ML20212N903

From kanterella
Jump to navigation Jump to search
Resident Insp Rept 50-271/87-02 on 870105-0202.No Violations Noted.Major Areas Inspected:Actions on Previous Insp Findings,Physical Security,Plant Operations,Licensee Actions in Response to IE Bulletins 83-08 & 83-07 & LERs
ML20212N903
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 03/02/1987
From: Elsasser T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20212N876 List:
References
50-271-87-02, 50-271-87-2, IEB-83-07, IEB-83-08, IEB-83-7, IEB-83-8, IEIN-86-106, NUDOCS 8703130199
Download: ML20212N903 (70)


See also: IR 05000271/1987002

Text

f

9

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

87-02

Docket No.

50-271

License No. DPR-28

Licensee:

Vermont Yankee Nuclear Power Corporation

RD 5, Box 169, Ferry Road

Brattleboro, Vermont 05301

Facility:

Vermont Yankee Nuclear Power Station

Location:

Vernon, Vermont

Dates:

January 5 - February 2,198

Inspector:

William J

aymond Se 'or Resident Inspector

Approved by:

/

"

3

N

' Thomas C. Elsasser, 04Wpf, Reactor Projects 3C

Dat'e

Inspection Summary: Inspection 'on JWuary 5

February 2,1987 (Report No.

50-271/87-02)

Areas Inspected:

Routine, unannounced inspection on day time and backshifts by

the resident inspector of: actions on previous inspection findings; physical

security; plant operations; licensee actions in response to IE Bulletins 83-08 and

83-07, and Information Notice 86-106; control rod surveillance testing; maintenance

activities; licensee event reports; plant procedure review status; and, station

battery room temperatures.

The inspection involved 71 hours8.217593e-4 days <br />0.0197 hours <br />1.173942e-4 weeks <br />2.70155e-5 months <br />.

Results:

No violations were identified in the nine areas inspected.

Routine re-

views of plant activities identified no conditions adverse to safe plant operations.

Licensee plans to complete feedwater nozzle examinations during the 1987 refueling

outage require further review and approval by the NRC staff (paragraph 5.1).

Lic-

ensee plans to defer core spray nozzle replacenent require further review and

approval by the NRC staff (paragraph 13.0).

The control and surveillance o' bat-

tery room environment requires further licensee and NRC review (paragraph 14.0).

_

B703130199 87030S

PDR

ADOCK 05000271

0

PDR _

e

i

DETAILS

1.

Persons Contacted

Interviews and discussions were conducted with members of the licensee staff

and management during the report period to obtain information pertinent to

the areas inspected.

Inspection findings were discussed periodically with

the management and supervisory personnel listed below.

Mr. D. LaBarge, Senior Operations Engineer

Mr. D. Taylor, Senior Maintenance Engineer

Mr. D. Legere, Senior Maintenance Engineer

Mr. J. Pelletier, Plant Manager

Mr. G. Johnson, Operations Supervisor

Mr. J. Sinclair,-Security Supervisor

Mr. R. Wanczyk, Technical Services Superintendent

Messrs. R. Bernero, V. Rooney, W. Raymond and Commissioner James Asselstine

attended a meeting of the Vermont State Nuclear Advisory Panel (VSNAP) on

January 21, 1987 in Montpelier, Vermont to discuss general topics involving

nuclear safety issues, NRC and state relations, the status of the reviews of

the Mark I Containment Safety Study completed by the licensee, and the issue

of containment venting. The plans to address containment safety issues with

other Mark I users was also discussed.

The issue of containment venting will

be addressed further in a future meeting of the VSNAP in the Brattleboro,

Vermont area.

2.

Summary of Facility Activities

The plant continued routine operations at rated power during the report period.

A Region I specialist inspector completed an inspection of the radioactive

waste packaging, classification and shipping programs during the period of

January 12-16, 1987 (Inspection Report 87-01).

3.

Status of Previous Inspection Findings

3.1 (0 pen) Unresolved Item 85-40-09: RHR Pump Inspection Schedule. Continued

vendor problems in producing acceptable replacement impellers for the

residual heat removal (RHR) pumps caused the licensee to halt production

of the components.

Licensee and Bingham management met on January 5,

1987 in Portland, Oregon to review the manufacturing process, the cause

for the problems that resulted in eight unacceptable impellers, and the

additional actions that would be taken by the vendor to assure delivery

of acceptable components. The earliest shipping date for four new im-

pellers was February 13, 1987, and, based on this schedule, the licensee

planned to begin the six week RHR pump inspection and refurbishment pro-

gram on February 23, 1987.

The resident inspector will continue to fol-

low the licensee's plans and actions.

,

. . .

. .

_ - - _ _ _ _ _ _ _ - _ - - - - _ _ _ _ _

9

8

.

3

3.2 (0 pen) Unresolved Item 86-10-12: SLC Technical Specifications. By letter

FVY 87-10 dated January 16, 1987, the licensee proposed changes to Tech-

nical Specification 4.4.A (Proposed Change No. 136) that would better

reflect the revised and upgraded standby liquid control (SLC) system

functional test requirements now contained in Revision 8 of CP 4203.

The enhanced specifications now explicitly require insitu functional

testing of a trigger assembly taken from the same manufacturing batch

as those to be used for the subsequent operating cycle. The inspector

noted that the specifications were enhanced by requiring that the SLC

tank sodium penetaborate concentration be verified within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of

make-up to the tank.

No inadequacies were identified.

As dscussed in Inspection 86-10 (Appendix I,Section V), this item re-

mains open pending further quality assurance review of the squib valve

vendor to assure programmatic issues are resolved, and subsequent review

by the NRC.

3.3 (Closed) Follow Item 85-30-03: LER on Spurious Group III Isolations.

LER 85-11 dated November 6,1985 and LER 85-11, Revision 1 dated June

11, 1986, were submitted following spurious Group III isolatior.s that

occurred on October 8, 1985, October 12, 1985 and October 20, 1985. The

inspector reviewed the LERs and noted that they accurately described the

circumstances of the events. The presently installed equipment has

functioned properly since October 20, 1985. The inspector had no further

questions. This item is closed.

3.4 (Closed) Violation 86-08-06: Installation of Defective NAMC0 Contact

Blocks.

Licensee corrective actions for this item were also reviewed

during Inspection 86-10, and were discussed at a management meeting in

NRC Region I on July 29, 1986. The licensee responded to this item by

letter FVY 86-72 dated August 12, 1986, to describe the following cor-

rective actions that addressed the identified programmatic deficiencies.

(1) Detailed inspection criteria were received from NAMCO and were used

for onsite receipt inspection of subsequent orders. The licensee will

apply 100% receipt inspection for NAMCO orders until confidence is ob-

!

tained that apparent programmatic deficiencies are resolved. (ii) Visits

were made to the vendor's facilities to perform pre-shipment inspections

of materials, review the manufacturing process, and to complete an

evaluation of materials with defects of the type found at Vermont Yankee.

The vendor planned to make changes to the manufacturing process, includ-

ing the method of attaching the contact assembly to the block.

The licensee concluded that defects found by the inspector in the out-

board main steam isolation valves were caused during installation of the

blocks following the licensee's re-inspection of the switches during the

nonconformance report (NCR) process. The licensee stated that contact

carriers had not been inspected as part of the NCR process since they

did not contain arc suppression barriers and were not considered similar

-_____________

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

g

a

.

4

parts. The licensee stated that the corrective actions in progress per

the NCR and Part 21 report process during the NRC inspection would have

resulted in appropriate resolution of the matter.

During a discussion with the instrument and controls supervisor on

January 28, 1987, the inspector noted that he was responsible for assur-

ing that the 100% receipt inspection criteria be applied to future NAMC0

orders, but that no formal mechanism had been established to accomplish

the requirement. The licensee stated that a written notice would be

,

issued to identify the need to perform 100% inspections until such time

as deemed unnecessary.

The inspector had no further comments on the licensee's response at this

time and the licensee's corrective actions are considered complete. The

licensee's corrective actions process will be reviewed during subsequent

routine NRC inspections.

3.5 (Closed) Unresolved Iten 86-08-05: NAMC0 QC and Final Packaging Controls.

This item was also reviewed during Inspection 86-10. Additional licensee

artions on the item in conjunction with the vendor are discussed in

'

paragraph 3.4 above. The licensee's submittal of a Part 21 report on

the defective NAMC0 contact blocks provided notification to the NRC of

the potential generic applicability of this item to other users of the

materials.

The NRC's Vendor Program Branch performed an inspection at

the vendor's facilities in July, 1986 (Report 378/86-01) to review the

equipment qualification process, the QA controls applied by the vendor,

and the vendor followup actions in response to the Part 21 report sub-

mitted by the licensee. The vendor determined that the bakelite mate-

rials in the contact blocks were susceptible to damage from thermal shock,

such as could occur when a package of replacement parts were shipped via

airfreight and subjected to the cold temperatures of upper atmospheric

flight. The Vendor Program Branch will follow additional NAMCO actions

relative to shipping practices and customer notifications of potential

product damage.

This item is closed.

l

3.6 (Closed) Unresolved Item 86-10-09: Status of Materials Procured Under

Purchase Orders 1630 and 1631. The licensee completed actions to verify

that all unacceptable materials were sent back to the vendor, and to

verify that materials remaining at the site were acceptable. The ac-

ceptability of remaining materials was demonstrated by acceptable second

receipt inspections of materials returned or issued, and spot checks of

stock items. The results of the review were provided in a memorandum

to the plant services manager dated October 20, 1986, along with attached

receipt inspection checklists. This item is closed.

3.7 (Closed) Unresolved Item 85-40-02: Drywell Epoxy Coating. The licensee

completed actions during the outage to inspect the drywell epoxy coating

and remove the sections of epoxy from those locations where the coating

was peeling away (reference MR 86-0818). The licenseo verified that the

underlying primer was acceptable and capable of providing corrosion pro-

_ _ -

_

3

'

.

9,

Ty

'

j

.

5

i

i

tection for the drywell skin.

Plans were established to evaluate the

failure mechanism for the epoxy coat, to complete periodic inspections

_of the primer, and to repair it as.necessary during subsequent outages

-

to assure corrosion protection of the containment shell is maintained.

No inadequacies were identified. Inis item is closed.

,

4.0 .0bservations'of Physical Security

-

S_ elected ~ aspects of plant physical security were reviewed during regular and

backshift hours to verify that controls were in accordance with the security

-

plan and approved-procedures. This review included the following security '

measures: guard staffing; verification of physical barrier integrity'in the

protected and vital areas; verification that isolation zones were maintained;

and implementation of access controls, including identification, authorization,

'

badging, escorting, personnel and vehicle' searches.

..

!

4.1~ Security Events

'

On December 30,'1986, a moderate loss of physical -security effectiveness

occurred-due to a hardware failure within the security computer console.

The event was reported via the Emergency Notification System at 5:30 p.m.

,

on December 30, 1986, and a written report dated January 6,1987, was

'

submitted as Physical Security Event Report 86-07. The inspector re-

,

viewed the circumstances involved in .the event, the compensatory actions -

taken,-the corrective actions to prevent recurrence of the hardware-

failure, and the physical security event report.

No-inadequacies were

,

identified.

4.2 -On February 3, 1987, the inspector as notified at 3:30 p.m. by the

Vermont State nuclear engineer of a matter having security significance.

The State of Vermont received a letter on January 21, 1987 containing

allegations relating to security at the Vermont Yankee plant. The in-

spector obtained information regarding the substance of the allegation,

and relayed that information to NRC Region I management and appropriate

'

security personnel at the plant at 4:00 p.m.

Augmented security measures

were implemented at the plant commensurate with the allegations, as pre-

sented during a meeting with plant management at 6:40 p.m. on February

3, 1987, and summarized in a memorandum from J. Sinclair to File 6.0/VYSD

87-04 dated February 4, 1987. The inspector reviewed implementation of

the augmented security measures. This matter was referred to the Federal

Bureau of Investigation, for appropriate investigative action by that

agency in'accordance with Section 236 of the Energy Reorganization Act

of 1974. No inadequacies were identified.

