MONTHYEARML24282B0112024-10-29029 October 2024 NRC Letter Issuing Report for September 2024 SRS Sdf Oov ML24297A2552024-02-28028 February 2024 SRMC-CWDA-2024-00016, Rev. 0, Memo: Evaluation of the FY2023 Inventory Update for the Saltstone Disposal Facility ML23176A0092023-05-25025 May 2023 Savannah River Mission Completion LLC, Annual Groundwater Monitoring Report January 12, 2023 ML23024A1062023-04-20020 April 2023 U.S. Nuclear Regulatory Commission Technical Evaluation Report for the 2020 U.S. Department of Energy Savannah River Site’S Saltstone Disposal Facility Performance Assessment ML23080A2852023-03-28028 March 2023 NRC Letter for February 1, 2023, Onsite Observation Visit for the SRS Saltstone Disposal Facility ML24297A2452023-03-0101 March 2023 SRMC-CWDA-2023-00018, Rev. 1, Memo: Siltation and Fouling of Drainage Layers in Final Covers for Waste Containment Systems ML23214A0062023-02-28028 February 2023 SRNL-STI-2022-00593, Revision 0, Results for the September Bimonthly Calendar Year 2022 Tank 50 Salt Solution Sample ML22026A3962022-02-0909 February 2022 U.S. NRC Letter for Fourth Set of RAI Questions for U.S. DOE 2020 SRS Sdf Performance Assessment ML21341A5502021-12-14014 December 2021 Letter - Third Set of Rais for the 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment ML21279A1732021-10-18018 October 2021 NRC Letter Supplementing the NRC Monitoring Plan for the DOE Savannah River Site Saltstone Disposal Facility ML21273A0572021-10-0404 October 2021 NRC Review Schedule for the Review of the DOE 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment ML21242A5102021-09-28028 September 2021 U.S. NRC Letter for Report for August 12, 2021, Onsite Observation Visit to U.S. DOE Savannah River Site Saltstone Disposal Facility ML23268A4512021-06-17017 June 2021 Sc DHEC Approval of DOE SRS Industrial Wastewater Closure Plan for FDB-5 and FDB-6 ML21133A2952021-06-0303 June 2021 Second Request for Additional Information Regarding the 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment ML21312A0832021-05-17017 May 2021 LWDP-SUTP-SSF-177, Rev. 0, Saltstone Disposal Unit 7 Project - Tank Initial Leak Test ML21040A4922021-03-0101 March 2021 Request for Additional Information Regarding the 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment ML23268A4522021-02-25025 February 2021 Sc DHEC Approval of DOE SRS Alternative Grout Request for FDB-5 and FDB-6 ML23268A4502021-02-0303 February 2021 SRR-CWDA-2021-00010 Attachment 1, Technical Justification for Use of Low Slump Concrete and Zero-Bleed Clsm ML20254A0032020-10-0505 October 2020 Preliminary Review of the U.S. Department of Energys Submittal of the 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment ML20148M2012020-07-10010 July 2020 Acknowledgement of the U.S. Department of Energy'S Submittal of the Savannah River Site Saltstone Disposal Facility Performance Assessment for Technical Review and Closure of the April 30, 2012, Type-IV Letter of Concern ML20189A5912020-07-0606 July 2020 WDPD-20-34 DOE Transmittal Letter 2020 Savanna River Site Saltstone Disposal Facility Performance Assessment Rev 0 ML20279A7852020-06-10010 June 2020 SRR-CWDA-2020-00052, Rev. 0, Follow-Up to Tanks 12H and 16H Grouting Operations Document Request in Support of Us NRC F and H Area Tank Farms Monitoring Activities ML23087A0062020-05-0707 May 2020 SRN-19-0082.0, Rev. 0, Clsm Proposed Tcs Hydraulic Conductivity Test ML19143A0842019-08-13013 August 2019 U.S. Nuclear Regulatory Commission March 18 - 19, 2019 Onsite Observation Visit Report for the Savannah River Site Tank Farms ML19150A2952019-08-0505 August 2019 Supplement to the 2013 U.S. Nuclear Regulatory Commission Saltstone Disposal Facility Monitoring Plan ML18311A1842019-02-0606 February 2019 U.S. Nuclear Regulatory Commission August 13-14, 2018, Onsite Observation Visit Report for the Savannah River Site Tank Farms ML20206L1332018-12-13013 December 2018 SRNL-L3200-2018-00177, Design Checking of Porflow Modeling Supporting the Saltstone Performance Assessment - December 2018 ML18219B8592018-11-0101 November 2018 Memorandum: U.S. Nuclear Regulatory Commission July 9 - 11, 2018, Onsite Observation Visit