Letter Sequence Other |
---|
|
|
MONTHYEARML20151K0611997-07-28028 July 1997 Responds to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Listed Generic Issues Addressed Project stage: Other ML20211J0721997-09-30030 September 1997 Submits Response to NRC GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Other ML20199B1251997-11-0505 November 1997 Discusses Info Submitted Re 120-day Response to GL 96-06, Assurance of Equipment Operabiltiy & Containment Integrity During DBA Conditions, Per Implementation of Mods.If Commitments Revised,Revised Response Should Be Submitted Project stage: Other ML20216J0921998-03-18018 March 1998 Ack Receipt of 970128,0228,0728 & 0930 Submittals Re GL 96-06, Assurance of Equipment Operability & Ci During DBA Conditions. Addl Info Re Applicable Design Criteria for Piping & Valve & Drawing of Piping Between Valves Requested Project stage: Other ML20216G9451998-04-15015 April 1998 Requests Addl Info Pertaining to GL 96-06 Dtd 980930,which Included Request for Licensees to Evaluate Cooling Water Systems That Serve Containment Air Coolers to Assure Not Vulnerable to Waterhammer & two-phase Flow Conditions Project stage: Other ML20236U5011998-07-23023 July 1998 Special Rept:On 980624,Unit 1 Site Damaged by Tornado & High Winds.Alert Declared by DBNPS Staff,Dbnps Emergency Response Facilities Activiated & Special Insp Team Deployed to Site by Nrc,As Result of Event Project stage: Other ML20238F7971998-08-28028 August 1998 Submits Response to NRC Request for Addl Info Pertaining to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Request ML20205K5641999-04-0707 April 1999 Forwards Response to NRC 980415 RAI Re GL 96-06, Assurance of Equipment Operability & Ci During Design-Basis Accident Conditions. Rept FAI/98-126, Waterhammer Phenomena in Containment Air Cooler Swss, Encl Project stage: Other 1998-03-18
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P2061999-10-26026 October 1999 Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified ML20217N3851999-10-20020 October 1999 Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr ML20217N2321999-10-15015 October 1999 Requests NRC Approval to Use Alternative to Requirements of 10CFR50.55a(f)(4)(ii).Licensee Requests Extension to Specified Schedule for Implementing Updates to IST Program ML20217G9201999-10-14014 October 1999 Discusses Utils Request for Approval of Quality Assurance Program Changes PY-CEI-NRR-2438, Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl1999-10-14014 October 1999 Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl ML20217F8371999-10-0808 October 1999 Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV ML20217A5641999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification ML20212L0691999-09-30030 September 1999 Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 ML20216J6701999-09-24024 September 1999 Forwards Post Examination Documentation for Written Operator Initial License Examination Administered at Davis-Besse Nuclear Power Station on 990920.Without Encls ML20212D3501999-09-21021 September 1999 Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 05000346/LER-1998-001, Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached1999-09-0909 September 1999 Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached ML20216E5961999-09-0707 September 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20211P3001999-09-0707 September 1999 Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified ML20211K6681999-08-30030 August 1999 Forwards Copies of Certified Personal Qualification Statement - Licensee (NRC Form 398) for Operator Candidates Listed Below.Without Encls ML20211K6611999-08-30030 August 1999 Forwards Copies of Operator License Renewal Applications for Individuals Listed.Operators Have Successfully Completed Appropriate Operator Requalification Training Program at Dbnps.Without Encls ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days ML20211H0201999-08-25025 August 1999 Forwards semi-annual FFD Rept for 990101-0630 for DBNPS, Unit 1,IAW 10CFR26.71(d) ML20211D1171999-08-20020 August 1999 Forwards Insp Rept 50-346/99-09 on 990623-0802.Violations Identified & Being Treated as Noncited Violations ML20211G3911999-08-20020 August 1999 Forwards Update to Estimated Info for Licensing Action Requests Through 010930,re Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates PY-CEI-NRR-2411, Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl1999-08-19019 August 1999 Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl ML20211J9201999-08-13013 August 1999 Urges NRC to Find Funds for Stockpiling Radiation Pills for Residents Living Near Plant ML20211B0161999-08-13013 August 1999 Forwards SE Accepting Evaluation of Second 10-year Interval Inservice Insp Program Request for Relief Numbers RR-A16, RR-A17 & RR-B9 for Plant,Unit 1 ML20210T1061999-08-12012 August 1999 Forwards Preliminary