ML20235K631

From kanterella
Jump to navigation Jump to search

Const Team Insp Rept 50-353/87-11 on 870622-0702.Violations Noted.Major Areas Inspected:Hpci & Core Spray Sys & Const Practices on safety-related Piping & Equipment in Drywell, Reactor Bldg,Control Room & Diesel Generator Bldgs
ML20235K631
Person / Time
Site: Limerick Constellation icon.png
Issue date: 09/10/1987
From: Gray E, Gray H, Kaplan J, Kaucher J, Kamal Manoly, Paulitz F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20235K584 List:
References
50-353-87-11, NUDOCS 8710050172
Download: ML20235K631 (46)


See also: IR 05000353/1987011

Text

_ _ - _ _ _ _ _ _ - _ _ _ .

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

87-11

Docket No.

50-353

l

License No. CPPR-107

Category

A

Licensee:

Philadelphia Electric Company

2301 Market Street

Philadelphia, Pennsylvania 19101

Facility Name:

Limerick Generating Station, Unit 2

-

Inspection At:

Limerick Pennsylvania

Inspection Conducted: June 22 - July 2, 1987

9/03 / 6 7

Inspectors:

eN

E. H. /ra ,Le m Leade

&KA

rkus,

G

T

date

H

K. A. Manoly, Lead 6feactor Engineer

date

(f

9/et/f 7

~

. E. Kaucher, Resident Inspector

date

L . WY

  • ]/off7

H.

. Ka lan, Lead Reactor Engineer

/' da/ e

t

fMODY

9kl27

F. Paulitz, fleact'or Engineer

'd a te

Approved by:

/

%

- 9/C3/87

H. Gray, Acting, Chi ffiaterials

date

and Processes Secti81i

Su

R8an 87e nssa

O

PDR

-.

. - _ _ _ _ _ - _ _ _ _ _ _ _ _ _

.

.

2

Inspection Summary: Announced Construction Team Inspection conducted on

June 22 - July 2, 1987 (Inspection Report No. 50-353/87-11)

Areas Inspected:

The High Pressure Coolant Injection (HPCI) system, Core

Spray system and construction practices on other safety related piping and

equipment in the Drywell, Reactor Building, Control Room and Diesel Generator

Buildings were inspected. This construction inspection included piping,

mechanical, electrical, instrumentation and controls, and structural systems,

procedure reviews and observation of construction practices. The purpose of-

this inspection was to verify that the systems and hardware are being con-

structed with acceptable quality and in compliance with NRC regulations,

licensee commitments, and design specifications.

Results: The inspectors concluded, based on the sample of systems and

hardware inspected, that the plant systems and hardware are being constructed

substantially in accordance with NRC requirements and licensee commitments and

that construction is progressing with an acceptable level of quality. .However,

three violations were identified.

The violations include (1) failure to verify certain instrument data sheets,

parts lists, assembly drawings and connection diagrams as updated to the Unit 1

installed condition;-(2) not recording both ambient and motor temperature

during surveillance of a core spray motor requiring continuous heating; and,

(3) the finding of a fillet weld not in conformance with the AWS 01.1 code

after final QC inspection. Also, an apparent violation of 10 CFR 50.55e was

identified in that a design deficiency involving an emergency diesel generator

and fire protection system interaction was not reported.

This apparent viola-

tion will be the subject of a scheduled enforcement conference.

In addition, six unresolved items were identified.

These involved procedure

for covering of socket weld joints prior to welding, non safety steam piping

and drains located over diesel generator electrical components, flow switch

failure modes, procedures for review of document changes, errors in instrument

data sheets and a question of 50.55(e) deportability on SDR No. 135.

1

l

4

t

L__________.

J

!,

~l

e

>

i.

1

,

.

1

1

1

TABLE OF CONTENTS

PAGE NO.

<

1.0 Scope and Purpose of the Inspection . . . . . . . . . . . . .

4

q

i

2.0 Persons Contacted . . . . . . . . . . . .. . . , . . . . . . .

5

{

,

3.0 Safety Related Components, Piping Systems and Supports. . . .

6

3.1 Scope and Objective. . . . . . . . . . . . . . . . . . .

6

3.2 Inspection Criteria. . . . . . . . . . . . . . . . . . . . 6

3.3 Inspection Activities. . . . . . . . . . . . . . . . . .

8

3.4 Findings . . . . . . . . . . . . . . . . . . . . . . . .

8

3.5 Conclusions. . . . . . . . . . . . . . . . . . . . . . .

13

4.0 Electrical System Supports. . . . . . . .

.14

.. .. ....

4.1 Scope and Objective. . . .

. . . .

14

....... . ...

4.2 Inspection Criteria. . . . . . . . . . . . . . . . . . .

14

.

4.3 Inspection Activities. .

.14

.

... .... .. . ....

4.4 Findings . . . . . . . . . . . . . . . . . . . . . . . .

16

4.5 Conclusions. . . . . . . . . . . . .

. .

17

..

....

5.0 Electrical Power System . . . . . . . . . . . . . . . . . . .

18

5.1 Scope and Objective. . . . . . . . . . . . . . . . . . .

18

5.2 Inspection Criteria. . . . . . . . . . . . . . . . . . .

20

5.3 Inspection Activities.

................22

5.4 Findings . . . . . . . . . . . . . . . . . . . . . . . .

22

5.5 Conclusions. . . . . . . . . . . , . . . . . . . . . . .

28

6.0 Instrumentation and Control s. . . . . . . . . . . . . . . . .

29

6.1 Scope.

. . . . . . . . . . . . . . . . .

29

.......

6.2 Inspection Criteria.

. . . . . . . . . . . . . . . . .

29

6.3 Inspection Activities. . .

. . . . . . .

.30

.... ..

6.4 Findings . . .

. . . . .

32

........ .... . ..

6.5 Conclusions.

. . . .

33

......

... .... . . . .

,

7.0 Project Organization.

. . .

34

.........

.. .. ..

7.1 Construction Supervision and Management.

. . . .

34

.. ..

7.2 Project Engineering. . . . . . . . . . . . . . . . . . .

34

7.3 Construction Engineering . . . .

. . . . .

35

.......

8.0 Unresolved Items. . . . . . . . . . . . . . . . . .

....35

9.0 Exit Meeting. .

. . . . .

36

. ...... .... . ... .. .

Attachments

I

Persons Contacted

II

Drawings, Procedures and Documentation Reviewed

II-a Safety Related Components, Piping and Supports Inspected

II-b Electrical Safety Related Supports Inspected

II-c Electrical Power Systems Inspected

II-d Instrumentation and Controls Inspected

l

1.

i

___ _ _ _________ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ - _ _ _

.

l

l

I

l

l

1

DETAILS

i

1.0 Scope and Purpose of the Inspection

l

The Limerick Unit 2 plant is estimated to be 64% construction complete

and 90% engineering complete as of June 1987.

The purpose of this

.

inspection was to examine aspects of construction activities to establish

l

l

if selected work in progress is being done in accordance with construction

j

codes and procedural requirements.

The following inspection activities

)

regarding various aspects of construction, engineering, Quality Control and

)

Quality Assurance were performed during this team inspection.

]

Review of the Limerick Unit 2 construction program and inspection of

installed components to determine if they are in accordance with

engineering drawings and procedures and commitments in the Final

i

Safety Analysis Report (FSAR).

l

Review of procedures applicable to work, materials and construction.

Observation of components in the field.

Interviews with the construction work force at work ar as to deter-

mine if proper training, materials and instructions are provided to

properly handle and install components.

Review of work installation packages.

Independent measurements where possible.

Review of documentation to determine conformance to regulatory and

code requirements.

Evaluation of how QA is involved in construction and how QC checks

work in progress and after completion.

Examination of interfaces between Project Engineering, Construction

Engineering and the construction workforce.

The inspection was directed toward the High Pressure Coolant Injection

(HPCI) and Core Spray Systems followed by a sampling of other safety

related systems and components.

The piping, pipe and electrical supports;

electrical components, instrumentation and controls (I&C); pumps, valves,

welding, documentation work packages and procedures for the HPCI and core

spray systems were examined or reviewed.

I

l

l

._-___-_____O

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

>

..

.*

5

2.0 Persons Contacted

Numerous licensee 'and licensee contractor personnel were contacted during

the inspection. Attachment I is a list of the principal individuals who

were contacted by the NRC inspectors.

.

i

______________j

1

.

6

i

!

3.0 Safety Related Components, Piping Systems and Supports

3.1 Scope and Objective

>

The scope of the piping system inspections included the core spray,

loop B and the high pressure coolant injection (HPCI) system.

Both

of these systems are part of the Emergency Core Cooling Systems

(ECCS).

In accordance with part 6.3 of the FSAR, the HPCI system is

intended to provide sufficient water to the reactor coolant system

to maintain the water level above the top of the core #:c, breaks in

I

lines less than 1 inch nominal diameter. The core spray system is

to provide spray cooling of the core and to provide water inventory

makeup of the reactor coolant system during large pipe breaks.

Following inspection of the HPCI and the core spray systems, other

piping and pipe supports in the drywell and reactor building were

examined during dayshift and second shift plant tours.

During

inspection of installed piping and pipe supports, work packages.

including drawings, redlines, and Field Change Notices / Field Change

Requests (FCN/FCR's) were examined for work in progress.

Discussions

were held with craftsmen to find out if they were being provided with

adequate instructions, drawings, procedures and assistance or

guidance from field engineers.

The specific portions of the HPCI and Core Spray Systems inspected

are tabulated in Attachment II.a of this report.

3.2 Inspection Criteria

The governing criteria for the piping system inspections were:

10 CFR 50

Final Safety Analysis Report (FSAR)

Safety Evaluation Report (SER)

l

ASME Section III, Class 1 (NB) and Class 2 (NC) and Section IX

The verification of correct piping system installation was performed

either by visual inspection or by independent measurements on

accessible components and supports.

The detailed criteria used for the inspection of these installations

were those described in the specific installation specification.

The inspection attributes for piping and fittings included selected

verification of the following:

linear and angular measurements related to piping runs and

i

support locations;

,

1

L

1

I

u___.

___

__

l

- _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ - _ _ _ - _ _ -

'

.s

..

