20 2.2.1.16.9 [3.3.9] S2 Valley Threshold Setpo1nt/ABA & GRBA 0.85 2.2.1.16.10 [3.3.9] Smax Amplrtude Trip Setpoint/ABA 1.50 2.2.1.16.11 [3.3.9] DR3 Growth Rate Factor Setpolnt/GRBA 1.60 2.2.2 Isolation Actuation Instrumentation 2.2.2.1 Primary Cornainment Isolation 2.2.2.1.1 3.3.6.1 Reactor Vessel Water Level LO'N, Level 3 ~ 13.0 inches<0 l 2.2.2.1.2 3.3.6.1 Reactor Vessel Water Level Low Low, Level 2 ~ -38.0 lnches<e) 2.2.2.1.3 3.3.6.1 Reactor Vessel Water Level Low Low Low, ~ -129 lnches(e)

Level 1 2.2.2.1.4 3.3.6.1 Drywall Pressure - High  ;.:; 1.72 psig 22.2.1.5 3.3.6.1 SGTS Exhaust Radiation - High :5 23.0 mR/hr 2.22.1.6 [3.3.6] Main Steam Line Radiati6n - High High  ;.:; 15 x full power background wtthout hydrogen injection (a) See Figure 2.2-1.

SUSQUEHANNA - UNIT 2 TRM /2.0-7

Instrument Trip Setpoint Program Rev. 12 2.2 TABLE 2.2-1 (Page 3 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [fRO] TRIP FUNCTION TRIP SETPOINT 2.222 Secondary Containmem Isolation 2.2.2.2.1 3.3 6.2 Reactor Vessel Water Level - Low Low, ~ -38.0 inches(a)

Level2 2.2.2.2.2 3.3.6.2 Drywall Pressure - High s 1.72 psIg 2.2 2.2.3 3.3 6.2 Refuel Floor High Exhaust Duct Radiation - s 18 mR/hr High 2.2.2.2.4 3 3.6.2 Railroad Access Shaft Exhaust Duct Radiation - s 5 mR/hr High 2.2.2.2.5 3 3.62 Refuel Floor Wall Exhaust Duct Rad1abon - s 21 mR/hr High 2.22 3 Main Steam Line Isolation 2.2.2.3.1 3.3.61 Reactor Vessel Water Level - Low Low Low, ~ -129 mches(a)

I.

Level 1 2.2 2.3.2 3.3.6.1 Main Steam Line Pressure - Low ~ 861 psig 2.2.2.3.3 3 3 6.1 Main Steam Line Flow - High s 173 psid 2.2.2 3.4 3.3.6.1 Condenser Vacuum - Low ~ 9.0 inches Hg vacuum 2.2.2.3.5 3.3.6.1 Reactor Building Mam Steam Lme Tunnel s 177°F Temperature - High 2.2.2.3.6 This Section Not lJsed 2 2.2 3.7 This section is not used.

2.2.2.3.8 [3 3.6] Turt:Jme Building Main Steam Tunnel s 197°F Temperature - High 2.2 2.4 Reactor Water Cleanup System Isolation 2.2.2.4.1 3.3 6.1 Reactor Vessel Water Level - Low Low, ~ -38 inches(a)

Level2 2.2 2.4.2 3 3.6.1 RWCU 11 Flow - High s 59 gpm 2.2.2.4 3 3.3.61 RWCU Flow - High s 462 gpm 2 2.2 4.4 3.3.61 RWCU Penetration Area Temperature - High s 131°F 2 2.2.4.5 This sectJon Is not used 2.2 2.4.6 3.3.6.1 RWCU Pump Area Temperature - High s 147°F 2.2 2.4 7 This section is not used 2.2 2.4.8 3.3.6.1 RWCU Heat Exchanger Area Temperature - s 147°F High 2 2.2 4.9 This section is not used.

(al See Figure 2.2-1.

SUSQUEHANNA - UNIT 2 TRM / 2.0-8

Instrument Trip Setpoint Program Rev. 12 2.2 TABLE 2.2-1 (Page 4 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [fRO] TRIP FUNCTION TRIP SETPOINT 2.2 2.5 Reactor Core Isolation Cooling System Isolation 2.2.2.5.1 3.3.6.1 RCIC Steam Line 11 Pressure - High s 138 Inches H20 2.2.2.5.2 3.3.6.1 RCIC Steam Supply Line Pressure - Low ~ 60 pslg 2.2.2.5.3 3.3.6.1 RCIC Turbine Exhaust Diaphragm Pressure - s 10.0 pslg High 2.2.2.5.4 3.3.61 RCIC Equipment Room Temperature - High s 167°F 2.2.2.5.5 3.3.6.1 RCIC Pipe Routing Area Temperature - High s 167"F 2.2.2.5.6 3.3.6.1 RCIC Emergency Area Cooler Temperature - s 167°F High 2.2.2.5.7 3.3.6.1 Drywall Pressure - High s 1.72 psig 2.2.2.6.8 This section is not used.

