ML20235V048

From kanterella
Jump to navigation Jump to search
Insp Repts 50-327/87-50 & 50-328/87-50 on 870706-0805.No Violations or Deviations Noted.Major Areas Inspected: Operational Safety Verification,Including Operations Performance,Sys Lineups,Radiation Protection & Safeguards
ML20235V048
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/28/1987
From: Jenison K, Mccoy F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20235V045 List:
References
50-327-87-50, 50-328-87-50, NUDOCS 8710140514
Download: ML20235V048 (37)


See also: IR 05000327/1987050

Text

UNITED STATES

[Se Riog

,

D

NUCLEAR REGULATORY COMMISSION

o

y"-

[n

REGION il

y

j

101 MARIETTA STREET.N W.

's

ATLANTA GEORGIA 30323

%

f

m , * *#

1

Report Nos.:

50-327/87-50, 50-328/87-50

Licensee:

Tennessee Valley Authority

500A Chestnut Street

Chattanooga, TN 37401

Docket Nos.:

50-327 and 50-328

License Nos.: DPR-77 and DPR-79

Facility Name:

Sequoyah Units 1 and 2

Inspection Conducted: July 6, 1987 thru August 5, 1987

[*CC

Ik

Inspector:[K. M~ Jenison, Senior /Esigni Irispector

_f//C/#)'

~

Date' Signed

Accompanying Personnel:

P. E. Harmon, Resident Inspector

D. P. Loveless, Resident Inspector

W. K. Poertner

esident Inspector

W.

anch S uoyah Restart Coordinator

9[2

7

Approved by.

/

F. R. McCoy, Chief, Projtetf Section 1

{Vate />igne'd

Division of TVA Projects

SUMMARY

Scope: This routine, announced inspection involved inspection onsite by the

Resident Inspectors in the areas of: operational safety verification (including

operations performance, system lineups, radiation protection, safeguards and

housekeeping inspections); maintenance observations; review of previous

inspection findings; review of licensee identified items; review of inspector

follow-up items; Surveillance Instruction Review Program, Restart Testing

Program; and review of 1984 Thimble Tube Ejection Event.

Results:

Three unresolved items were identified:

327,328/87-50-01, Control of systems required for mode 5 operation,

paragraph 11.b.

327,328/87-50-02, Adequacy of the long term surveillance instruction

program, paragraph 11.b.

327,328/87-50-03, Preoperational testing of the containment spray pumps

and the ice condenser doors, paragraph 13.

8710140514 870929

PDR

ADDCK 05000327

G

PDR

-_

__

r

1

-

,-..

,,

i

-

> REPORT DETAILS

1.,

Licensee Employees Contacted

H. L. Abercrombie,. Site Director

.*J. T.tLa Point, Deputy Site Director

'

  • L. M. Nobles, Plant Manager

8. M. Willis, Operations and Engineering Superintendent

8. M. Patterson,' Maintenance Superintendent

R.'J. Prince, Radiological-Control Superintendent

H. R. Harding, Licensing-Group Manager

i. -

L. E. Martin, Site Quality Manager

D. W. Wilson, Proje::t Engineer

R.=W; Olson, Modifications Branch Manager

J. M.- Anthony, Operations Group Supervisor.

R. V. Pierce, Mechanical Maintenance Supervisor

,M. A. Scarzinski, Electrical Maintenance Supervisor

H. D. Elkins,LInstrument Maintenance Group Manager

E R. W. Fortenberry,.-Technical Support Supervisor

  • G. 8. Kirk,. Compliance Supervisor

-

0. C. Craven,-Quality Assurance Staff Supervisor

"J. H. Sullivan, Regulatory Engineering Supervisor-

J. L. Hamilton, Quality Engineering Manager

D. L Cowart, Quality Engineering Supervisor

.H. R. Rogers, Plant Operations Review Staff

  • R. H. Buchholz, Sequoyah Site Representative-

M..A.. Cooper, Compliance Licensing Engineer

  • R. P. Denise, Manager SI Review Program-

Other . licensee employees contacted included technicians, operators, shift

engineers, security force members, engineers and maintenance personnel.

  • Attended exit interview

2.-

Exit Interview

The inspection scope and findings were summarized with the Plant Manager

and members of his' staff on August 5, 1987.

The licensee acknowledged the

inspection findings and did not identify as proprietary any of the

material reviewed by the ' inspectors during this < nspection.

During the

reporting period, frequent' discussions were held with the Site Director,

Plant Manager and other managers concerning inspection findings.

3.

Licensee Action on Previous Inspection Findings (92702)

(Closed) Unresolved Item (URI) 327,328/87-02-03, use of WR to Perform

Modifications to Control Room Drip Pans.

The inspector reviewed issues

related to the control building roof leaks identified in inspection report

87-08.

During this inspection all items were considered closed with the

- _ _ _ -

-

_

_

h

-

,;

E

2-

!

' i

exception of' satisfactory completion of roof repairs.

The' inspector

reviewed Maintenance Instruction SMI-0-400-3, Removal and Replacement of

^

Control- Building Roof Sealant.

Re-roofing was applied and completed on

June 5,1987 per this- procedure and WR B222858.

Security aspects of this

modification are discussed briefly in paragraph Sb of this report.

This

. item is closed.

'

(Closed) URI 327,328/86-32-07, Functional Test of Chlorine Monitor.

This

item is- closed i by issuance of VIO 327,328/87-36-01 for failure to

adequately test the Chlorine Monitor.

l

4;

Unresolved Items

,

Unresolved. items are matters about which more information is required to

determine whether they are acceptable or may' involve violations or

deviations.

Three_ unresolved items - were -identified during this

inspection, and are~1dentified.in paragraphs 11 and 13.

5 .'

Operational Safety Verification (71707)

a.

Plant Tours

~The inspectors observed control room operations, reviewed applicable

logs, conducted discussions with control room operators, observed

shift turnovers, and confirmed operability of instrumentation.

The

inspectors verified the operability of selected emergency systems,

and verified compliance with Technical Specification (TS) Limiting

Conditions for Operation (LCO).

The inspectors verified that

maintenance work _ orders had been submitted as required and that

follow-up activities and prioritization of work was accomplished by

,

the licensee.

,

Tours of the diesel- generator, auxiliary, control, and turbine

buildings, and containment were conducted to observe plant equipment

conditions, including potential fire hazards, fluid leaks, and

excessive vibrations and plant housekeeping / cleanliness conditions.

No violations or deviations were identified,

b.

Safeguards Inspection

In the course of the monthly activities, the inspectors included a

' review of the licensee's physical security program.

The performance

!

,

of various shifts of the security force was observed in the conduct

1

of daily activities including protected and vital area access

controls; searching of personnel and packages; badge issuance and

retrieval; patrols and compensatory posts; and escorting of visitors.

In addition, the inspectors observed protected area lighting,

protected and vital areas barrier integrity.

The inspectors verified

= _ _ _- - - _ _ _ _

_

_

__

_

_

- _ _ _

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - . . _ _ - _ _ _ _ _ _ _ _

_

__

-

_ - _ _

. _ - _

_

,

'

a

,

3

)

an interface. between the security organization and operations or

maintenance.

Specifically,. the resident inspectors - observed

emergency drills; . responded to fires, inspected security during out-

ages, reviewed licensee security event reports /offsite communication

verified protection

of safeguards.information, and verified onsite

!

capabilities.

j

i

' The -inspector observed work being performed under.WR B222858 on the -

!

control building . roof.

This maintenance work required moving the

protected area back to open the control building roof.

The security.

plan for Sequoyah was- temporarily updated to include provisions for

.;

this work.

The: inspector verified- that temporary fences, alarms,

!

cameras, lighting and compensatory posts were all in place.

The

inspector observed portions of the return to service of the original

fence and lighting = systems. 'The inspector had no further. questions.

No violations or. deviations were identified.

c.

Radiation Protection

The inspectors observed health physics (HP)' practices and verified

implementation of radiation protection control.

On a regular basis,

radiation work ipermits - (RWPs) were reviewed and specific work-

. activities were monitored to ensure the activities were being

,

conducted inj accordance' with applicable RWPs.

Selected radiation

protection instruments were verified operable and calibration

frequencies were' reviewed.

No violations or deviations were identified.

' 6.

Monthly Surveillance Observations-(61726)

The inspectors observed / reviewed' TS recuired surveillance testing and

,

verified that testing was performed ' n accordance with adequate

(

procedures; that test instrumentation was calibrated; that LCOs were met;

I

that test. results met acceptance criteria requirements and were reviewed

'

l

by personnel other than the individual directing the test; that

deficiencies were identified, as appropriate, and that any deficiencies

identified during the testing were properly reviewed and resolved by

management personnel; and that system restoration was adequate.

For

complete tests, the . inspector verified that testing frequencies were met

and tests were performed by qualified individuals.

The inspector witnessed a performance of Surveillance Instruction (SI)-40,

Centrifugal- Charging Pump.

The purpose of this SI is to perform the TS

I

required ASME section XI testing of the pumps.

The inspector noted that

the.TSs required that the charging pumps be tested on recirculation flow

only and that SI-40 as presently written tests the pumps while they are

providing charging and seal injection flow.

Discussions with the

mechanical test section determined that SI-40 is presently under revision

i

z

-

-

-

-

-

. _ - _ _ _

. _ _ -

. _ _ _ _ _ _

-

.

.

,

f'.

~4

to test the pumps on recirculation flow only and-that the SI will be

performed with the required ' lineup prior to unit startup.

The inspector

does not: consider that the SI as' presently being performed calls into

question the-operability of the charging pumps based on the fact that the

system flow resistance has been. reduced and the pump discharge pressure is

still required to be above the value required by_the TSs. .It would. appear:

that the present method of testing the pumps is a better indicator of pump

performance than just testing on recirculation flow.

The inspector noted

no discrepancies during the actual performance of-the SI.

L

7. .

Monthly Maintenance.0bservaticas (62703)

Station 1 maintenance activities of safety-related systems and components

were . observed / reviewed during special maintenance inspection 327,

328/87-37.

8.

Licensee Event. Report (LER) Follow-up (92700)

LERs reviewed during this inspection are identified in paragraph 11 of

this report.

'

- 9.

Inspector Follow-tip Items

Inspector. Follow-up Items. (IFIs) are matters of concern to'the inspector

which 'are documented and tracked in inspection reports to allow further

review: and evaluation by the inspector.

The following IFIs have .been

reviewed and . evaluated by the inspector.

The inspector has either

resolved the concern identified, determined that the ifcensee has

. performed adequately in the area, and/or determined that . actions taken by

the licensee have resolved'the concern.