7

1

branch connection types and locations;

conformance of the piping details to the applicable piping

isometric as modified by redline change, Field Change

Notice (FCN) or Field Change Request (FCR).

welder and weld joint identification.

welder performance qualification

field work packages.

piping bend and elbow radii;

support mark numbers, functions and locations;

a

proper flow direction marks on valves;

piping wall thickness; as measured were compared to the ASME

-

code, NC3640 requirements and the Limerick calculation sheet.

correct sequential location of valves on piping runs; and,

proper identification and orientation of valves and Limitorque

e

operators.

The inspection attributes for pipe supports included selected

verification of the following:

as-built configurations compared to support detail drawing (BZ

series), including dimensions of members;

support orientation;

connection to the proper structure;

direction of restraint;

sizes and quality of weld on hangers, including welded

attachments to piping;

baseplate dimensions and location of structural attachments to

a

baseplate;

baseplate bolt (concrete expansion or Richmond insert)

tightness, edge distance and the bolt mark identification for

Hilti bolts;

restraint bleed holes open and free of foreign material;

_ _ _ _ - _ _

_ _ _ _ _ - _ _ _ _ .

o

,

8

grouting of floor mounted baseplates and gap sizes for wall

mounted plates; and,

pipe routing and support locations such that movements of

piping due to vibration, thermal expansion, etc., would not

likely cause contact with other pipes, supports, equipment or

components.

3.3 Inspection Activities

Inspection of the core spray and high pressure coolant injections

system consisted of the following activities:

Walkdown inspection of as-built piping components (including

fittings and attachments), equipment and system supports;

Independent comparison of selected piping components and

supports to the attributes identified in Section 3.2;

Comparison of valve and pump identifications to those shown on

the P&lDs and isometric drawings.

Review of selected QA Audits, QC inspections, non destructive

examinations, ASME Code Authorized Inspection signoffs, non

conformance reports and dispositions, the involvement of

construction engineering and the specific work packages.

Review of representative shop and field data sheets, associated

NDE reports, and material test repnets for base metai and weld

filler materials as required by ASME III-NC and ASME IX.

Measurements of pipe sizes and wall thickness were made.

Visual inspection of welds and component surfaces.

3.4. Findings

a.

Visual Examination

The walkcown inspection did not reveal any significant

deficiencies or discrepancies.

The piping components including

valves and connections were found to conform to the drawing and

work package requirements including redline revisions, FCN's and

FCR's.

Valve 2F007 shown on drawing DCA-419-1, a gate valve

'

with full functional flow from either end was found to be

installed in the inverted position in accordance with the Field

_ _ _ _ _ - _

.

.

_ _ _

_ _ - _

--

-_

_ _ _

,

s* . . ,

..

-

9

Changes' Notice (FCN) dated MarchI16, 1987'.

The piping drawing.

.

will be revised by project engineering to include this. change,

b.

Measurements of Pipe Wall Thickn'ss

e

The inspector determined' wall thickness measurements at 132-

locations in.the HPCI and CS systems using an ultrasonic "D"

meter. ~All readings exceeded speci.fied minimum wall require--

ments' of the P-300 piping specification, the Limerick piping :

minimum wall calculation sheets and the ASME Code Section III,

NC 3641.

'

c.

Documentation Review

ihe inspector randomly selected various: items in the CS

and HPCI systems-for documentation review.

These. items were

'

identified during a walk-down and are discussed below.

'

..

Field Welds FW-4, FW-6 and FW-12 (150-GBB-212-1)

!

=

A review of weld data' sheets indicated that the subject'

joints.were welded in,accordance with qualified Section IX

Welding Procedure PI-AT-LH/5 using the Tunsten Inert Gas-

(TIG) process for an open butt root pass'and the manual

metal arc-(MMA) process for the remaining. layers.

Review of. typical. filler metal reports for bare wire ~and

electrodes used in the fabrication of these welds revealed

no deficiencies. A check of four welders (P78, PTF, P3M'&

PSE) involved in welding these joints disclosed proper

i

qualification at the 1.ime of. production welding. Documen-

tation showed that these-welds'were examined by radiography

and magnetic' particle inspection.

Qualification and certi-

fication for three NDE inspectors noted on the inspection

records was reviewed and found to-be satisfactory.

I

Spool Pieces HBB-208-1-2 and HBB-209-1-4. A review of

document packages furnished by Texas Pipe Bending' revealed

material test reports conforming to designated SA carbon

steel material specifications (SA 105, SA 106 Gr.B and SA

<

234 WPB). These data packages contained acceptable liquid

p

penetrant and radiographic reports.

l-

1

l

l

a__L_____-__

_ - _ _ _ _ _ _ _ _ _

6

l

'

10

Core Spray Pump - S/N - 0771131

The document package contained certified test reports that

conformed to SA 516 Gr 70 and SA 333, carbon steel-material

specifications. The material reports showed satisfactory

tensile properties and acceptable impact test results at

i

+10 F.

'

Valves

The inspector reviewed several valve packages in the HPCI

and Core Spray Class 2 systems and noted a variance in

impact testing.

Some valves such as the Anchor Darling 12"

150# gate valve (HV-F072) were furnished with impact test

results whereas other valves such as the Atwood & Morrel

12"-150 valve (2F021) were not impact tested.

In response

to the inspector's question concerning this difference,

Bechtel's principal engineer stated that only the contain-

ment isolation valves greater than 6" 0.D. nominal pipe

size, in the Class 2 system required impact testing. The

inspector sampled documentation for valves over 6" and

confirmed that the containment isolation valves requiring

impact testing exhibited acceptable impact test results.

The lowest service temperature for the HPCI and CS piping

systems are 40 F and 42 F, the lowest water temperature

anticipated in the suppression pool and condensate tank,

i

respectively.

These temperatures should be well above the

nil ductility transition (NDT) temperature for heat treated

(normalized) carbon steel castings of the sizes encountered

in the HPCI and CS systems.

For example the Limerick data

showed that normalized SA-352 Gr LCB castings used for

,

pressure boundary parts, such as body and bonnet, exhibited

I

acceptable impact properties at 0 F or lower.

The inspector reviewed several Class 2 containment isola-

tion valves packages in the HPCI and CS systems and one

Class 1 valve package in the CS system and verified that

the pressure boundary parts of valves with nominal pipe

size greater than 6" were impact tested and had acceptable

impact properties.

The sampling showed that for those

valves which did not require impact testing, castings were

j

normalized, a heat treatment which should provide accept-

j

able impact properties.

]

l

)

l

\\

\\

I

I

- _ _ _ _ _ _ -

-_

_

.

'-

11

Bolts and Nuts

The inspector randomly selected two purchase order

packages covering bolts and nuts, P.O. 8031-F - 60251 and

l

P.O. 18240 - F203929.

The packages contained mill test

reports indicating conformance to SA 193-B7 (bolts) and

SA-194 Gr 7 (nuts) along with magnetic particle inspection

reports.

d.

Audit Reports

The inspector reviewed audit reports generated by Bechtel and

PECo QA organizations.

The Bechtel audits as tabulated below

covered the installation of valves and small bore and large bore

piping.

Small Bore

Large Bore

Valve

Pipinj

Piping

..

Audit:

PFA 797-

PFA 820 -

PFA -

2/20/87

6/2/87

12/23/86

Next Scheduled

Audit:

7/24/87

1st Qtr. 88

9/14/88

The Bechtel audit reports for construction of piping included

material traceability, welding, NDE and hydrostatic testing and

were written in great detail. The valve audits included wall

thickness measurements, hydrostatic testing, orientation, flow

direction and weld quality.

The inspector reviewed eleven (11) PECo Audit reports and two

surveillance reports covering a period between December 1986

and June 1987.

No significant problems or deficiencies were

reported.

PECo performs surveillance checks of safety related

construction including electrical, instrumentation and controls,

mechanical, piping, welding and nondestructive examination. The

surveillance activities result in PECo QA being fully involved

in ongoing construction activities.

Review of the audics indi-

cated that problems are identified at early stages to provide

for timely corrective actions.

e.

Non Conformance Reports

The inspector reviewed five NCR's (#1170, #1160, #11453,

  1. 10975 and #10439) and concluded that no gross deficiencies

or discrepancies were encountered. All conditions described in

the NCRs were eliminated by refurbishment or other suitable

actions as approved by engineering.

I

- - - -- --

i

b

.

'

12

'

,

-

f.

Bechtel Weld Laboratory and Weld Shops

The inspector witnessed bend testing of root and face specimens

prepared from two performance qualification test assemblies

fabricated by Welder P26.

The welder was being tested on 2"

Sch. 80 carbon steel pipe using an open butt TIG procedure

PI-T in the 2G and SG positions. The bend specimens were

successfully bent to ASME IX requirements. The inspector toured

the weld shop and examined several spool pieces currently being

welded.

Review of associated work packages and interviews with

the welders indicated that welding was being performed by

qualified welders in accordance with prescribed weld procedures

and work package requirements.

g.

Cleanliness of Material During Installation

Construction Procedure CP-P-7, paragraph 5.3.1 requires

that open ends of mechanical equipment and piping be sealed

except when being worked.

PECO QA had previously identified a

problem.with construction maintaining proper pipe spool end

cove' rage as noted in the QA site monthly report dated 5/5/87.

The NRC inspection team observed a large number pipe and

equipment openings and determined that almost all pipe and

equipment open ends were properly covered with the following

exceptions.

HCD-211-E19

No cover on the end of a short pipe extending

from a closed valve at elevation 283', AZ

0.

DBD-203-1-1 and DBD-204-1 *, The feedwater piping closure weld

preparation',, although nearly in alignment were

not covered.

SP-DCB-XX

Three CRD lines were not in sockets and

were uncovered.

Dirt or debris was not observed

on the surface of the closed valve below the

socket.

Each of the above isolated cases were corrected by the

licensee.

Numerous CRD pipe to socket weld joints at about the

265' elevation had the CRD pipe resting in the socket directly

I

above the closed CRD system valve for each pipe section.

The

socket weld joints were not covered.

The inspector verified

that the pipe to socket fitup tack and weld sequence for these

[

welds did require removal of the pipe from the socket, removal

of any dust or particles from the socket and examination of the

valve which is located directly below the sockets prior to tack

welding the pipe in the socket.

This operation is monitored by

QC inspection and construction engineering.

The procedure

CP-P-7, part 5.3 does not address the requirement for control of

_ - - - - - -

I

-_

_ .