NRC Forms 398 & 396 for Listed Candidates,Per Operator License Exam Scheduled for Week of 990913.Encl Withheld ML20210S6071999-08-11011 August 1999 Provides Final Response to NRC RAI Re GL 98-01, Y2K Readiness of Computer Systems at Npps ML20210P8051999-08-0909 August 1999 Forwards Insp Rept 50-346/99-15 on 990712-16.No Violations Noted.However,Several Deficiencies Were Identified with Implementation of Remp,Which Collectively Indicated Need for Improved Oversight of Program IR 05000346/19980211999-08-0606 August 1999 Refers to NRC Insp Rept 50-346/98-21 Conducted on 980901- 990513 & Forwards Nov.Two Violations Identified Involving Failure to Maintain Design of Valve & Inadequate C/A for Degraded Condition Cited in Encl NOV 05000346/LER-1998-009, Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl1999-08-0606 August 1999 Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl ML20210H6101999-07-30030 July 1999 Informs That Region III Received Rev 21 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Revision Was Submitted Under Provisions of 10CFR50.54(q) in Apr 1999 ML20210H0491999-07-28028 July 1999 Forwards Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, to Allow Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G5521999-07-28028 July 1999 Provides Addl Response to 980923 OL Licensing Exam Rept 50-346/98-301 Re OL Exam Administered in Aug 1998.Results of Root Cause Investigation & Corrective Actions,Discussed ML20210G3831999-07-27027 July 1999 Forwards Application for Amend to NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20211P3071999-07-26026 July 1999 Forwards Final Rept for 990504 Biennial Radiological Emergency Preparedness Exercise for David-Besse Power Station.No Deficiencies Identified for Any Jurisdiction During Exercise ML20210G4391999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumentation, & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20210G7151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrument - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5151999-07-26026 July 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G3211999-07-26026 July 1999 Forwards Written OL Exam & Supporting Matl for Exam to Be Administered at DBNPS During Week of 990913.Listed Encls Withheld from Public Disclosure Until After Exam Complete ML20210C4381999-07-20020 July 1999 Forwards Insp Rept 50-346/99-08 on 990513-0622.Unidentified RCS Leak Approached TS Limit of 1 Gallon Per Minute Prior to Recently Completed Maint Outage.Three Violations of NRC Requirements Identified & Being Treated as NCVs ML20209G3681999-07-15015 July 1999 Advises That Info Submitted in & 990519 Affidavit Re Design & Licensing Rept,Davis-Besse,Unit 1 Cask Pit Rack Installation Project,Holtec Intl, HI-981933,marked Proprietary,Will Be Withheld from Public Disclosure ML20207H6401999-07-0909 July 1999 Discusses Closure of TAC MA0540 Re Util Responses to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Staff Has Revised Info in Rvid & Releasing It as Rvid Version 2 ML20209D1341999-07-0808 July 1999 Forwards Notice of Withdrawal of Application for Amend to Operating License.Proposed Change Would Have Modified Facility TSs Pertaining to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves 05000346/LER-1998-012, Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached1999-07-0707 July 1999 Forwards LER 98-012-01,which Is Being Submitted to Provide Addl Info Re 981018 Occurrence.Commitment List Attached ML20209C3981999-07-0101 July 1999 Responds to NRC Re Violations Noted in Insp Rept 50-346/98-21.Corrective Actions:Developed Rev to Boric Acid Control Program & Work Process Guideline on Plant Leakage ML20209B5821999-06-24024 June 1999 Provides Justification for Rev to Completion Date for One of Insp follow-up Items Cited in Insp Rept 50-346/98-03, Designated as Inspector follow-up Item 50-346/97-201-10 ML20196G1251999-06-23023 June 1999 Responds to NRC RAI Re GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants ML20196E5321999-06-17017 June 1999 Forwards Addl Info Re Relief Request RR-A16 to Support NRC Approval of Relief Request ML20195K2751999-06-16016 June 1999 Forwards Safety Evaluation Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195F9071999-06-10010 June 1999 Forwards Application for Amend to NPF-3,changing Tech Specs 3/4.6.4.4, Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20195F8851999-06-0707 June 1999 Withdraws 950929 License Amend Application,Proposing Mod to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves ML20207G0751999-06-0707 June 1999 Forwards Insp Rept 50-346/99-04 on 990323-0513.Violations Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy 1999-09-09