5.0 Inspection Tours and Operational Status Reviews

'

Plant tours were conducted routinely to review activities in pregress and to

verify compliance with regulatory and administrative requirements. Tours of

accessible plant areas included the control room, reactor building, cable

spreading and switch gear rooms, diesel rooms, turbine building, and grounds

.

.

- - . - . - - . - . -

- , - , - , -

- . -

-

.

.

.

6

within the protected area.

Radiation controls were reviewed to verify access

control barriers, postings, and posted radiation levels were appropriate.

Plant housekeeping conditions were verified to be in accordance with the re-

quirements of AP 0042. Shift logs and records were reviewed to determine the

status of plant conditions and changes in operational status.

Items that

received further review are discussed below.

5.1 Reactor Building Ventilation Logic Status

During a review of control room panels at 8:30 a.m. on January 7, 1987,

the inspector noted that the reactor building ventilation system bypass

lamp was lit on panel CRP 9-15.

This indicated that the primary contain-

ment isolation system (PCIS) trip inputs from the Al channel of the re-

fuel floor zone and/or reactor building ventilation radiation monitors

were in a bypassed condition. The inspector noted that the logic bypass

'

switch, SW-A, which controls the bypass lamp, was in the OFF position.

The switch is normally used only during logic system surveillances and

there was no testing in progress at the time (testing per OP 4326 was-

last performed during the week of December 29,1986).

The inspector informed the shift supervisor of the item and actions were

taken immediately to investigate the status of the bypass switch contacts

and the PCIS actuation channels. The operators verified that no other

indication existed that a bypass was in effect by verifying that the

keylcck switch was in the OFF position and no annunciators were in effect

on panel CRP 9-5.

The bypass indication cleared at 8:45 a.m. after the

operator cycled the switch from 0FF to its other two operating positions.

Instrument & Control (I&C) personnel completed additional investigations

-

of the status of the logic circuit per MR 87-025.

This review confirmed

by 11:25 a.m., based on SW-A contact resistance measurements, that actu-

ation contacts in the K23 and K24 logic channels were not in a bypassed

state.

The SW-A keylock switch has three positions (K50A/0FF/K49A) and was found

in the OFF position. The switch is a compound device using six GE Type

CR2940 control switches stacked and/or ganged together to provide twelve

sets of contacts, eight of which are used for the PCIS bypass function

as follows: two contacts for the bypass indication lamp; two for the CRP

9-5 annunciator circuit; and four contacts used in the logic train for

actuation relays K23 and K24 (two each).

For the bypass lamp to have

i

been illuminated, either contacts 17/18 or 23/24 on the stack had to be

'

closed with the switch in the 0FF position.

The licensee conciuded that

the lamp contacts had operated improperly in the as-found condition on

January 7,1987. No reason for the malfunction was identified, and the

e

!

failure could not be repeated after cycling the switch several times.

The third bank of contacts for the bypass lamp indication was replaced

i

with a new CR2940 control switch on January 30, 1987.

l

.

.

.

7

The inspector reviewed the licensee response and corrective actions, and

identified no inadequacies. The bypass switch is cycled during monthly

surveillances of the PCIS logic channels. The switch bypasses only the

high radiation signal inputs from the ventilation monitors, and does not

block the trip signals from a downscale failure of the monitors. Based

on the arrangement of the switch contacts in the logic channel, the sub-

sequent random failure of any single contact could not defeat the ful-

fillment of the safety function to assure a PCIS isolation following

increased radiation levels either in the reactor building ventilation

exhaust or on the refueling floor, since the. redundant monitors in those

zones would cause the PCIS channel actuation.

The inspector noted that the day shift operators had completed the shift

turnover and their oncoming reviews of the plant status. These reviews

did not detect the potential bypass condition. The inspector noted that

the formal turnover sheets in AP 0150.03 do not include a requirement

that the operator check the stauts of the bypass lamps on panels CRP 9-15

or 9-17.

The inspector discussed this item with the operations super-

visor on January 8,1987, who stated that the matter would be reviewed -

to determine whether a change to the round sheets should be made to in-

clude a periodic check of the back panel safety-related bypass lamps and

keylock switches. The licensee determined that no changes to the round

sheets were necessary, for reasons documented in a memorandum to File

10.0 dated January 16, 1987.

The incident and significance of the bypass

indication were reviewed with operations personnel.

The inspector had no further comments on this item at the present time.

The status of the PCIS actuation channels will be reviewed further during

subsequent routine inspections.

5.2 Feedwater Leak Detection

The inspector reviewed the feedwater sparger leakage detection systen

and the monthly performance summary provided by the licensee in accord-

ance with letter FVY 82-105.

The licensee reported that, based on the

leakage monitoring data reduced as of Cecember 31, 1986, there were no

deviations in excess of 0.10 from the steady-state value of normalized

thermocouple readings, and no failures in the sixteen thermocouples in-

stalled on the four feedwater nozzles. No unacceptable conditions were

identified.

5.3 Safety System Review

The residual heat removal, high pressure coolant injection, residual heat

removal service water, standby liquid control, reactor core isolation

cooling, core spray and standby gas treatment systems were reviewed to

verify the systems were properly aligned and fully operational in the

standby mode. The review included: (1) verification that accessible

major flow path valves were correctly positioned; (2) verification that

- -

.

_

_

.,.

.

-_

__

_

.

.

<

-

.

8

.

power supplies were energized; and, (3) visual inspection of major com-

ponents for leakage, proper lubrication, cooling water supply, and

general condition. No inadequacies were identified.

5.4 Operation with Inoperable Equipment

Actions taken by plant personnel during periods when equipment was in-

operable were reviewed to verify : Sat: (1) technical specification limits

were met; (2) alternate testing or inspection was completed satisfactorily

per AP 0025; and, (3) equipment return to service upon completion of re-

pairs was proper. The above reviews were completed for the following

items: (1) the B core spray pump, removed from service on January 20,

1987 for balancing of the thrust. bearing; (ii) removal of the A service

water pump on January 13, 1987 for motor adjustments; and (iii) removal

of the A standby gas treatment system on January 13, 1987 for charcoal

replacement.

5.4.1

Loss of "B" Station Air Compressor

The inspector also reviewed the actions taken by operators at

4:50 p.m. on January 17, 1987 when the B air compressor supply

breaker tripped and the compressor discharge check valves

failed open. Operator actions were prompt and effective to

isolate the faulty compressor and restore the air header to

a normal status prior to loss of other plant systems.

Header

air pressure decreased from the normal value of 110 psig to

about 77 psig prior to recovery to normal with the standby air

compressor. The B compressor was released for maintenance.

No inadequacies were identified.

5.4.2

Inoperable Diesel Generator

Plant operators declared the B diesel generator inoperable at

12:15 p.m. on January 7,1987 when the auxiliary operator noted

that relief valve SR72-78 had failed open, causing the compres-

sor to run continuously and overheat.

The compressor was

secured and alternate system testing was begun in accordance

with Technical Specifications 3.10 and 3.5. The diesel air

start tanks were full at the normal pressure of 220 psig, and

thus were capable of starting the diesel upon demand at the

time the condition was discovered. Maintenance personnel

tested and cleaned the relief valve, and found that it lifted

at the proper setpoint of 260 psig.

No specific reason for

the relief valve to open was identified. With the relief valve

installed, the air compressor was retested satisfactorily and

the B diesel generator was declared operable at 2:20 p.m.

The

resident inspector reviewed the licensee's response and cor-

rective actions and identified no inadequacies.

__

_ _ - - _ _ _ _ _ _

.

.

.

9

.

5.4.3

8 RPS HC Set Failure

,

The B reactor protection system (RPS) motor genertor (MG) set

tripped off line at 12:20 p.m. on January 7,1987 while the

reactor was operating at 100% of rated power.

Loss of the B

RPS bus caused a one-half scram condition and a primary con-

tainment Group III isolation to occur. The reactor building

,

normal ventilation isolated and the standby gas treatment

system started, as expected.

Control room operators switched

the 8 RPS bus to its alternate supply, reset the scram and

isolation, and returned the reactor building ventilation to

normal conditions by 12:27 p.m.

Subsequent review by mainten-

ance persennel determined that the coil of the K1 relay in the

MG set voltage control circuit had failed, which caused the

MG set output to trip on underfrequency.

The relay was re-

placed and the MG set was retested satisfactorily and returned

to service at 2:20 p.m.

Plant operators reported the ESF

actuation to the NRC headquarters duty officer per 10 CFR 50.72.b(2)(ii) at 1:10 p.m. on January 7, 1987. The licensee

reported this esent as LER 87-01 dated February 6, 1987, which

accurately described the event and corrective actions. The

resident inspector reviewed the licensee's response to the

event and identified no inadequacies.

6.0 Emergency Response Facilities

The inspector met with the plant manager on January 23, 1987 to review license

plans to modify the working spaces within the present administration building

,

to improve the Technical Support Center (TSC) and correct deficiencies iden-

tified by previous licensee and NRC audits. The licensee will modify the

spaces in phases and plans to expand the current " communications" room prior

to the 1987 emergency exercise. The inspector provided input to the licen-

see's planning for the TSC relative to the location of the emergency notifi-

cation phone and the location of NRC personnel who respond to site emergencies.

The inspector identified no inadequacies in the licensee's plans. The in-

spector noted further that the adequacy of the response center will be re-

viewed by the NRC Region I staff during a future emergency facilities inspec-

tion.

7.0 Response to IE Bulletins and Notices

7.1 IE Bulletins

The inspector reviewed the licensee's response to IE Bulletin 83-08 which

was provided by letter FVY 84-31 dated March 30, 1984.

The licensee re-

viewed the information presented in the bulletin and concluded that none

of the electrical circuit breakers in safety related applications have

undervoltage trip attachments, and no plans existed to use such breakers.

No inadequacies were identified.

..

-

- - .

. - -

. .

_ . _

, _ _ _

_ __ ._.-,_ -- . .

.

.

10

The inspector reviewed the licensee's response to IE Bulletin 83-07 which

was provided in letter FVY 84-26 dated March 22, 1984. The licensee

reviewed the vendor files in light of the concerns stated in the bulletin

and concluded that no materials supplied to Vermont Yankee came from

Ray Miller, Inc. The licensee also stated that the procurement program

would be' enhanced by adding criteria to the vendor selection process that

would assess the ability of vendors to prevent fraud and assure authen-

ticity cf products supplied to the facility. No inadequacies were iden-

tified.

7.2 Information Notices

In accordance with NRC Region I Temporary Instruction 87-02, the inspec-

tor reviewed actions taken by the licensee in response to the feedwater

line rupture event at the Surry Nuclear Power Plant.

Information Notice

(IN)86-106 was received at the site and assigned for. licensee review

and followup. Preliminary recommendations to address the concerns in

the notice were provided in a memorandum to the senior operations engi-

neer dated February 4,1987 (File 10.2).

The licensee has had a program in place for several years to monitor for

wall thinning in piping between the turbine, moisture separators, and

reheaters that carry wet steam. The program was instituted as a result

of previous steam. leaks in the piping. The most recent example of a

problem was through wall thinning and leakage in the feedwater minimum

flow line.

Corrective actions to repair susceptible piping were taken

during the 1984 and 1985 outages. As part of this existing program, 100

susceptible areas were identified for followup and a sample of 30 repre-

sentative areas were selected for measurement during the 1987 outage.

As a result of the information notice, the licensee plans to modify the

measurements program during the 1987 outage to include portions of the

feedw&ter system piping.

Limited licensee and NRC observations of the

low pressure water piping during periods when valves or pumps were apart

for repair have not shown evidence of erosion, corrosion or wall thinning

in the feedwater/ condensate streams.

The 1987 inspection program was under development as of this inspection.

>

The selection criteria to be used to identify piping areas for examina-

tion were contained in the February 4th memorandum. The inspector noted

that the selection criteria did not include the following: (1) piping

runs that contain fittings less than 10 pipe diameters apart; and,

(ii) oxygen concentration in the process fluid. The inspector noted that

oxygen levels less than 10 parts per billion could cause piping materials

to be more susceptible to erosion and corrosion due to interference with

the formation and maintenance of the protective magnetite coating.

The

licensee stated that these items would be considered for inclusion in

the pipe selection criteria.

.

.-.

- -

.

-

_ _ _ .