(Closed) IFI 327,328/86-60-08, Qualification and Certification of Sequoyah

,

Quality Control (QC) Inspectors. The inspector reviewed a selected number

j

of QC department inspector certification folders. The folders reviewed

i

contained the proper certification documents for each inspector with only

1

one minor clerical error. A review was conducted of the QC site

certification matrix which is the working document used to select

inspectors for specific jobs. A comparison was made between the

i

certification documents in the folders and the site certification matrix.

Several discrepancies were found which prompted -the QC department to

undertake a 100% reverification of the matrix against the certification

folders. One additional discrepancy was found during this reverification.

L An investigation revealed that none of the. discrepancies resulted in QC

inspectors working on jobs they were not certified to inspect. This item

is closed.

10.

10 CFR Part 21 Reports

(Closed) P2184-05,ITE-27N Undervoltage Relays.

ITE-27N undervoltage

relays are utilized on the shutdown boards for degraded voltage

_ _ - _ _ _ _-_____

-

_

i

.

5

protection. In October of 1984 the licensee replaced resistor R-11 with a

200 kilo-ohm resistor to correct the design deficiency identified with the

ITE-27N undervoltage relays.

The inspector reviewed the maintenance

request forms associated with the modification and verified that the work

was completed.

This item is closed.

'

(Closed) P2184-01,A Control Panel . Bracket Support welded to the diesel

lube oil cooler has developed cracks in the weld and resulted in a small

lobe oil cooler leak.

The inspector verified that_ the control panel

support had been modified such that it was no longer welded to the diesel

generator lube oil cooler.

This item is closed.

i

1

11.

Surveillance Instruction Program (61700, 61726)

'

The licensee's submittal of March 24,1987 (Gridley/Ebneter), described

the Sequoyah surveillance instruction review and revision program.

The

intent of this program, as described in this document, was to ensure all

TS requirements were addressed and that sis and their supporting

instructions, covered by the program scope, were technically adequate to

fulfill the surveillance requirements of the Sequoyah TS.

An NRC

inspection (327,328/87-36) was conducted during the period of May 26

through June 5, 1987.

Four areas requiring additional inspection and one

unresolved item (URI 327,328/87-36-02) were identified.

URI 327,

1

328/87-36-02 was not formally addressed by the licensee at the time this

I

inspection took place, and will therefore remain an open startup item. The

four areas reviewed were as follows:

a.

Part II to Appendix F checklist of SI-1, Surveillance Program

Administrative Adequacy

The licensee stated in its submittal that "Part II of the checklist

is not being completed for this program".

This implied that Part II

to Appendix F would not be completed prior to the startup of Sequoyah

,

Unit 2.

The licensee explained that certain items in Part II are

i

from upper-tier documents and are checked to ensure necessary

1

compliance.

Exception was taken by the NRC to this portion of the SI review

i

program and the licensee was asked to re-evaluate whether or not one

I

or all of the five most likely examples (listed below) would affect

l

the technical adequacy of surveillance performance.

The five

!

examples which most likely would affect the technical adequacy of

surveillance performance were:

consideration of common mode failure possibilities (Part II,

1

-

Item 1)

l

requirement for SRO approval to perform the SI (Part II,

-

l

l

Item 6)

]

l

l

l

l

. _ _ _ .

g

.

6

l

1

verification of impact on redundant loops (Part II, Item 7)

-'

verification of performance consistency (Part II, Item 18)

-

requirements for independent verification (Part II, Item 21)

<

-

During a review of this issue in inspection report 327,328/87-36 it

was determined that two licensee organizations (Quality Assurance and

the Surveillance Instruction Validation / Verification group) had also

identified the same issue.

The implementation of a licensee review

and corrective action, if required, were deferred to this inspection

from inspection 327,328/87-36.

The inspectors reviewed the licensee's evaluation of this issue which

was provided in memos (R. Densie/L Nobles) dated July 25 and 30,

1987.

The licensee's evaluation referenced a joint memo written

between the SI program manager and the site QA manager and concluded

that the SI-1 Appendix F Part II Items 1, 6, 7,18, and 21 were

adequately addressed. The licensee conducted a review of its IRG and

SIVV group findings and determined that of 105 instructions reviewed

for Items 1, 6, 7,18, and 21,18 procedures had negative findings.

The licensee determined that the identification of 18 individual

procedures that had concerns in this area did not constitute a

generic problem and that "the SI program has clear written guidance

to include - basic administrative requirements in the production of

sis, and the fact that we did not use the SI-1 Appendix F Part II

checklist to implement the program is inconsequential." The position

was further supported by an indepth review conducted by the licensee

which yielded only 5 of 111 surveillance procedures having

administrative procedures which had the " Potential" of being impacted

by one of the five administrative items.

The inspector reviewed this

evaluation and the particular procedures and could identify no sis

which would positively have been affected by one of the above stated

administrative issues.

In addition, the inspectors conducted indepth technical reviews of

the following sis in order to determine if the instruction was able

i

to perform its technical intent as written; whether the instruction

fulfilled the requirement of the surveillance requirement for which

I

credit was taken by the licensee; and whether any SI-1, Appendix F

Part II issues affected the technical adequacy of the sis.

SI-256, Periodic Calibration of Overcurrent and Ground Fault

Relays on RCPs and Backup Devices on 6.9kV Unit Boards, Units 1

and 2, Revision 9, June 2,1987. The inspector reviewed this SI

1

and found it to be adequate. However, the inspector nc;ed the

wordings in section 6.2 of the SI, stated that "The activities

within each data package need not be performed in the sequence

specified by this procedure" could contribute to different ways

of performing the SI by different individuals.

The inspector

- _ - _

-

.

. _ . ._

__ _ _ _ . - -_ __ _____ _ - ____ __ - _ _ - -_-__

..

,

7

discussed this' interpretation with the licensee, who stated that

the wording will be rephrased in a more stringent manner during

the.long-term surveillance instruction program.

SI-257, Periodic Functional of RCP Protective Devices, Units 1 -

and 2, Revision 11, June 2,:1987.

The inspector reviewed this

SI and found of t to be adequate. However, in Section 6.2 of the

SI, a. statement allows performance of the procedure in any

sequence. The inspector discussed this interpretation with the

licencee, 'who stated that the wording will be rephrased in a

more stringent manner during the long term surveillance instruc-

tion program.

SI-266.1.1, 60-Month Inspection of ITE'7.5HK-500 6900V Breakers,

Unit 1.and Common, Revision 2, June 3,1987. The inspector

i

considered this: SI to be adequate.

The insp'ector noted that

section 6.26 of the SI addressed a numeral

1000" without any

units or definitions associated with it.

The inspector noted

the appropriate unit would be " number of trips".

The inspector

also noted that the SI has a statement that allows out of'

sequence performance of the steps in the SI.

The inspector-

considered this would allow the SI to be performed in a dif-

ferent manner or sequence and may produce different' results.

The inspector -also noted the SI is very brief. (e.g. Section

6.7), and not clear (e.g. section 6.22). and the figures are not

clear -or legible.

The licensee- stated that the electricians

performing this SI are trained to read and use it correctly and

that they. have vendor references 'available from vendor manual

control.

The inspector requested a copy of the vendor manual,

and noted that the figures are indeed better illustrations.

The

inspector discussed the ~SI with the SI review program manager

and stated that if any document was worth' placing in the proce-

dure it was worth being legible.

The SI review program manager

agreed.

SI-7.3, Diesel Generator Fuel Oil Transfer Pump Performance

Test, Unit 0,

Revision 1,

June 2,

1987.

The inspector

considered the SI to be adequate. However, the inspector noted

the SI does not address common-mode failure nor does it make

i

reference to electrical maintenance section instruction letter

EMSL-A36. The licencee stated that they have instruments

designated for use on each train, and they will incorporate

EMSL-A36 into the SI. The inspector also noted that TS 4.0.5

required the SI to be performed in conformance with ASME

guidelines which stipulated a monthly test schedule. However,

the NRC has agreed in a letter (Novak/Parris) dated April 5,

1985, to a quarterly test schedule. The inspector noted that

p

'

this NRC letter is not made a reference in the SI.

!

l

m__________.___

___

n-_

__

_

.

._

._

.

.

_ _ . _ _ _ _ .

.

.

8

SI-275.1, Testing of Non-Clase IE Load Circuit Breakers Fed from

Class IE Buses, Units 0,1, Revision 8, April 23,1987.

The

inspector considered this SI adequate. However, the inspector

noted that this SI also allows out-of-sequence performance of.

the procedure. This SI is short, and has one prime objective,

which is to infect a current of 300% to verify that the breaker

would trip within a certain ' time range.

Further, this short

test would normally be administered to about 30 different

circuit breakers whenever the SI is performed. In view of this,

the inspector considered such wordings inappropriate for the SI.

SI-275.2, Testing of Non-Class 1E Load Circuit Breakers Fed from

Class IE Buses, Units 0, 2, Revision 12, April 23,1987.

The

inspector considered this SI adequate, and the comments for this

SI are identical to those for SI-275.1 above.

SI-102 EM, Diesel Generator Monthly Electrical Inspections,

Units 1, 2, Revision 4, . April 21,1987.

This SI was determined

to be technically adequate.

This SI also was determined to be

administrative 1y adequate with regard to Review Checklist items

II.1,6,7,18 and 21.

SI-93,

Reactor Trip Instrumentation Functional Tests,

Conditional 7-Days, (Prior to Startup), Units 1 and 2,

Revision 10, May 1,

1987.

This SI was determined to be

technically adequate.

This SI also, was determined to be

administrative 1y adequate with regard to the Review Checklist

Items II.1,6,7,18,and 21.

5I-153.4, Test Requirements for the Electric Hydrogen Recombiner

System, Unit 2, Revision 2, May 11,1987.

The inspector con-

sidered the SI to be adequate. However, with regard to common

mode failure, the procedure only made reference to EMSL-A36.

SI-92, Remote Shutdown Monitoring Instrumentation Pressurizer

Pressure Channel Calibrations, Refuel Outage, Units 1 and 2,

Revision 12, April 8,

1987.

This SI was determined to be

technically adequate.

This SI was also determined to be admin-

istratively adequate with regard to Review Checklist Items

II.1,6,7,18, and 21.

l

SI-109, Channel Calibration for RHR Flow Rate for Remote Shut-

down Monitoring, Refueling Outage, Units 1 and 2, Revision 9,

May 2, 1987.

This SI was determined to be technically adequate.

This SI was also determined to be administrative 1y adequate with

'

regard to Review Checklist Items II.1,6,7,18, and 21.