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217P2061999-10-26026 October 1999 Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified ML20217N3851999-10-20020 October 1999 Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr ML20217G9201999-10-14014 October 1999 Discusses Utils Request for Approval of Quality Assurance Program Changes ML20217F8371999-10-0808 October 1999 Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV ML20217A5641999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification ML20212L0691999-09-30030 September 1999 Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 ML20212D3501999-09-21021 September 1999 Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 ML20211P3001999-09-0707 September 1999 Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days ML20211D1171999-08-20020 August 1999 Forwards Insp Rept 50-346/99-09 on 990623-0802.Violations Identified & Being Treated as Noncited Violations ML20211B0161999-08-13013 August 1999 Forwards SE Accepting Evaluation of Second 10-year Interval Inservice Insp Program Request for Relief Numbers RR-A16, RR-A17 & RR-B9 for Plant,Unit 1 ML20210P8051999-08-0909 August 1999 Forwards Insp Rept 50-346/99-15 on 990712-16.No Violations Noted.However,Several Deficiencies Were Identified with Implementation of Remp,Which Collectively Indicated Need for Improved Oversight of Program IR 05000346/19980211999-08-0606 August 1999 Refers to NRC Insp Rept 50-346/98-21 Conducted on 980901- 990513 & Forwards Nov.Two Violations Identified Involving Failure to Maintain Design of Valve & Inadequate C/A for Degraded Condition Cited in Encl NOV ML20210H6101999-07-30030 July 1999 Informs That Region III Received Rev 21 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Revision Was Submitted Under Provisions of 10CFR50.54(q) in Apr 1999 ML20210C4381999-07-20020 July 1999 Forwards Insp Rept 50-346/99-08 on 990513-0622.Unidentified RCS Leak Approached TS Limit of 1 Gallon Per Minute Prior to Recently Completed Maint Outage.Three Violations of NRC Requirements Identified & Being Treated as NCVs ML20209G3681999-07-15015 July 1999 Advises That Info Submitted in & 990519 Affidavit Re Design & Licensing Rept,Davis-Besse,Unit 1 Cask Pit Rack Installation Project,Holtec Intl, HI-981933,marked Proprietary,Will Be Withheld from Public Disclosure ML20207H6401999-07-0909 July 1999 Discusses Closure of TAC MA0540 Re Util Responses to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Staff Has Revised Info in Rvid & Releasing It as Rvid Version 2 ML20209D1341999-07-0808 July 1999 Forwards Notice of Withdrawal of Application for Amend to Operating License.Proposed Change Would Have Modified Facility TSs Pertaining to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves ML20195K2751999-06-16016 June 1999 Forwards Safety Evaluation Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20207G0751999-06-0707 June 1999 Forwards Insp Rept 50-346/99-04 on 990323-0513.Violations Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20207G0621999-06-0404 June 1999 Forwards Insp Rept 50-346/98-21 on 980901-1201 & 990425-0513.Violations Identified & Licensee Being Provided Opportunity to Either Respond to Violations within 30 Days or Inform NRC That LER Rept Already Contain Info Requested ML20207B8161999-05-25025 May 1999 Confirms Discussion Between Members of Staffs to Have Mgt Meeting on 990608 in Oak Harbor,Oh to Discuss Recent Performance at Davis-Besse as Described in Plant Performance Review ML20207B3141999-05-24024 May 1999 Informs That in September 1998,Region III Received Revision 20 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Rev Submitted Under Provisions of 10CFR50.54(q) ML20206T0881999-05-18018 May 1999 Confirms 990517 Telcon Between Lindsey & M Bielby Re Arrangements Made for Administration of Licensing Exam at Facility for Week of 990913 ML20206N5311999-05-11011 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Aj Mendiola Will Be Section Chief for Davis-Besse Npp.Organization Chart Encl ML20206H2291999-05-0707 May 1999 Forwards Proposed Change to Plant,Unit 1,TS Bases Section 2.2.1, Limiting Safety Sys Settings - Reactor Protection Sys Instrumentation Setpoints - Rc Pressure - Low,High & Pressure Temp ML20206B8171999-04-27027 April 1999 Forwards Insp Rept 50-346/99-05 on 990405-09.No Violations Noted.Purpose of Insp Was to Examine on-line Maint Risk Assessment Program Recently Implemented in Response to Maint Work Control Weaknesses ML20205G5681999-03-26026 March 1999 Advises of Completion of Plant Performance Review on 990202 to Develop Integrated Understanding of Safety Performance. Overall Performance of Plant Acceptable.Plant Issues Matrix & Insp Plan Encl ML20207G1701999-03-0505 March 1999 Forwards Insp Rept 50-346/99-01 on 990102-0212.No Violations Noted ML20207D4351999-02-25025 February 1999 Forwards Insp Rept 50-346/99-02 on 990202-05.No Violations Noted.Examples of Deficiencies with Station Procedures, Similar to Those Identified Through Staff self-assessments & in Previous NRC Insps,Were Noted IR 05000346/19960141999-02-17017 February 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-346/96-14 