.-

- ..

-

-

' l

.

>>:

s

I

.

?

^

~

.11

j

'-

. ,

i

The inspector noted further that the licensee uses a system to inject

oxygen into the condensate-feedwater stream at a point just downstream

'

of the condensate pumps. The oxygen injection system is used during.

reactor startups to control oxygen within the desired levels.

The inspect'or had no further comments in this f arca at the present time.

No inadequacies were identified.

8.0 Control Rod Scram Time Test. Requirements

The inspector met with the technical services superintendent and the reactor

engineer on January 21, 1987 to discuss the requirements for control rod scram'

-testing contained in. Technical Specification 4.3.C.1.

The licensee's position

regarding the testing requirements were contained in a File.13.1 memorandum

.from J.C. Brooks to R.J. Wanczyk dated January 21, 1987, with~ attachments.

--Specification 4.3.C.2 requires that "during or-following a controlled shutdown

-of.the reactor, but not more frequently than 16 weeks nor less frequently than-

32 weeks," 50% of the control rods shall be scram time tested. -All control

'

rods shall be tested each year. All control rods were scram time tested prior

to the reactor startup from the outage in July,1986 (per specification

4.3.C.1), and scram time measurements were obtained on at least 50% of the

rods during the inadvertent scram on October 4, 1986, 14 weeks after the

startup from the outage. The licensee reviewed this matter with the NSSS

vendor to determine whether he could take credit for this rod time data even

though-it fell outside the 16-week interval. The licensee could identify no

' basis for the-maximum frequency limit of 16 weeks, other than to preclude

excessive rod testing in conjunction with frequent plant shutdowns. Based

on the above, the licensee took credit for the October rod data, and will

complete scram time measurements on the remaining 50% of the rods within 32

weeks of the October measurements.

The licensee's position was discussed with NRC Region I management and with

.

the NRR project manager.

No inadequacies were identified.

9.0 Extended Work Hours

The inspector reviewed operations department shift staffing and overtime re-

ports for the period from January,1986 to January,1987 to verify the use

of overtime was maintained within the administrative limits of AP 0036, Re-

vision 5.

Department staffing was sufficient to man six shifts, resulting

in the occasional use of overtime during normal power operations.

Five shif ts

were used during the outage, with a moderate use of overtime. Use of overtime

during the outage was within the guidelines. No instances were identified

'

where overtime in excess of the guidelines was required.

No inadequacies were identified.

.....,....-_._,,._.-_m.-.-_..

, . . , . . . . . , _ , _ , , , _ _ _ . _ , _ . - _ . ,

.. -.-. m .

--__

_ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ - _ _ _ _

.

.

,

12

e

10.0 Maintenance Activities

Selected maintenance activities in progress during the inspection were re-

viewed to determine the scope and nature of work done on safety-related

equipment. The review confirmed: (1) the repair of safety-related equipment

received priority attention; (2) technical specification limiting conditions

'

for operation were met while components were out of service; and, (3) perform-

ance of alternate safety-related systems was not impaired.

Maintenance activities associated with the following items were reviewed to

verify (where applicable) correct procedure compliance and equipment return

to service, including operability testing.

10.1 MR 87-079, B Core Spray Pump Salancing - The licensee removed the B core

spray pump from service on January 20-21, 1987 to balance the motor shaft

by the addition of weights on the outboard (thrust bearing) end.

Pump

vibrations at the thrust bearing improved as a result of the balanced

-

shaft, but remained in the " rough" range. The pump was declared operable

at 2:50 p.m. on January 21, 1987. The licensee is planning additional

balancing of the shaft at a later time. No inadequacies were identified.

1

'

10.2 MR 86-2265, B Emergency Core Cooling System Battery Ground - During a

discussion with I&C personnel on January 15, 1987, the inspector noted

that the licensee had isolated a ground on the B battery system for the

analog trip system. The ground was located in the printed circuit board

for reactor pressure transmitter PT 2-3-56A(M). The initial results of

the licensee's investigation were that the ground was caused by a faulty

filter capacitor in the 24-volt power supply for the analog trip card.

The trip card is a Rosemount 71000 Series Analog trip system component.

The licensee has noted failures in the filter capacitors on three cards

during the last operating cycle and on two cards during the present

operating cycle. The 710-series units have been in service since about

1984, when they were installed as replacements for Rosemount 510-series

units, as p'.*t of a change to assure operability in potentially harsh

environments, as determined by the environmental qualification program.

No inadequacies were identified.

10.3 MR 87-025, RBV Logic Bypass Switch.

See paragraph 5.1 above for further

discussion of this item.

No inadequacies were identified.

11.0 Review of LERs

The licensee event reports (LERs) listed in Attachment I were reviewed to

verify the reports were submitted in accordance with the requirements of 10 CFR 50.73.

For each report, the inspector verified that (1) the LER accu-

rately described the event; and, (ii) the root cause was identified and ac-

tions taken or planned were appropriate to prevent recurrence.

_

..:

6

13

Additionally, on January 16, 1987 the inspector provided the licensee Attach-

ment II, a detailed evaluation of LER quality made by the NRC Office of

Analysis and Evaluation of Operational Data (AE00) using the basic methodology

presented in NUREG 1022, Supplement 2.

In general, the LERS were found to

be above the average in quality.

LER quality especially improved in the later

half of 1986 following the use of new licensee procedures developed in re-

sponse to. the previous set of AE00 comments.

No inadequacies were identified, except as noted below.

11.1 Report Timeliness

The inspector noted that seven LERs were not submitted within the 30-day

period required by 10 CFR 50.73. The subject LERs are listed below,

along with the number of days late: LER 86-14 (80 days), 86-09 (3 days),

86-08 (3 days), 86-04 (1 day), 86-03 (2 days), 85-13 (9 days), and, 85-07

(2 days). Of these seven reports, two were notably late at 9 and 80 days.

LER 86-14 was submitted in response to Inspection Report 86-15 issued

on September 16, 1986 due to the licensee's initial disagreement that

the missed SLC surveillance constituted a technical specification viola-

tion. The licensee's response to the event was reviewed and found ac-

ceptable as discussed further in section 11.3 below.

Inspector concerns regarding the timeliness of LER submittals were dis-

cussed with licensee personnel. The inspector stated that this matter

should receive further management attention to assure that reports are

submitted within the 30-day period. This matter will be reviewed further

during subsequent inspections (UNR 87-02-01).

11.2 LER 86-12, MOV Failure

The inspector noted, based on information from the NRC Office of AE00,

that conflicting information was provided by the licensee in LER 86-12,

that described a potentially generic concern with Limitorque motor

operators. The original LER 86-l'2 dated July 10, 1986 stated that Mobil

EP-1 grease was installed in 40 valves during the outage as part of the

vendor's recommendation for routine preventive maintenance (PM).

LER 86-12, Revision 1, dated August 22, 1986 stated that Mobil EP-0

grease was used. The grease actually used during PM on the 40 valves

was Exxon Nebula EP-0 grease. The less viscous grease leaked past the

spring peak seal and effectively increased the torque setpoint.

The 40 valves rebuilt during the outage included those in the drywell,

the steam tunnel and elsewhere in the plant. The drywell and steam

tunnel valves would potentially be subjected to the more severe environ-

mental conditions during postulated accidents.

The Limitorque manufac-

turer recommends only two greases for use in the valve operators, Exxon

Nebula EP-0 or SUN 0CO 50 EP, and specifically, only Nebula EP-0 is con-

.

..

14

sidered acceptable for valves used in safety-related applications for

which environmental qualification is required.

There are 162 safety-

related and non nuclear safety motor operated valves in the plant.

The

licensee's preventive maintenance program addresses roughly one-third

of all the remaining valves during each outage.

The inspector noted that

for the remaining 122 valves in the plant, the licensee's past maintenance

practices have included adding Mobil Mobilux EP grease with the Exxon

Nebula EP grease supplied in the operators by the manufacturer.

The inspector reviewed the qualification documentation by the licensee

in Section 13.1 of the Environmental Qualifications Manual governing

motor operated valves to determine whether safety related valves with

mixed greases were environmentally qualified.

The licensee's qu111 fica-

tion program specifically addressed the adequacy of motor operators that

used a mixture of Mobil and Exxon EP-0 greases.

Based on an engineering

evaluation provided in a letter from an Electric Power Research Institute

(EPRI) staff consultant dated February 18, 1986, the licensee determined

that the valves with the mixed greases were not susceptible to short term

degradation, and were therefore environmentally qualified, particularly

for valves in relatively low dose areas outside the primary containment.

However, the licensee engineering organization did recommesid that the

grease in the subject operators be changed out to Exxon EP-0 grease on

a phased basis over tiie course of subsequent outages, with priority given

to valves showing signs of lubricant leakage.

The inspector noted, based

on discussions with maintenance personnel, that plans were in progress

to complete OP 5220 inspections on 18 valves, and change the grease on

24 additional valves during the 1987 outage.

The inspector had no further questions regarding the status of Limitorque

motor operators at Vermont Yankee and the licensee's program to install

Exxon Nebula EP-0 grease.

However, the erroneous information supplied

by the licensee in LER 86-12 and LER 86-12, Revision 1 should be cor-

rected to identify to other Limitorque users that the vendor-recommended

EP-0 grease can cause torque switch setting problems because of its

viscosity.

This item is unresolved pending sut,mittal of a revised LER

86-12, and subsequent review by the NRC (UNR 50-271/87-02-02).

11.3 LER 86-14, SLC Surveillance

,

NRC review of this LER identified two items that were inaccurate.

The

licensee's summary of the event stated that the need to sample the tank

following the water addition was provided in the " turnover" briefing with

the following shift.

The inspector noted that NRC review of the event

determined that the sample request was not included in the turnover.

Additionally, the licensee reported this event under the "other" category

of the 10 CFR 50.73 requirements.

The inspector noted that the incident

could have been reported under section 50.73(A)(2)(1)(b), as an operation

or condition prohibited by the technical specifications.

The violation

of the technical specification surveillance requirement was addressed

in Inspection 86-15.

The licensee's response to the violation was de-

.

_

-

_

_ _

_

__

. _ . . _ _

_ --

-_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _

'

-,

..

.

15

scribed in letter FVY 86-96 and found acceptable in Inspection 86-22.

The above items were discussed with the licensee. The accuracy of in-

formation will be reviewed further during subsequent inspections.

12.0 Plant Procedure Review Status

The inspector reviewed the status of procedures in the biennial review cycle

to determine the current status of the procedure reviews and the number of

procedures that were overdue in review.

The status was summarized in a Pro-

cedure Follow Statistics List dated January 16, 1987.

Plant actions were

successful prior to the 1985 outage in essentially eliminating the backlog

of plant procedures that were overdue in the biennial review cycle. Based

on the success of the existing PORC review methods, no further action was

taken to use subcommittees for procedure reviews. To address regulatory con-

l

cerns on assuring PORC reviews of procedures within two years, the review

process was revised to assure standing procedures were acceptable for con-

tinued use pending issuance of the new revisions.

However, the number of overdue procedures increased during the 10-month re-

circulation pipe replacement outage and reached a total of 70 by August, 1986.

Licensee efforts were successful in reducing the total procedures past due

in review to 58 as of January 1987, and of these, 34 reviewed by the PORC and

21 required final review by the Manager of Operations. Of the 58 overdue

procedures, 28 were overdue by less than 3 months, 17 were 3 months past due,

and 13 were 6 months past due. All procedures that were either 3 or 6 months

past due had been reviewed by the PORC to verify whether the procedures were

acceptable for continued use "as is" pending issuance of the new revision,

or should not be used until revised.

The continued review of routine procedures at the corporate level is assuring

continued overall quality of plant procedures. The corporate reviews appeared

to be timely and did not contribute to the backlog.

Continued licensee efforts in this area should eliminate the backlog and

assure reviews of plant procedures are completed in a timely manner.

No inadequacies were identified.

!

13.0 Core Spray Safe-End Replacement

!

By letter FVY 87-07 dated January 12, 1987, the licensee submitted for NRC:NRR

approval the proposed plans to address the core spray nozzle safe ends. The

nozzle-to-safe-end welds on both core spray nozzles were found cracked during

i

inspections completed in 1986. By letter dated June 16, 1986, NRC:NRR ap-

proved the weld overlay design and repair methodology, approved interim plant

operation with the overlays, and recommended that the safe ends be replaced

during the 1987 refueling outage.