'

L

SI-247.701, Reponse Time Test of the Turbine-Driven Auxiliary

Feedwater Pump, (Refueling Outage), Units 1 and 2, Revision 4,

June 25, 1987.

This SI was determined to be technically

_ ____-_

.J

.c

'

.

9

adequate.

This SI was also determined to be administrative 1y

adequate with regard to Review Checklist Items 11.1,6,7,18, and

21.

SI-118,

Motor-Driven Auxiliary Feedwater Pump and Valve Auto-

matic Actuation,

Units 1 and 2, Revision 16, June 19,1987.

This SI was determined to be technically adequate.

This SI was

also determined to be administrative 1y adequate with regard to

the Review Checklist Items II.1,6,7,18, and 21.

SI-118.1, Turbine-Driven Auxiliary Feedwater Pump and Valve

Automatic Actuation, Units 1 and 2, Revision 16, June 19,1987.

This SI was determined to' be technically adequate.

This SI was

also determined to be administrative 1y adequate with regard to

Review checklist Items II.1,6,7,18, and 21.

b.

Surveillance Instruction Performance Observation

The following instructions were reviewed and observed during

performance in the field.

The procedures that were performed by the

licensee were previously licensee validated /or to be validated PORC

approved documents.

SI-24. A, Control Room Air Cleanup Subsystem (Train A).

The

inspector observed the performance of this procedure on July 28,

1987.

This instruction implemented the requirements of TS

surveillance requirement (SR) 4.7.7.b.

Step 5.1 of the

procedure requires the performer to verify the system lineup

prior to starting the fan.

This step was performed by verifying

damper position from the Control Room or utilizing the status

file and the configuration logs.

The inspector determined that

the use of these logs was appropriate.

Operations Section

Letter Administrative (OSLA)-58, Maintaining Cognizance of

Operational Status, requires that systems needed for the mode of

operation be maintained in accordance with the system operating

instruction (501) unless otherwise configured in the status log.

This SI appears to be adequate to meet the surveillance

requirement.

SI-38, Shutdown Margin, Units 1 and 2.

On July 26, 1987, the

inspector observed the performance of this procedure and

reviewed the results.

The instruction was found to meet the

requirements of SR 4.1.1.2.a and SR 4.1.1.2.b for current mode 5

performances.

The inspector questioned the Nuclear Engineer

about the Xenon contribution calculations.

The method used for

l

this performance only addressed Xenon content following steady

state operations.

A further review showed that Technical

!

Instruction (TI)-22, Shutdown Margin Calculation - Units 1 and

2, (one of the procedures utilized by the SI) gives additional

methods of calculating Xenon worth which includes appropriate

!L_-_ __ -

-

_

_

. .

__

.

10.

methods for transient operations.

This SI was not reviewed for.-

'

modes 1 through 4 uses.

The inspector'had no further questions.

,

  • -

_ SI-175, . Low Pressur'e CO

System - Level and. Pressure.

The

2

inspector reviewed this procedure to determine that it met the

requirements of SR. 4.7.11.3.2.a.-

On July 28, 1987, the inspec-

tor observed a performance of this instruction.

This procedure

appeared to be adequate.

SI-180, Fire Pump Start Test.

The inspector observed a perfor-

mance of this procedure conducted on July 29,1987.' -The SI

appeared to be adequate and no. discrepancies were noted.

'

"'

SI-90.72, Quarterly Functional Test of Reactor Trip /ESF Instru-

mentation, Rack 12 - Unit 2.

The inspector observed portions of

this instruction on July 28, 1987.

The instruction being

performed was Instrument Maintenance Instruction (IMI)-99 FT

9.1, "Online/Offline", Functional Test of Steam Pressure Devia-

tion Channel. IV, Rack 12 (loops P-516 and P 546) - Units 1 & 2.

_

This- instruction

implemented. the requirements of SR- 4.3.2.1.1.C.I.e, SR 4.3.2.1.1'.C.1.f and SR 4.3.2.1.1.C.4.d.

The

inspector questioned the. knowledge of the technicians on the

accuracies of the M&TE being.used.'

This will be followed in

future inspections.

The inspector observed testing up to step

5.15. in which 'the. pressure test point number was determined by .

the licensee to be incorrect.

The test was halted until it

could be corrected.

The inspector had no further questions.

SI-194, Periodic Calibration of Ice Condenser System.

The

inspector ' observed portions of this. instruction July 301987.

The SI appeared to be adequate and no discrepancies were noted.

SI-51, Weekly Chemistry Requirements. The inspector observed

portions of this instruction on July 30,1987.

The SI appeared

to'be adequate and no discrepancies were noted.

SI-128, Emergency Core-Cooling System Residual Heat Removal

Pumps.

The inspector observed a performance of this SI

conducted on July 31, 1987, on RHR pump 2A-A.

During the

performance of the SI the pump flow rate exceeded the acceptance

criteria as specified in the SI.

Investigation determined that

valve HCV-74-36 was in the open position which 'resulted in the

2A-A pump being cross connected with the 2B-8 pump which was

being used for shutdown cooling.

Valve HCV-74-36 was closed and

the surveillance was successfully accomplished.

Discussion with

l

the ASE determined that valve HCV-74-36 was not returned to its

l:

' required position after the completion of maintenance activi-

l

ties.

____ ___ - ____________________________ -

_ _ _ _ _

'

.

11

Review of the. circumstances that' resulted in valve HCV-74-36

being open and control of other systems required for mode 5 will

be identified as unresolved item 327, 328/87-50-01.

'

51-83, Channel Calibration for Radiation Monitoring.

The

inspector observed portions of this surveillance conducted on

July 29,1987.

During the performance of step 5.3 the Unit 1

Assistant Shift Engineer stopped personnel from performing the

procedure.

Radiation monitor 0-RM-90-101-0 was being cali-

brated.

Section 1 states that this monitor does not have any

TS requirements, so when the procedure was started an entrance

into an LC0 was not considered.

Step 5.3.7.2 requires the

monitor pump to be shutoff.

The pump circulates air through

monitors RM-90-101-A,B, and C.

Since RM-90-101-B is a TS

related monitor in the auxiliary building ventilation system, an

LCO (TS 3.3.3.10.b) was entered when the pump was shut off

without the knowledge of the operators or the technicians

performing the surveillance.

The licensee did however realize

the situation and took the appropriate action within the TS LCO

limits.

Additionally, a change was mde to the surveillance

instruction to reflect the common mode failure of the three

radiation monitors and the related TS requirement.

This is an

example of an SI-1, Appendix F, Attachment II, item 1 (common

mode) which must be addressed by the licensee in its long term

program and will be followed by URI 327,328/87-50-02,

c.

Inspector Follow-up Items and Licensee Event Reports

Open items are matters of concern to an inspector which are

documented and tracked in inspection reports to allow further review

<

and evaluation by inspectors.

The following open items were reviewed

and evaluated by the inspector in inspection report 327,328/87-36 and

determined to need additional action in order to be closed.

A brief

description of the current status of these items is provided below:

)

(Closed) URI 327,328/86-32-04, Pump performance data sheets from

SI-45.1 and SI-46 indicated a common practice of lining-out and

j

initialing original data, then recording new data without documenting

1

why the changes were made.

The licensee has issued Administrative

i

Instruction AI-47 Rev. O, Conduct of Testing. This procedure provides

{

adequate control for recording and documenting test changes.

This

i

URI is considered closed.

(0 pen) IFI 327, 328/86-32-12, Scaling data sheets in TI 41-68 contain

several scaling factor errors. Corrections to TI 41-68 have been made

1

and the revised procedure is being reviewed. Pending an approved

revision of TI 41-68 this item will remain open. Corrective action

j

must be complete prior to restart of both Units 1 and 2.

1

l

(Closed) URI 327, 328/86-32-07, Functional testing of Chlorine

Detection System requires that the alarm / trip function be tested as

,

,

part of the functional channel test.

Inspection Report 327,328/87-36

!

'

determined this item to be a violation.

URI 327,328/86-32-07 is

l

l

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _

- - . - _

-

_

_,

v

-

,3 :

,

7

>

,

>

12

' closed, the licensee'si cwrective actions will be followed in '

Violation 327,328/87-36-01.-

_ (Closed) IFI 327,328/86-49-02, The licensee identified during a

review of an internal tracking system, that TS surveillance 4.7.9.e.3

and 4.7.9.f may not'have been complied with during the' implementation"g

of SI-162.2. LA review of the licensee's actions indicates a thrbugh

review was made concerning the implementation. of SI-162.2. !The ,

W

results of their review indicates. that personnel error occurred

,

during calculations of snubber drag forces. The licensee revised the

procedure to clarify' the method for performing calculations.

Revision 6 of SI-162.2 which was approved on June 5, 1987, appears to

1

<

meet the funttional testing requirements for safety-related snubbers.

This IFI is considered closed.

-

I{

(Closed) Violation 327/06-20-08, Approxinstely 20 vent, drain and ,

test containment isolation valves were not verified to be in'their

proper position when SI-14, Verification of Containment lategrity,

was performed on. Hay 20, 1985. Revi m of the licensee's corrective

!q

action indicated all valves were' incorporated in either 51-14.1 or.

SI-14.2, except for 70-763.

1. d

,

Subsequently, the licensee has determined that the position of valve

70-763 does not require position verification because it.is a back-up

valve to 70-M6.

Violation 327,328/86-20-08 ie considered closed.

>

One additior,a1 IFI 'was reviewed which was not~ previously reviewed'in

. inspection report 327,328/87-36:

(Closed)'IFI. 327, 328/85-45-13,: Review implementation of DEP47 with

respect to tinely review of Watts 8ar' NCRs at Sequoyah.

The licensee

handles this issue through the implementation of AI-12, Rev.1,

Corrective Action. This instruction requiles items which may have a

potential affect on operability or have significant 4 pact on

conditions that affect quality be immediately transmitted to other

affected sites.

This procedure appears to' provide adequate control

to ensure timely dissemination of generic issues.

This IFI is

r,

closed.

The following licensee event reports (LERs) vera reviewed and closed.

The inspector verified that: reporting requirements had been met;

causes had been identified; corrective actinqs , appeared appropriate;

generic applicability had been considered; the LER forms were

complete; the licensee had reviewed the event; no unreviewed safety

I

questions were involved; and no new violations or deviations of

regulations or TS conditions were identified.

'

LERs Unit 1

i,87-005

Inadvertent Reactor Trip Breaker Opening Due To Personnel

l

Error During Performance Of A Post Maintenance Response

i

Time Test.

The maintenance technician was counseled on the

importance of correctly reading and following procedures to

i(

. . . _ _ _ _ _ _ - - - _ - .

o

1

g

r

,

.