on 970225.Ack That Due to Plant Events,There Has Been Delay in Completion of C/As for Violation 50-346/96-14c ML20203F2541999-02-10010 February 1999 Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function ML20206S0811999-01-22022 January 1999 Forwards Insp Rept 50-346/98-18 on 981110-990102.No Violations Identified.Conduct of Activities at Davis-Besse Generally Characterized by Conservative Plant Operations, & Effective Engineering Involvement in Plant Issues ML20199H5821999-01-20020 January 1999 Forwards SE Re Ampacity Derating Issues Due to Application of Thermo-Lag Fire Barrier Matl at Plant ML20198E6821998-12-17017 December 1998 Forwards Insp Rept 50-346/98-20 on 981116-20.No Violations Noted.Implementation of Licensed Operator Requalification Program Was Generally Characterized by Safety Conscious Operations & Sound Evaluation of Operator Performance ML20198C9881998-12-15015 December 1998 Informs That as Part of NRC PRA Implementation Plan, Commission Assigned Two SRAs to Each Regional Ofc.Sras Will Routinely Assess Licensee Event Repts,Plant Event,Insp Findings & EAs from Risk Perspective ML20198B5391998-12-0909 December 1998 Forwards Insp Rept 50-346/98-17 on 980918-1109 & NOV Re Inadequate Maint Work Order Used by Electrician During Removal of Primary Water Storage Tank Temp Indicator ML20196G1621998-12-0303 December 1998 Submits Response to Request for TS Interpretation Re Surveillance Interval Extension Allowances ML20196H4411998-12-0303 December 1998 Confirms Plans to Hold Meeting on 981216 in Lisle,Il,To Discuss Recent Performance at Davis-Besse & Actions Being Implemented by Licensee ML20198B1511998-12-0202 December 1998 Forwards Insp Activity Plan for Next 6 Months & Plant Issues Matrix.Infor Provided to Minimize Resource Impact on Staff & to Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival Onsite ML20196J5111998-12-0101 December 1998 Fowards Year 2000 Readiness Audit Rept,Which Documents Results of NRR Audit Conducted at Facility from 981027-29 ML20196D4371998-11-25025 November 1998 Discusses Concerns Re Announced Asset Transfer Between Firstenergy Corp & Duquesne Light Co ML20196C6491998-11-20020 November 1998 Forwards Insp Rept 50-346/98-19 on 981014-23.No Violations Noted.Inspectors Reviewed Circumstances Surrounding Events Leading Up to & Following Reactor Trip IR 05000346/19983011998-11-0909 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-346/98-301OL Issued on 980923.Effectiveness of C/A Will Be Reviewed Following Submittal of Root Cause Investigation Results ML20155J1471998-11-0303 November 1998 Informs That on 981007,NRC Administered GFE Section of Written Operator Licensing Exam to Employees of Facility. Exam Answer Key for Forms a & B,Grading Results & Individual Answer Sheets Encl.Without Encl ML20155B6641998-10-28028 October 1998 Forwards Safety Evaluation Re Request for Reduction in Commitment Changes in QA Program Matl Receipt Insp Process ML20154Q6711998-10-16016 October 1998 Forwards Insp Rept 50-346/98-15 on 980914-18.No Violations Noted.Emergency Preparedness Program Effectively Implemented During 980624 Tornado Event & Station Personnel Responded Well to Event ML20154Q5891998-10-14014 October 1998 Forwards Insp Rept 50-346/98-14 on 980808-0918.No Violations Noted.Online Safety Equipment Outages Were Performed Well & IAW Established Procedures ML20154H0241998-10-0606 October 1998 Discusses Arrangements Made During 980924 Telcon for Insp of Licensed Operator Requalification Program at Davis Besse Nuclear Power Station During Wk of 981116 ML20154D1801998-09-30030 September 1998 Forwards Insp Rept 50-346/98-16 on 980831-0904.No Violations Noted 1999-09-07
[Table view] |
Text
___
=,/caso m5 $h-fb ge *,. UNITED STATES
- 5
,j NUCLEAR REGULATORY COMMISSION WASHINGTON D.C. 3066H001 -
'g*****,d November 5, 1997 Mr. John K. Wood Vice President - Nuclear, Davis-Besse Centerior Service Company c/o Toledo Edison Company Davis Besse Nuclear Power Station 5501 North State Route 2 Oak Hart >or, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - INFORMATION PERTAINING TO IMPLEMENTATION OF MODIFICATIONS ASSOCIATED WITH GENERIC LETTER 96-06, " ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS" (TAC NO. M96803)
Dear Mr. Wood:
The staff issued Generic l.etter (GL) 96-06 on September 30,1996. The GL requested-licensees to determine: (1) if containment air cooler cooling water systemr. are susceptible to either waterhammer or two-phase flow conditions during postulated accident conditions; and (2) if piping systems that penetrate the containment are susceptible to thermal expansion of fluid so that overpressurization of piping could occur. By letter dated January 28,1997, as supplemented by letters dated February 28, July 28, and September 30,1997, you submitted your 120-day response to GL 96-06. The staff is currently performing a detailed review of your response.