-

.

.

16

In the January 12, 1987 letter, the licensee provided the basis for the de-

terminations that the repaired nozzles were acceptable for continued, interim

service through the end of the next operating cycle (Cycle 13), and proposed

deferral of the nozzle replacement until a subsequent outage. The licensee

committed to inspecting the overlay repairs in accordance with EPRI/NRC weld

inspection criteria, and to provide the detailed plans for inspecting the

overlays in May,1987. This item is unresolved pending NRC:NRR acceptance

of the licensee's proposed plans, and further review of the licensee's actions

during a subsequent inspection (UNR 87-02-03).

14.0 Battery Temperature Limits

The inspector reviewed licensee controls for battery room and electrolyte

temperature in response to a request for information from NRC Region I on

January 30, 1987!. Based on a review of operating, maintenance and surveil-

lance procedures, the inspector determined that no procedural controls exist

~

to monitor battery room temperatures, establish temperature limits for battery

environments, or to otherwise control room temperatures within prescribed

limits. Procedure OP 4210 is used to complete weekly surveillance on bat-

teries at the facility and does incorporate requirements to apply a tempera-

ture correction to specific gravity readings. The temperature readings are

obtained from the monitored battery pilot cells and are used to correct

specific gravity readings relative to the reference temperature of 77 degrees

F.

The acceptance criteria for assuring operability of batteries monitored

per OP 4210 is that battery cell voltage be greater than 2.13 volts and

specific gravity be greater than 1.19 corrected to 77 degrees F.

The inspector reviewed available vendor information for Exide and C&D bat-

teries for information regarding battery temperatures limits. Both manuals

indicated battery room temperatures within the range of 60 to 90 degrees F

were acceptable. The inspector reviewed OP 4210.01 data recorded during the

,

surveillance period of October,1986 to February,1987, for batteries associ-

ated with the rain station DC system, the UPS system, the ECCS system, the

emergency lighting diesel generator, the fire water pump diesel generator,

the reactor protection system, the relay house-switchyard system, the RCIC

alternate supply, and the A emergency diesel generator. The te ;t data showed

that minimum voltage and specific gravity limits were met for all temperature

conditions for each battery. Electrolyte temperatures for each test were

found within the 60 to 90 degree F range on all batteries, except as noted

below.

The electrolyte temperature was outside the range of 60 to 90 degrees F as

follows: (i) emergency lighting diesel generator: temperature within the range

of 50 to 60 degrees from October 20 until January 19, 1987, with a low of 47

degrees F January 26, 1987; (ii) AS2-A diesel generator room: temperature of

59 and 54 degrees on January 19th and 26th, respectively.

Several other bat-

teries had measured electrolyte temperatures in the range of 60 to 70 degrees

F.

The inspector noted that, based on the OP 4210 acceptance criteria, the

batteries were considered operable.

f

a

.

.

.

17

This matter was referred to the licensee for further review and followup to

address the following concerns expressed by the inspector: (1) the effects

of low room temperatures on battery capacity - C&D vendor information suggests

that battery capacity can be reduced by up to 9.8% for temperatures as . low

as 62 degrees F; (2) what were the battery environmental conditions specified

in the battery design specifications supplied to the battery vendor, or

otherwise stated, what is the limit on temperature range to establish an

operability envelope for the battery; and, (3) what actions should be done

to monitor battery room temperatures to assure batteries remain within the

established range. This item is unresolved pending completion of licensee

actions to review this matter and subsequent review by the inspector (UNR

50-271/87-02-04).

15.0 Management Meetinar

Preliminary inspection findings were discussed with licensee management peri-

odically during the inspection. A summary of findings for the report period

was also discussed at.the conclusion of the inspection and prior to report

issuance.

.

-

-.,-

_,...,.,.7

- .

. _ , _ . - - - _ - - . - - - - -

..

.,---.--_.r...._,,-

. , _ . , _ - - . - ~ . ~ - - - , ,

,.

__

_ _ _ - _ .

_ _ _ _ _

_ _ _ _ _ _

.

.

ATTACHMENT I

LER SUMMARY

LER Number

Summary Description

85-007

While performing type C rate testing, several (9) valves were found

Revision 1

to have seat leakage above that permitted by TS 3.7.A.4

85-008

Personnel discovered an error in the offsite dose rate calculations

procedure, which did not correspond to TS Section 3.8.E

85-009

A full scram signal was received from the scram circuit while im-

plementing a design change in the RPS system

85-010

Conductors installed in contact with the sharp edge of the end of

the electrical penetration assembly sleeve

85-011

Spurious signals on refuel floor zone radiation monitor resulted

in isolation of the RB ventilation system and activation of the SGTS85-012

Freon was released in the vicinity of the CR air intake duct while

servicing the air conditioners which activated the CR habitability

system

86-001

Containment valves missing from Appendix J 1eak rate test program

86-002

Calculational error discovered in the Environmental Qualification

Program which underpredicted the postulated radiation exposure for

parts in the H2/02 analyzer system

86-003

Two main steam relief valves actuation pressures were above the

setpoints86-004

The "A" SLC squib valve failed to fire during performance of annual

surveillance

86-005

Ultrasonic indications of intergranular stress corrosion cracking

(IGSCC) were detected in inconel 182 weld butter of both spray

nozzles86-006

Unanticipated scram signal during LPRM cable testing / troubleshooting

86-007

1985/86 Appendix J Type A test failure due to penetration leakage

86-008

Unanticipated scram during mode switch movement

86-009

"C" SRV accumulator failed leak test due to check valve seat leak

_

_ _ - - _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

.

.

,

Attachment I

2

LER Number

Summary Description

86-010

Inadvertent reactor scram signal on loss of RPS caused by broken

relay armature

86-012

Motor operator failure due to torque switch hydraulic lockup

86-013

Reactor scram during startup due to inoperable intermediate range

monitors86-014

Failure to sample SLC tank after water addition

86-015

High flux reactor scram in hot standby due to cold feedw.ter in-

jection

86-016

Missed Appendix J leak test due to personnel error

87-001

Isolation, Half Scram and SBGT Initiation due to RPS MG Set relay

failure.

1

- _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

_

,k.-4-

2

-

.a

w

> _ _ ~ +

a

_

-

a s

e

a

.a

-

O

_.

-

9

ATTACHMENT II

J

AE00 SALP INPUT FOR

,

i

-VERMONT YANKEE-

!

OPERATIONS (LER QUALITY) FOR

THE ASSESSMENT PERIOD OF

,

1 OCTOBER 1985 TO 31 DECEMBER 1986

,

1

i

I

,

I

-

>

5

i

i

f

a

,. .

. .

. ..

. . . . .

.

. .

. .

-

.

. . .

.

.

. .

.

. .

. . .

.

- .

. .

.

_ - _ _ _ _ _ _ _ _ _ .

.

.

'

t

SUMMARY

' An evaluation of the content and quality of a representative sample of

the Licensee Event Reports (LERs) submitted by Vermont Yankee during the

October 1, 1985 to December 31, 1986 Systematic Assessment of Licensee

Performance (SALP) period was performed using a refinement of the basic

methodology presented in NUREG-1022, Supplement No. 2.

This is the second

time the Vermont Yankee LERs have been evaluated using this methodology.

The results of this evaluation indicate improvement in that the

Vermont Yankee LERs now have an overall average score of 8.3 out of a

possible 10 points, compared to their previous overall average score of 7.1

and a current industry average score of 8.2 (i.e., the average of the

latest overall average LER score for each unit / station that has been

evaluated to date using this methodology).

One weakness identified in the Vermont Yankee LERs involves the

requirement to adequately discuss personnel error (Requirement

50.73(b)(2)(ii)(J)(2)].

Two strong points for the Vermont Yankee LERs are the discussions

concerning the safety assessments (Requirement 50.73(b)(3)] and the failure

mode, mechanism, and effect of failed components (Requirement 50.73(b)(2)(11)(E)].

1

..

.

.

..

'

t

AE00 INPUT TO SALP REVIEW FOR

VERMONT YANKEE

Introduction

.

In order.to evaluate the overall quality of the contents of the

Licensee Event Reports (LERs) submitted by Vermont Yankee during the

October 1, 1985 to December 31, 1986 Systematic Assessment of Licensee

Performance (SALP) assessment period, a representative sample of the unit's

LERs was evaluated using a refinement of the basic methodology presented in

NUREG-1022, Supplement No. 2.1

The sample consists of a total of

15 LERs, which is considered to be the maximum number of LERs necessary to

have a representative sample.

See Appendix A for a list of the LER numbers

in the sample.

It was necessary to start the evaluation befo.e the end of the SALP

assessnent period because the input was due such a short time after the end

of the SALP period. Therefore, all of the LERs prepared during the SALP

assessment period were not available for review.

Methodology

The evaluation consists of a detailed review of each selected LER to

i

determine how well the content of its text, abstract, and coded fields meet

the criteria of 10 CFR 50.73(b).

In addition, each selected LER is

compared to the guidance for preparation of LERs presented in NUREG-1022

and Supplements No. 1 and 2 to NUREG-1022; based on this comparison,

suggestions were developed for improving the quality of the reports. The

purpose of this evaluation is to provide feedback to improve the quality of

LERs.

It is not intended to increase the requirements concerning the

" content" of reports beyond the current requirements of 10 CFR 50.73(b).

Therefore, statements in this evaluation that suggest measures be taken are

not intended to increase requirements and should be viewed in that light.

However, the minimum requirements of the regulation must be met.

1

.-

. --

.

.

. -

. _ - _ _ _ _ - - - ~ _ - _ _ _ - - _ .

-

- - - - - - .

-

_ _ _ _ _

_ _ _ - _ _

.

.

!

-t-

l

The evaluation process for each LER is divided into two parts.

The

'

first part of the evaluation consists of documenting comments specific to

the content and presentation of each LER.

The second part consists of

determining a score (0-10 points) for the text, abstract, and coded fields

of each LER.

The LER specific comments serve two purposes:

(1) they point out what

the analysts considered to be the specific deficiencies or observations

concerning the information pertaining to the event, and (2) they provide a

basis for a count of general deficiencies for the overall sample of LERs

that was reviewed. Likewise, the scores serve two purposes:

(1) they

serve to illustrate in numerical terms how the analysts perceived the

content of the information that was presented, and (2) they provide a basis

for determining an overall score for each LER.

The overall score for each

LER is the result of combining the scores for the text, abstract, and coded

fields (i.e., 0.6 x text score + 0.3 x abstract score + 0.1 x coded fields

score - overall LER score).

The results of the LER quality evaluation are divided into two

categories:

(1) detailed information and (2) sumnary information. The

detailed information, presented in Appendices A through 0, consists of LER

sample information (Appendix A), a table of the scores for each sample LER

(Appendix 8), tables of the number of deficiencies and observations for the

text, abstract and coded fields (Appendix C), and comment sheets containing

narrative statements concerning the contents of each LER (Appendix D).

-

When referring to these appendices, the reader is cautioned not to try to

directly correlate the number of comments on a comment sheet with the LER

scores, as the analysts has flexibility to consider the magnitude of a

deficiency when assigning scores.

Discussion of Results

A discussion of the analysts' conclusions concerning LER quality is

presented below. These conclusions are based solely on the results of the

evaluation of the contents of the LERs selected for review and as such

2

___

1

- __

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ .

.

.

f

'

i

represent the analysts' assessment of the unit's performance (on a scale of

0 to 10) in submitting LERs that meet the criteria of 10 CFR 50.73(b) and

the guidance present in NUREG-1022 and its supplements.

Table 1 presents the average scores for the sample of LERs evaluated

for the unit.

In order to place the scores provided in Table 1 in

perspective, the distribution of the overall average score for all

units / stations that have been evaluated using the current methodology is

provided on Figure 1.

Additional scores are added to Figure 1 each month

as other units / stations are evaluated.

Table 2 and Appendix Table B-1

provide a summary of the information that is the basis for the average

scores in Table 1.

For example, Vermont Yankees's average score for the

text of the LERs that were evaluated is 8.4 out of a possible 10 points.

