MONTHYEARML20056H4991993-08-19019 August 1993 Advises That Based on Review of 920918 Submittal,Ipeee Submittal Schedule of 950930 Acceptable Project stage: Approval ML20151K0611997-07-28028 July 1997 Responds to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Listed Generic Issues Addressed Project stage: Other ML20211J0721997-09-30030 September 1997 Submits Response to NRC GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Other ML20199B1251997-11-0505 November 1997 Discusses Info Submitted Re 120-day Response to GL 96-06, Assurance of Equipment Operabiltiy & Containment Integrity During DBA Conditions, Per Implementation of Mods.If Commitments Revised,Revised Response Should Be Submitted Project stage: Other ML20216J0921998-03-18018 March 1998 Ack Receipt of 970128,0228,0728 & 0930 Submittals Re GL 96-06, Assurance of Equipment Operability & Ci During DBA Conditions. Addl Info Re Applicable Design Criteria for Piping & Valve & Drawing of Piping Between Valves Requested Project stage: Other ML20216D6701998-04-0909 April 1998 Forwards RAI Re GL-92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity, Issued May 1995.GL Requested Licensees to Perform Review of RPV Structural Integrity Assessments in Order to Identify,Collect & Rept Data Project stage: RAI ML20216G9451998-04-15015 April 1998 Requests Addl Info Pertaining to GL 96-06 Dtd 980930,which Included Request for Licensees to Evaluate Cooling Water Systems That Serve Containment Air Coolers to Assure Not Vulnerable to Waterhammer & two-phase Flow Conditions Project stage: Other ML20236U5011998-07-23023 July 1998 Special Rept:On 980624,Unit 1 Site Damaged by Tornado & High Winds.Alert Declared by DBNPS Staff,Dbnps Emergency Response Facilities Activiated & Special Insp Team Deployed to Site by Nrc,As Result of Event Project stage: Other ML20237A4691998-08-10010 August 1998 Forwards TR BAW-2325, Response for Addl Info Re Reactor Pressure Vessel Integrity, in Response to NRC 980409 RAI Re GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity Project stage: Other ML20237D3831998-08-21021 August 1998 Forwards Response to NRC 980318 RAI Re Ipeee.Summary of Reliability Considerations for Intact RCS & Small LOCA Cases,Provided as Encl Project stage: Other ML20238F7971998-08-28028 August 1998 Submits Response to NRC Request for Addl Info Pertaining to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Request ML20205J1171999-03-29029 March 1999 Forwards Rev 1 to BAW-2325, Response to RAI Re RPV Integrity, Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity. Rev Includes Corrected Values in Calculations Project stage: Response to RAI ML20205K5641999-04-0707 April 1999 Forwards Response to NRC 980415 RAI Re GL 96-06, Assurance of Equipment Operability & Ci During Design-Basis Accident Conditions. Rept FAI/98-126, Waterhammer Phenomena in Containment Air Cooler Swss, Encl Project stage: Other ML20207H6401999-07-0909 July 1999 Discusses Closure of TAC MA0540 Re Util Responses to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Staff Has Revised Info in Rvid & Releasing It as Rvid Version 2 Project stage: RAI ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days Project stage: RAI ML0331404022003-11-20020 November 2003 Letter, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Other ML0400200522003-12-30030 December 2003 Response to RAI Concerning Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0505406132005-03-0303 March 2005 Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions (TAC No. M96803) Project stage: Other ML0511002912005-04-15015 April 2005 Response to NRC Request for Additional Information Concerning GL-96-006, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0620901032006-07-25025 July 2006 Response to NRC Request for Additional Information Concerning Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0620604832006-07-25025 July 2006 Dale L. Miller/Steven P. Moffitt - NRC Staff'S Notice of Deposition (John Messina) Project stage: Request M061025, COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display2007-04-20020 April 2007 COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display Project stage: Request ML0705105802007-04-20020 April 2007 COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display Project stage: Request ML0711500772007-04-20020 April 2007 Supplemental Information Concerning Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Supplement ML0713604802007-05-31031 May 2007 NRC Receipt of Davis-Besse, Unit 1 Response to GL 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions. (TAC M96803) Project stage: Other 1998-08-28
[Table View] |
Special Rept:On 980624,Unit 1 Site Damaged by Tornado & High Winds.Alert Declared by DBNPS Staff,Dbnps Emergency Response Facilities Activiated & Special Insp Team Deployed to Site by Nrc,As Result of Event| ML20236U501 |
| Person / Time |
|---|
| Site: |
Davis Besse  |
|---|
| Issue date: |
07/23/1998 |
|---|
| From: |
Jeffery Wood CENTERIOR ENERGY |
|---|
| To: |
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
|---|
| References |
|---|
| 2546, GL-88-20, GL-92-01, GL-92-1, GL-96-06, GL-96-6, TAC-M83613, TAC-M96803, TAC-MA0540, TAC-MA540, NUDOCS 9807300212 |
| Download: ML20236U501 (2) |
|
Text
...#
4 man
_em Davis-Besse Nuclear Power Station yy@r 5501 North State Routei m
oak Harbor. Ohio 43449-9760 l
o
' John K. M '
419-249-2300 Yce President-Nuclear Fax: 419-321-8337 Docket Number 50-346
. License Number NPF-3
~ Serial Number 2546 July 23 -1998 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001
Subject:
Tomado Event Effect on Submittal of Information to the NRC Ladies and Gentlemen:
On June 24,1998, the Davis-Besse Nuclear Power Station (DBNPS) Unit Number 1 site was
' damaged by a tornado and high winds. As a result of this event, an Alert was declared by the DBNPS staff, the DBNPS Emergency Response Facilities were activated, and a Special
. Inspection Team was deployed to the site by the NRC, Due to this event and follow up actions, including responding to oral NRC Region III and NRC l
Office of Reactor Regulation requests for information related to the event, it has become necessary.to reschedule the responses to several formal NRC requests for additional information that existed prior to the June 24,1998, tornado.' This rescheduling was discussed with Mr. Allen G. Hansen, DBNPS NRC Project Manager, on July 9 and 13,1998. The following list provides a brief description of the subject response, the NRC Technical Assignment Control (TAC) Number, the previous date the response was due to the NRC, and the revised due date.
j Previous Revised
. TAC Number.
Description D yg ate
. Due Date D
)g MA0540 Generic Letter 92-01, Rev.1, 07/10/98 08/10/98 Sup.1: Reactor Vessel Structural Integrity ~
.V gb L.
. M96803 Generic Letter 96-06: Contain-01/16/98 08/17/98 ment Cooling (Two requests and status of 11RFO modifications)
M83613
- Generic Letter 88-20, Sup. 4:
07/21/98 08/21/98 IPEEE I
98073002i21990723 ?
PDR ADOCK 05000346 S
PDRj I
i
Docket Number 50-346 License Number NPF-3 Serial Number 2546 Page.2 These necessary extensions result in schedule changes of not more than 31 days. It should be noted that very good progress has been made in the completion of TAC numbered issues to date in 1998, with nearly 30% of such issues being completed and closed since March.
1 Should you have any questions or require additional information, please contact Mr. James L.
l Freels, Manager-Regulatory Affairs, at (419) 321-8466.
j Very truly yours, I
i l
DR /laj cc:
A. B. Beach, Regional Administrator, NRC Region III S. 3. Campbell, NRC Region III, DB-1 Senior Resident Inspector A. G. Hansen, DB-1 NRC/NRR Project Manager Utility Radiological Safety Board i