Implementing corrective actions to resolve the GL 96-06 issues can have a significant impact on outage schedules and resources. Some licensees have indicated that it would be prudent to take more time to better understand the specific concems that have been identified in order to optimize whatever actions are needed and to assure that they do not ultimately result in a detriment to safety. Current issues and ongoing efforts that could influence a licensee's decision in planning corrective actions include:
- 1. Risk implications of installing relief valves to deal with the thermal overpressurization issue;
- 2. Feasibility of using the acceptance criteria contained in Appendix F to Section lil of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (AS'ME Code) for the permanent resolution of the GL 96-06 issues;
- 3. Ongoing tests by the Electric Power Research Institute to support a generic resolution of the overpressurization of piping issue; and EC FRE CBlTES CDPy ,
i a ,
11llllijlli,1ll.ll gol D 9711190224'971105 &
PDR ADOCK 05000346 ?
P PM L
~
- v J. Wood ,
- 4. . Questions regarding the staff's closure of Generic Safety lasue 150,."Overpressurization
~
of Containment Penetrations." ;
Risk insights and industry initiatives that are being considered or that may be proposed could -
also influence the course of action that licensees take to resolve the GL 96-06 issues.- ,
Licensees are responsible for assessing equipment operability, determining actions, and establishing schedules that are appropriate for resolving the specific conditions that have been identified. In determining the appropriate actions and schedules for resolving GL 96-06 issues, licensees should consider, for example, the continued validity of existing operability determinations, compensatory actions required to maintain operability, the safety significance associated with the specific nonconformances or degraded conditions that have been identified, risk insights, and the time required to complete any generic initiatives and/or plant-specific actions (for example, engineering evaluations, design change packages, material procurement, and equipment modification and installation).
Also, analytical solutions employing the permanent use of the acceptance criteria contained in the ASME Oode, Section lil, Appendix F (or other acceptance criteria) may present viable altematives to plant modifications and can be used where appropriate, justifed, and l evaluated in accordance with NRC roouirements such as 10 CFR 50.59, as applicable.
l Licensees may find the revised guidance contained in GL 91-18, "Information to Licensees Regarding Two NRC Inspection Manual Sections en Resolution of Degraded and Nonconforming Conditions and on Operability," Revision 1, dated October 8,1997, helpful in determir ing appropriate actions and schedules. Although adjustments in schedules may be warranted on the basis of these (and other) considerations, specific actions that have been defined and are clearly needed should not be delayed without suitable justification.
It is the staff's current position that licensees can use the ASME Code, Section lil, Appendix F, criteria for interim operability determinations for degraded and nonconforming piping and pipe supports until permanent actions have been identified and approved by the l
NRC (as applicable) for resolving the GL 96-06 issues. This guidance supplements the guidance provided by GL 91-18 for resolution of these issues.
In order to further facilitate resolution of the GL 96-06 issues, the NRC will participate in a '
public workshop on this topic later this fall. The workshop proceedings will be summarized by the NRC staff and made publicly available. The need for additional NRC guidance and generic communication will be considered upon completion of the workshop.
if you choose to revise your commitments for resolving the GL 96-06 issues, you should
. submit a revised response to the GL. Your revised response should include appropriate
. discussion of the considerations discussed above, the current resolution status, actions l-E t.