!

f

'l

,

13

i

socket weld cleanliness where a pipe is positioned in the socket

without welding or covering of the weld joint. This is an

!

unresolved item pending PECo review of CP-P-7.and possible re-

vision to define the cleanliness requirements for pipe to socket

'

weld joints including the maximum time between tack welding and

root pass welding of pipe to socket welds.

(50-353/87-11-01)

3.51 Conclusions

!

Based.on NRC inspection of installed piping, pipe supports and

I

safety related components and review of applicable documentation and

I

procedures it was concluded that installation is proceeding per

drawings traceable to the FSAR and in accordance with applicable

procedures

The work packages were found to be readily available

i

.for use and up to date for the work status.

Quality control,

quality assurance, project- engineering and construction engineers

were found to be involved in the construction activities.

No

significant problems were identified.

l

l

I

.

- - _ . - - - . - _ . - - -

-

. __ _

...

14

4.0 Electrical System Supports

4.1 Scope and Objective

The scope of the electrical system supports inspection included

review of the activities performed by project engineering, construc-

tion and quality assurance. The inspection included interview of

cognizant personnel, review of pertinent procedures and examination

of electrical raceways, wireways (gutters) and conduit support

installations.

The primary objective of the inspection was to

determine whether electrical system supports were installed in

accordance with regulatory requirements, FSAR commitments and

approved construction specification and drawings.

Additional

objectives were to determine whether the procedures, instructions

and drawings used to accomplish construction activities were

adequate and whether quality related records accurately reflected

the completed work.

4.2 Inspection Criteria

The governing criteria for the inspection of electrical system

installations were:

10 CFR 50

Final Safety Analysis Report (FSAR)

AISC Steel Construction Manual

AWS Structural Welding Code (Steel) 01.1

AWS Structural Welding Code (Sheet Steel) 01.3

4.3 Inspection Activities

The inspection of electrical system supports included the following:

Review of the approach and process used by Project and

Construction Engineering in selection of the various types of

electrical system supports.

Review of the procedures governing the selection and spacing of

required supports. Attachment II-b provides a listing of

documents reviewed.

Performance of a walkdown verification of the electrical system

supports in the control (switchgear and cable spreading rooms)

and the diesel buildings (D-room). Attachment II-b provides a

listing of inspected electrical installations.

Review of quality control inspection records of electrical

supports systems verified in the walkdown.

1

- - _ - ___.

I

,_ __ .

_ _

_

_

_ _ _ _ _ _ -

_ _ - __ - -_ _ __

.

'

15

,

Overview of construction activities

The size and routing of raceways was determined by the

electrical discipline.

Designation and location of required

supports was shown on the electrical. raceway layout drawings by

the project civil / structural engineering discipline.

Supports

,

I

designated on the raceway drawings were selected from speciff-

cation E-1406-2.

Deviations from the generic or specific con-

t

figurations identified in the specification, required the

origination of Field Change Requests (FCR's) by construction.

The majority of Unit 2 cable' tray and conduit installations

were erected during the Unit I construction phase.

These

l

installations (designated as Unit 1 and common area) were

selected from specification E-1406-1.

Unit #2 installations

,

erected after the restart of construction in January 1935 were

!

mainly located in the reactor and diesel buildings.

Bechtel

has the responsibility for the design, selection and construction

of all cable tray, conduit and gutter support installations.

'

The responsibility for inspection of all Category I electrical

installations is Bechtel's and of Category IIA installations is

PEC0's.

Selection of conduit supports was performed by field engineering

!

based on requirements in specification E-1406 which included

size of conduit and span (maximum 10'-0").

Drawings showing

layout of supports and connection details were prepared by field

l

personnel, and included as a construction aid occument in the

l

work packages, for use by the construction craft for erection.

Field personnel performed inspection of completed conduit

installations and transmitted the work packages to QC for final

inspection. As-built drawings were made for conduit supports

j

installed in the common areas of units 1&2.

I

Gutter supports in the common areas of Units 1&2 were selected,

detailed, and inspected in a similar process to that utilized

for the conduit supports in these areas. Work packages for

gutters installed after the restart of Unit 2 construction has

typically contained the list of gutters to be installed, esti-

mated length, reference to support configurations and details in

l

specification E-1406-2 and the location of the supports along

!

the length of gutters.

I

The inspection of electrical system support installations was

'

performed to the attributes in the quality control instruction

QCI-E-2.0.

l

_ _ _ _ _

_ - _ _

_

,

_ _ _ - - _

. _ _ _ _ _ _ _ _ - _ _ _ _

____ __ _ _ - -

.

'

16

4.4 Findings

The following findings'were noted during the review and inspection

of activities related to electrical system support installations.

Some discrepancies were noted during the inspection of Category

a.

IIA electrical support installations in the cable spreading room

at elevation 254'-0".

These included:

(1) A drawing error.

resulting in lack of identification of support P7 for tray Nos.

20TBV, 20TCW, 20TDX, 20TEY & 20KFZ in proximity of building

column line No. 23, (2) A lack of documentation of configuration

.'

for support No. CSR8A(SIM), and (3) An improper connection of

support S6 (brace type) to an adjacent C30 support rather than

to designated tray (20TGT) rail.

The inspector.found that the category IIA installations in the

room were erected during the construction of Unit 1.

These in-

stallations were not yet inspected by PECO (QC inspection of IIA

installations is the responsibility of PECO).

The inspector was

informed that' field change requests were issued to document and

resolve the above noted discrepancies during this inspection.

b.

The approach adopted for selection and documentation of generic

or specific support configurations and details for cable tray,

gutter and conduit installations was found to be cumbersome,

difficult to follow and open to interpretations.

Specification

No. E-1406-1 & 2 for conduit and cable tray notes and details

consists of four large volumes containing immense selections for

generic and specific support configurations and details.

The

inspector did not identify safety problems resulting from the

!

practice described above,

However, some of the discrepancies

i

noted in category IIA installation (item 1 above) could have

resulted from the complexity of this approach.

It is note-

worthy that the electrical system supports examined were found

to provide adequate structural restraint to the installations

involved.

c.

Inspection of multiple conduit and gutter support No. CBL-G-474

in the cable spreading room at elevation 254'-0" resulted in the

identification of two deficiencies in the fillet weld connecting

the top end of the diagonal brace to the vertical member in the

frame.

The fit-up gap between the connecting tube steel sec-

i

tions exceeded the 1/16" limit of AWS DI.1 welding code, and

,

the weld size was smaller than the minimum required 3/16".

In

l

some portions along the length of the weld, the size of the

j

weld was less than 1/8".

Upon inspection of the similar frame

j

(No. CBL-G475) in the cable spreading area in Unit 1, the same

i

weld was found to be undersized (i.e. less than 3/16").

Review

I

of QC inspection records (QCIR no. E1175-W-124) indicated that

]

- - _ -__ __-__ -_ ___

. _ _ _ _ _ _ .

i

,

17

the welds on both supports in Units 1&2 were accepted by QC in

)982. The deficiency identified in the electrical supports'

welds is a violation of the master quality control instruction

QCI-W-1.00, the project instruction 8031/W2.00 for welding and

non-destructive examination and Criterion X of Appendix B to

10 CFR 50 for inspection.

(50-353/87-11-09)

4.5 iConclusi_on

Based on results of the review and inspection of electrical system

supports, the team concluded that the systems were adequately

supported for anticipated design loads.

Though the approach for

.

selection and documentation of support configurations was rather

i

cumbersome and involved, and in several cases was difficult to

follow, the inspection of Category I installations did not result in

the identification of any non conformances other than the case of

undersized fillet welds on the multiple conduit and gutter supports

'

noted in Section 4.4 above.

Several discrepancies were also noted

l

during the inspection of seismic category IIA support installations

'

in the cable spreading room, however, they were not yet inspected by

PECO's QC.

4

_ - . _ . _ _ _ . . - _ . - _ . - . . - - - -

t

'

.

18

5.0- Electrical Power Systems

l

5.1 Scope and Objective

Objective

This inspection was conducted to determine if construction activities

related to safety related electrical systems and components were in

conformance to the requirements of 10 CFR Part 50 Appendix B and the

licensee's commitment in the Safety Analysis Report (SAR).

The objective of the inspection activities was to determine the

conformance of safety related electrical systems and components to

applicable requirements.

The following inspection activities were

performed:

Review of procedures for the electrical systems and components to

determine if the above requirements and commitments have been

adequately translated into applicable construction specifica-

tions, drawings, work procedures, and instructions, and whether

these procedures are of sufficient detail and clarity for

adequate work performance and control.

Review of quality assurance plan and activities to determine

that changes to these procedures were controlled and that the

quality control inspection plan of installed safety related

electrical components has attributes which reflect the

requirements of the procedures.

Review of records to determine if the licensee and contractor

systems for preparing, reviewing, and maintaining records are

functioning properly; that the records reflect work accomplish-

ment consistent with the above requirements and commitments;

and, to determine if the records indicate any generic problems,

management control inadequacies, or other weaknesses of safety

significance.

Direct observation and independent evaluation of selected work

performance, work in progress and completed work to determine

whether activities related to safety related electrical systems

and components were being controlled and accomplished in ac-

cordance with the above requirements, commitments and licensee's

procedures.

Determine if inadequacies, in these work activi-

ties, concerning electrical systems and components indicate a

management control problem or generic weakness.

i

l

!

1

I

_ _ __ _-__ _ _ - _ _ _ _ _ _ _ . _ _ . _ _ .

_

_

._ _

__J

_ _ _ - _ _ _ - _ _ _ .

_ -

- -

.

.

19

, .

,

t

Independent evriuation to determine if the correct electrical

requirisents were incorporated into the purchase specification

of se Hcted safety related electrical components; that the

purchased eciuipment received has the correct electrical require-

ment's (through verification of vendor test data and/or name

. plate dsta); and, that the equipment received was stored, in

accordance with procedures, as determined by direct observation

or recrds.

?

Direr. observation,)cdependentevaluationandinterviewsof

'

16 ensee and contractor' personnel to determine if the on-site

and off site engineg ing activities are being performed in

'accordacce vith the above requirements, commitments and licensee

procedorrr.