From Table 2 it can be seen that the text score actually results from the

review and evaluution of 17 different requirements ranging from the

discussion of plant operating conditions prior to the event

[10 CFR 50.73(b)(2)(11)(A)] to text presentation. The percentage scores in

the text summary section of Table 2 provide an indication of how well each

text requirement was addressed by the unit for the 15 LERs that were

evaluated.

Discussion of Specific Deficiencies

A review of the percentage scores presented in Table 2 will quickly

point out where the unit is experiencing the most difficulty in preparing

LERs.

For example, requirement percentage scores of less than 75 indicate

that the unit probably needs additional guidance concerning these

requirements. Scores of 75 or above, but less than 100, indicate that the

unit probably understands the basic requirement but has

either:

(1) excluded certain less significant information from many of the

discussions concerning that requirement or (2) totally failed to address

the requirement in one or two of the selected LERs.

The unit should review

the LER specific comments presented in Appendix D in order to determine why

it received less than a perfect score for certain requirements. The text

3

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ __ _0

.. ._ _

_ _ _ _ _ - _ _ _ _ _ _ _ _ .

.

.

.

a

'

TABLE 1.

SUMMARY OF SCORES

FOR VERMONT YANKEE

l

______________________________________________________________________

Average

High

Low

_______

____

___

Text

8.4

9.7

7.1

Abstract

7.9

10.0

6.3

Coded Fields

8.8

9.9

7.6

Overall

8.3

9.7

7.1

c.

See Appendix B for a summary of scores for each LER that was evaluated.

___________________________________________________________________________

4

,

l

l

O

o

s

~

e

-

-

-

-

-

-

-

-

-

-

-

0

r

6

o

.

.

c

.

.

s

.

.

R

.

.

5

E

i

i

6

L

.

a

.

.

e

.

.

g

.

.

a

0

r

i

i

7

e

.

yI.

s

v

.

.

e

r

a

.

.

o

l

e

zi

c

e

.

.

s

.k

5

la

n

7

e

a

r

.

l

g

e .Y

.

a

l

t

.

n

r

v

.o

a

e

.

o

m

v

.

r

.

a

0

e

f

i.V

o

8l

l

a

a

r

n

.

.

e

o

v

.

.

O

i

t

.

I

.

u

5

.

.

b

8

s.

.

ir

t

gk i

.

.

s

.

.

iD

gbl

.

. 0

a

i

9

.

.

s

1

.

.

e

.

I

.

ru

.

.

5

g

-

-

-

-

-

-

-

-

-

-

-

9

i

0

9

8

7

6

5

4

3

2

>

0

2

1

F1

1

1

g O8g m53

o

hz

i

'

'

-

l

.ll

ll

l

lllE

.

.

TABLE 2.

LER REQUIREMENT PERCENTAGE SCORES FOR VERMONT YANKEE

4

_____________________..___________________________________________________

+

TEXT

____

Percentage

a

Requirements [50.73(b)] - Descriptions

Scores ( )

_____________

______________________________________________________

(2)(ii)(A)

- - Plant condition prior to event

90 (15)

(2)(ii)(B)

- - Inoperable equipment that contributed

b

(2)(ii)(C)

- - Date(s) and approximate time (s)

77 (15)

(2)(ii)(D)

- - Root cause and intermediate cause(s)

89 (15)

(2)(ii)(E)

- - Mode, mechanism, and effect

100 ( 8)

(2)(ii)(F)

- - EIIS codes

0 (15)

(2)(ii)(G)

- - Secondary function affected

b

(2)(ii)(H)

- - Estimate of unavailability

100 ( 1)

(2)(ii)(I)

- - Method of discovery

93 (15)

(2)(ii)(J)(1) - Operator actions affecting cou.se

75 ( 2)

(2)(ii)(J)(2) - Personnel error (procedural deficiency)

79 ( 7)

(2)(ii)(K)

- - Safety system responses

92 ( 6)

,

(2)(ii)(L)

- - Manufacturer and model no. information

88 ( 8)

(3) - - - - - - Assessment of safety consequences

91 (15)

(4) - - - - - - Corrective actions

89 (15)

(5) - - - - - - Previous similar event information

93 (15)

(2)(1)

- - - - Text presentation

82 (15)

ABSTRACT

________

Percentage

a

Requirements [50.73(b)(1)] - Descriptions

Scores ( )

_____________

______________________________________________________

- Major occurrences (immediate cause/effect)

97 (15)

- Plant / system / component / personnel responses

91 ( 8)

- Root cause information

76 (15)

- Corrective action information

68 (15)

,

- Abstract presentation

71 (15)

i

6

--

. _ _ - _.

.--

.- -

. . -

. -

. - - . _ _ . - - - .

.

--

.

.

'

TABLE 2.

(continu:d)

_ _ _ _ ' _ _ _ - - - _ _ - _ _ - - _ _ _ _ - - _ _ - - _ - _ - _ _ - _ - _ _ - - - _ _ _ _

i

_

' CODED FIELDS

-__--__--__-

Percentage

a

Item Number (s) - Descriptions

Scores ( )

_----_____--____-_-__-___-_-----___ -_____--__-----___

---__________

1,

2, and 3 -

Plant name(unit #), docket #,

page #s

99 (15)

4------

Title

64 (15)

5,

6, and 7 -

Event date, LER no.,

report date

96 (15)

8---

--

Other facilities involved

100 (15)

9 and 10

- -

Operating mode and power level

98 (15)

Reporting requirements

97 (15)

11


Licensee contact information

97 (15)

12


Coded component failure information

93 (15)

13


14 and 15 - -

Supplemental report information

90 (15)

____-__--____-----_-__ --___

o.

Percentage scores are the result of dividing the total points for a

rcquirement by the number of points possible for that requirement.

(Note:

Some requirements are not applicable to all LERs; therefore, the

number of points possible was adjusted accordingly.)

The number in

parenthesis is the number of LERs for which the requirement was considered

cpplicable.

b.

A percentage score for this requirement is meaningless as it is not

possible to determine from the information available to the analyst whether

,

l

this requirement is applicable to a specific LER.

It is always given 100%

i

if it is provided and is always considered "not applicable" when it is not.

l

- - - - - _ _ _ - _ - - _ - _ _ _ - - - - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - - _ - _ _ - _ _ - - _ - _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _

l

l

!

!

!

i

7

l

l

I

,r.

.- .

. - - ,

-

,,-

- - - - - -

- - - - - - .

, , ,

, . . . - . - , , _ - -

1

~

.

.

.g

l

requirements with a score of less than 75 or those with numerous

i

deficiencies are discussed below in their order of importance.

In

addition, the primary deficiencies in the abstracts and coded fields are

discussed.

Three text requirements have marginally acceptable scores but are

mentioned here because of the high percentage of LERs with a problem

concerning these requirements. The three requirements are:

,

}

.

1.

Dates and times, Requirement 50.73(b)(2)(11)(C),

2.

Operator actions affecting the event,

Requirement 50.73(b)(2)(ii)(J)(1), and

3.

Personnel and procedural error, Requirement 50.73(b)(2)(ii)(J)(2).

i

Date/ time information was considered deficient in seven of the LERs.

In

particular, date/ time information was not included to indicate when the

plant was returned to a safe and stable condition and when corrective

i

actions were completed. The score for Requirement 50.73(b)(2)(ii)(J)(1)

was reduced because one of the two LERs for which this requirement was

'

considered appropriate failed to discuss the operator actions in the text

although the actions were discussed in the abstrat see Appendix D, LER

,

Sample No. 12). As a reminder, the abstract is supposed to be a summary of

the text; therefore, the t;at should discuss all information presented in

!

the abstract. Finally, the score for Requirement 50.73(b)(2)(11)(J)(2)

{

could be improved b) ensuring that all aspects of the requirement are

discussed once personnel or procedural error is identified.

See Appendix 0

i

for specific comments concerning these deficiencies.

,

All fifteen LERs failed to provide the Energy Industry Identification

System (EIIS) codes for each component and system referred to in the text,

j

Requirement 50.73(b)(2)(11)(F).

!

8

.

.

6

,

While there are no specific requirements for an abstract, other than

those given in 10 CFR 50.73(b)(1), an abstract should as a minimum,

summarize the following information from the text:

1.

Cause/Effect

What happened that made the event

reportable.

2.

Responses

Major plant, system, and personnel

responses as a result of the event.

3.

Root / Intermediate

The underlying cause of the event. What

caused the component and/or system

failure or the personnel error.

4.

Corrective Actions

What was done immediately to restore the

plant to a safe and stable condition and

what was done or planned to prevent

recurrence.

Numbers 1 and 2 above were adequately summarized in the abstracts of

the LERs reviewed.

Number 3 had a marginally acceptable score of 76% and

Number 4 had a score of 68%.

Both of these can be improved by ensuring

that the cause and corrective action information that is contained in the

text is adequately summarized in the abstract.

Again, the abstract should not contain information that is not

discussed in text (i.e., don't introduce new information in the abstract).

If, when writing the abstract, new information is deemed necessary, the

text should be revised so as to discuss this information.

Note that the

!

average abstract score (7.9) is lower than the text score which indicates

that text information is not being adequately summarized in abstract.

Further improvement in the abstract score could be obtained by using the

full space available (i.e., the 1400 spaces).

I

The main deficiency in the area of coded fields involves the title.

Item (4). Twelve of the titles failed to adequately indicate root cause,

seven failed to include the result, and two failed to include the link

l

'

9

l

1

.

.

'

.

between the cause and result. While the result is considered to be the

most important part of the title, cause and link information (as suggested

in NUREG-1022, Supplement No. 2) must be included to make a title

complete.

Example titles are presented in Appendix D for some of the LERs

which were considered to have poor titles.

Table 3 provides a summary of the areas that need improvement for the

Vermont Yankee LERs. For additional and more specific information

concerning deficiencies, the reader should refer to the information

presented in Appendices C and D.

General guidance concerning these

requirements can be found in NUREG-1022, Supplement No. 2.

It should be noted that this is the second time that the

Vermont Yankee LERs have been evaluated using this same methodology.

The

previous evaluation was reported in November of 1985. Table 4 provides a

comparison of the scores for both evaluations. As can be seen, the

Vermont Yankee LERs have improved since the previous evaluation and are now

above the current industry overall average of 8.2.

(Note:

The industry

overall average is the result of averaging the latest overall average score

for each unit / station that has been evaluated using this methodology.)

10

.

.

'

.

TABLE 3.

AREAS MOST NEEDING IMPROVEMENT f0R VERMONT YANKEE LERs

Areas

Comments

Dates / times

It would be helpful to include date/ time

information for when the plant is in a safe

and stable condition and for when the

corrective actions are completed.

Operator actions

Be sure to discuss operator actions that

affect the course of the event in the text.

Personnel / procedural error

Discuss all required aspects of

personnel / procedural error.

ElIS code

EIIS codes should be provided for each

component or system referred to in the text.

Abstracts

Cause and corrective action information from

the text should be mentioned in the

abstract. Discuss all information in the

text that is summarized in the abstract.

Be sure to use the full space available.

Coded fields

a.

Titles

Titles should be written such that they

better describe the event.

In particular,

the root cause and result should be

provided in each title.

/

11

..

.

.

TABLE 4.

COMPARISON OF LER SCORES FROM PREVIOUS EVALUATION

Report Date

N_ovember-85

January-86

Text average

7.0

8.4

Abstract average

7.0

7.9

Coded fields average

8.2

8.8

Overall average

7.1

8.3

.

12

.

.

'

REFERENCES

1.

Office for Analysis and Evaluation of Operational Data, Licensee Event

Report System, NUREG-1022 Supplement No. 2, U.S. Nuclear Regulatory

Commission, September 1985.

2.

Office for Analysis and Evaluation of Operational Data, Licensee Event

Report System, NUREG-1022, U.S. Nuclear Regulatory Commission,

September 1983.

3.

Office for Analysis and Evaluation of Operational Data, Licensee Event

Report System, NUREG-1022 Supplement No.1, U.S. Nuclear Regulatory

Commission, February 1984.