2.2.2.5.9 This section Is not used.

2.2.2.6 High Pressure Coolant Injection System Isolation 2.2.2.6.1 3.3.6.1 HPCI Steam Line /1 Pressure - High s 370 inches H20 2.2.2.6.2 3.3.6.1 HPCI Steam Supply Line Pressure - Low ~ 104 psig 2.2.2.6.3 3.3.6.1 HPCI Turbine Exhaust Diaphragm Pressure - s 10 psig High 2.22.6.4 3.3.6.1 HPCI Equipment Room Temperature - High s 167°F 2.2.2.6.5 3.3.6.1 HPCI Emergency Area Cooler Temperature - s 167°F High 2.2.2.6.6 3.3.6.1 HPCI Pipe Routing Area Temperature - High s 167°F 2.2.2.6.7 3.3.6.1 Drywall Pressure - High s 1.72 psig 2.2.2.6.8 This section is not used.

2.2.2.6.9 This section is not used.

2.2.2.7 Shutdown Cooling/System Isolation 2.2.2.7.1 3.3.6.1 Reactor Vessel Water Level - Low, Level 3 ~ 13.0 lnches<al 2.2.2.7.2 3.3.6.1 Reactor Vessel Steam Dome Pressure - High s 98 psig 2.2.2.7.3 [3.3.6] RHR Flow - High s25,000 gpm 2.2.3 ECCS Actuation 2.2.3.1 Core Spray System 2.2.3.1.1 3.3.5.1 Reactor Vessel Water Level - Low Low Low, ~ -129 inches<al Level 1 2.2.3.1.2 3.3.5.1 Drywall Pressure - High s 1.72 psig 2 2.3.1.3 3.3.5.1 Reactor Vessel Steam Dorne Pressure - Low ~ 396.5, s 428.5 psig injection permissive

  • {al See Figure .2.2-1.

SUSQUEHANNA - UNIT 2 TRM / 2.0-9

Instrument Trip Setpoint Program Rev. 12 2.2

  • TABLE 2.2-1 (Page 5 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO] TRIP FUNCTION TRIP SETPOINT 2.2.3.2 LPCI Mode of RHR System 2.2.32.1 3.3.5.1 Reactor Vessel Water Level - Low Low Low,  ;::,: -129 inches(9 l Level 1 2.2.32.2 3.3.5.1 Drywall Pressure - High ~ 1.72 psig 2.2 3.2.3 3.3.5.1 Reactor Vessel Steam Dome Pressure - Low,  ;::,: 396.5, ~ 428.5 psig lnJectlon permissive 2.2.3.2.4 3.3.5.1 Reactor Vessel Steam Dome Pressure - Low,  ;::,: 236 pslg, decreasing Recirculation Discharge Valve pennlssive 2.2.3.3 HPCI System

.2 2.3.3.1 3.3.5.1 Reactor Vessel Water Level - Low Low,  ;::,: -38 lnches(a)

Level2 2.2 3.3.2 3.3.5.1 Drywall Pressure - High. ~ 1.72 pslg 2.2.3.3.3 3.3.5.1 Condensate Storage Tank Level - Low  ;::,: 40.5 inches above tank bottom 2.2.3.3.4 3.3.5.1 Reactor Vessel Water Level - High, Level 8 ~ 54 Inches 2.2.3.4 Automatic Depressurization System (ADS) 2.2.3.4.1 3.3.5.1 Reactor Vessel Water Level - Low Low Low, ~ -129 inches Level 1 2.2.3.4.2 3.3.5.1 Drywall Pressure - High ~ 1.72 pslg 2.2.3.4.3 3.3.5.1 ADS llmer ~ 102 seconds 2.2.34.4 3.3.5.1 Core Spray Pump Discharge Pressure - High  ;::,: 135, ~ 155 psig 2.2.3.4.5 3.3.5.1 Low Pressure Coolant Injection Pump  ;::,: 121, ~ 129 psig Discharge Pressure - High 2.2.3.4.6 3.3.5.1 Reactor Vessel Water Level - Low, Level 3  ;::,: 13 inches Confirmatory 2.2.3.4.7 3.3.5.1 ADS Drywall Pressure Bypass "fimer ~ 420 seconds 2.2.3.5 Loss of Power - ECCS Actuation 2.2.3.5.1 4.16kv ESS Bus Undervoltage (Loss of Voltage < 20%)

2.2.3.5.1.1 3.3 8.1 Bus Undervottage  ;::,: 823.2, ~ 856.8 Volts 2.2 3.5.1 2 3.3.8.1 Time delay ~ 0.4, ~ 0.6 seconds 11

( ) See Figure 2.2-1 .