13

1

prevent recurrence of simtiar events.

Maintenance craft

personnel received training on the details of this LER.

l-

This issue is closed.87-007

Deficient Procedures Fail To Include Response Time Testing

,0f A Small Portion Of Several Radiation Monitor Channels.

Tne licensee has updated the procedures to include response

time testing as specified in the TS. This issue is closed.87-008

Essential Raw Cooling Water Surveillance Requirement Not

Met As A Result Of A Surveillance Instruction Being

Inadequate Due To Personnel Error.

The licensee took

corrective action to ensure the eight manual isolation

e

valves 'were in their normal positions. In addition, SI-33

was revised to include the eight manual isolation valves

which should prevent recurrence of this issue.

This item

1

is closed.87-009

Ice Condenser pH Surveillance Requirement Not Met Due To

Plant Personnel Not Following Procedure.

The licensee

corrected procedure TI-11, which had conflicting sample

'

temperature values with the values specified in SI-58.

The

value was adjusted to 20 degrees C.

Both procedures-

conform to the specified value in the TS.

This item is

closed.

,,

e

87-014

BIT Heater Not Verit'ied Operable Every 31 Days Due To

Procedure InadequacyJ

The licensee revised SI-16 to

include the requirement to verify BIT Heater operability.

This item is closed.87-017

Surveillance Instruction Review Which Identified A

Potential Failure To Meet Minimum Boron Concentration Due

To Analytical Technique.

The licensee revised TI-11 and

7I-16 to retiect correct analytical technique.

This item

it' clued.

LERs Unit 2

87-006

Inadequate Determination Of The Heat Flux Hot Channel

i

Factor By The Incore Computer Program Due To Personnel

!

Error.

The licensee corrected the computer program anu

established the requirement for double verification of

changes to core monitoring computer programs.

This item is

closed.

In addition, the following Unit 1 LERs were reviewed in Inspection

Report 327, 328/87-36 and found to require additional licensee

corrective action.

A status and a brief discussion of these LERs is

addressed'below:

___

-.

_ _ .

_ - _ _ _ _ _ _

_ _ - _ _ _ _

.___

.

14

86-020

Failure To Perform A Quarterly Functional Test per TS.

SI-244.2 Rev. 7 does not contain a channel functional check.

for-radiation monitor relay F-15-43.

SI-244 also does not

contain a check for F-15-43 although the LER states that

the SI for unit I should be correct.

The licensee has

revised these procedures to include a functional check for

F-15-43.

This LER is considered closed.

y

86-039

Two Surveillance Requirements Not Performed Because of

Inadequate Procedures.

This item concerns the testing of

',,

the total interlock function for permissive P-4 in that two

of the five functions were not checked.

The licensee

e

developed and approved a new procedure, SI-268.3 Rev. O.

This procedure coupled with SI-94.2 Rev. 2 and SI-90.82

'

Rev. 5 now covers testing of the total interlock functions

i

for permissive P-4. This LER is considered closed.

i

/

86 042

Two Surveillance Requirements Not Performed Because of

Inadequate Procedures.

The licensee has requested relief

from ASME Boiler and Pressure Vessel Code,Section XI,

>

r

,

Subsection IWP-3100 -for several safety-related pumps

because of possible damage to the pump by throttling of the

pump miniflow recirculation loops during the running of the

test.

This item will remain open pending the response to

this issue.86-044,

Inadequate Verification Of ECCS Flow. Procedure SI-137.3

ms found to be inadequate in that it did not inclade RCP

seal pressure differential requirements.

Revision 4 of

SI-137.3 adequately addresses seal pressure differential

requirements. This LER is considered closed.

I

86-048

Inadequate Verification Of ECCS Flow Due To Procedural

'

-Inadequacy.

SI-260.2 was found to be inadequate in that

y

it allowed the testing of the CC' in mode 6 with their

miniflow valves closed.

A new procedure, SI-260.2.1 was

, . ,

issued to test the CCPs in mode 5 with their miniflow

,

valves open, and SI-260.2 is to be revised as part of the

.

,

"~/

corrective action for this LER.

Both CCPs 2a-A and 28-8

j

have been otisfactorily tested in mode 5.

The Unit 1 CCPs

1

.

will be tened before Unit I restart, and this LER will

l

remain a Unit I restart item only.

j

r

.$

"

d.

During the performance of inspection 327,328/87-36 several questions

i

were raised with respect to the Surveillance Instruction Program.

!

The questions were addressed in two memos to file (R. Denise/

I

L. Nobles) dated July 25 and 28,1987.

The inspector reviewed the

l

,

licensee's position on each of the questions which are summarized

i

below.

]

.

1

1

_ _ _ _ _ _ _ _ __

_

1

,

.--

-

..

_ - _

-

._-__-

.

.

+

15

Question 1.

The inspector-observed that the licensee's surveillance

instruction program description does not fully' discuss the long term

program and' no dates have been set for its completion.

The licensee

agrees that the long. term program has not yet been fully developed

and . documented. .This appears to be a restart issue, because it will

be -necessary to extract a long term commitment- in the licensee's

Nuclear Performance Plan addressing the surveillance instruction.long.

term program.

.In. addition,. several examples of issues which could

affect.-the adequacy- of the surveillance instructions have been

~

identified in the previous paragraphs of this section.

The

determination of a long term surveillance review program will be

.URI 327,328/87-50-02.

Question 2.

The inspectors determined that there was a second

independent group of reviewers which was not clearly addressed in the

ilicensee's submittal.

TVA stated that the group was identified in

-the SI program submittal'but was not named.

The group was determined

to be the Surveillance Validation and Verification group, and the

-inspector.has no further comments.

Question ' 3.

The inspectors . questioned the terms " independent

verification, independent review, second party verification, and

double verification signoff" which were used throughout the

licensee's submittal.

The licensee stated that "i_ndependent

verification, second party' verification and double verification

signoff" mean that an action has been independently (by another

p' arty) verified as complete and signed off.

The licensee stated that

independent verification and its interchanged words for the concept,

all- mean. verified; it is not acceptable that the first person simply

tell the second person that the required action was taken".

The

licensee has defined independent review to mean that "a person not

involved in the preparation of a work product has reviewed that work

product, usually a. document such as an SI".

The inspector has no

further comments.

Question 4.

The inspectors commented that it was not clear what

l

program or method was used to determine which instructions would not

be. included in the SI program prior to restart.

A set of criteria

was provided by the licensee froc a memo (L. Nobles / Plant staff)

dated January 20, 1987.

The criteria is separate from the SI review

program and is not referred to in the SI review program.

Based on a

,.

l

review of those SI procedures not reviewed in the prior to startup

phase of the SI review program, the inspectors were not able to

identify any procedures which, in the inspector's opinion, should be

reviewed prior to startup of either unit.

The inspector has no

further comments.

Question 5.

The inspectors questioned whether or not the latest

(post-CAR 86-050) SI-1 Appendix F (Part 1) checklist would be used by

the licensee to review those instructions which were determined not

-

_ _ _ - - _ _ _ _ -

_.

- - _

_

'

-

t

16

to be revised prior.to the startup of either unit.

The licensee

stated that "those instructions not on the list to be revised are

reviewed using the post-CAR 86-050 SI-1 Appendix F (Part 1) checklist

- to confirm that the instruction was adequate for its last performance

and fulfilled TS requirements.

If the review indicates that the

instructions are not technically adequate such that verification of

equipment operability is unsatisfactory, .these instructions will be

revised and performed prior to restart."

The inspector has no

further comments.

Question 6.

The inspectors stated that it was not clear what

standards are being used to determine skill of the craft in

Section III of the licensee's program.

The memos referred to above,

still did not define what level of craft skill the procedures were

written to.

The licensee's position was that the purpose of the SI

program is to write instructions which can be followed step by step

to fulfill the surveillance requirement.

However, neither the SI

program nor any other document supplied during this inspection

defined the skill level at which the sis are written.

This is

another example of the need to determine a long term SI review

program and will be followed by URI 327,328/87-50-02.

t

Question 7.

The inspectors commented that it was not clear what

training / screening process was used for personnel revising and

i

reviewing the instructions, especially'the responsible section super-

for persons who previously did

questionable work.

TVA stated that

visors determine the appropriate level of experience and knowledge

required to review and revise the instructions".

There does not

appear to be any objective standards established within the SI review

program to establish the minimum technical qualifications for those

p'ersons doing the technical reviews.

TVA additionally stated that

the qualifications for personnel performing SI reviews is governed

i

by SQA-21, and require a level of seniority, comp"etence, endorsement

j

by the supervisor and Plant Manager's approval.

The inspector

'

reviewed SQA-21 with respect to the standards set to determine if a

person was qualified to review and revise SI.

SQA-21 consisted of

only a list a names and gives no process or qualification standards

for reviewers.

This is another example for the need to identify a

long term SI review program and will be followed by URI 327, 328/

87-50-02.

Question 8.

The inspectors noted that section V. A of the licensee's

i

SI program stated that there is a dashed line from the site quality

'

assurance organization to the site Plant Manager and figure 1 in the

SI program showed a solid line.

The licensee determined that the

solid line in figure 1 was a typographical error and that the site

Quality Assurance Manager did not report to the Plant Manager.

The

inspector had no further comments.

>

hm__._-______-____.w__-

- _ _

,

. - - -

-

- - - - - _ - -

.;

.

)

'

e

17

1

Question 9.

The inspectors stated that the use of temporary changes

during validation needs to be clarified, especially on whether the

temporary changes will be made permanent.

The use of temporary

changes to procedures in general is still an open issue identified in

j

Inspection Report 327,328/86-62.

l

!

Question 10.

The inspectors noted that- figure 2 of the SI review

l

program plan did not show a return to the originating section after

final typing, and that this.should be clarified.

The licensee stated

that "the originating sections are the final reviewers of the changes

to the instructions".

The inspector had no further comments.

Question 11.

The inspectors observed that the verification /

validation package, ' Appendix J of the program plan, permitted

validation through simulated performance.

The NRC took the position

that validation through the use of simulated performance was not

acceptable.

The licensee stated that "a few instructions utilized

simulation equipment in the development of the SI, but verification

and validation are with plant equipment.

There was one case where a

spare fire hose was used instead of an inservice fire hose to

demonstrate the hydrostatic test setup, but this is not simulation in

the sense which would be inappropriate for validation."

The

inspector had no further comments.

Question 12.

The inspectors observed that the verification /

validation package, Appendix J of the SI review program plan,

permitted instructions which were only for data collection not to be

validated.

The NRC disagreed with this position.

The licensee in

the above cited memos stated that "we agree with this comment, and

all instructions which require such actions are verified / validated."