1

I

'

l

l

l

13

L

9

s

APPENDIX A

LER SAMPLE SELECTION

INFORMATION

FOR VERMONT YANKEE

l

l

I

_ _

.

'

TABLE A-1.

LER SAMPLE SELECTION FOR VERMONT YANKEE

Sample Number

LER Number

Comments

1

85-009-00

SCRAM

2

85-010-00

3

85-012-00

ESF

4

86-001-00

5

86-002-00

6

86-003-00

7

86-004-00

8

86-005-00

9

86-007-00

10

86-008-00

SCRAM

11

86-009-00

12

86-010-00

SCRAM

13

86-011-00

SCRAM

14

86-012-01

'

15

86-013-00

A-1

i

6

APPENDIX B

EVALUATION SCORES Of

INDIVIDUAL LERS FOR VERMONT YANKEE

. _ .

.

.

..

_ _ _ _

_ _ _

.

, - _ _ _ _ _ _ _ _

..

-

TABLE B-1.

EVALUATION SCORES OF INDIVIDUAL LERS FOR VERMONT YANKEE

.

. -___________ _________...........____..________.._____________ __________

a

LER Sample Number

1

2

3

4

_______________....

_______....-________________5

6

7

8

__ ......._____.___________

Text

7.1

7.6

7.6

9.3

9.3

9.3

9.2

8.9

Ab0 tract

6.6

8.8

8.2

9.5

6.5

8.6

6.7

6.9

Coded Fields

8.3

8.5

8.5

8.9

9.0

9.0

7.6

8.5

Ovarall

7.1

8.0

7.9

9.3

8.4

9.1

8.3

8.3

_____________________________.__ .. ____________________________.._________

a

LER Sample Number

9

10

11

12

13

_______________..___ ..___...._________. __.____________14

15

Average

____...____________

Tcxt

7.6

7.6

9.1

7.6

7.6

9.2

9.7

8.4

Abstract

6.3

7.0

8.1

7.8

8.1

9.8

10.0

7.9

C:ded Fields

9.7

8.9

8.0

9.8

8.3

9.9

9.2

8.8

Ovarall

7.4

7.6

8.7

7.9

7.8

9.5

9.7

8.3

.._________...______..____

See Appendix A for a list of the corresponding LER numbers.

o.

_____._____.....________......_____....__....__.....__.... ___________...

B-1

_ _ _ _ _ - _ _ - . - _ _ _ _ _

a

APPENDIX C

DEFICIENCY AND OBSERVATION

COUNTS FOR VERMONT YANKEE

-

- -

-

.

,_

.

.

'

TABLE C-1.

TEXT DEFICIENCIES AND O8SERVATIONS FOR VERMONT YANKEE

-

Number of LERs with

Deficiencies and

Observations

_

_

, ,

Sub-paragraph

Paragraph

Description of Deficiencies and Observations

Totals'

Totals (

)

a

50.73(b)(2)(11)( Al--Plant operating

3 (15)

conditions before the event were not

included or were inadequate.

50.73(b)(2)fli)(B)--Discussion of the status

0 ( 1)

of the structures, components, or systems

that were inoperable at the start of the

event and that contributed to the event was

not included or was inadequate.

50.73(b)(2)(11)(C)--Fa11ure to include

7 (15)

sufficient date and/or time information.

a.

Date information was insufficient.

7

b.

Time information was insufficient.

5

50.73(b)(2)(11)[0,1--The root cause ana/or

5 (15)

intermediate fatiure, system failure, or

personnel error was not included or was

inadequate.

a.

Cause of component failure was not

2

included or was inadequate

b.

Cause of system failure was not

1

included or was inadequate

c.

Cause of personnel error was not

2

included or was inadequate.

50.73(b)(2)(ii)(E_)--The failure mode,

0 ( 8)

mechanism (insnediate cause), and/or effect

(consequence) for each failed component was

not included or was inadequate.

4.

Failure mode was not included or was

inadequate

b.

Mechanism (insnediate cause) was not

included or was inadequate

c.

Effect (consequence) was not included

or was inadequate.

C-1

-

-

-

-

-

.

-

- -

.

.

'

TA8tE C-1.

(continued)

Number of LERs with

Deficiencies and

Observations

Sub-paragraph

Paragraph

Description of Deficiencies and Observations

Totals'

Totals (

)

50.73(b)(2)(tilf f)--The Energy Industry

15 (15)

Identification System component function

identifier for each component or system ws

not included.

50.73(b) 2)J11)(G:--For a failure of a

0 ( I)

i

componen", with mu'tiple functions, a list

of systems or secondary functions which

were also affected was not included or was

inadequate,

t

50.73(b)(2)(ti)(H)--For a failure that

0 ( 1)

renderer' a train of a safety system

,

inoperable, the estimate of elapsed time

from the discovery of the failure untti the

train w s returned to service was not

included.

50.73(b)(2)(11)(Il--The method of discovery

1 (15)

of each component failure, system failure,

i

personnel error, or procedural error ws not

included or w s inadequate.

.

!

4.

Method of discovery for each

I

component failure was not included

or was inadequate

i

b.

Method of discovery for each system

0

failure was not included or was

'

inadequate

c.

Method of discovery for each

0

.

personnel error w s not included or

4

l

w s inadequate

'

d.

Method of discovery for each

0

procedural error ws not included or

was inadequate.

C-2

. _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ . _

- _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ - _ - _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ - - - _ _

.

.

'

TABLE C-1.

(continued)

Number of LERs with

Deficiencies and

Observations

Sub-paragraph

Paragraph

Des:riation of Deficiencies and Observations

Totals'

Totals (

)

50.73 :b)(2)(ill(J)(11--Operator actions that

1 ( 2)

. affec",ed the course of the event including

operator errors and/or procedural

deficiencies were not included or were

inadequate.

30.73(b)(2)(it)(J)(21--The discussion of

4 ( 7)

each personnel error was not included or was

J

inadequate,

a.

OBSERVATION: A personnel error was

1

implied by the text, but was not

expitcitly stated,

b.

50.73(b)(2)(ii)(J)(2)(11--Olscussion

2

as to whether the personnel error was

cognitive or procedural was not

included or was inadequate,

c.

50.73(b)(2)(11)(J)(2)(111--Discussion

0

as to whether the personnel error was

contrary to an approved procedure, was

a direct result of an error in an

approved procedure, or was associated

with an activity or task that was not

covered by an approved procedure was

not included or was inadequate.

d.

50.73(b)(2)(11)(J)(2)(tiil--Discussion

0

of any unusual characteristics of the

work location (e.g., heat, noise) that

directly contributed to the personnel

error was not included or was

inadequate.

e.

50.73(b)(2)flil(J)(2)(lvi--01scussion

1

of the type of personnel involved

(i.e., contractor personnel, utility

licensed operator, utility non11 censed

operator, other utility personnel) was

not included or was inadequate.

C-3

_

_

_

_ _ _ _ _ _ _ - _ _ - - -

.

.

'

TA8LE C-1.

(continued)

Nutrber of LERs with

Deficiencies and

Observations

_

Sub-paragraph

Paragraph

Description of Deficiencies and Observations _

Totals *

Totals (

)

50.73(b)(2)(11)(K)--Automatic and/or manual

1 ( 6)

safety system responses were not included or

were inadequate.

50.73(b)(2)(11?(L)--The manufacturer and/or

2 ( 8)

model number of each failed component was

not included or was inadequate.

. . ,

10.73(b)(31 -An assessment of the safety

4 (15)

consequences and implications of the event

was not included or was inadequate.

a.

08 SERVAT!0N: The availability of

0

ether systems or components capable

of mitigating the consequences of the

event was not discussed.

If no other

systems or components were available,

the text should state that none

existed,

b.

CBSERVATION:

The consequences

3

'

-

of the event had it occurred under

more severe conditions were not

discussed.

If the event occurred

under what were considered the most

severe conditions, the text should so

state.

50.73(b)(41--A discussion of any corrective

4 (15)

actions planned as a result of the event

including those to reduce the probability

of sistlar events occurring in the future

was not included or was inadequate.

C-4

.

.

'

TABLE C-1.

(continued)

'

Number of LERs with

Deficiencies and

Observations

Sub-paragraph

Paragraph

Description of Deficiencies and Observations

Totals *

Totals (

)

a.

A discussion of actions required to

I

correct the problem (e.g., return the

component or system to an operational

condition or correct the personnel

error) was not included or was

inadequate,

b.

A discussion of actions required to

4

reduce the probability of recurrence

of the problem or similar event

(correct the root cause) was not

included or was inadequate,

c.

OBSERVATION: A discussion of actions

0

required to prevent similar failures

in similar and/or other systems (e.g.,

correct the faulty part in all

components with the same manufacturer

and model number) was not included or

was inadequate.

50.73(blf51--Information concerning previous

1 (15)

similar events was not included or was

inadequate.

C-5

.

.

'

'

TASLE C-1.

(continued)

Number of LER$ with

Deficiencies and

Observations

Sub-paragraph

Paragraph

Desertotton of Deficiencies and Observations

Totals'

Totals (

)

50.73(b)(2)(il--Text presentation

'5 (15)

inadequacies,

a.

OBSERVATION: A diagram would have

0

aided in understanding the text

discussion.

b.

Text contained undefined acronyms

2

and/or plant specific designators,

c.

The text contains other specific

3

deficiencies relating to the

readability.

a.

The "sub-paragraph total" is a tabulation of specific deficiencies or

observations within certain requirements.

Since an LER can have more than

one deficiency for cortain requirements. (e.g., an LER can be deficient in

the area of both date and time information), the sub-paragraph totals do

not necessarily add up to the paragraph total,

b.

The " paragraph total" is the number of LERs that have one or more

requirement deficiencies or observations.

The number in parenthesis is the

number of LERs for which the requirement was considered applicable.

C-6

..-.

-

_ _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ - -

.

. '

'

TABLE C-2.

A8STRACT DEFICIENCIES AND OBSERVATIONS FOR VERM0NT YANKEE

Number of LERs with

Deficiencies and

Observations

Sub-paragraph

Paragraph

gggrlotion of Deficiencies and Observatic.ni

Totals'

Totals (

)

A summary of occurrences (insnediate cause

1 (15)

and effect) was not included or was

inadequate

A summary of plant, system, and/or personnel

3 ( 8)

responses was not included or was

inadequate.

a.

Summary of plant responses was not

0

included or was inadequate.

b.

Summary of system responses w s not

1

included or ws inadequate.

c.

Summary of personnel responses w s not

2

included or was inadequate.

A summary of the root cause of the event

5 (15)

was not included or was inadequate.

A summary of the corrective actions taken or

10 (15)

planned as a result of the event was not

included or w s inadequate.

C-7

_ _ _ _ _ _ _ _ _ _ _ _ _

- _ __

.

'

'

TASLE C-2.

(continued)

(

4

'

Number of LERs with

Deficiencies and

Observations

'

Sub-paragraph

Paragraph

f

Description of Deficiencies and Observations

Totals *

_ Totals (

)

Abstract presentation inadequacies

10 (15)

,

a.

085ERVATION: The abstract contains

3

inforr.ation not included in the text.

2

The abstract is intended to be a

,

summary of the text, therefore, the

text should discuss all information

,

'

4

summarized in the abstract.

t

b.

The abstract was greater than

0

4

1400 characters

c.

The abstract contains undefined

0

acronyms and/or plant specific

designators.

d.

The abstract contains other specific

9

,

i

deficiencies (i.e., poor

summarization, contradictions, etc.)

!

a.

The "sub-paragraph total" is a tabulation of specific deficiencies or

observations within certain requirements.

Since an LER can have more than

one deficiency for certain requirements, the sub-paragraph totals do not

j

necessarily add up to the paragraph total,

i

b.

The " paragraph total" is the number of LERs that have one or more

'

"

deficiency or observation.

The number in parenthesis is the number of LERs

,

for which a certain requirement was considered applicable.

I

i

'

1

!

I

l

!

I

I

i

I

l

1

I

I

C-8

i

!

t

1

.

-

- - -

-

-

-

-

.

.

_

.

.

'

TABLE C-3.

C00E0 FIELOS Off!CIENCIES AND 08SERVATIONS FOR VERN0NT YAMEE

Number of LERs with

,

Deficiencies and

,_

Observations

Sub-paragraph

Paragraph

Description of Deficiencies and Observations

Totals *

Totals (

)

facility Name

0 (15)

a.