  • SUSQUEHANNA - UNIT 2 TRM / 2.0-10

Instrument Trip Setpoint Program Rev. 12 2.2

  • TABLE 2.2-1 (Page 6 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO] TRIP FUNCTION TRIP SETPOINT 2.2.3.52 4.16kV ESS Bus Undervoltage (Degraded Voltage< 65%)

2.2.3.5.21 3.3.8.1 Bus Undervoltage ~ 2641.1,::;; 2748.9 Volts 2.2.3.52 2 3.3.8.1 T1me delay ~ 2.7,:,; 3.3 seconds 22.3.5.3 4.16kV ESS Bus Undervoltage (Degraded Voltage,< 93%)

2.2.3.5.3.1 3.3.8.1 Bus Undervoltage 2 3829.3,::;; 3906.7 Volts 2.2.3.5.3.2 3.3 8.1 Time Delay (Non-LOCA) 2 4 minute, 30 seconds

,; 5 minute, 30 secomds 22.3.5.3.4 3.3.8.1 Time Delay (LOCA) 2 9,:,; 11 seconds 2.2.3.5.4 480V ESS Bus 08565 Undervoltage (Degraded Voltage,< 65%)

2.2.3.5.4.1 [3.8.5] 480V Basis 2 308.9,::;; 315.1 Volts 2.2.3.5.4.2 t3 8.5] Tlme Delay 2 4.5,:,; 5.5 seconds 2.2.3.5 5 480V ESS Bus 08565 Undervoltage (Degraded Voltage, < 92%)

2.2.3.5.5.1 [3.8.5] 480V Basis 2 437.6, :,; 446.4 Volts 2.2.3.5.5.2 [3.8.5] Time Delay 2 9, :,; 11 seconds 2.2.4 ATW$ Alternate Rod Injection and Rech:culation Pump Trip 2.2.4.1 3.3.4.2/[3.1.1] Reactor Vessel, Water Level - Low Low, 2 -38 Inches(&)

Level2 2.2.4.1 3.3.4.2/[3.1.1] Reactor Vessel Steam Dome Pressure - High  ::;; 1135 pslg 2.2.5 End of Cycle Recirculation Pump Trip 2.2.5.1 3.3.4.1 Turbine Stop Valve-Closure  ::;; 5 5% closed 2.2.52 3.34.1 Turbine Cor1trol Valve - Fast Closure 2 500 pslg 2.2.6 Reactor Core Isolation Cooling System Actuation 2.2.6.1 3.3.5.2 Reactor Vessel Water Level - Low Low, ~ -38 inches(al Level2 2.2.6.2 3.3.5.2 Reactor Vessel Water Level - High, Level 8  ::;; 54 lnches(aJ 2.2.6.3 3.3.5.2 Condensate Storage Tank Level- Low 2 36.0 inches above tank bottom (el See Figure 2.2-1 .

  • SUSQUEHANNA - UNIT 2 TRM / 2.0-11

Instrument Trip Setpoint Program Rev. 12 2.2 TABLE 2.2-1 (Page 7 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO] TRIP FUNCTION TRIP SETPOINT 22.7 Control Rod Block 2.2.7.1 Rod Block Monitor 2 2.7.1.1 3.3.2 Low Power Range - Upscale See COLR - TRO 3.2 3.3.2 Intermediate PoWer Range - Upscale See COLR - TRO 3.2 3.3.2 High Power Range - Upscale See COLR - TRO 3.2 2.2.7.1.2 3.3.2 Low Power Range Setpoint See COLR - TRO 3.2 3.3.2 Intermediate Power Range Setpolnt See COLR-TRO 3.2 3.3.2 High Power Range Setpoint See COLR - TRO 3.2 2.2.7.2 APRM 2.2.72.1 [3.1.3] Simulated Thermal Power-High - Two Loop 0.55 W + 54.2%

Operation 2.2.7.2.2 [3.1.3] Simulated Thermal Power-High - Single Loop 0.55 0/11- [),,W) + 54.2%(c)

