ML040020052
| ML040020052 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 12/30/2003 |
| From: | Myers L FirstEnergy Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3014, GL-96-006, TAC M96803 | |
| Download: ML040020052 (3) | |
Text
FENOC FENOC 5501 North State Route 2 FstEney Niclear Operating Company Oak Harbo Oio 43449 Low W Myers 419-321-7599 Chief Operating Officer Fax: 419<321-7582 Docket Number 50-346 License Number NPF-3 Serial Number 3014 December 30, 2003 United States Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555-0001
Subject:
Response to NRC Request for Additional Information Concerning Generic Letter 96-06, "Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions" (TAC No. M96803)
Ladies and Gentlemen:
This letter transmits a FirstEnergy Nuclear Operating Company (FENOC) response to a Nuclear Regulatory Commission (NRC) Request for Additional Information (RAI) related to the Davis-Besse Nuclear Power Station, Unit 1 (DBNPS) response to Generic Letter (GL) 96-06, "Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions." GL 96-06, issued by the NRC on September 30, 1996, requested, in part, that licensees evaluate their cooling water systems that serve containment air coolers to assure that they are not vulnerable to waterhammer and two-phase flow conditions.
By letter dated November 20, 2003, (letter Log Number 6137), the NRC staff requested that FENOC respond to three observations with regard to the DBNPS responses to GL 96-06.
Additionally, because FENOC has modified the DBNPS cooling water piping to the containment air coolers, the NRC staff requested that FENOC review the DBNPS responses to GL 96-06 and supplement them where appropriate. Although the NRC staff has also concluded that the DBNPS response to the two-phase flow issue was acceptable, due to recent piping modifications the NRC staff requested that FENOC either affirm that the DBNPS responses are still valid in this area or supplement the responses for two-phase flow. The NRC requested that FENOC respond within 45 days of the date of the letter with a schedule for responding to these requests.
The updated responses requested in the NRC's RAI are dependent upon activities to be performed during 14RFO; therefore, FENOC will provide the requested responses within 90 days following the completion of 14RFO. FENOC will promptly notify the NRC of any change in schedule if additional time is necessary to provide a complete response.
AD7S;2
S.
Docket Number 50-346 License Number NPF-3 Serial Number 3014 Page 2 If you have any questions or require further information, please contact Mr. Kevin L. Ostrowski, Manager - Regulatory Affairs, at (419) 321-8450.
Very truly yours, CWS/MSH Enclosure cc:
Regional Administrator, NRC Region III J. B. Hopkins, DB-1 NRC/NRR Senior Project Manager C. S. Thomas, DB-1 NRC Senior Resident Inspector Utility Radiological Safety Board
Docket Number 50-346 License Number NPF-3 Serial Number 3014 Enclosure Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station, Unit Number 1, (DBNPS) in this document. Any other actions discussed in the submittal represent intended or planned actions by the DBNPS. They are described only for information and are not regulatory commitments. Please notify the Manager -
Regulatory Affairs (419-321-8450) at the DBNPS of any questions regarding this document or associated regulatory commitments.
COMMITMENTS DUE DATE The updated responses requested in the NRC's RAI are Within 90 days dependent upon activities to be performed during following completion 14RFO; therefore, FENOC will provide the requested of 14RFO responses within 90 days following the completion of 14RFO.
FENOC will promptly notify the NRC of any change in None schedule if additional time is necessary to provide a complete response.