-

,

?

i

Direct obse/ vat' ion, lnersonnei interviews, and record reviews to

5i

determine if the QuaDty Assurance Program is being conducted

  • ",

!

in accordance with procedures and (1) that electrical personnel

.

inchw"og quality control personnel are following these pro-

l

cedures, (Q that the attributes for inspection are understood

>

,

l

l

through trainirg and verified by audits, (3) that nonconformance

'

of electried system u d components are identified and evaluated

for corrective 4ction in a timely manner, (4) that non-conform-

,

l

ing items are revi+;wed and accepted, rejected, repaired or

'

,

reworked in acco @ nce with documented procedures, and (5) that

"

those items accepted "as-is" have as a basis proper engineering

basis and justification.

,

,

Direct observation and procedure review to determine (1) if the

a

safety reisted electrical system and components are subject to

,

substantial degrada' tion due to interactions of non-safety

related systea,s, and (2) if non-safety interactions could result

in common cause failure.

,

.fcope

.

lhe selecteitportions of the safety related electrical system and

comporets inspected associated with the Division 2 ECCS, High

<

Presst re,Ccient Injection System (HPCI) and the B Loop Core Spray

-

+

Systed-a~re e "follows:

1

'

,

'

Code Spray Pump 2BP206, 4KV breater, Safeguard Bus D22.

i

a

dmergency Diesel Generator 22, lead cable & raceway.

=

Care Spray Pump 2BP206, motor, cable and raceway.

125 VDC System Division 2, Channel B, battery, charger, UPS,

/

cable and raceway.

/,tI,o

Core Spray Pump 2DP206, 4KV breaker, Safeguard Bus D24.

,

Emergency Dir el Generator 24, leac' cable and raceway.

J

~ a 1

,

y

!

A

P

$

r

,

t

1

___

_2__

_ _ -

- - - - - - _ - - _ _ _ _ - _ _ - - -

--_ - - --__- - - - - -- - - - -

_

o

20

Core Spray Pump 2DP206, motor, cable and raceway.

125 VDC System Division 4, Channel D, battery, charger, UPS,

cable and raceway.

l

5.2 Inspection Criteria

5.2.1

Electrical Systems and Components

The following attributes were inspected to ensure that the Class

IE electrical systems and components receipt inspection, storage

and installation were in compliance with NRC requirements,

licensee's FSAR and procedural commitments:

Electrical components received and inspected as specified

in QC instructions.

Installed components are protected from construction

activities to prcelude physical damage and dirt.

Installed components that require protection from moisture

have their space heaters energized.

Alpha numeric and color identification as specified in the

FSAR and installation specification.

Components are installed in accordance with the drawings.

i

Emergency diesel generators and motors are meggered as

-

required.

Procedures for the receipt inspection, storage and instal-

lation have been translated from the NRC requirements and

licensee's FSAR into the licensee's purchase specifications.

QC personnel monitor the above activities with records

which are audited by QA.

Identify and determine any adverse non safety-related

i

systems or components which may interact to prevent the

Class 1E electric system from conforming to the criteria

and bases stated in the FSAR.

l

Verify by reviewing procedures, drawings and visual inspec-

tion that the licensee's commitments in the FSAR are met,

h

_ _ - _ - _ _

_

.

i

21

5.2.2

Cables & Raceways

1

The fol'owing attributes were inspected to ensure that cable

and raceway receipt inspection, storage and installation were in

compliance with NRC requirements, FSAR and procedural

commitments:

Cables received and inspected as specified in QC

instructions.

Cables reels stored to protect cables, cable ends protected

from moisture.

Alpha-numeric and color identification of electrical

cables, raceways as specified in the FSAR and int

llation

specification.

Location and configuration of the electrical raceways as

shown on the drawings.

Electrical raceway routing as shown on the cable pull

ticket.

Cable manufacture, insulation type, jacket type and

conductor type and size as listed on the purchase specifi-

cation and cable pull ticket.

No physical damage to cables and raceways.

During cable installation pull tension and bend radius not

exceeded.

Procedures for the receipt inspection, storage and instal-

lation for cables and raceways adequately translate from

the FSAR commitment and purchase specifications.

QC personnel monitor the above activities with records

which are audited by QA.

l

Installed cables not terminated have ends capped, temporary

cable markers and exposed cables protected by flame proof

material.

Power cables 480 volt or higher are meggered.

- _ _ _ _ - _

- _ _ _

_

.-

--.

,

.
  • ~

ll

22

>

l

5.3 Inspection Activities

l

Cables & Raceways

The' inspector reviewed the documents listed in Attachment II-c

with respect to cables and raceways, in general, and specifically

j

those listed in paragraph 5.1, scope.

The inspector visually in-

'

spected the cable storage area, cable cutting from the master reels

and intermediate storage in the plant prior to installation.

The-

cables and raceways installed or being installed were visuelly

inspected to the criteria listed in paragraph 5.2.

Interviews were

held with personnel associated with the above activities including

QC and QA personnel.

Electrical Systems & Components

The inspector reviewed the documents listed in Attachment II-c

with respect to the Class IE electrical systems and components.and

to those listed in paragraph 5.1, Scope. The inspector visually

inspected the 500KV and 230KV switchyards, 4KV switchgear and 125

and 250 volt direct current systems in the control building, 480

volt load centers and motor control centers in the reactor building

and the emergency diesel generators.

The inspector interviewed

personnel including QC and QA, who were conducting inspections,

installation, and storage surveillance activities.

Engineering

'

personnel were also interviewed at the Pottstown BCI office and at

the site,

5.4 Findings

a.

Cables and Raceways

The inspector found no deficiencies associated with procedures,

records, receipt inspection or storage of cables.

,

During a plant walkdown the inspector observed a QC hold tag on

an installed but not terminated cable.

The referenced NCR

11958 indicated that for cables in the A-B segment of the

ine.ta11ation the maximum allowable pull tension had been ex-

ceded by 54% and in one pull box cable 2BB20233A minimum bend

radius of 6 inches was reduced to 5 inches.

The resolution of

the NCR is unresolved and has been identified as item

(50-353/87-07-02) by the inspector.

No other deficiencies were identified concerning cable

installation.

(-

r

LL ___ _ -

_

-

.

. _ _ _

-

._ _.

- ..

.

. _ _

.

.

.

.g3

ll'

With regard to QA oversight, the licensee completed a QA cable

pulling audit 2E-258 on June 16, 1987.

The audit is being.

currently reviewed by the licensee. A cable storage QA audit

2E-264 was initiated on June 19, 1987 and is currently in

progress.

b.

Electrical System and Components

Long Term Storage

1

The inspector reviewed licensee documentation related to storage

and maintenance of installed electrical equipment such as

electric motors and the emergency diesel generators.

He also

observed the conditions of these items in the field.

The

following deficiencies were identified.

Core Spray Pump Motors

Procedure PSP-G-5.1, revision 6, requires that licensee main-

tenance activities be performed in accordance with construction

procedure CP-G-3.

Procedure CP-G-3 instruction requires that

the special instructions of the equipment manufacturer be shown

on the Maintenance Action Cards (MAC) and be conducted at the

recommended-frequency.

The inspector reviewed MAC 370273, 370395, 356530 and 356531 for

the period of May 29, 1976 and June 16, 1987 associated with the

core spray pump motors.

The MAC card requires that both the

motor and room temperature be recorded.

The acceptance criteria

was that the motor temperature be 5 F above the room temperature,

to preclude moisture in the motor winding. The requirement was

per GE document 22A2724.

Contrary to the above, only one tem-

perature measurement was recorded on the MAC cards.

Failure

to follow Procedure CP-G-3 is considered a violation (50-353/87-

11/03).

Also, during the facility walkdown on June 23, 1987 the in-

.

2

spector observed that the core spray pump 2BP206 motor space

heaters were not energized.

The licensee issued a Long Term

Maintenance Action Item (MAI) No. 3512 on June 25, 1987 to re-

energize the motor space heater. The licensee had determined

that the space heater electrical circuit breaker had tripped.

The heaters were wired to a different circuit breaker and will

be monitored for operability.

_ - _ - _ _ - _

.

24

\\

The licensee issued finding Report No. 2N-568 on June 26, 1987

that identified that BCI LTM QC failed to properly complete

special instructions outlined in the above MAC cards.

Non-conformance Report NCR No.12114 was issued on June 30, 1987

to provide for field disposition.

The licensee reviewed

sixty-four (64) MAC cards and determined that three additional

MAC cards were not filled out properly with both the motor and

room temperature.

However, this review did indicate that storage

maintenance of the motors was properly performed while they were

retained at the Adwin facility.

Emergency Diesel Generators

The following MAC cards for the emergency diesel generators

(EDG), concerning the megger requirements of the armature and

field, were reviewed by the inspector:

354983 through 354990,

357360 through 357367 and 364991 through 364998.

These MAC

cards were for the time period from January through May 1987.

The megger tests were not taken during April 1987 and were

rescheduled for May 1987.

The tests were again not taken during

May 1987. The licensee issued a NCR 11930 dated May 11, 1987 to

provide corrective action.

This corrective action was to per-

form the megger test as required by procedure CP-G-3 in accor-

,

dance with procedure CP-E-7.

If the megger test was found

l_

acceptable this would meet the project design requirement for

the intended use.

The megger tests were performed on June 16,

1987.

The megger tests were found acceptable for EDG 2BG501 and

2DG501. However, for EDG 2AG501 they were found to be unaccept-

able in that three windings were found to have 56%, 58% and 70%

of the accepted values respectively.

EDG 2CG501 also had one

unacceptable winding that measured 75% of the accepted value.

The inspector observed that the emergency diesel generators

2AG501 and 2C501 electrical space heaters were not energized on

June 22, 1987.

The licensee stated the heaters were deenergized

to perform the megger test.

However, EDG 2AG501 space heaters

were not energized as determined by the inspector on June 23 and

24, 1987.

The licensee determined that the EDG 2AG501 space

heaters were inoperable due to heater failure.

The licensee

issued a Maintenance Action Item No. 3507 on June 25, 1987 to

provide temporary supplemental heat to the EDG.

This heat will

be applied until the permanent beaters have been replaced and

reenergized.

The licensee remeggered EDG 2AG501 and 2CG501 on

June 30, 1987.

The inspector reviewed the results of these

megger tests and found they were acceptable.

Prior to the conclusion of the inspection, the LTM QC group,

were reinstructed to CP-G-3 and PSP-G-5.1 requirements for

proper documentation of inspections using the Maintenance Action

Cards.

