NRC Review Schedule for the Review of the DOE 2020 Savannah River Site Saltstone Disposal Facility Performance Assessment
ML21273A057
Person / Time
Site: PROJ0734
Issue date: 10/04/2021
From: Harry Felsher
NRC/NMSS/DDUWP/LLWPB
To: Comeau C
US Dept of Energy, Savannah River Operations Office
Harry Felsher, 301-415-6559
References
Download: ML21273A057 (3)


Text

October 4, 2021 Mr. Charles Comeau Waste Disposition Programs Division U.S. Department of Energy Savannah River Operations Office P.O. Box A Aiken, SC 29802

SUBJECT:

REVIEW SCHEDULE FOR THE REVIEW OF THE U.S. DEPARTMENT OF ENERGYS 2020 SAVANNAH RIVER SITE SALTSTONE DISPOSAL FACILITY PERFORMANCE ASSESSMENT

Dear Mr. Comeau:

The U.S. Nuclear Regulatory Commission (NRC) staff is providing the schedule for its review of the 2020 U.S. Department of Energy (DOE) Savannah River Site (SRS) Saltstone Disposal Facility (SDF) Performance Assessment (PA). By letter dated October 5, 2020, the NRC sent a Preliminary Review Letter (see the NRCs Agencywide Documents Access and Management System [ADAMS] Accession No. ML20254A003) to the DOE. The Enclosure to that NRC Letter provided the NRC staff Request for Supplemental Information (RSI) Comments. That NRC Letter included: Due to the need for the supplemental information about the SDF and uncertainty when the DOE will provide the supplemental information to the NRC, the NRC will not provide a review schedule at this time. After receiving the supplemental information, the NRC will develop a project schedule for the review and provide the schedule to the DOE and South Carolina.

The DOE provided four Responses to the NRC RSI Comments on November 18, 2020, March 30, 2021, June 8, 2021, and August 3, 2021 (ADAMS Accession Nos. ML21159A059, ML21089A119, ML21160A059, and ML21217A076). Following the direction in that NRC Preliminary Review Letter, now that the DOE has provided all the Responses to the NRC RSI Comments, and now that the NRC staff has reviewed those DOE Responses, the NRC is providing the following Review Schedule for the 2020 DOE SRS SDF PA to the DOE:

NRC Review Schedule for the 2020 DOE SRS SDF PA (Rev. 0)

MILESTONE DATE NRC Received Final DOE Response to the NRC RSI Comments 08/03/2021 NRC Issues Request for Additional Information (RAI) Questions Set #3 12/31/2021 NRC Issues RAI Questions Set #4 02/21/2022 DOE Provides Final Responses to RAI Questions Set #3 03/30/2022 DOE Provides Final Responses to RAI Questions Set #4 05/23/2022 NRC Issues Letter with enclosed Technical Evaluation Report 04/04/2023

C. Comeau In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC Web site at https://www.nrc.gov/readingrm/adams.html.

If you have any questions regarding the SDF PA Review, then please contact me at 301-415-6559 or via e-mail at Harry.Felsher@nrc.gov.

Sincerely, Signed by Felsher, Harry on 10/04/21 Harry D. Felsher, Sr. Project Manager Low-Level Waste and Projects Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Materials Safety and Safeguards Docket No. PROJ0734 cc: WIR ListServ

Ltr ML21273A057 NMSS/DUWP NMSS/DUWP NMSS/DUWP OFFICE NMSS/DUWP/RTAB

/LLWPB /RTAB /LLWPB NAME HFelsher HF ARidge AR CMcKenney CM MRalph MR DATE Oct 1, 2021 Oct 4, 2021 Oct 4, 2021 Oct 4, 2021 NMSS/DUWP OFFICE

/LLWPB NAME HFelsher HF DATE Oct 4, 2021