Operation 2.2.7.2.3 [3.1.3] Simulated Thermal Power-High Clamp  :-; 108% of RATED THERMAL PO\o\lER 2.2.7.2.4 [3.1.3] Downscale :2: 5% of RATED THERMAL PO\/1/ER 2.2.7.2.5 [3.1.3] Neutron Flux - High (Setdown)  :-; 12% of RATED THERMAL POvVER 2.2.7.3 Source Range Monitors 2.2.7.3.1 [3.1.3] Upscale  :::2E5 cps 2.2.7.3.2 [3 1.3] Dovmscale 2 3.0 cpsCbl 2.2.7.4 Intermediate Range Monitors 2.2.7.4.1 [3.t.3] Upscale  :-; 108/125 divisions of full scale 2.2.7.4.2 [3.1.3] Downscale 2 5/125 dMslons of full scale 2.2.7.5 Scram Discharge Volume 2.2.7.5.1 [3.1.3] Water level - High  ::: 35.9 gallons 2.2.7.6 Reactor Coolant System Recirculation Flow 2.2.7.6.1 [3.1.3] Upscale 114%

Cbl With a signal-to-noise ratio 2 2, or within the limits of Figure 2.2-2.

(cl For single loop operation, the valve of !:iW = 8.7 .

    • SUSQUEHANNA - UNIT 2 TRM / 2.0-12

Instrument Trip Setpoint Program Rev. 12 2.2 TABLE 2.2-1 (Page 8 of 8)

INSTRUMENTATION SETPOINTS SYSTEM/REFERENCE LCO [TRO] TRIP FUNCTION TRIP SETPOINT 2.2.8 CREOASS 2.2.8.1 3.3.7.1 Main Control Room Outside Air Intake ~ 5 mR/hr Radiation Monitor 2.2.8.1.1 3.3.7.1 Reactor Vessel Water Level - Low Low, ~ -38.0 lnches(a)

Level2 2.2.8.1.2 3.3.7.1 Drywell Pressure - High ~ 1.n pslg 2.2.8.1.3 3.3.7.1 Refuel Floor High Exhaust Duct ~ 18 mR/hr Radiation - High 2.2.8.1.4 3.3.7.1 Railroad Access Shaft Exhaust Duct Radiation ~ 5 mR/hr

-High 2.2.8.1.5 3.3.7.1 Refuel Floor Wall Exhaust Duct ~ 21 mR/hr Radiation - High 2.2.9 Feedwater/Maln Turbine Trip System AcitJatlon 2.2.9.1 3.3.22 Reactor Vessel Level - High ~ 54.0 inch~(a) 2.210 MVP Isolation 2.2.10.1 [3.3.11] Main Steam Line Radiation - High High ~ 15 x full power background without hydrogen injection (a) See Figure 2.2-1

    • SUSQUEHANNA - UNIT 2 TRM /2.0-13

Instrument Trip Setpoint Program Rev. 12 2.2 WATER LEVEL NIIMENCLATLRE f£IGHT A]!(]VE 800 NJ. VESSEL ZERll READit<<i

<IN.)

(8) 581. 5 +54 (7) 366. 5 +39 (4) 'SS7, 5 +30 (3) ~5 +13 (2) 489. s -38

<1) 398. 5 -129 5- MAIN STEAM LINE WIDE RAN'.iE NARROW RM&~

BCJTTIJ4 CF STEAM DRYER SKIRT

+60 +60-+60::c:+60~

(8)

-0

~

HFCI C'i > >J <!S' (7) 39 HI 13 FEED 498. 38 SCRAM

\!ATER CONTRIBUTE (2) INITIATE RCIC, mADS HPCI, ARI TRIP RECIRC PIMPS

-129

=7 (1) INITIATE RHR, CS START DIESEL CClfTRIBUTE m ADS

-150 CLOSE MS IV' S

~IVE FUEL

. .J 181,0-RECIRC INLET RECIRC 161. NlZZLE llllTLET NJZZLE 100 NOTE* SCALE IN INCt£S 50 ABOVE VESSEL Z£RD FIGURE 2. 2-1 REACTOR VESSEL WATER LEVEL SUSQUEHANNA - UNIT 2 TRM / 2.0-14

Instrument Trip Setpoint Program Rev. 12 2.2 Instrument Trip Setpoint Table 2.2 3

2.8 2.6 2.4 2.2 \

2 \

CA 1.8 \

(I...

u

\

1.6 w

~ 1.4 \ Acceptable

~

\

1.2 '

0 ~

u

~

a::::

1

--r--. r-- ........

Cf) 0.8 0.6 Not Acceptable 0.4 0.2 0

2 6 10 14 18 22 26 30 Signal-to-Noise Ratio Figure 2.2-2 Minimum SRM Trip Setpoint Versus Signal~to-Noise Ratio SUSQUEHANNA - UNIT 2 TRM / 2.0~15