The field disposition to NCR No. 12114 was to megger

test the pump motors.

This megger test was made on July 2, 1987.

The results of these megger readings were reviewed by the in-

spector and found acceptable.

- _ _ - _

s

e

25

c.

FSAR Commitments

Diesel Generator Exhaust System

The emergency diesel generators exhaust system had been chtngad

from the original design to preclude a potential exhaust leak

into the engine air intake.

The current design of the exhaust

system has the exhaust pipe turned up vertically and exhausting

about 5 feet above the building roof.

The FSAR documented that the Emergency Diesel Generators (EDG)

exhaust had been designed to the following conditions:

Protect the exhaust pipe above the roof line to prevent

blockage due to a postulated tornado missile.

Prevent the exhaust pipe from ice and snow blockage.

Prevent rain, melting ice or snow from entering the engine

via the exhaust system.

The inspector reviewed a design change package to install heat

tracing to the exhaust pipe and establish procedure for

surveillance and corrective action in the event of snowfall

greater than 10 inches.

The inspector identified no

deficiencies in the design change package.

d.

Potential System Interaction

>

Diesel Generator Building Floor Drain System

The FSAR stated that the diesel generator cell is provided with

trapped and vented floor drains and an adequate drainage capa-

city to cope with the maximum sprinkler water flow in each room.

The drainage system is arranged to prevent flow from one diesel

generator cell from backflooding into another cell.

The in-

spector reviewed the drain system configuration and the

l

licensee's evaluation in response to Information Notice No. 83-44

" Potential Damage to Redundant Safety Equipment as a Result of

Backflow through the Equipment and Floor Drain System." No

deficient conditions were identified in the diesel generator

drain system.

Diesel Generator Buildino Heating System

The inspector observed that the building heating steam and

condensate return lines passed over three of four motor control

centers (MCC) and piping including a heat exchanger was located

over each of the diesel control panels (DCP).

All of the above

piping and heat exchangers were seismic supported such that the

_____ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-_

- __ _

_-

- _ - _ _

- - _ _ .

_.

4

9

26

piping and heat exchangers would not cause failure of safety-related

electrical components during a postulated seismic event.

However,

leaking of the steam or condensate on the MCC or DCP is not precluded

from occurring prior to or during a seismic event.

The licensee recognized this potential adverse interaction

between the building heating system, as designed, and the as-

sociated emergency diesel generator. A modification was pro-

posed to relocate the heaters on Unit I during the past refue-

ling cutage.

No mention was made concerning the piping located

over the motor control centers.

Furthermore, the modification

was considered by the licensee to be a low priority item and was

not made on Unit 1 during the past refueling outage. This is an

unresolved item pending licensee review of this issue.

(50-353/87-11-02)

Restoration of Offsite Electrical Power after a System Blackout

The SF6 type Power Circuit Breaker (PCB) will trip if below

40 F during a blackout if gas storage heaters are not

energized. The inspector reviewed the procedure " System

Restoration Following Complete Shutdown," noting that system

power restoration is initiated by closing of a breaker not

sensitive to ambient temperature.

The inspector reviewed the

power breaker closure sequence following a system blackout and

had no further questions.

e.

Inspector Followup of Previously Identified Items

During this inspection, Significant Deficiency Reports (SDR)

were reviewed to establish reporting consistency with 50.55(e).

Most of the SDRs were concerned with construction issues and

proper determinations were found to have been made with respect

to deportability.

However, two exceptions were identified as

discussed below.

SDR No. 135

The SDR No.135 involved identification of improper wiring of

the standby liquid control system and did not clearly indicate

if the wiring discrepancy was the result of a construction

problem or design error.

SDR No. 135 was found by the licensee

to not be reportable, however, it could be reportable if a design

deficiency is the cause of the problem. This is an unresolved

item pending determination of the problem cause of SDR No. 135.

(50-353/87-11-10)

SDR No. 159

As noted in report 50-352/85-09, during June 1984 as a part of

Unit I start up testing, the licensee identified a design

- _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

__ -

_ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _

.

l

l

l

27

1

deficiency that could cause all four Emergency Diesel Generators

(EDG) to shut down in the event of a loss of offsite power.

l

In the event of a loss of offsite power coincident with a LOCA,

'

this design deficiency would not cause the EDGs to shut down.

The deficiency is that the non-safety fire detection system

would initiate a false fire indication after retur,iing to

service from a loss of power condition.

This would occur due to

an imbalance, during the time period required for the flow

sensors to reach equilibrium following restoration of power, in

the control system wiring bridge that senses flow in the fire

system water lines.

This fire indication would then shut down

those diesel generators that were running under certain circum-

stances.

Prior to the completion of inspection 352/85-09, the

licensee had established the cause of this problem and corrected

it by changing a system timer from I second to 60 seconds. The

i

issue remaining in 1987 is the conformance of the licensee to

the reporting requirements of 10 CFR 50.55(e).

The Significant Deficiency Report (SDR) No. 159 which was

questioned for adequacy by the NRC inspector during inspection

352/85-09 was reviewed later by the licensee.

The open item

352/85-09-01 and technical issues of report 352/85-09 for the

EDG fire protection interaction including potential shutdown of

the four diesels were evaluated and closed in report 352/85-37.

During this inspection, 353/87-11, the inspector reviewed the

deportability aspect of SDR No. 159.

The original design of

the fire water flow detection system and interaction with the

emergency diesel generators did result in conditions where those

diesels in operation (a maximum of four) could be inadvertently

shutdown.

This is a significant design deficiency.

The failure

to report this deficiency to the NRC in accordance with 10 CFR 50.55(e) is an apparent violation (50-353/87-11-04).

Licensee Corrective Action for EDG Trips on June 20 & 21, 1984

To prevent further trips of the EDG such as those that occurred

during Unit 1 start up testing the design change package No. 0474

and modification 1-1131-13A,24A were issued correcting the

situation by August 2, 1984.

The corrective action was to

change a time delay relay and was documented in inspection

report 50-352/85-09.

Unit 2 was originally constructed using

the longer time delay relay.

During this inspection, 353/87-11, the interaction between the

Fing Protection Actuation Detection System (FPADS) and the Emer-

gency Diesel Generators (EDG) was reviewed for comparison to the

requirements of IEEE Standard 323. The FPADS is not safety

related while the EDG is safety related presenting a condition

where a non-safety related system failure could shut down a

safety related system.

One of the determinations of IEEE

_

_ _ .

_

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

__

_-

0

28

\\

l

l

St'andard 323 is to have the supplier of safety related compo-

L

nents determine the. end of life to preclude common. cause

i

failure. Although not classified as safety related, the

j

interaction of the flow switches with the safety related

emergency diesel generators indicates that a high degree of.

reliability for these switches is appropriate.

The inspector

discussed the need for performing a. failure modes and effects

analysis for these switches as part of the corrective action

,

evaluation.

The licensee had not performed such an analysis.

j

i

This concern of insufficient reliability data on a non-safety

j

system that could affect a safety system as discussed above is

considered an unresolved item.

(50-353/87-11-05)

{

Electrical System and Component Identification

.]

The inspector observed that the battery rooms for Unit 2 had not

!

been identified. This lack of identification relative to unit,

channel, division or bus had been previously identified as item

50-353/86-09-01 and was closed on the basis of proposed licensee

action in inspection report 50-353/86-20. The inspector con-

firmed that Unit 14KV switchgear and battery room were properly

identified including Unit 2 4KV switchgear. This identification

was done by PECo. Since the Unit 2 battery rooms had not been

turned over from the AE this identification.was not completed.

,

The licensee'has directed the AE to identify these room

'

similarly to those done on Unit 1. The inspector has no further

concerns about this item.

5.5 Conclusion

.

The electrical system in general has been properly designed,

purchased, installed and maintained in accordance to the NRC require-

ments and the licensee commitments.

The inspector has not identified any deficiencies in the cable

receipt inspection, storage, cutting from master reels, installation,

QA/QC records, or procedures including the raceway systems. At the

time of the inspection an estimate of 30% of the cables had been

installed.

A violation was identified with regard to proper completion of

Maintenance Action Cards.

In addition, there oppeared to be some

weakness in the area of electrical equipment long term maintenance

storage. This is in regard to motors and emergency diesel generators,

space heaters energization, megger test and temperature surveillance

of motors. Greater attention to the implementation of the MAC

systems could possibly preclude some of these problems.

The inspector did not identify any deficiencies in receipt inspec-

tion, installation, or procedures associated with electrical systems

or components.

'

_ _ _ _ _ _ _ _ .

___

_-__-

- _ _ - - _ - _ - - - _ _ _ _ _ _ - _ - _ _ _ - _ _ _ _ _ _ - - - _ _ - _ - _ _ _ _ _ - - _ _ - - - _ _ _ _ _ - _--

,

29

Unresolved items were identified with regard to EDG building heating

system piping located over EDG motor control centers, reliability of

flow switches in the fire protection system and their interaction

with the EDG and deportability of a design deficiency under

requirements of 10 CFR 50.5S(e).

6.0 Instrumentation and Control

6.1 Scope

An inspection of the Instrumentation and Controls (I&C) for the High

Pressure Coolant Injection (HPCI) System, Core Spray (CS) System and

parts of the Residual Heat Removal (RHR) System was conducted to

determine the adequacy of:

installed hardware, construction proce-

dures, design change process, conformance to design documents and

requirements, design drawings, construction work packages, quality

programs, engineering interface, and documentation of completed

design and construction.

Completed work activities and in process work were inspected.

Additionally, current design activities associated with the

candidate systens were reviewed.

I

6.2 Inspection Criteria

l

The fundamental criteria for the inspection consists of the FSAR,

SER, and 10 CFR 50 Appendix B.

In order to verify compliance with the above documents, the

installed I&C commodities and design activities were examined with

respect to the following attributes:

Instrument installations

tubing bend radii

tubing ovality

torquing of support bolts

instrument location

clearance requirements

proper supports

tubing slope

a

instrument line valving

installation of fittings

instrument identification

sensing line routing

control of instrument line penetrations

control and use of flex hose

=

_ - _ - _ _ _

,

30

I&C Cables and Terminations

cables properly identified

a

cable integrity

conductors properly located and terminated

a

redundant cables properly separated

cable routing in accordance with design criteria

a

Control Circuit Design

proper review and approval of design drawings

FSAR logic requirements incorporated in drawings

drawing standards complied with

a

system functional requirements (i.e. pumps & valve controls)

a

reflected in final design

consistency between levels of design drawings

a

6.3 Inspection Activities

Instrument Installation

The instrument installations listed below were visually examined for

conformance with the attributes listed in section 6.2.