The inspector had no further comments.

Question 13.

The inspectors observed that Appendix J of the SI

review program plan permitted the cognizant reviewer to perform

instruction validation.

The NRC disagreed with this process.

The

licensee stated that "we agree with this and in the program,

validations are not performed by the instruction preparer and the

permissive comment in appendix J is not implemented." This licensee

did discuss one exception to the above statement.

This issue needs

to be included in the licensee's long term SI program and will be

followed as URI 327,328/87-50-02.

The inspector had no further

comments.

Conclusion:

The TVA SI program, as submitted to the NRC, has produced

adequate sis i.1 the short term.

The present surveillance instructions are

adequate to support the startup of either unit.

Long term control of

surveillance instruction upgrades including temporary changes, qualified

reviews, and administrative checklist items are not adequately described

___

.

. 3

,

'

,

p

-

.

a

18

Vw

l-

..

L

in~ the licensee's submittals.

The submittal of 'a' detailed long term

SI program with' completion. dates and milestones is considered to be a

'

startup item and will be~ addressed as such' in the staff's SER for

surveillance instruction review.

I

12.

Reevaluation;of the Seal Table Spill Event of 1984

The' ins)ector reviewed the following ' documents in an effort to resolve the

seal taale: issue.:

IR-327/84-11

,

.IR-327/84-24

'

IR-327/84-12 (HP report)

Nuclear Safety Review Staff (NSRS) Report 1-84-12-SQN.

Office of Nuclear Power Response to NSRS Report

Notice of Violation and Imposition'of. Civil Penalties EA84-119

Response to N.O.V. EA-119 date-6/6/85l

Revised-response;date 7/22/85.

IR-327/86-35 which closed IFI 84-11-03

IR-327/86-35-27 which closed VIO 327/84-24-01 thru -03

Inl addition to these - base documents, the . inspector reviewed . Various

' procedures, instructions and documents relating to the five items to be

-l

closed.

These documents are referenced where the individual items are'

discussed.

'

Violation 50-327/84-24-01

Technical Specification 6.8.1 requires the licensee to establish, imple-

ment, and maintain procedures recommended in Appendix A of Regulatory

Guide 1.33, Revision 2, February 1978.

Items 1.c,:1.e, 1.1., 7.e(1) and 9

,

of Regulatory Guide 1.33 specify that procedures are required-for equip-

ment. control, arocedure review-and approval, access to containment, access

,

control to raciation areas including a radiation work permit- system, and

. performing maintenance, respectively.

Contrary to the 'above, the licensee failed to establish and implement

adequate procedures for the conduct of equipment control, procedure review

and - approval, . performance of maintenance, radiation work permit access

control, and access to containment.

Examples of these failures are cited

below:

TVA Response

1.

Admission or Denial of the Violation

TVA admits the violation occurred as stated.

2.

Reason for the Violation

The violation resulted from the fact that adequate procedures were

not established and existing procedures were not implemented for the

____=_:--

_ _ _

_

_

__

. _ _

_

_

__ -

.

Lr

19

control of maintenance activities associated with the Unit 1 moveable

detector system.

NRC Comment:

,

(The presented " Reason for the Violation" only reiterates the cited

violation; it does not address the root cause of the violation.

Without adequate root .cause identification, the corrective actions

that follow for the specific examples tend to be symptomatic in

nature.)

Examples of Violation 327/84-24-01:

a.

On April- 19,1984, maintenance procedure SMI-0-94-1 for instru-

ment thimble tube cleaning and flushing was not implemented in

that Step 1.1 of the procedure forbids use of the thimble

cleaning system at power, and cleaning activities were performed

with Unit 1 at 30 percent power.

The procedure established at-

that time was inappropriate for use at elevated reactor coolant

system pressures and temperatures.

Corrective Action:

Special Maintenance Instruction (SMI)-0-94-1 has been cancelled

and replaced with Maintenance Instruction (MI)-1.10 "Incore Flux

Thimble Cleaning and Lubrication" incorporating lessons learned

in the thimble tube cleaning incident.

NRC Comment:

(This was a procedural violation.

Cancelling the procedure does

not address the violation.

No cause analysis is indicated by

the response, only that the problem was corrected by cancelling

the offending procedure.

The reason for the violation has not

i

been identified.

This response is inadequate.)

b.

Maintenance procedure SMI-0-94-1 was inadequately established

when issued on July 10, 1981, in that it contained no initial

conditions and no post-maintenance inspection or quality

assurance requirements for the thimble tube high pressure seals

which constitute a reactor coolant pressure boundary.

Corrective Action:

SMI-0-94-1 has been cancelled and replaced with MI-1.10.

MI-1.10 contains the applicable initial conditions to be met,

post-maintenance inspections to be done, and quality assurance

requirements (hold points) for the thimble tube high pressure

seals.

In addition, the incore thimble tube maintenance has

been included in the outage scheduling process.

l

-__

-

l

.

l

20

NRC Comment:

(As in item [a] above, cancellation of the flawed procedure does

not address the root cause.

This response addresses only the

symptom, not the cause.

Proper corrective action would include

.

action taken to preclude the issuance and use of a procedure

I

that was inappropriate for the conditions in effect at the time.

Failure to take adequate corrective action in this instance

I

should be considered a contributor to a later incident; namely,

the issuance and use of SI-166.3 to stroke-time test valve

1-FCV-63-1, which resulted in a RCS spill on February 1,1987.

L

The inability to recognize and correct a root cause continues to

l

lead to recurring failures involving inadequate procedures,

I

procedures used in inappropriate conditions, and cognizant

I

violations of procedures).

c.

Maintenance request implementing procedures for control and

review of maintenance activities associated with Maintenance

Request (MR) A-238084 dated April 18, 1984, was not implemented

in that:

(1) MR A-238084 did not delineate the applicable sections of

SMI-94-1 to be performed and thus provided inadequate work

instructions.

(2) MR A-238084 did not delineate requirements associated with

the job safety analysis as required by procedure SQM2,

Maintenance Management System.

(3) MR A-238084 did not reference the incore instrument

disassembly / reassembly instructions of MI-1.9.

(4) As of April 19, 1984, the Field Quality Engineering review

of MR A-238084 did not identify the deficiency of (a) above

and did not identify that the post maintenance testing and

quality assurance requirements referenced in MR A-238084

did not exist.

Corrective Actions:

A review of the MR process and QA review process has been

performed to ensure they meet the requirements of SQM-2, Main-

tenance Management System.

As a result of this review the

following adjustments have been made to upgrade the QA review

program:

(1) Initial MR review has been restricted to QA engineers,

management personnel (M-3 or above), or individuals desig-

nated by the section supervisors.

Designated individuals

f

- _ _

_ _ _ -

.

21

must contact a QA engineer for concurrence prior to

i

approving an MR.

!

NRC Comment:

(While .this corrective action implies that the violation

was caused by allowing unqualified individuals to review

MRs, that conclusion is not stipulated.

As a consequence,

1

it is not possible to determine the adequacy of the

i

corrective action taken.

Additionally, the procedure or

i

instruction that implements the corrective action is not

listed).

(2) Additional training has been provided to those personnel

authorized to review MRs.

The training included the

following:

(a)

Review of SQM-2 requirements for MR reviews.

(b) Review of requirements for identifying post-

maintenance testing for each MR.

(c) Review of Quality Assurance Section Instruction Letter

detailing MR review process (QA-SIL 5.3).

NRC Comment:

(The corrective actions listed imply that the training

given was of a one-shot, non-continuing nature.

This does

not appear adequate to prevent the recurrence of this

problem as the list of qualified reviewers changes.

This

appears to be a temporary fix).

(3) The Quality Assurance Section Instruction Letter, which

provides guidelines for review of maintenance request, was

revised to update systems and components requiring

post-maintenance testing.

d.

Administrative Instruction (AI)-8, Access to Containment, was

not adequately established as of April 19, 1984, in that:

(1) No guidance or positive controls are delineated in the

procedure to ensure that af riocks remain accessible for

egress routes.

(2) Paragraph 2.4 did not clearly delineate those maintenance

l-

activities on the incore flux monitoring system for which

the clearance on the incore flux drive motors could be

I

,

i

!

l

!

l

l

4

[-- -

__

l

_

_

. _ .

_ _ _

'

.

i

22

removed.

This resulted in incore detector system disas-

sembly activities being performed without the appropriate

clearance in effect.

Corrective Actions:

AI-8, Access To Containment, has been revised to clarify hold

order requirements for maintenance on the moveable detector

system and to ensure operability of personnel airlock

communications.

NRC Comment:

(This response appears adequate.

The corrective action should

preclude a recurrence of this violation.)

e.

AI-3, Clearance Procedure, paragraph 5.1.4, requires that no

work begin on equipment under clearance until the clearance is

issued to the person responsible for the work.

This requirement

was not properly implemented in that as of April 19, 1984, the

clearance for the incore detector drive motors covering thimble

tube cleaning activities was issued to a member of the opera-

tions staff and not to a field services supervisor responsible

for the cleaning activity.

Corrective Actions:

Sequoyah Nuclear Plant (SQN) personnel have been instructed to

ensure the person responsible for work is on the clearance (hold

order) prior to commencing work per AI-3, " Clearance Procedure,"

requirements.

This has been accomplished by including the AI-3

requirements in pre-outage briefing, periodic management safety

meetings, and by use of the existing clearance procedure

training classes.

NRC Comment:

(This response is inadequate as evidenced by a similar occur-

)

rence on February 1,1987, when a clearance on valve 1FCV-63-1

!

was issued to the ASE and not to the person responsible for the

work.

Positive controls in the form of specific changes to

clearance procedures and/or instructions on the hold / caution

tags may be indicated.

Every time a clearance is issued,

specific requirements such as issuance to applicable persons

should be mandated and controlled.

Training and lecturing

workers on adherence to procedures may be effective for rela-

tively simple procedures, but the use of upper tier documents

and the complicated nature of the procedure in question should

be considered when corrective actions are planned.)

- - _ - _ _

..

_

__

_

~

.

23

f.

Radiation Work Permit (RWP) 02-1-00102 issued January 1,1984,

for seal table area inspection and maintenance required workers

to verify the presence of a clearance on the incore instrument

probes prior to entering the containment lower compartments and

annulus.

This requirement was not implemented on April 18-19,

1984, by workers entering the seal table area in-that the

clearance was not in effect on the problems during work

activities.

Corrective Actions:

The RWP procedure and RWP cover sheet have been revised to

require the RWP timesheet to be removed when incore probes are

in use.

AI-8 also contains requirements for having the RWP

l

timesheet approved and in place for maintenance activities on

the moveable detector system.