Report for the Savannah River Site Saltstone Disposal Facility ML18235A0682018-10-23023 October 2018 NRC Letter with NRC-DOE Joint Plan for SRS Sdf ML18219B0352018-10-16016 October 2018 Supplement to the 2013 U.S. Nuclear Regulatory Commission Saltstone Disposal Facility Monitoring Plan ML18107A1612018-06-29029 June 2018 NRC Letter Supplementing 2013 NRC Sdf Monitoring Plan Based on January 2018 Trr Recommendations ML18033A0712018-03-0101 March 2018 Clarification of the Number of Monitoring Factors in Both the U.S. Nuclear Regulatory Commission'S 2013 Saltstone Disposal Facility Monitoring Plan and the 2015 Tank Farms Monitoring Plan ML20279A7882016-05-0909 May 2016 SRR-TCR-2016-00007, Tank 12 Grouting Liquid Spill Lessons Learned ML20206L1282015-06-12012 June 2015 SRNL-L3100-2015-00108 Rev 0, SDU2A Core Sample Test Designation - 06-12-2015 ML20206L0332006-10-19019 October 2006 ESH-WPG-2006-00132, Z-Area Industrial Solid Waste Landfill Vault Cracking (U) 2024-02-28
[Table view] |
Text
Mr. Charles Comeau Waste Disposition Programs Division U.S. Department of Energy Savannah River Operations Office P.O. Box A Aiken, SC 29802
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSION AUGUST 12, 2021, ONSITE OBSERVATION VISIT REPORT FOR THE SAVANNAH RIVER SITE SALTSTONE DISPOSAL FACILITY
Dear Mr. Comeau:
The enclosed Onsite Observation Visit (OOV) Report describes the U.S. Nuclear Regulatory Commission (NRC) OOV on August 12, 2021, at the Savannah River Site Saltstone Disposal Facility (SDF). The OOV was conducted in accordance with Section 3116(b) of the Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005 (NDAA), which requires the NRC, in coordination with the NDAA-Covered State, to monitor certain disposal actions taken by the U.S. Department of Energy (DOE) for assessing compliance with the performance objectives set out in Title 10 of the Code of Federal Regulations (10 CFR) Part 61, Subpart C. The five 10 CFR Part 61 Subpart C performance objectives are: §61.40 (General Requirements); §61.41 (Protection of the General Population from Releases of Radioactivity);
§61.42 (Protection of Individuals from Inadvertent Intrusion); §61.43 (Protection of Individuals during Operations); and §61.44 (Stability of the Disposal Site after Closure).
This was the 22nd SDF OOV since the NRC began monitoring the DOE SDF disposal actions under NDAA Section 3116(b) in October 2007. The main activities conducted during the August 2021 SDF OOV were: (1) discuss operating and disposal structure status; and (2) tour the construction of Saltstone Disposal Structure (SDS) 8 and SDS 9. Those OOV activities were consistent with the activities described in the NRC Guidance for the August 2021 SDF OOV dated July 27, 2021 (available via the NRC Agencywide Documents Access and Management System [ADAMS] at Accession No. ML21210A156).
That Guidance was developed using the SDF Monitoring Plan, Rev. 1, dated September 2013 (ADAMS Accession No. ML13100A113) and the five NRC letters to the DOE that supplemented the 2013 SDF Monitoring Plan (ADAMS Accession Nos. ML17097A351, ML18033A071, ML18107A161, ML18219B035, and ML19150A295). The NRC 2013 SDF Monitoring Plan, as supplemented, contains the monitoring areas and monitoring factors established to evaluate performance of the SDF. The August 2021 SDF OOV did not result in any changes from the 2013 SDF Monitoring Plan, as supplemented.
If you have any questions, or need additional information, regarding this OOV Report, please contact Mr. Harry Felsher of my staff at Harry.Felsher@nrc.gov or at (301) 415-6559.
September 28, 2021
C. Comeau In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's ADAMS, accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html.
Sincerely, Patricia K. Holahan, Director Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards Docket No. PROJ0734
Enclosure:
NRC Onsite Observation Visit Report Signed by Holahan, Patricia on 09/28/21
ML21242A509; Ltr ML21242A510 OFFICE NMSS/DUWP
/LLWPB NMSS/DUWP
/RTAB NMSS/PMDA NMSS/DUWP/RTAB NAME HFelsher ARidge MRalph CMcKenney DATE Aug 31, 2021 Aug 31, 2021 Sep 1, 2021 Sep 2, 2021 OFFICE NMSS/DUWP NAME PHolahan DATE Sep 28, 2021