Additionally, the completed work packages were compared with the

requirements of the Instrumentation Installation Details, M-830, to

verify incorporation of design requirements.

The instrument line from the discharge line of the safeguard

pirdng fill pump to pressure switch PSL-52-231A, work package

JTL-52-01-09Q-A.

The instrument support, instrument, and isolation and drain

valves, work package JML-52-01-09Q-A for PSL-52-231A.

The instrument line from the discharge line of RHR pump 2CP202

te instrument rack 20-C077, work package JTR-51-05-22A-A.

i

in process work activities on Instrument rack 20-C010 (reactor

vessel level), including tubing and instrument cables.

In process work activities on instrument rack 20-C005 (Drywell

pressure), including tubing and instrument cables.

Suppression Pool temperature element installations for

TE-41-2018, D, F and H and TE-41-202 B, D, F and H.

A complete walkdown of the CS and HPCI pump rooms was performed

to verify proper separation of instrument tubing and conduit,

instrument locations compared to that required by P&ID and

general work practices.

..

_ _ - _

-_

.

31

Instrumentation Design Activities

A review of both the field engineering and resident engineering

activities was performed during the process of the inspection.

Additionally, some General Electric and PECo engineering activities

were reviewed.

The following is a list of the activities reviewed.

The relocation of core bores for instrument lines (RHR pump

discharge pressure transmitters) including the preparation and

resolution of Field Change Notices, preparation of Drilling

Excavation Checksheets and resolution of a Field Change Request

for cutting rebar.

Preparation and disposition of a Field Change Request for

addition of weep holes to instrument support tube steel.

Preparation and disposition of Field Deviation Disposition

Request (FDDR) for modification of Unit 2 local instrument

racks to conform to Unit 1 as-built design.

Preparation and disposition of FDDR for replacement of

transmitter E41-ND578 by Bechtel, which was removed from Unit 2

instrument rack for use on Unit I and was originally supplied

by General Electric.

Preparation by PECo of the procedure for Calculation of Nuclear

Safety - Related Instrument Setpoints.

Preparation, revision and issuance of General Electric

Instrument Data Sheets and Design Specification Data Sheets.

Storage of Instrument Components

Activities for protection and storage of instrument components were

reviewed during the course of the inspection and are listed below.

Warehouse storage of instrument components including climate

control, cleanliness,' issuance, storage and receipt.

Procedures and practices for protection of installed

instruments and racks from construction dirt and physical

damage.

Temporary field storage of instruments after removal from the

warehouse and prior to installation in the field,

I

i

l

\\

'I

_ _ _ _ _ _ _ - - . _ . - _ - -

e

32

HPCI and CS Control Schemes

In order to verify that the requirements for initiation and control

of HPCI and CS systems meet the design requirements specified in the

FSAR the following control schemes were reviewed.

,

HPCI initiation circuits for isolation valves and the HPCI pump

turbine were reviewed to verify the logic and consistency of

control circuits with functional design requirements.

6.4 Findings

Based on the review of documer,ts and examination of instrument

I

installations, the following findings were identified.

a.

Although very few instrument installations have been completed

at this point in the construction, the quality of workmanship

and conformance to design requirements for those installations

inspected was found to be adequate.

Quality Control, field

engineering and craft personnel appear to be knowledgeable,

conscientious and well managed.

Innovative ideas, such as

tightness gauges for compression fittings, have been

incorporated in the project to provide for consistency and

time saving,

The use of the '" work package" concept seems to

provide a well defined scope of work which is controllable and

auditable, Overall, work on instrument installations is

proceeding smoothly; however, it is early in the process,

b.

Interface between Bechtel Field Engineering and Resident

Engineering appears to be procedurally well defined and adhered

to, and evidenced by the disposition of field change requests

reviewed during the conduct of the inspection,

c.

Field storage of installed instrument racks consists of both

fabric coverings and plywood structures and no evidence of

damage was found by the inspector.

I

I

d.

Warehouse storage facilities for instrument components were

found to be clean, well organized, properly labeled and have

adequate climate controls.

The procedures for receipt and

j

issuance of components are structured to maintain positive

j

control, and include a controlled entry data base of all

'

components which lists ID number, location, receipt date,

issuance date and status codes.

The inspector found no areas

{

of concern.

l

w _- _

_

_

l.

4

...

33

e.

PEco has assumed responsibility for performing setpoint

calculations for nuclear safety-related instruments.

In

preparation for this activity they have prepared a draft

procedure which was reviewed by the inspector and found to be

in compliance with the requirements of Regulatory Guide 1.105

as well as the latest ISA standard for preparation of

setpoints for' nuclear safey-related instruments.

f.

At the time of the stop work on Unit 2, in 1985, General

Electric unitized the-design drawings for both Unit I and

Unit 2.

However, not all of the drawings for Unit 2 were

design verified.

Examples of this problem are Construction

Drawing No. 16908370TR for HPCI leak detection and Instrument

Data Sheet No. 234A9312TR for the reactor water cleanup system.

General Electric issued a letter stating that all Unit 2 unique

drawings should be considered unverified until Unit 2 construc-

tion restart and subsequent review of the drawings.

The subject

drawings were released to Bechtel under separate transmittal

letters which contained no warning that the drawings were not

i

design verified.

Subsequently, the drawings were issued to the

project. As of the completion of this inspection there were

still unverified instrumentation drawings which have been issued

to the project for construction, including, instrument data

sheets, parts lists, assembly drawings and connection diagrams.

The-issuance of unverified design documents is a violation of

both 10 CFR 50, Appendix B, Criterion VI and Appendix D to the

Limerick PSAR as stated in the notice of violation in Appendix A

of this report.

(50-353/87-11-06)

g.

The elementary diagrams, logic diagrams and schematic diagrams

reviewed as part of this inspection were found to be accurate

and in conformance with the design basis committed to in the

FSAR.

No areas of concern were noted.

h.

As part of its design process General Electric will perform a

design review of all Unit 2 design documents, for which it is

responsible, to ensure that all changes have been incorporated

and that the final design meets the licensing bases.

The

,

inspector questioned if procedures were in place to ensure that

'

the impact of the modified drawings is evaluated for existing

l

hardware for which construction is complete.

Bechtel

Construction has procedures in place to perform the required

evaluation; however, PECO testing and Laboratories Division, who

is responsible for loop and instrument calibrations and some

l.

post construction testing, has no written procedure for perform-

ing review of document changes for effect on completed work.

This item will remain unresolved pending additional clarifica-

tios +.o be provided by the licensee.

(50-353/87-11-07)

1.

The inspector reviewed the instrument data sheets and design

specification data sheets for the CS and HPCI. Although these

items had been design verified the inspector found a number of

errors such as instrument element ranges incorrectly listed,

- _ _ _ - _ _ _ _ _ _ - _ _ .

._

-__

_

-_.

'

- .

h

34

l!,

rated instrument accuracy incorrectly stated, and incorrect

instrument scales in the instrument data sheets for HPCI. Ad-

ditionally, a significant number of errors have been detected by

GE subsequent to the original verification.

This item will

remain unresolved pending further investigation to explain the

source and significance of the errors.

(50-353/87-11-08)

i

6.5 Conclusions

i

The installed instrumentation inspected was found to be of good

quality and to satisfy the criteria established in section 6.2.

Quality records were found to be acceptable.

Design documents appear

to reflect the requirements of the FSAR and are reflected in the

as-built configuration in the plant.

An item of non conformance with

the document control requirements of 10 CFR 50, Appendix B was

identified in that unverified design documents were issued for

construction.

7.0 Project Organization

7.1 Construction Management and Supervision

The Limerick Unit 2 construction is a major task involving a work

-force of approximately 4200 personnel of diverse skills.

The

interactions between the main contractor, sub contractors and PECo

are numerous, complex and controlled by people, documentation

quality controls, quality assurance, procedures and NRC regulations.

Management of construction has been delegated to Bechtel Construction

by PECo. Oversite of Bechtel activities is provided by the PECo

construction division for the mechanical, electrical and cost and

schedule areas; and by the PECo Quality Assurance Division for audit

and surveillance of activities for the purposes of monitoring and

controlling quality.

Bechtel activities in Limerick Unit 2 construc-

tion include construction management, project supervision, craft

supervision, construction engineering, project engineering, cost and

scheduling, quality control, inspection, procurement, subcontract

administration and safety. The reactor vessel internals are instal-

led by the General Electric Company and the heating and ventilation

(HVAC) by the Schneider Power Corporation.

'The inspectors. interviewed PECo and Bechtel construction managers,

engineering managers, supervisors and workmen to establish how manage-

mont of construction is supposed to be accomplished and to determine

if management has been successful in providing the construction work

l

force with the necessary tools, training, procedures, hardware, super-

vision and controls necessary to properly install piant components.

This aspect of inspection and observation of specific plant systems

and related documentation as described in this report has resulted in

the conclusion of the NRC team that construction is proceeding with

'

adequate management planning and controls.

l

l

4

- - _ _ - _ - _ _ _ .

_.

___

. _ _ _ _

_ _ - _ . ___-_ __-__-_ -

.-

- _ _

_ -- _

.c

35

7.2 . Project Engineering

Bechtel Corporation is responsible for all design activities related

to Unit 2 of the Limerick Station.

The Project Resident Engineering

(PE) staff represents the majority of the project engineering organi-

zation.

The bulk of staff is located in'Pottstown within a few miles

of the plant site. The PE staff has a small representation on site

(approximately 40 engineers) for coordination of project activities

with construction engineering.

The balance of the project engineer-

ing staff is located in Bechtel's home office in San Francisco

(SFHO) with an overall responsibility for coordination of mechanical,

. electrical and civil / structural systems activities and performance of

generic and special analyses.

The Resident Engineering staff has the overall responsibility for

plant physical design in the mechanical, civil / structural and

electrical disciplines in addition to the planning and control and

quality assurance activities.

The resident engineering staff assigned to the plant site reports to

the Pottstown organization.

