Expresses Concern Re Pending Massive NRC Reorganization & Impact Upon Intense NRC Review Schedule for Facility Restart Program.Urges Many Key Reviewers Assigned to Restart Review Be Kept
ML20213G422
Person / Time
Site: Rancho Seco, 05000000
Issue date: 02/05/1987
From: Julie Ward
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
Shared Package
ML20213G127 List:
References
FOIA-87-229 JEW-87-107, NUDOCS 8705180281
Download: ML20213G422 (2)


Text

6 b

(SMU=

SACRAMENTO MUNICIPAL UTILITY DISTRICT ~ 6201 S Street. P 0. Box 15830. Sacramento CA 95852 1830.1916)452-3211 AN ELECTRIC SYSTEM SERVING THE HEART CF CAllFORNIA February 5, 1987 JEW 87-107 Mr. Victor Stello Executive Director for Operations U. S. Nuclear Regulatory Commission 7735 Old Georgetown Road Maryland National Bank Building Bethesda, MD 20555

Dear Mr. Stello:

Your staff has been reviewing our progress with the development and implementation of our Action Plan for Performance Improvement.

We recognize that the scope of work we have undertaken is large and that our schedule for completing it is aggressive.

We have reviewed the schedule of information submittals with your staff and have agreed that it is possible for them to meet the project schedule.

In addition, we have prepared and submitted our Restart Report which is, in effect, our version of your staff's Safety Evaluation Report (SER).

Our intent with that report was to assist your staff by providing the background information needed for the SER.

It is our understanding that the staff believes this to be a valuable input.

Nonetheless, I remain concerned with the pending massive reorganization of the staff and its impact upon the intense NRC review schedule for restart of Rancho Seco.

Having been i

associated with several significant reorganization efforts, I know that current day tasks suffer as individuals begin to i

contemplate new roles and responsibilities.

This letter is to urge you to attempt to keep as many key NRC reviewers assigned to the Rancho Seco review as possible for the period needed to complete their individual tasks.

This will assure that the education and updating of new reviewers will be kept at a minimum and assure that the regulatory review process will not impact an orderly restart.

8705180281 870512 PDR FOIA 302:33 eLO KNAPIK87-229 PDR RANCHO SECO NUCLEAR GENERATING STATION 14440 Twin Cities Road. Herald. CA 95638 9799;(209) 333-2935

s 2

s Mr. Stallo February 5, 1987 I appreciate your consideration in this regard.

Sincerely, d

((

Joh

. Ward t*

Deputy General Manager, Nuclear cc:

J.

B. Martin, NRC Region V T. D'Angelo, NRC Rancho Seco G

I l

.