Unit number was not included or

incorrect.

b.

Name was not included or was

incorrect.

c.

Additional unit numbers were included

i

but not required.

Docket Number was not included or was

0 (15)

incorrect.

Page Number was not included or was

1 (15)

incorrect.

Title was left blank or was inadequate

14 (15)

4.

Root cause was not given in title

12

b.

Result (effect) was not given in title

2

c.

Link was not given in title

7

Event Date

1 (15)

4.

Date not included or was incorrect.

O

b.

Olscovery date given instead of event

I

date.

LtR Number was not included or was incorrect

0 (15)

Report Date

1 (15)

4.

Date not included

0

b.

OSSERVATION: Report date was not

I

within thirty days of event date (or

discovery date if appropriate).

Other facilities information in fleid is

0 (15)

inconsistent with text and/or abstract.

Operating Mode was not included or was

1 (15)

inconsistent with text or abstract.

C-9

-

-

-

- -

- - _ - - _ _ _ _ _

.

.

TA8tE C-3.

(continued)

Number of LERs with

Deficiencies and

Observations

Sub-paragraph

Paragraph

Description of Deficiencies and Observations

Totals'

Totals (

l

Power level was not included or was

0 (15)

inconsistent with text or abstract

l

Reporting Requirements

2 (15)

a.

The reason for checking the "0THER"

0

requirement was not specified in the

abstract and/or text.

b.

08SERVATION:

It may have been more

0

appropriate to report the event under

,

a difforent paragraph.

-

1

c.

08SERVATION:

It may have been

2

appropriate to report this event under an

additional unchecked paragraph.

t

e

Licensee Contact

2 (15)

!

'

4.

Fleid left blank

0

.

b.

Position title was not included

2

l

l

c.

Name was not included

0

!

d.

Phone number w,ts not included.

0

l

'

Coded Compor.ent f ailure Information

1 (15)

!

F

f

a.

One or more component failure

0

sub-fields were left blank,

r

b.

Cause, system, and/or component code

0

is inconsistent with text.

c.

Component failure ftold contains data

0

,

when no component failure occurred.

.

!

d.

Component failure occurred but entire

I

t

t

fleid left blank.

,

1

i

!

i.

f

j

I

!

T

C-10

t

l

'

t

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

_____

,

..

.

'

TABLE C-3.

(continued)

l

Number of LERs with

Deficiencies and

l

Observations

.

Sub-paragraph

Paragraph

l

Description of Deficiencies and Observations

Totals'

Totals (

)

Supplemental Report

2 (15)

a.

Neither "Yes"/"No" block of the

0

supplemental report field was

checked.

b.

The block checked was inconsistent

2

with the text.

Expected submission date information is

0 (15)

,

!

inconsistent with the block checked in

l

Item (14).

!

!

a.

The "sub-paragraph total" is a tabulation of specific deficiencies or

observations within certain requirements.

Since an LER can have more than

one deficiency for certain requirements, the sub-paragraph totals do not

necessarily add up to the paragraph total.

l

b.

The " paragraph total" is the number of LERs that have one or more

>

l

requirement deficiencies or observations.

The number in parenthesis is the

number of LERs for which a certain requirement was considered applicable.

!

l

1

l

,

1

,

l

C-11

-.

_ - -

- _ . . . _ - . . - _ _ _ - . _ _ _ _ - - . . - - .

_

- _ - _ _

. -

. . . - - -

-

- - .

- . - -

O

e

e

APPENDIX 0

LER COMMENT SHEETS FOR

VERMONT YANKEE

.

.

.

TA8LE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

1.

LER Number: 85-009-00

Scores: Text - 7.1

Abstract - 6.6

Coded Fields - 8.3

Overall = 7.1

Text

1.

50.73(b)(2)(11)(q1--Date/ time information for major

occurrences is inadequate.

This information needs to

be provided for major occurrences throughout the

event (e.g., times for repairs and return of the

plant to a safe and stable condition).

2.

50.73(b)(2)(11)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

3.

50.73(b)(2)(11)(J)(2)--It appears that personnel

error is involved in this even'., but it is not

discussed. Why were the shorting links removed and

why had the drain valves been left partially open?

4.

50.73(b)(3)--Discussion of the assessmen* of the

safety consequences and implications of the event is

inadequate.

OBSERVATION: The' consequences of the

event had it occurred under more severe conditions

should be discussed.

If the event occurred under

what are considered the most severe conditions, the

text should so state.

5.

50.73(b)(4)--Discussion of corrective actions taken

or planned is inadequate. Were the shorting links

reinstalled and the design change completed? Are

actions such as improving the review process,

sufficient to prevent a similar event in the future?

6.

Acronym (s) and/or plant specific designator (s) are

undefined.

RPS, SRM, and HCU should be defined.

Abstract

1.

10.73(b)(11--Summary of root cause is not included.

2.

50.73(b)(11--Summary of corrective actions taken or

planned as a result of the event is inadequate (see

text comment 5).

0-1

.

.

-

..

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

1.

LER Number: 85-009-00 (continued)

3.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded Fields

1.

Item (4)--Title:

Root cause is not included and the

result is incomplete. A more appropriate title might

be " Inadvertent Scram Signal and Contaminated Water

Leak While Implementing a Design Change Due to

Personnel Error". The personnel error is an

assumption based on the missing shorting links and

partially open valves (see text comment 3).

2.

Item (9)--Operating mode is not included.

,

i

a

i

0-2

,

.

. _.

.

--- .

.

.- ._ _.

_ . _ - . . _ .

____ . _ _ _ _ _

!

.

.

.

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

2.

LER Number: 85-010-00

Scores:

Text - 7.6

Abstract - 8.8

Coded Fields - 8.5

Overall - 8.0

Text

1.

50.73(b)(2)(ii)(C)--Approximate date information for

the return to service of the affected penetrations is

not included.

2.

50.73(b)(2)(ii)(D)--The root and/or intermediate

cause discussion concerning the penetration

conduction installation error is inadequate. Was the

error a design error, procedure error, or cognitive

personnel error?

3.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

4.

50.73(b)(2)(ti)(J)(2)--Discussion of the personnel

error is inadequate.

50.73(b)(2)(11)(J)(2)(1)--Discussion as to whether

the personnel error was cognitive or procedural is

not included.

5.

50.73(b)(2)(ii)(L)--Identification (e.g.,

manufacturer and model no.) of the failed

component (s) discussed in the text is inadequate.

Abstract

1.

50.73(b)(1)--Summary of root cause (personnel error)

is inadequate.

See text comment numbers 2 and 4.

Coded Fields

1.

Item (4)--Title:

Root cause (personnel error) and

link (inspection) are not included. A more suitable

title might be:

"Drywell Electrical Penetration

Conductors Found During Inspection With Degraded

Insulation Caused by Personnel Installation Errors."

2.

Item (131--Component failure occurred but entire

field is blank.

D-3

.

.

-

.

.

,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

!

,

Section

Comments

3.

LER Number: 85-012-00

Scores: Text - 7.6

Abstract - 8.2

Coded Fields - 8.5

Overall - 7.9

Text

1.

50.73(b)(2)(11)(C)--Time information for major

occurrences is inadequate. When were the Toxic Gas

Monitors and the Control Room Habitability System

reset (e.g. time)?

2.

50.73(b)(2)(11)(D)--The root and/or intermediate

cause discussion concerning the freon being drawn

into the air intake is inadequate. Given that there

have been no similar events, is this the first time

that freon has been purged from the air. conditioning

units or, if not, was there some other condition

(such as a strong wind) that contributed to the event?

3.

50.73(b)(2)(11)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

4.

50.73(b)(4)--01scussion of corrective actions taken

or planned is inadequate. The corrective measures

that are to be taken to prevent recurrence of this

event are not discussed.

5.

Acronym (s) and/or plant specific designator (s) are

undefined. What is the significance of "(R-22)"?

Abstract

1.

See text comment number 2.

2.

See text consent number 4.

3.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded Fields

1.

Item (4)--Title: Cause and link are not included. A

better title would be, " Freon Gas Purged from An Air

Conditioner Enters Control Room Air Intake Resulting

In Control Room Habitability System Actuation Via The

Toxic Gas Monitors".

0-4

.

.

,

a

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

4.

LER Number: 86-001-00

Scores: Text - 9.3

Abstract - 9.5

Coded Fields - 8.9

Overall = 9.3

Text

1.

50.73(b)(2)(11)(F1--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

.

2.

50.73(b)(2)(ii)(J)(2)(iv)--Discussion of the type of

3

personnel involved (i.e., contractor personnel,

utility licensed operator, utility nonlicensed

operator, other utility personnel) is inadequate.

Abstract

1.

No comment.

Coded Fields

1.

Item (31--The page number on the third page is

incorrect.

2.

Item (4)--Title:

Root cause is not included.

'

3.

Item (ll)--0BSERVATION:

It appears it would have

been appropriate to also report this event under

i

paragraph (s) 50.73(a)(2)(i).

!

l

l

l

!

i

,

D-5

-.

.

.

.

,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

5.

LER Number: 86-002-00

Scores:

Text = 9.3

Abstract = 6.5

Coded Fields = 9.0

Overall = 8.4

Text

1.

50.73(b)(2)(11)(A)--Discussion of plant operating

conditions before the event is inadequate. Was the

outage for refueling?

2.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

Abstract

1.

50.73(b)(1)--Summary of personnel errors is

inadequate. Which personnel were involved? What was

the reason for the nonconservative calculations?

2.

50.73(b)(1)--Summary of corrective actions taken or

planned as a result of the event is inadequate. What

replacement material was planned? When was the

replacement scheduled?

3.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

The discovery date is not included.

Coded Fields

1.

Item (4)--Title:

Root cause (personnel calculation

errors) is not included.

l

l

l

l

l

!

0-6

!

--

.- .

.-

-- -- --, . ---

_. --

. - - _

.

.

!

l

..

.

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

6.

LER Number: 86-003-00

Scores:

Text - 9.3

Abstract - 8.6

Coded Fields - 9.0

Overall - 9.1

Text

1.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

2.

50.73(b)(2)(11)(L)--The text does not actually state

that the relief valves are Target Rock valves.

3.

A logical transition does not exist between all

ideas. Some ideas are not presented clearly (hard to

follow).

Abstract

1.

50.73(b)(1)--Summary of corrective actions taken or

planned as a result of the event is inadequate.

The

fact that the performance of the valves will continue

to be tracked / evaluated was not mentioned in the

abstract.

2.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded Fields

1.

Item (4)--Title:

Cause and link are not included. A

better title might be, "During Technical

Specification (T.S.) Required Test Two Main Steam

Relief Valves Actuated Above Their T.S. Setpoint--

i

Cause Is Steam Cuts On Pilot Disc and Seat".

2.

Item (11)--Given the information provided in the

j

" Analysis of Event", it is not clear why this event

was reported under requirement 50.73(a)(2)(v).

3.

Item (13)--Only one line need have been filled in.

l

l

0-7

i

_

__.

- -_

-

_ _ _

_

.- - - - - -

.

- - - - - - -

.

_

.

.

_ _ _ . _ _ _ .

._

_ _ _ _

.

.

. ..

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

7.

LER Number: 86-004-00

Scores:

Text - 9.2

Abstract - 6.7

Coded fields - 7.6

Overall - 8.3

Text

1.

50.73(b)(2)(11)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

2.

50.73(b)(2)(ii)(L)--Identification (e.g.,

manufacturer and model no.) of the failed

component (s) discussed in the text is inadequate. A

unique identification, such as a model number, was

not given for the Conax trigger assembly.

Abstract

1.

50.73(b)(11--Summary of corrective actions taken or

,

]

planned as a result of the event is not included.

2.

OBSERVATION: The abstract contains information not

included in the text. The abstract is intended to be

a summary of the text; therefore, the text should

discuss all information summarized in the abstract.

The last sentence of the abstract is not mentioned in

the text.

3.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded Fields

1.

Item (4)--Title:

Root cause (manufacturing error)

and result (inoperable Standby Liquid Control system)

,

are not included.

i

2.