, , . - . . , , - . , , . - , , . - . - - . , . , . ~ _ _ . . , - . .
+ ,,.:.
t..
.. JJohn K. Wood. Davis-Besse Nuclear Power Station, Unit 1 ,
Toledo Edison Company ,
cc:
Mary E. O'Reilly . .
Robert E. Owen, Chief
' Centerior Energy Corporation Bureau of Radiological Health 300 Madison Avenue Service Toledo, OH 43652.. Ohio Department of Health .
P.O. Box 118 James L. Freels . Columbus, OH 43266-0118-Manager - Regulatory Affairs Toledo Edison Company James R. Williams, Chief of Staff
- Davis-Besse Nuclear Power Station . Ohio Emergency Management Agency >
5501 North State - Route 2 2855 ^ West Dublin Granville Road Oak Harbor, OH 43449-g760 Columbus, OH - 43235-2206
' Gerald Chamoff, Esq. Donna Owens, Director
= Shaw, Pittman, Potts Ohio Department of Commerce and Trowbridge Division of Industrial Compliance 2300 N Street, NW. Bureau of Operations & Maintenance
- Washington, DC 20037 6606 Tussing Road c P.O. Box 4009 .
Regional Administrator Reynoldsburg, OH 43068-9009 U.S. Nuclear Regulatory Commission 801 Warrenville Road Ohio Environmental Protection Agency Lisle,IL 60523-4351 DERR.-Compliance Unit ATTN: Zack A. Clayton Robert B. Borsum P.O. Box 1049
. Babcock & Wilcox Columbus, OH 43266-0149 '
- Nuclear Power Generation Division 1700 Rockville Pike, Suite 525 -State of Ohio Rockville, MD 20852 Public Utilities Commission 180 East Broad Street Resident inspector . Columbus, OH 43266-0573 U.S. Nuclear Regulatory Commission 5503 North State Route 2 Attomey General Oak darbor, OH . 43449 - Department of Attomey
. 30 East Broad Street James H. Lash, Plant Manager- Columbus, OH 43216 Toledo Edison Company Davis-Besse Nuclear Power Station President, Board of County 5501 North State Route 2 Commissioner of Ottawa County Oak Harbor, OH. 4344g-9760 Port Clinton, OH 43252 Roy P. Lessy, Jr.
' Akin, Gump, Srauss, Hauer & Feld, LLP :
1333 New Hampshire Ave., NW., Ste. 400
. Washington, DC 20036 ,
c i t
y ,'n :
,, "...... f>,
c'4 -s
.y,, .
f * ,j ~
4^ ~
3 J. Wood - -
- 4
)
u remaining to be completed, and plans'being considered for final resolution of the GL' 96-06 issues.
Please contact me at 301415-1390 if you have any questions. ;
Sincerely, Original sign-4 by: -
Allen G. Hansen, Project Manager Project Directorate lil-3 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation ,
Docket No. 50-346 cc: See next page DISTRIBUTION:
Docket File:
PUBLIC PD3-3 R/F
>- + EAdensam (EGA1)-
. GMarcus
,0GC. *
,-ACRS ^
- BWetze!
- ,3 'y, LMarsh GHubbard * '
GGrant, Rlli ,
g, n
>..J-- -
,ip *g _1 ,
- ,{ __(
l' , DOCUMENT NAME: G:\DAVISBEEDB96803.LTR ,
- " '( -m OFFICE PD3 3:PM C PD3-3:LA , C :
NAME AHansen CBoyle %
( DATE //fl97 : ll/p97.
OF HCIAL RECORD COPY V.
f
- f-
= , s , t' 7
,,e**
. J. Wood remaining to be completed, and plans being considered for final resolution of the GL 96-04 issues.
Please contact me at 301415-1390 if you have any questions.
Sincerely, Original signed by:
Alien G. Hansen, Project Manager Project Directorate lll 3 Division of Reactor Projects Ill/lV Office of Nuclear Reactor Regulation Docket No. 50 346 cc: See next page DISTRIBUTION:
Docket File PUBLIC PD3-3 R/F EAdensam (EGA1)
GMarcus OGC ACRS BWetzel LMarsh GHubbard GGrant, Rill DOCUMENT NAME: G:\DAVISBES\DB96803.LTR OFFICE PD3-3:PM C PD3-3:LA .
C NAME AHansen CBoyle (l@
DATE r/f/97 ll/997 V OF FICIAL RECORD COPY L