NRC Comment:

(While this corrective action appears adequate and relative to

the issue, no evidence can be found of the implementation of the

I

corrective action in a review of the RWP procedure RCI-14.

If

later revisions have removed this stipulation, failure to

maintain commitments may be indicated).

Violation 50-327/84-24-02

,

Technical Specification (TS) 6.5.1.6 requires that the Plant Operations

Review Committee (PORC) review unit operations to detect potential nuclear

,

safety hazards and review all procedures required by TS 6.8.1.

!

Contrary to the above, these requirements were not implemented in that the

PORC:

1.

Did not meet and review the operational hazards associated with

thimble tube cleaning activities to be conducted in containment with

the unit at power on April 19, 1984.

I

2.

Did not adequately review maintenance procedure SMI-0-94-1 for

thimble tube cleaning and flushing on July 10, 1981, as evidenced by

the deficiencies identified in Violation 1.(b) above.

TVA Response

1.

Admission Denial of the Violation

TVA admits the violation occurred as stated.

-

_ _ - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

- - - - - - - - -

~-

- ' - - - - - - - - - - - - - - - - - -


t

.

!

I

24

'

2.

Reason for the Violation

i

The violation occurred due to personnel error in that the hazards

associated with . cleaning the thimble tubes at power were not

i

recognized.

Consequently, the PORC did not convene and review this

activity prior.to performance.

NRC Commenti

(The root cause of item 1 is stated as personnel error in that the

hazards associated with the tube cleaning were not recognized and

submitted to PORC for review.

Personnel error is applicable when one

individual makes an avoidable error.

If one individual incorrectly

determined that PORC involvement was not required, the process of

.

submittal to PORC should be reviewed.

If the failure identified by.

the violation is determined to be a collective failure by the PORC, a

single individual. was not responsible for the error and a program-

>

matic or procedural error is indicated.

The presented " Reason for

Violation' does not address item 2, which states that an inadequate

1

review of SMI-0-94 was performed by PORC.)

Corrective Action

a.

The PORC is performing more indepth detailed reviews of pro-

cedures and activities to ensure compliance with established

plant requirements.

Additionally plant management personnel who

serve as members of PORC have reviewed the duties and

responsibilities of PORC, as identified in TS Section 6.5.1.6

and Sequoyah Standard Practice SQA-21, Onsite Independent Review

(Plant Operations Review Committee).

b.

AI-4 Requirements for PORC review of plant instructions will be

followed for plant activities.

l

NRC Comments:

1

(Corrective Action item [a] addresses only the quality of PORC

reviews.

The violation clearly states that PORC did not meet and

review the operational hazards associated with the thimble tube

cleaning process.

The corrective action does not match the violation

or even the stated reason the violation occurred.

Consequently,

corrective action [a] appears inadequate to correct the original

error or to preclude recurrence.)

(Corrective Action item [b] states that AI-4 will be followed in

future PORC reviews.

This implies that AI-4 was not necessarily

i

followed previously.

Mandating

AI-4 adherence as a corrective

action carries the implication that some other, unspecified, set of

review criteria was in use when PORC reviewed SMI-0-94-1 in July of

1981.

Application of and adherence to a procedure that was already

in place and required to be folicwed is not an appropriate corrective

action).

1

-

_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _

25

Violation 50-327/84-24-03

10 CFR Part 50, Appendix B, Criterion II requires that activities affec-

ting quality shall be accomplished under suitably controlled conditions

which includes the use of appropriate equipment.

In addition,

Criterion III requires that appropriate measures be established for the

I

selection and review for suitability for the application of equipment.

Contrary to the above, as of April 19, 1984, the modified incore flux

monitoring system thimble cleaning tool used for thimble cleaning activi-

l

ties at power was not appropriate equipment for use on the reactor coolant

'

pressure boundary in that excessive stresses were transferred to the high

p essure seal on incore thimble D-12.

This resulted in a breach of the

j

reactor coolant pressure boundary.

In addition, management controls for

and reviews of modifications to the original vendor-supplied cleaning tool

were inadequate to prevent inappropriate modification of the tool and

subsequent use.

TVA Response

1.

Admission or Denial of The Violation

TVA admits the violation occurred as stated.

2.

Reason for the Violation

The violation occurred due to inadequate management controls being

established to ensure modifications to "special tools" received

appropriate reviews and approvals to prevent unauthorized modifi-

cations and use.

Corrective Actions:

Sequoyah Nuclear Plant has evaluated the need for establishing a program

to control the use and modification of "special tools." As a result of

this evaluation, SQN Standard Practice SQM-63, Special or Modified

Tooling-Primary System, has been issued outlining the requirements to be

followed for the use and modification of "special tools. '

In general,

special tools used on equipment fitting the following criteria fall within

the scope of SQM-63:

a.

Components which are in service, pressurized or energized.

b.

Components which, if the tool caused failure of the component, could

cause loss of primary coolant or the loss of uncontrollable amounts

of radioactive contaminated water during the use of the tool,

c.

Components which, if the tool caused failure of the component, I

could cause the loss of a safety function while the tool is

being used.

-_-

_ _ _ - _ _ _ - - _ _ _ _ _ _ - _ _ _ _ _ _ - - _ _ - - - _ - __ _ _- _.

-

-

._

- - _ _ _ _ _ - _ _ _

_

_ _ - _ _ .

_ _ _ . _ - _

.

.

..

..

_ _ -

. -

._

-

.

26

,

This Instruction may.also be used to document evaluations of other tools

as requested for reasons such'as-industrial safety considerations.

NRC Comment:-

)

.

.

.

.

.

1

(The. reason for the violation and the corrective action appear adequate in

-i

this response.)

-l

13. -Restart Test' Program

During ~ this . inspection period a special team . inspection was conducted to

evaluate the effectiveness of the Restart Test Program review process.

The objectives of this inspection were as follows:

To' verify that the Restart. Test Group (RTG) functional review process

is being adequately implemented.

.To verify that components / systems functions that are. identified as

requiring testing are properly dispositioned.

To provide a s' ample assessment of the technical adequacy of several

sis used to satisfy the functional testing requirements.

To provide 'a sample assessment of the technical adequacy of several

portions. of previously. completed preoperational tests that are being

used to satisfy the functional testing requirements.

_To provide a sample assessment of the effectiveness of previous post

maintenance testing.-

To provide a sample assessment of the correctness of the FSAR as it

relates to system functional requirements.

Tha inspectors reviewed the . identified system packages to verify

compliance to the specified program.

Specifically, the following items

were addressed during this review:

Verify that the functional analysis report (FAR) matrix package

contains the following documents as applicable:

Documents

i

l

FAR (SIL-5)

Functional Review Matrix (SIL-2)

Punchlist Report (SIL-2, sect 5.2)

Test Outline (SIL-2, sect 5.7)

Restart Test Program Interface

Report (SIL-2, sect 5.1)

_-

____-

,

.

1

27

Review (10-20%) Division of Nuclear Engineering (DNE) documents to

Restart Test Engineer (RTE) which list component / system functions

and verify that the functions were listed on the functional review

matrix (FRM) (SIL-2, Section 5.1).

'

Determine if RTE has identified any additional component / system

)

functions as a result of the reviews and ascertain the' reason the

i

functions . were 'not listed by DNE. . Verify that any additional

i

functions identified during the review were listed on the Punchlist

!

and determine if they were properly identified to DNE and if.the item

,

resulted in a Condition Adverse to Quality Report (CAQR).

Obtain

i

copies.'of any transmittal memorandum and place in system jacket.

Discuss with RTE their background experience and verify

qualifications, documented training, and required reading are in

accordance with SIL-1.

Review the FAR, including the punchlist report and FRM to verify

that, the above documents are in agreement as to number of identified

retests / tests to be performed, the disposition of punchlist items,

and the resolution of identified interface items.

Additionally, the

conclusions reached by the RTE should be evaluated and discussed with

the RTE.

The following points should be considered when performing

the above review:

(a) If the function has never been tested: is testing planned; what

type of function (i.e., control, indication, safety, etc.); will

a special test be written or will the existing SI be modified?

If a safety function is involved, was existing SI inadequate?

Was CAQR issued?

(b) If function was last tested during preoperational testing,

'

should it be included in an existing SI as a requirement or an

enhancement, added to a preventive maintenance program or ISI

program, etc.?

(c) Are TS, FSAR, and/or design criteria document changes necessary?

What method has TVA used to identify / track these changes?

'

Evaluate the supervisory and JTG review and approval of the system

package

On selected systems verify that the FRM reflects the functions listed

in the applicable FSAR and TS section.

l

On selected systems, conduct a sample review of the SI, preopera-

tional test, PMT, etc. , which TVA is taking credit for and verify

that the test and results were satisfactory. SIL-2, section 5.2 can

be used as a guide in this area. Also the checklists which are part

of the FAR should be evaluated.

_ _ _

,

a

28

The systems reviewed along with the inspectors findings are discussed

below:

a.

System No. 62, Chemical and Volume Control System (CVCS), is

described in Section 9 of the Final Safety Analysis Report (FSAR) and

applicable sections of the TSs.

The inspector discussed with the

RTEs: their related experience and educational background and

determined that both individuals were qualified per the procedure

requirements.

Their review of the system resulted in: (1) twelve

additional functions being added to the DNE listing of the system

functional requirements; (2) identifying redundant instrumentation

not included on a regular calibration schedule; (3) identification of

Condition Adverse to Quality Reports (CAQRs) not previously reviewed

for generic applicability for CVCS related equipment; (4) one valve

stroke time be:ng different than that in the FSAR but was found to be

included in a revision request; and (5) drawings were found with

discrepancies.

The restart test package appeared to be adequate

based on the selected sample reviewed by the inspector.

Areas found

to be deficient had been documented on punchlist or other tracking

documentation.

b.

System 92, Neutron Monitoring, is described in Section 7.2.1.1 of the

FSAR and Section 3.1.1.1 of the TS.

The inspector reviewed the FAR

'

and discussed the review process with the RTE.

The inspector

reviewed approximately 20% of the DNE documents submitted to the RTE

which listed component / system functions and verified that the

i

functions were listed in the FRM.

The inspector verified that all

'

open items in the FAR were listed on the punchlist.

The inspector

sample reviewed corpleted surveillance instructions listed in the FRM

to validate functions and verified that the functions were tested as

specified in the FRM.

The inspector did not attend the JTG meeting

i

that approved the system 92 FAR but was informed by the RTE that the

i

JTG review of the FAR found one technical error that had to be

'

corrected prior to final JTG approval.