In the mechanical and civil areas, the

staff provides support to construction in problems associated with

rebar cutting, custom fit supports and penetration seal program.

The interface between Project Engineering and construction engineer-

ing staffs was evident from observation of the frequency of meetings

(weekly) between department heads and counterparts, in both organiza-

'

tions.

The licensee (PECo) maintains oversight over the PE staff

activities by stationing an engineer from their corporate organiza-

tion in the Pottstown office.

l

Specific details relating to activities performed by the PE organi-

zation in the mechanical area were addressed in NRC inspection

report No. 353/86-20,

7.3 Construction Engineering

The Construction Engineering Department is responsible for material

availability / procurement, walkdown for installation / interference

check, installation, inspection and providing as-built information.

In addition, CE is responsible for obtaining prior Project

Engineering (PE) approval of any design changes necessary for

construction.

As of June 1987, the Construction Engineering (CE) staffing level

was at 580. CE is divided into the pipe support, walding,

electrical, civil, instrumentation, mechanical, HVAC, piping, quality

engineering, material control and systems / change departments.

_ _ - _ _ - _ - - _ _ _ _ _ _ - = _ _

_.

, _ _ _ - _ _ - _ _ _ _

,

e.

(

!

!

"

36

i

l

l

Construction Engineering is the interface group between project

engineering, who'is responsible for all design activities, and the'

plant construction work force.

Construction engineering prepares

the work instruction packages and. works with the construction crafts

to have components installed in accordance with the work package,

drawin'gs and procedures.

Construction engineering performs the first

line inspection of completed work af ter completion by construction.

Bechtel QC performs inspections of completed work after construction

engineering to meet code and procedural requirements and to provide

control over the construction activities.

8.0 Unresolved Items

i

Unresolved items are matters about which more information is required to

ascertain if it is acceptable, a violation, or a deviation.

Unresolved

items are discussed in sectio.ns 3.4(g), 5.4(d), 5.4(e), 6.4(h) and 6.4(i).

9.0 ' Exit Meetin_g

..

The Inspectors met with licensee representatives on-July 2,1987 and

presented the findings of the inspection. The licensee did not identify

any proprietary information contained within the scope of the. inspection.

Written information other than requests for information was not provided

to the licensee during this inspection.

a=_-__________

- _ _ _ .

_. _ - _ _ - _ .

.

O

Attachment I - List of Persons Contacted

Philadelphia Electric Co. (PECo)

x W. Boyer, Supervising Engineer

  • J. Clarey, Supt. Limerick 2

x J. Conway, Fire Protection Assistant

  • J. Corcoran, Mgr. QA LGS 2
  • R. Crofton, QAE
  • T.

Dey, QAE

  • D. DiPaolo, QA Branch Head LGS 2
  • L. Dyer, QAE
  • D. Fetters, Project Mgr.
  • T. Gotzis, Asst. General Supt. Construction

x A. Jones, Electrical Engineer

  • J. Kemper, Sr. V.P. Eng/ Prod

x*G. Lauderback, QA Branch Head

.

  • D. Marascio, QAE
  • K. Meck, QA Engineer

x 0. Neff, Compliance Engineer

  • P. Pavlides, Director, QA

x D. Poliero, Performance Engineer

  • L. Pyrih, Chief Mechanical Engineer
  • J. Rubert, Site Supervisor, QA

x W. Shuff, Electrical Branch Head (UZ)

  • T. Szonntagh, QAE

x*T, Tucker, QA Engineer

Bechtel

  • G. Bell, PQAE

x R. Dantuluri, Elect. Dyp. Supt.

D. Davis, Lead Instrumentation Engineer

  • M. Fisher, Subcontracts Sr. Field Engineer

H. Greenwalt, QA Engineer

  • C,

Headrick, APC QCE

R. Holt, Reactor Lead Instrumentation Engineer

  • A. Kumau, Asst. Lead Civil Engineer
  • G. Kelly, CS QAE
  • H. Linsinbigler, Asst. Project Field Engineer
  • S. Loofbourrow, Lead Const. Engineer
  • T. Molenaro, Project Supt.

W. Mourer, Construction Manager

x 3. Mukherjee, Mech. Grp. Supt.

x*R. Palaniswany, Resident Project Engineer

l

  • N. Powell, Project Engineer

l

  • K. Powers, Project Field Engineer

[

G. Sims, Reactor Instrumentation Engineer

l

l

1

-

_ _ _ _ _ _

- _

_-_

_

l

.

Attachment I

2

l

General Electric

l

  • C. Brinson, QA Rep
  • D. DiFilippo, QC Supervisor

l

  • A. Lileck, Construction Manager
  • M. Quirin, Project Manager

N_R_C_

  • J. Durr, Engineering Branch Chief, DRS

x*H. Gray, Lead Reactor Engineer

  • H. Kaplan, Lead Reactor Engineer

x*J. Kaucher, Reactor Engineer

  • J. Linville, Section Chief, DRP 2A
  • K. Manoly, Lead. Reactor Engineer

x*F. Paulitz,. Reactor Engineer

  • Indicates those present at the exit meeting.

xIndicates those present at the June 30, 1987 meeting

on Electrical 50.55(e) issue.

I

'l

____-__

fu.

l

.

I

i

. Attachment II-a - Drawings used during piping inspections

High Pressure Coolant Injection

P&ID Drawings M55 and M56

l

l

ISO

Description

14" EBB-229

Pump Discharge

12" EBB-231

To Cont. Isolation Valve HV208

16" HBB-210

To Pump Suction

16" & 34" - HCB205

Pump Suction Line

'

20" HCB-202

Pump Suction Line

20" HCD-219

From Condensate Storage Tank

12" EBB-208

HPCI Pump Steam Inlet

20" HBB-208

HPCI Pump Turbine Exhaust

16" HBB-209

HPCI Pump Suction from Wetwell

l

14" EBB-229

HPCI Pump to Core Spray

1

..

Core Spray (Loop B - Pumps B & D)

l

P&ID Drawing M52 and M41

16" HBB-220

Pump Suction from Wetwell

'

14" HBB-220

CS Pump B&D tie in

12" GBB-212

CS Pump Discharge

14" GBB-212

Pump B&D Common Discharge Line

to HPCI Tie in (12" EBB-231)

12" DCA-210

Inside Containment

12" DCA-419

To Reactor Vessel Nozzle

Core Spray Sparger

In Reactor Vessel (GE)

l

.

___ _ - -

_

_.

.

i

.

Attachment II-b - Electrical System Supports

1.

Documents Reviewed

E-1406-1 & 2: Conduit and Cable Tray Notes, Symbols and Details

E-49: Specification for Cable Trays for LGS Unit 1 & 2

QCI-W-1.00: Quality Control Instruction for Welding and

Non-Destructive Exam ~ination for Structural and Electrical Component

Installation

QCI-E-2.0: Quality Assurance Instruction for Installation of Exposed

Raceway & Seismic Bracing - Welding Acceptance for Electrical

Raceway / Support Installations

2.

Electrical System Supports Inspected and Related QC Inspection Records

Switchgear Area (#8): Elevation 239'-0" (DWG No. E-1117)

- CBJ-122 for Conduit No. 2BC004-5" RS

- CBJG-72 for Box No. 2DG015

- CBJ-225 for Conduit No. 20D081-6" RS

- CBJ-39 for Conduit No. 2BD007-4" RS

Cable Spreading Room (Area #8): Elevation 254'-0" (DWG No. E-1226)

W4, P7 & C3 for Trays Nos. 20TBV, 20TCW, 20 TDX, 20TEY & 20KFZ

-

-

CSR8A(SIM) for Trays Nos. 20RBB, 20KAD & 20RBA99

F6 for Tray Nos. 2CTSA, 2CTTA, 20TBR, 20TAA, 20TUA & 20KSA

-

CSR 22 for Trays Nos. 20 RAS, 20 RAT & 20RA

-

S6 for Trays Nos. 20TFS & 20TGT

-

-

CBL-G474 for Conduits and Gatters Nos. IAH039-2" RS,

IBH036-2" RS, 1AGI46, IDGI17, 1CGIl0, IDG034 & 1CG033

i

Diesel Generator (D) Building, Elevation 217'-0"

l

!

-

004 for Tray No. 2DCDB05

005 for Tray No. 2DCDB05

-

-

011 for Tray No. 20CDB03

-

012 for Tray No. 2DCDB02

1

19 for Tray No. 2DCDB01

-

i

l

-

101 & 102 for Gutter No. 20G803

-

1389 for conduit No. 2DS100 - 1h" RS

_ _ _ _ _ _ _ - _ _ _ _ _ _

- _ _ _ _ - _

-

,

.

.. .

Attachment II-c - Electrical Power Systems - Documents Reviewed

Final Safety Analysis Report, Section 8

Safety Evaluation Report NUREG-0991, August 1983

Supplement No. 1, December 1983

Supplement No. 2, October 1984

Supplement No. 3, October 1984

Supplement No. 4, May 1985

Supplement No, 5, July 1985

Supplement No. 6, August 1985

Specification for Medium Voltage Metal Clad Switchgear and Associated Bus

Duct, 8031-E-7, revision 2.

Specification for 5000 volt and 15000 volt power cables, 8031-E-29,

revision 2.

Specification for 5000 volt and 15000 volt power cables, 8031-E-29,

revision 12.

Procedures

Quality Assurance Plan Volume I Design and Construction Phase, April 1, 1987.

Processing of Nonconformance Reports, CP-D-1, revision 4.

Permanent Plant Cable Installation and Termination, CP-E-2, revision 4.

Electrical Raceways, CP-E-3, revision 3.

Installation of Internal Raceway and Equipment Seals and Electrical Raceway

Fireproofing, CP-E-4, revision 3

Non-NSSS Electrical Equipment, CP-E-6, revision 6.

Insulation Resistance Testing, CP-E-7, revision 0.

Long Term Storage / Maintenance / Lubrication of Permanent Plant Equipment and

Materials Prior to Turnover, CP-G-3, revision 3.

[

!

Quality Control Instructions

Receiving Inspection, R-1.00, revision 18

Storage Facilities, S-1.00, revision 3

Installation of Electrical Cables, E-4.0, revision 12.

Storage Instructions for Vertical Induction Motors in indoor unheated

i

environment, 261A3283, May 15, 1987.

