MONTHYEARML23291A4242023-10-24024 October 2023 1 to Updated Final Safety Analysis Report, Chapter 7, Section 7.6, All Other Instrumentation Systems Required for Safety ML23292A2122023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 222.1 Through 222.2 PLA-8081, 1 to Updated Final Safety Analysis Report, Questions and Responses 121.1 Through 121.212023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 121.1 Through 121.21 ML23292A2252023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 17, Section 17.1, This Section N/A to FSAR ML23292A2242023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 032.1 Through 032.103 ML23292A2232023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 331.1 Through 331.19 ML23292A2222023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions 321.1 Through 321.7 ML23292A2212023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Response 260.1 ML23292A2202023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 441.1 Through 441.15 ML23292A2182023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 1, Questions 010.1 Through 010.26 ML23292A2152023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 423.1 Through 423.58 ML23292A2142023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 005.1 Through 005.6 ML23292A1982023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 17, Section 17.2, Quality Assurance During the Operations Phase ML23292A2102023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions 313.1 Through 313.9 ML23291A1132023-10-12012 October 2023 Submittal of Revision 71 to Updated Final Safety Analysis Report and Revision 25 to Fire Protection Review Report ML23292A2082023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 422.1 Through 422.4 ML23292A2052023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions 021.01 Through 021.88 ML23292A2042023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 130.1 Through 130.28 ML23292A2032023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 211.1 Through 211.296 ML23292A2012023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 16, Section 16.2, Proposed Final Technical Specifications ML23292A2002023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 18, Responses to TMI Related Requirements ML23292A1992023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 371.1 Through 371.30 ML23292A1952023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 281.1 Through 281.29 ML23292A2132023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 362.1 Through 362.25 ML23292A2092023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 421.1 Through 421.42 ML23292A2162023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 040.1 Through 40.99 ML23292A1942023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Response 361.1 Through 361.5-1 ML23292A1962023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions 123.1 Through 123.9 ML23292A2282023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Question and Response 440.1 ML23292A2112023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 400.1 ML23292A2072023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions 230.1 Through 230.8 ML23292A2022023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Response 112.1 Through 112.10 ML23292A2192023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 231.1 Through 231.5 ML23292A2272023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Figures Referenced in the FSAR Are Withheld Under 10 CFR 2.390 ML23292A2262023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Chapter 16, Section 16.1, Preliminary Technical Specifications ML23292A2062023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 372.1 Through 372.28 ML23292A2172023-10-12012 October 2023 1 to Updated Final Safety Analysis Report, Questions and Responses 410.1 Through 410.13 2023-10-24
[Table view] |
Text
SSES-FSAR QUESTION 442.1 Provide a diagram of the control area that indicates the area designated "at the controls. 11
RESPONSE
Figure 442.1-1 illustrates the area designated "at the controls."
Rev. 46, 06/93 442.1-1
Security-Related Information Figure Withheld Under 10 CFR 2.390 SUSQUEHANNA STEAM ELECTRIC STATION UNITS 1 & 2 FINAL SAFETY ANALYSIS REPORT MAIN CONTROL ROOM FIGURE 442.1-1
Security-Related Information Figure Withheld Under 10 CFR 2.390 SUSQUEHANNA STEAM ELECTRIC STATION UNITS 1 & 2 FINAL SAFETY ANALYSIS REPORT MAIN CONTROL ROOM FIGURE 442.1-1
SSES-FSAR QUESTION 442.2 The description of administrative procedures should include Fire Protection and Temporary Procedures of an administrative nature.
RESPONSE
A revision to FSAR Subsection 13.5.1.3 has been made to include fire protection and temporary procedures as topics addressed by administrative procedures.
Rev. 46, 06/93 442.2-1
SSES-FSAR QUESTION 442,3 Figure 442.1-1, submitted by Revision 4, does not adequately define the "at the controls" area. For example, an operator should not routinely enter areas behind control panels, yet Figure 442.1-1 shows the area behind panel 1Z651 (2Z651) as being "at the controls." It does not appear that an operator would have an unobstructed view of the control panels from this position. Revise Figure 442.1-1 to indicate the surveillance area (an area where continuous attention can be given to reactor operator conditions and to the manipulations at reactor controls) and areas which may be entered by the operator at the controls to verify receipt of an annunciator alarm or initiate corrective action in the event of an emergency. Please note that Regulatory Guide 1.114, "Guidance on Being Operator at the Controls of a Nuclear Power Plant," provides information on this subject.
RESPONSE
Figure 442.1-1 is an accurate description of the control room area defined as "at the controls." Panels 1Z651 and 2Z651 are in fact typers that stand approximately waist-high and in no way obstruct the operator's view at the control panels. The operator has a significant need to have access to the 4 typers in this area to obtain information vital to the safe operation of the plants. Regulatory Guide 1.114 was used extensively in the preparation of the FSAR, and it is our opinion that we are in complete compliance with this publication.
Rev. 46, 06/93 442.3-1