Additionally, the inspector

.

noted that all system 92 functions were validated with surveillance

1

instructions. The inspector considers that this FAR adequately

addresses all system 92 functions and validations.

c.

System 30A1 and 30A2, Auxiliary Building Gas Treatment System and

Auxiliary Building Secondary Containment Enclosure, are described in

!

'

section 3/4.7.8 of the TSs and section 9.4.2 of the FSAR.

The

inspector interviewed the RTE and determined that the individuel met

the education and related experience requirement.

A review of the

!

engineer's actions associated with the restart tast package for this

system included the following: (1) deficiencies in the DNE listing of

the system functional requirements had resulted in additional

items

being added to the listing; (2) discrepancies identified between the

FSAR, TS, and the design specifications were added to the punchlist;

(3) CAQRs were reviewed for generic applicability for the system

equipment; (4) Engineering Change Notice Packages were reviewed and

. - _ _ _

-

y

1

'

.

29

I

!

i.

'

i

evaluated, and

(5) interface points were identified and listed.

I

Based on a sample review of selected items, the inspector determined

that the restart test package for this system was acceptable.

d.

System No. 65, Emergency Gas Treatment System (EGTS), is described in

Section. 6.2 of the FSAR Section 6.2 of the TS.

The EGTS consists of

the Annulus Vacuum Control and - the Air Cleanup subsystems.

The

primary safety function is to maintain negative pressure within the

annulus and to remove airborne particulate and vapors from air drawn

from the annulus that may contain radioactive nuclei.

The inspector

reviewed the functional analysis report / matrix package for the EGTS

which contained the required documents.

The RTE is an experienced

contractor.

His qualification, documented training and required

reading were in accordance with TVA requirements.

All safety-related

functions were identified on the FRM.

The RTE identified two non-

safety related functions which are included as punchlist items.

One

TS change was requested- for paragraph 4.6.1.8.d.1 to change the

specification for the pressure drop across the combined HEPA filters

and charcoal absorber banks from less than 8-inches water gauge to

less than 5-inches water gauge.

This item is tracked on TVA's

punchlist.

The licensee determined that SI-142, EGTS Filter Train

Test, was inadequate in that it would not enable detection of bypass

leakage around the EGTS filters.

CAQR SCP871216 was written to

document this and proposed corrective action will include detection

of bypass leakage within the scope of the test. Based on a sample

review of selected items, the inspector determined that this restart

test package was acceptable.

e.

System 90, Radiation Monitoring, is described in Section 11 of the

FSAR and Sections 3.3.3.1, 3.3.3.9, 3.3.3.10, and 3.4.6.1 of the TS.

The inspector reviewed the FAR, FRM, and FAR punchlist and conducted

discussions with the RTE.

The inspector also observed the licensee

perform testing that validated functions identified in the FAR.

The

FAR identified two valves that were required to reposition after

receiving a signal from the appropriate radiation monitor that are

not being routinely tested.

The RTE has punchlisted this item. The

licensee will incorporate this testing into existing sis and perform

the additional testing.

After RTE review of the test results the

punchlist item will be cleared. Inspector review of the FRM and

punchlist identified that the punchlist and FAR did not agree on open

items, one FAR open item was omitted from the punchlist, and the FRM

did not properly document which documents the RTE had reviewed.

Both

of these items are administrative in nature and have been discussed

with the RTE.

These items have been added to the inspector's

l

punchlist for system 90 future follow-up.

The FAR required SI-83,

Channel Calibration for Radiation Monitors, be performed to validate

system 90 functions.

The inspector observed portions of this SI

being performed by the licensee and was satisfied with the

performance.

Per inspector discussion with the RTE, the intent when

preparing the system 90 FAR was to cover all raciation monitors that

,

.__

______ _-

.

30

i

!

are FSAR or TS invoked.

There are additional area radiation monitors

that are not FSAR nor TS invoked that are located throughout the

plant that are not discussed in the FSAR.

Subsequent to JTG approval

of the system 90 FAR, the RTE discovered that area radiation monitor

2-RE-90-2 (area monitor at containment door hatch) is TS required.

Radiation monitor 2-RE-90-2 was not addressed in the FAR and the RTE

i

'

is in the process of adding this area radiation monitor to the FAR.

This item has been added to the inspector punchlist for future follow

up.

f.

System 74, Residual Heat Removal, is described in section 5.5.7 of

!

the FSAR and Section 3.4.1.3 of the TS.

The principal function of

l

the system is to remove decay heat from the reactor core during

shutdown conditions.

The DNE input to the RTE included these

functions and the transfer and refueling mode of system operations

were added by the RTE.

The safety injection mode of system operation

was picked up by the Safety Injection system and Containment Spray.

system which are described in FAR packages 63A and 72 respectively.

Interfaces include the 6.9 KVA, 480VAC, component cooling water and

heating and ventilation systems. During interviews with the RTE the

inspector' determined that he was qualified to perform the reviews and

l

his output satisfied program requirements.

The review process

'

resulted in the need for a special test to be developed to satisfy

the testing requirements for the interlock between the containment

sump valve and the RHR inlet isolation valves.

This test requirement

,

was punchlisted against the final package approval and will be tested

and resolved prior to complete closure.

g.

System 18, Diesel Fuel Oil, is described in Section 9.5.4 of the FSAR

and Section 8 of the TS.

The inspector verified that the deficien-

cies identified in Inspection Report 327,328/87-43 regarding the

!

transfer capacity of the 7-day-tank to the 1-day-tank transfer pump

was resolved in the JTG approved system 18 FAR package.

Additionally,

the inspector

veriffad that the RTE qualifications satisfied the

program requirements.

h.

System 250, Vital Control Power.

This system is described in Sectica

8.3 of the FSAR and Section 8.2 of the TS.

The July 27, 1987 JTG

approved FAR was reviewed by the inspector.

During this review the

inspector compared the functions described in the FSAR and TS against

the functions identified by the RTE on the FRM. Additionally, the

'

inspector's sample of functions identified by DNE indicated a

'

consistency with the RTE's findings.

The RTE met the program

requirements for qualifications and demonstrated a thorough knowledge

of the system when interviewed by the inspector.

Two new tests were

identified to check the battery output ripple amplitude and to check

the harmonic distortion of the system inverters.

i.

System 31A, Control 8uilding Environmental Control, is described

in Section 9.4 of the FSAR and Section 3/4.7.7 of the TS.

The

July 20, 1987 JTG approved FAR was reviewed by the inspector.

The

l

.

.

_ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _

__

f

'

.

lr.

i

31

inspector verified that FSAR and TS functions were included in the

FRM review. A 20% sample of functions provided by DNE as required by

SQEP-63 indicated that they had been included in the FRM.

The

testing of system functions using original preoperational tests and

current sis were sampled to confirm satisfactory results as to the

acceptability of the specified test to satisfy the functional testing

requirement.

The RTE's qualifications were verified and the _

,

inspector's interview with the individual indicated that he was

knowledgeable of the system he was reviewing.

The inspector examined

the functional analysis package open items punchlist to confirm that

functions which require new tests were properly dispositioned.

Two

new tests have been identified which when issued will check battery

room exhaust fan C-8 time delay and isolation damper failed position

verification.

i

j.

System 72, Containment Spray (CS).

The preliminary findings of the

RTE review of this system were discussed in Inspection Report 327,

'

328/87-43.

During that review CAQR SQP870860 was issued due to the

fact that the preoperational test for the CS pumps was not adequately

satisfied, in that the pump head may not be adequate to provide the

required system flow.

The resolution for the original preoperational

test deficiency was to insta'11 an in-line orifice.

Although the

installation of this orifice did resolve the pump head issue, it

created a flow problem and this condition has existed since the

installation of the orifice. The RTE indicated that the special test

currently being developed will verify pump head and evaluate heat-

exchanger D/P in the event that additional analysis becomes necessary

due to actual pump head not satisfying original design.

This issue

is identified as URI 327, 328/87-50-03, pending resolution and

evaluation of CAQR SQP870860.

k.

System 30A3 and 30A4, Containment Air Return Fans and Containment

.

Vacuum Relief System, are described in Sections 3/4.6.5.6 and 3/4.6.6

'

of the TS and Sections 6.6 and 6.2.6 of the FSAR.

The Containment

Air Return Fan system's primary safety function is to enhance the Ice

i

Condenser and Containment Spray heat removal operation by circulating

air from the upper containment to the lower containment, through the

ice condenser, and then back to the upper containment.

A secondary

function is to limit hydrogen concentration in potentially stagnant

regions by ensuring a flow of air from these regions.

The Vacuum

Relief System is designed to protect the primary containment from

excessive external force and does not provide any accident mitigating

function.

The inspector reviewed the functional analysis resort /

matrix packages for these systems which contained the requ" red

documents.

The inspector interviewed the Restart Test Engineer

(RTE), an experienced contractor, and determined that the individual

met the education and related experience requirements.

All

safety-related functions were identified on the FRM.

One TS change

was requested for paragraph 4.6.3.2 to change the requirement that

i

_ _ _

)

- _ -

-

_

'

.

32:

the' valves listed on Table'3.6.2 be demonstrated operable once per 18

months.

The method used in the surveillance requirement did not

demonstrate the isolation capability for.the three containment vacuum

relief lines which have separate pressure' switches that are com-

pletely ' independent of all other containment isolation signals from

any other system and the: valves would not respond to the = signals

specified in.SR 4.6.3.2.

This condition is identified in CAQR-SQP-

-870932 and is tracked on the TVA'punchlist.

The licensee determined that during conduct of preoperational test

TVA-6, not all of the ice condenser doors opened when the air return

fans were started as required by the design criteria. .This condition

was identified in CAQR-SQP-870860.

The corrective action for the

CAQR included revision of Section 5.2, System Testing, of the-SQN-DC-

V-13.9.5 design criteria to allow testing of the lower inlet doors to

the ice condenser by other approved methods.

The licensee did not

provide the inspector with an adequate analysis which provided

sufficient justification for not' testing the system as stated in the

original design criteria.

This issue is identified as URI'327, 328/

87-50-03, pending further evaluation by the inspector.

Test Witnessing

In addition to reviewing the above FAR packages the inspectors witnessed

the performance of portions of several sis that were identified by the

RTEs as being required to satisfy functional testing requirements.

SI-689, Auxiliary Control Air Operability Test.

The inspector witnessed

the performance of this test which verified that the safety-related air

compressors would start and " load" on a low air pressure signal and that

the non-CSSC equipment would isolate on further pressure drop to a speci-

fied set point.

The test instruction was appropriate for performance

of the test.

Some areas requiring minor maintenance were noted on the

test, comments and repair requests were generated.

The inspector has no

comments that have not been addressed.