,

_ - _ _ _

_

o

-

Attachment II-c

2

Diesel Generator packing, shipping, handling and storage instructions Colt

Industries Dwg. No. 11873300, revision 2.

Diesel Generator Annuicator Response, ARC-B0P-1CC514, page 63, revision 2.

System Restoration following Complete Shut-down, System Operation Division

Philadelphia Electric Company, revised June 1, 1986.

Conduits & Cable Tray Notes, Symbols & Details, E-1406

1.0 General Notes

2.0 Raceway and Dropout Cable Separation

3.0 Raceway Numbering and Marking

4.0 Conduit Notes.

Procedures

Standby Diesel Loading Test Procedure, P100.4, revision 4.

.

Loss of All AC Power (Station Blackout), E-1, revision 5.

Administrative Procedure for Control for In-Plant Storage, A-30.4, revision A.

Snow, SE-14, revision 1.

Records

Maintenance Action Cards

MAC, Core Spray Pump, 2AP206, June 1, 1987, motor & room temperature

MAC, Core Spray Pump, 2BP206, May 29, 1987, motor & room temperature

MAC, Core Spray Pump, 2CP206, June 15, 1987, matar & room temperature

l

MAC, Core Spray Pump, 2DP206, June 16, 1987, motor & room temperature

MAC, 480 volt Load Center 20B201, temperature, March 20, 1987,

June 18, 1987

MAC, Diesel Generator 2AG501, armature megger, December 13, 1986, April 14,

4

1987, May 13, 1987, field megger, January 5,1987, April 14,1987,

May 13, 1987

MAC, Diesel Generator 2BG501, armature megger, January 1,1987, April 14,1987,

May 13, 1987 field megger January 5,1987, April 14,1987, May 13,1987.

MAC, Diesel Generator 2CG501, armature megger, January 12, 1987, April 14,

1987, May 13, 1987, field megger, January 12, 1987, April 14, 1987,

May 13, 1987

MAC Diesel Generator 2DG501, armature megger, January 12,1987, April 14,

1987, May 13, 1987, field megger, January 5,1987, April 14,1987,

May 13, 1987

MAC, Core Spray Pump 2BP206, megger May 6, 1987.

MAC, Core Spray Pump 20P206, megger May 6, 1987.

'

l

l

'

________________ _

- - _ _ _ _

.

..

3

Attachment II-c

3

l

l

'

Maintenance Action Item

l

MAI, 3263, Core Spray Pump Motor energize space heaters, April 4, 1987

MAI, 3417, Core Spray Pump Motor, deenergize space heater to work pump,

June 2, 1987

MAI, 3438, Core Spray Pump Motor, reenergize space heaters, June 9, 1987.

MAI, 3512, Core Spray Pump Motor, reenergize space heater circuit breaker

Triped, June 23, 1987.

Instorage Maintenance System History Inquiry for Load Center 20B201 space

heater operability December 24, 1985 through June 18, 1987.

Nonconformance Report 11930, Diesel Generators not megger as required, April

11, 1987.

'

Field Inspection Report, NCR 11930, Diesel Generator Meggering, June 17, 1987

Nonconformance Report 11958, Overtension and minimum bend radius exceeded.,

Cables 2BB20233A, 2BB202338 and 2BB202330, May 21, 1987.

Shipping Notice Core Spray Pump, 2BP-206.from Eddystone to Limerick April 2,

1987.

Quality Control Inspection Record

Storage Facilities, Log No. SM00036, May 29, 1987

Permanent Plant Cable Reels, Log No. R3531, February 9, 1987

Q List Cables, Log No. R1479, July 6, 1982

Cable Installation for NCR 11958 above, May 4, 1987

Quality Assurance Report

No. 2E-236, Cable Laydown Areas, July 31, 1986

No. 2E-248, Cable Pulling Unit 2 PGCC cables, February 20, 1987

Drawings

PI&D, Fuel & Diesel Oil Storage and Transfer, M-20, sheet 7, revision 2.

PI&D, Plent Heating Steam, M-96, sheet I revision 30, sheet 2 revision 31

sheet 3 revision 18, sheet 4 revision 19, and sheet 5 revision 3.

Schematic Diagram Diesel Generator Control and Auxiliaries, E-591, sheet 1

revision 7, sheet 2 revision 4, sheet 3 revision 7, sheet 4 revision 1

i

sheet 5 revision 2, sheet 6 revision 4, and sheet 7 revision 2.

Electrical Schematic Engine Control, Colt Industries, 11870038, sheet 3,

revision 15.

l

1

Location of Drain Funnels and Caps, Diesel Generator Building, plan EL 217,

M-590, revision 0.

l

l

l

_____ . _ _ _ _ _ _ _ __

- _ _ _ _ _ _ - - _ _

a

P

i

' Attachment II-c

4

Drawings (Continued)

Normal Waste Drainage System, C-26, Sheet I revision 37, sheet 2 revision 9

Plumbing and Drainage Diesel Generator Building EL 217, M-550, revision 4

Plumbing and Drainage Symbols, Abbreviations and General Notes, M-500,

revision 15.

l

l

l

l

- - - - . - - - - - - - - - - - - - . - - - _ _ - - _ - - _ - _

- _ _ ___ -_

.

?

7

Attachment II-d - Instrumentation and Controls (I&C) Documents Reviewed

I&C Dccuments reviewed during CTI

Drawings

'

Isometric SP-HBB-270-E3, Reactor Building discharge line from safeguard fill

pump 2AP-256

Isometric FJ-52-01-09A, Safeguard Piping Fill Pump

Isometric SP-GBB-219-1E, Reactor Building RHR Pump 2CP202 Discharge Drain

Isometric FJ-51-05-22A, sheets 1 & 2, RHR Rack 20-0077

P&ID, M51, sheets 5, 6, 7 and 8 - RHR

I

P&ID, M52, sheets 3 and 4, CS

I

P&ID, M55, sheet 2, HPCI

P&ID, M56, sheet 2, HPCI pump

M-1542 Instrument Location Reactor Building Unit 2 Plan at EL 177 Area 17

E-369, Schematic Diagram, Safeguard Piping Fill Pump

M1-E41-1010-D-5.2, P&ID, HPCI

M1-E41-1010-D.-4.4, P&ID, HPCI

E-104, Schematic Block Diagram, HPCI, sheets 1 and 2

'

M1-E41-1040-E-017.2, Elementary Diagram, HPCI

M1-E41-1040-E-018.1, Elementary Diagram, HPCI

M1-E41-1040-E-019.2, Elementary Diagram, HPCI

M1-E41-1040-E-020.2, Elementary Diagram, HPCI

M1-E41-1040-E-021.2, Elementary Diagram, HPCI

M1-E41-1040-E-022.2, Elementary Diagram, HPCI

M1-E41-1040-E-023.2, Elementary Diagram, HPCI

M1-E41-1040-E-024.2, Elementary Diagram, HPCI

M1-E41-1040-E-025.2, Elementary Diagram, HPCI

M1-E41-1040-E-026.2, Elementary Diagram, HPCI

M1-E41-1040-E-027.2, Elementary Diagram, HPCI

M1-E41-1040-E-028.2, Elementary Diagram, HPCI

M1-E41-1040-E-029.2, Elementary Diagram, HPCI

M1-E41-1040-E-030.1, Elementary Diagram, HPCI

M1-E41-1030-F-08.8,

Functional Control Diagram, HPCI

)

M1-E41-1030-F-04.19, Functional Control Diagram, HPCI

{

M1-E41-1030-F-05.12, Functional Control Diagram, HPCI

M1-E41-1030-F-06.12, Functional Control Diagram, HPCI

M-830, Instrument Installation Details

M-601, Instrument Index

M-1-E41-4010-L-06.9, Design Specification Data Sheets for HPCI

M-1-E41-3050-H-02.1, Instrument Data Sheets for HPCI

M-1-E21-4010-L-04.8, Design Specification Data sheets for CS

j

M-1-E21-3050-H-02.1, Instrument Data Sheets for CS

i

M-772, Level Setting Diagrams

E-350, sheets 1 and 2, Schematic Diagram Core Spray Pumps

_ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _

.-

-

-J

_

_

_ _ _ _ . . - _ _ _ _

_

_

. _ _ _ .

- _ _ _ . - - - _ ..

_ - _ - _ - _ _ _

_ _ _ _ - _ - _ . - _ - - _ -

L,

. B'

' -

Attachment II-d

2

Procedures

l

General Electric Independent Design Verification Procedure E0P42-6.00

-

'

General Electric Document Distribution Procedure E0P 60-2.00

-

l

PECO Draft procedure - Calculation of Nuclear Safety-Related Instrument

-

Setpoints, TL-03-500I3

CP-0-10, Review, Implementation and Control of Design Change Package

-

CP-J-1, Fabrication and Installation of Instrumentation

-

l

CP-E-2, Permanent Plant Cable Installation and Termination

-

CP-F-2, Receipt Inspection, Storage and Withdrawal of Materials / Equipment

-

' Specifications

8031-C-105, Specification for Drilling and Chipping of Structural Concrete

-

8031-M-248, Design Specification for Nuclear Instrument Valves

-

8031-A-40-2-100, Penetration Seals Schedule Legend

-

Design Change Documents

FCN-CC-11

FCR-CC-173

FCN-MI-11

FCN-JS-28

FCN-CC-12

FCN-CC-31

FDDR-HH2-3670

FDDR-HH2-3775

Work Packages

JML-52-01-090-A, Install Instrument Support Instrument with Celebration Tee,

)

Isolation Valve and Drain Valve

JTR-52-01-090-A, Install Supports, Tubing and Flexhose

JMR-51-05-22Q-A, Mount and Install Instrument Rack

JTR-51-05-22Q-A, Install Instrument Line

Other Documents

General Electric letter, PE-3247, March 14,1985 - Design Verification of

-

Limerick Unit 2 Drawings

General Electric letter, PE-3564, June 18,1987 - Design Verification of

j

-

Limerick Unit 2 Drawings

!

-

Instruction Manual for HPCI Terry Turbine

M-251-59-1, Installation Manual for Metal Bellows Flexible Hose

-

M-251-58-1, Instruction Manual for Installation, Inspection and Handling

-

for Metal Bellows Flexible Instrument Hose

Limerick Generating Station Units 1&2 Project Q-List

-

i

\\

o