Item (5)--Discovery date is given instead of event

date. A discovery date is only supposed to be given

when the event date is not known. The event was

known to have taken place in August of 1984, so an

estimated event date of August 15, 1984 could be used

or conservatively August 1, 1984.

In either case,

the text could explain the uncertainty in the date

given.

Further, a more appropriate discovery date

would appear to be February 8, 1986.

i

1

i

D-8

,

--. - -

.. -

- - - - ..

-

_ .- . . _ - - _ - .

_

- _-.

.

_ _ _ .

_

_

.

.

..

, ,

.

,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

7.

LER Number:

86-004-00 (continued)

3.

Item (ll)--0BSERVATION:

It appears it would have

been appropriate to also report this event under

paragraph (s) 50.73(a)(2)(1) and 50.73(a)(2)(vii).

t

II

D-9

I

.

_

.

- -.

,

.

.____ .- _-- .-

.- ..

__-

. - .

-

.

.

..

.

,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

8.

LER Number: 86-005-00

Scores: Text - 8.9

Abstract - 6.9

Coded Fields - 8.5

Overall - 8.3

Text

1.

50.73(b)(2)(ii)(C)-- Approximate date information for

major occurrences is not included.

2.

50.73(b)(2)(11)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

Abstract

1.

50.73(b)(1)--Summary of occurrences [immediate

cause(s) and effects (s)) is inadequate. Discussion

of the impact of the weld flaws on structural

integrity is not included.

2.

50.75(b)(1)--Summary of corrective actions taken or

planned as a result of the event is inadequate.

Discussion of the planned inspections is not included.

3.

OBSERVATION:

The abstract contains information not

included in the text.

The abstract is intended to be

a summary of the text; therefore, the text should

discuss all information summarized in the abstract.

The NRC Information Notice 84-41 is not mentioned in

the text.

4.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded fields

1.

Item (4)--Title:

Root cause (intergranular stress

corrosion cracking) and link (ultrasonic inspection)

are not included.

D-10

.

.-.

-

--

-

.

.

_

--

-

-

-

--

,

.,

.

, . , .

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

9.

LER Number:

86-007-00

Scores: Text = 7.6

Abstract = 6.3

Coded Fields - 9.7

Overall = 7.4

Text

1.

50.73(b)(2)(11)(A)--Discussion of plant operating

conditions before the event is inadequate.

Plant

conditions such as operating mode or reactor

temperature and pressure are not provided.

2.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

,

3.

50.73(b)(3)--Discussion of the assessment of the

safety consequences and implications of the event is

inadequate.

It appears that T.S. 4.7.2

(10 CFR 50 Appendix J) and whatever T.S. that allows

reactor operation with leakage up to 0.8 wt. %/ day

L

are in conflict.

If the containment leakage was in

excess of that permitted by T.S. 4.7.2, hcw can there

be no potential adverse effects and how can another

T.S. say reactor operation is allowed with leakage

greater than that permitted by T.S. 4.7.2?

.

4.

50.73(b)(4)--Discussion of corrective actions taken

or planned is inadequate.

If the cause of the manway

bolts loosening is due to thermal expansion / cycling

over time, why is the long term corrective action

(number 2) tied to the removal /re-installation of the

drywell head? Is head removal /re-installation always

performed frequently enough to ensure the manway

bolts will not loosen between head removal?

l

S.

Some ideas are not presented clearly (hard to follow).

l

Abstract

1.

50.73(b)(1)--Summary of local leakage sources (cause)

'

is inadequate. The drywell head manway cover problem

should have been discussed.

2.

50.73(b)(11--Summary of corrective actions taken or

planned as a result of the event is inadequate.

The

corrective actions taken to prevent recurrence are

not presented in the abstract.

D-11

,..

-.

. . . . .

.

.

- - - - -

.

-_

._-

.

--.

. - . -

_

-

i

.

.

.

, . . .

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

9.

LER Number:

86-007-00 (continued)

3.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

4.

The last three sentences of the first paragraph of

the abstract are not needed.

Information concerning

the measured leakage would have been appropriate here.

Coded Fields

1.

Item (4)--The title could have indicated that there

were numerous identified leakage paths.

D-12

.

.

,, .

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

10. LER Number: 86-008-00

Scores: Text - 7.6

Abstract - 7.0

Coded Fields - 8.9

Overall - 7.6

Text

1.

50.73(b(2)(11)(0)--Deta11s as to how improper

movement of the mode switch caused the scram were not

included.

2.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

3.

50.73(b)(2)(ii)(J)(2)(1)--Discussion as to whether

the personnel error was cognitive or procedural is

not included.

4.

50.73(b)(3)--A discussion as to whether or not a

similar response could occur under more severe

conditic,s was not included.

If the event occurred

under what are considered the most severe conditions,

the text should so state.

5.

50.73(b)(5)--Information concerning previous similar

events is not included.

If no previous similar

events are known, the text should so state.

Abstract

1.

50.73(b)(1)--Summary of corrective actions taken or

planned as a result of the event is not included.

Coded fields

1.

Item (4)--The root cause is inadequately stated and

the link is not included. A more appropriate title

might be " Unanticipated Scram During Surveillance

Testing Due to Improper Mode Switch Moveinent

l

(Personnel Error)".

l

0-13

.

_

-

-

. _ _ . -

.

,

.

, ..

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YAhXEE (271)

Section

Comments

11. LER Number: 86-009-00

Scores:

Text - 9.1

Abstract - 8.1

Coded fields - 8.0

Overall - 8.7

Text

1.

50.73(b)(2)(11)(C)--Approximate date and time for the

return to service is not included.

2.

50.73(b)(2)(11)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

3.

50.73(b)(2)(ii)(I)--Discussion of the method of

discovery of the check valve leakage is not included.

4.

Discussion of the function of the steam relief valve

system is excellent. The event is presented in a

well-outlined format.

Abstract

1.

50.73(b)(1)--Summary of the root cause (dirt source)

is not included.

2.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded fields

1.

Item (4)--Title:

Root cause (dirt from air supply)

is not included.

An acronym, SRV, is present in the

title.

Acronyms should be avoided in a title unless

space is a problem.

2.

Item (71--0BSERVATION: Report date is not within

thirty days of event date (or discovery date if

appropriate).

3.

Item (ll)--Was the accumulator check valve leakage a

,

!

violation of a Technical Specification?

l

!

D-14

!

_- -

_.

.-.

_

. . - -

.

--.. -.

.

-

.

._

_

. - . . - . . _

_.

_

.

a

. . . .

,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

12.

LER Number: 86-010-00

Scores: Text = 7.6

Abstract - 7.8

Coded fields = 9.8

Overall - 7.9

Text

1.

50.73(b)(2)(11)(A)--Discussion of plant operating

conditions before the event is inadequate.

It would

be helpful to the reader to know more than just "the

plant was shutdown" (e.g., the operating mode).

2.

50.73(b)(2)(11)(D)--The root and/or intermediate

cause discussion concerning the shorted coil is

inadequate. Given that the failure is attributed to

end of coil life, it would be good to provide

infoimation concerning how long the coil has been

installed.

3.

50.73(b)(2)(li)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

4.

50.73(b)(2)(ii)(J)(1)--Discussion of operator actions

t!'at affected the course of the event is inadequate.

It is not explicitly stated in the text how the

electrician's actions (pulling the cover from the

distribution panel) contributed to the event.

The

abstract does present this information, however.

5.

50.73(b)(2)(ii)(K)--Discussion of automatic and/or

manual safety system responses is inadequate. All

safety systems that " functioned as designed" should

be named.

6.

50.73(b)(31--Discussion of the assessment of the

safety consequences and implications of the event is

inadequate. The " Analysis of Event" section states

that there were no adverse safety consequences from

this event since the reactor was in a shutdown

condition at the time of the event. What would have

been the adverse safety consequences had the reactor

not been shutdown? Given that the indications are

that other coils may reach end of life soon is there

any increased risk. Are all coil failures of this

type fail safe?

,

7.

A logical transition does not exist between all ideas.

D-15

--

.

-

-

.

- . -

-

-.

_.

-

- - -

.

o

o

, _ . ,

TABLE D-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

12.

LER Number: 86-010-00 (continued)

Abstract

1.

50.73(b):11--Summary of system response is

inadequa ;e.

If any safety systems actuate this

information would be good to include in the abstract.

2.

50.73(b)(11--Summary of cause information.is

inadequate. The fact that the coil failure was

attributed to end of life should be mentioned.

3.

50.73(b)(1)--Summary of corrective actions taken or

planned as a result of the event is inadequate. The

fact that all similar contactors within the A and B

RPS panels were inspected and found to have no

similar type problems should be mentioned. Are there

other similar contactors in other safety systems, as

well?

4.

OBSERVATION: The abstract contains information not

included in the text.

The abstract is intended to be

a summary of the text; therefore, the text should

discuss all information summarized in the abstract.

See text comment number 4.

5.

The abstract is written in a mach more logical

sequence of ideas than is the text.

Coded Fields

1.

Item (4)--The title should indicate that the broken

armature " caused a relay to drop out".

D-16

-.

-

-.-

__ . .

_

- . _ _ . ._

__

_ . _ _ _ _ _

_

_

~

_ ___ _ . _ .

s

-

,

.. .

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

13. LER Number: 86-011-00

Scores: Text - 7.6

Abstract - 8.1

Coded Fields - 8.3

Overall - 7.8

,

Text

1.

50.73(b)(2)(11)(C)--Date/ time information for major

occurrences is inadequate. When were the immediate

corrective actions taken, and when are the additional

corrective actions expected to be completed?

2.

50.73(b)(2)(ii)(D)--Was the source of the noise in

the IRM circuitry identified?

3.

50.73(b)(2)(11)(F)--The Energy Industry

.

Identification System component function

'

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

4.

50.73(b?(4)--Could anything be done to reduce noise

in the LRM circuitry (see text comment 2)? A

supplemental report appears to be needed to describe

the results of the engineering evaluation into the

RPS power supply.

Abstract

1.

50.73(b)(1)--Summary of root cause is inadequate.

The reason for the half scram due to RPS voltage

instability was not included (i.e., the recirculation

pump start causing an undervoltage condition).

2.

50.73(b)(1)--Summary of corrective actions taken or

planned as a result of the event is inadequate. The

engineering evaluation was not mentioned.

3.

Abstract does not adequately summarize the text.

Additional space is available within the abstract

field to provide the necessary information but it was

not utilized.

Coded Fields

1.

Item (4)--Title:

Root causes (undervoltage condition

and noise) are not included.

2.

Item (14)--The block checked is inconsistent with

information in the text (see text comment 4).

l

D-17

. - -

-

--

. i , 4

. . .

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

14. LER Number: 86-012-01

Scores: Text = 9.2

Abstract = 9.8

Coded Fields = 9.9

Overall = 9.5

Text

1.

50.73(b)(2)(ii)(C)--Approximate date and time for

return to service information for major occurrences

is not included.

2.

50.73(b)(2)(ti)(F1--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

3.

Acronym (s) and/or plant specific designator (s) are

undefined.

Abstract

1.

No comments.

Coded Fields

1.

Item (12)--Position title on Revision 1 is not

included.

1

0-18

- .-

-

-

_ _ _

-

.

m

, . . ,

. . .

,

TABLE 0-1.

SPECIFIC LER COMMENTS FOR VERMONT YANKEE (271)

Section

Comments

15. LER Number: 86-013-00

Scores:

Text - 9.7

Abstract - 10.0

Coded Fields - 9.2

Overall - 9.7

Text

1.

50.73(b)(2)(ii)(F)--The Energy Industry

Identification System component function

identifier (s) and/or system name code of each

component or system referred to in the LER is not

included.

2.

50.73(b)(4)--If the results of General Electric's

analysis of cause provide any new information or

result in any additional corrective actions, a

supplemental report should be submitted that provides

this information.

3.

The use of the diagram is a good practice for events

that are difficult to explain.

Abstract

1.

No comments.

Coded Fields

1.

Item (4)--The title could have included the phrase

"during start up".

'

2.

Item (12)--Position title is not included.

3.

Item (14)--The block checked is inconsistent with

information in the text.

See text comment number 2.

,

'

0-19