SI-193, Containment Building and Auxiliary Building Ventilation Test.

The inspector witnessed the performance of portions of this test which

calibrated the annulus differential pressure channel 1-P-30-127 which is

common to loops 1-P-30-126 and 1-P-30-127.

The test instruction was

appropriate for performance of the test.

The inspector has no comments.

Joint Test Group (JTG) Activities

During the -course of this inspection the inspector attended several

meetings of the JTG.

The meetings were attended by a quorum of members

and minutes were recorded.

The inspector considered the meetings to be an

integral part of the overall review / approval process and the members in

attendance realized their individual as well as cumulative responsibility

[

to the overall product quality.

However, the inspectors did note that

L_____ _ __

-

. _ _

_.

-

_ _ _ _ _ _ .

________ _ ______ __ __ _

i

-

.

Ik.

j

33

!

although 20 meetings have been conducted only 5 meeting minutes have been

issued.

The rest are still in the DRAFT state.

This was discussed with

,

the restart test program manager, who indicated that due to the number of

I

meetings currently being held they were behind and they recognized the -

-l

need to process the minutes in a more' rapid' fashion.

!

Miscellaneous' Activities

In addition to the above inspection the inspector discussed with the site

employee concern program representative (ECPR) any concerns which may have

been expressed by employees in this area.

The ECPR indicated that no

concerns have been expressed in this area.

Additionally, the inspector

attended the QA audit debrief for this area and determined that the

licensee's proposed corrective action for resolution of the audit findings

,

i

appeared to be appropriate.

During a meeting conducted on July 31, 1987, the licensee committed to

modify the current instruction on preparation of the final test analysis

report.

This modification is needed to ensure that the final product is

consistent between engineers and should ensure that open punchlist items

are properly resolved as well .as ensuring that the FRM open review items

are closed.

14.

Abnormal Operating Instructions

The inspector reviewed portions of the following abnormal operating

instructions (A0I):

A0I-2, Malfunction of Reactor Control System

AOI-3, Malfunction of Reactor Makeup Control

A0I-4, Nuclear Instrumentation Malfunctions

A01-5, Unscheduled Removal of RCP(s) Below P-8

A01-8, Tornado Watch / Warning

A0I-11, Loss of Condenser Vacuum

The inspector verified that the licensee had established procedures for

combating emergencies and other significant events as described in

Regulatory Guide 1.33.

Within this area no discrepancies were noted.

15.

Containment Hydrogen Analyzer Operability

l

During an inspection conducted November 12-21, 1986, (Inspection Report

i

327,328/86-62). the inspector identified several as-installed conditions

that could have affected the OPERABILITY of the containment hydrogen

l

analyzer (URIs 327/86-62-01, and 328/86-62-08).

At the conclusion of

(

that inspection, NRC Region II, Division of Reactor Safety, requested

'

the Office of Nuclear Reactor Regulation (NRR) to evaluate the identified

conditions and determine if the as-installed system satisfies the

OPERABILITY requirements of TS 3.6.4.1. As part of the NRC evaluation, TVA

was requested to verify several as-installed conditions and provide this

information to NRR.

_ . _ _ _ _ _ _

I

_

.

35

described accuracy was changed to plus or minus 1.5 percent

hydrogen.]

As a result of the initial inspection discussed above, a Notice of-

Violation was issued regarding inadequate design controls for this

installation.

Subsequent to the initial inspection the inspector has been

working with TVA and NRR/0SP to resolve the H2 analyzer OPERABILITY issue.

Additional information has been - requested from TVA .during numerous

telephone calls with NRR/OSP and TVA was requested to consult their vendor

as to the acceptability of the installed system regarding line slope

(i.e., water traps) and lack of insulation.

The OSP reviewer indicated to

TVA that the instrument accuracy issue may be acceptable provided that the

emergency procedures . reflected this inaccuracy, and the vendor provides

written evaluation of the actual installation.

TVA was requested to

walkdown the system and determine the location and magnitude of any water

!

traps.

The vendor provided supplemental information regarding water traps to TVA

1

in a January 13, 1987, letter.

The vendor stated in his letter that the

system-would still function provided that the inlet vacuum did not exceed

a cumulative water head in excess of 5 or 6 feet.

Greater vacuum will

adversely affect the addition of reagent and calibration gasses making

-

calibration unreliable.

TVA provided the inspector the above letter and

an internal note which documented a telephone conversation of May 19,

1987, between TVA 'and OSP. In that note, TVA indicated that they provided

OSP the following information:

(1) Details of the January 13, 1987 Comsip letter

(2) Information that indicated the worst water trap in the sample

lines did not exceed four (4) feet

(3) That the analyzer is not calibrated during an accident

(4) That the vendor pump data included in the analyzer instruction

manual showed that the pump was designed to pull up to 24 inches

of Hg (27 ft. of water) vacuum in the least effective mode

The inspector requested that TVA walkdown (with the inspector) the

as-installed system.

The walkdown was restricted to Unit 2 only and

included the area outside of containment as well as portions of the

installation inside the containment.

The results of this walkdown

indicated that the worst water trap outside containment was 5 feet vs. the

4 feet claimed in item (2) above.

However., when the inspector walked down

the portion inside containment, water traps of approximately 14 feet for

train

"A" and 7 feet for train

"B" were noted.

When questioned, TVA's

Division Of Nuclear Engineering (DNE) design personnel indicated that they

had not considered the portion inside containment as a potential problem,

as they felt that temperatures in the area of the sample line would

prevent moisture from condensing in the lines.

During further discussions

)

l

4

i

-_-_-

-

.

34

To understand ~ the issue regarding the OPERABILITY of the H2 analyzers the

~

following excerpt from Inspection Report 327,-328/86-62, is provided:

[During the review of modifications to the'H2 analyzer, the inspector

noted problems with the initial installation of the H 3 analyzers for

both Units 1 and 2.

The original H2 analyzers installed in the 1978

time frame were later upgraded to satisfy the requirements of NUREG 0737, TMI Action Plan.

NUREG 0737,,. Item II.F.1 (6), Containment Hydrogen Monitor, required'

the accuracy and placement of' the H2 monitors be provided and

justified to be adequate' for their intended function.

TVA in their

December 10, 1980 letter (L. M. Mills 'to A. Schwencer, NRC) on TMI

Action Plan Item II.F,1 (6) described the system as follows:

"As a

"

result of the analyzers capability and the mixing afforded by the-

hydrogen collection system which draws from compartments w;m,,n the

containment and: the containment dorae a true indication will be given

of the hydrogen concentration.within containment.

The analyzers are

calibrated to measure hydrogen concentration between zero and ten

percent with an accuracy of plus or minus one-tenth of one

percent...."

The field installation of the H2 monitors for both Units 1 and 2 did

-not implement the vendor (Comsip Delphi, Inc.) requirements regarding

sample line slope and insulation. 'The failure to properly route and

-insulate the sample lines results in the condensation of moisture for

'

the containment post accident H sample in-route to the detector.

2

This installation can create two potential problems: (1) water traps

present a tortuous path for the H ' gas to reach the detector although

i

2

the vendor did indicate, in a phone call, that the pump was capable

of pumping any water that reaches the analyzer; and (2) a true

reading of containment vapor H2 concentration ~is not possible as long

as ' actual containment moisture is greater than that the detector

sees.

The vendor indicated that the reading could be higher than

actual by as much as a factor of five although TVA analysis, performed'

,

at the inspector's request, indicated a in ser error.

'

{

These inaccuracies appear to be in the conservative direction-

i

however, decisions based on the H indications are not conservative.

j

2

Specifically, Sequoyah Function Restoration Guidelines FR-Z1,

,

Response to High Containment Pressure,-instructs the' operator to NOT

,

place H2 recombiners in service and to consult the technical support

center for containment hydrogen purge instructions if H2 indication-

{

is-greater than 6%.

These actions, if based on erroneous high H2

1

indication, would be non-conservative and may result in post accident

complications.

)

The installed system does not appear to provide the degree of

accuracy originally claimed in TVA's December 10, 1980 letter.

In a

subsequent change to Section 6.2.5.3 of the Sequoyah FSAR, the

_ - _ _

._ _

_ - .

,

-

-

-

-_

-

-

_.

_

._- -_

_ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

t

  • -y.

Y.f =

'l

_

r

s

,

' :1_ '

l

E

36

with DNE ' personnel they indicated that a Westinghouse analysis of con-

tainment temperature- post LOCA indicated that _their assumption may not

be correct in the area where the sample lines run near the containment

air' return fans.

'

The; inspector, requested that- TVA walkdown the rest of the inside

containment installation and provide a sketch showing water traps and

tub _ing installation.

The results of this walkdown are not complete; .

however, several additional installation problems have been . identified.

Specifically, test , connections for the train

"A" installation were .

determined to not match the installation drawing as to location with

respect to the containment liner.

Additionally, these test connections

- were found to not inc'lude valves specified ' on the drawing and were

additionally found with the ' lines uncapped.

These two discrepancies

were documented on CAQR SQP 870430 and SQP 87031 and were evaluated for

7

deportability - on Potential Reportable Occurrence (PRO) 2-87-011.

The

containment integrity aspects of the missing valves were evaluated by the

licensee and TVA determined that the valves were most probably removed

after. the ,last_ successful test of the system which was conducted in

August 1985'_ during the current outage.

In addition to the' test valve

- problem, the walkdown determined that the train'"A" installation did not

run to upper containment as required.

Consequently, the only sample point

is at the top of the pressurizer cubical, thus not being able to provide a

representative sample of containment H

concentration.

The walkdown also

g

determined that although the train "B

sample line penetrated the floor

of the upper containment, it only ran upward approximately 18 inches.

-

Neither of these installations appear to meet the design requirements for

the -system, 'and ~ containment dome concentration is considered by the

inspectors to have ncver been adequately measured.

TVA DNE engineers are

currently working on a design ' change to modify both trains of containment

H analyzers to reduce the water traps to acceptable values and to rerun

~

2

the upper containment sample points.

However, during discussions with~DNE

engineers the inspector was informed that the modification will run the

upper' containment sample point only 6 feet from the floor and the

inspector questions whether this location will provide a truly represen-

tative sample as to containment dome H2 concentration.

This issue will be

addressed in TVA's submittal to OSP on the H2 analyzer issue.

d

This item will be remain unresolved (URI 328/86-62-08) pending OSP upper

management review for enforcement action.

Although, the inspection has

i

concentrated only on Unit 2, similar conditions may exist on Unit 1 and

i

this will be tracked under the original URI 327/86-62-01.

1

l

l'

]

!

.

ll'

1

I

-

1

i

i

L

___x

i