Rev 1 to Monthly Operating Rept for Sept 1986
ML20206R374
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/30/1986
From: Behnke C
BALTIMORE GAS & ELECTRIC CO.
To:
Shared Package
ML20206R141 List:
References
NUDOCS 8704220155
Download: ML20206R374 (1)


Text

.

C s

co**************************************************************************

UNIT 2 OPERATING DATA REPORT co**************************************************************************

Docket No. 50-318 April 6, 1987 Prepared by C.

Behnke Tel. (301) 260-4871 OPERATING STATUS

~~~~~~~~~~~~~~~~

1. UNIT NAME Calvert Cliffs Unit 2
2. REPORTING PERIOD SEPTEMBER (Rev 1)
3. LICENSED THERMAL POWER (MWT) 2700
4. NAMEPLATE RATING (GROSS MWe) 918
5. DESIGN ELECTRICAL RATING (NET MWe) 845
6. MAXIMUM DEPENDABLE CAPACITY (GROSS M 860
7. MAXIMUM DEPENDABLE CAPACITY (NET MWe 825
8. CHANGE IN CAPACITY RATINGS none 9.

POWER LEVEL TO WHICH RESTRICTED n/a

10. REASONS FOR RESTRICTIONS n/a This month Year-to-Date Cumulative
11. HOURS IN REPORTING PERIOD 720 6,551 83,279
12. NUMBER OF HOURS REACTOR WAS CRITICAL 641.8 6,234.0 69,677.0
13. REACTOR RESERVE SHUTDOWN HOURS 11.6 35.9 1,296.6
14. HOURS GENERATOR ON LINE 634.4 6,199.7 68,611.0
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,545,715 15,925,122 172,407,158
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 509,150 5,334,970 56,856,494
18. NET ELECTRICAL ENERGY GENERATED (MWH) 483,816 5,106,059 54,256,316
19. UNIT SERVICE FACTOR 88.1 94.6 82.4
20. UNIT AVAILABILITY FACTOR 88.1 94.6 82.4
21. UNIT CAPACITY FACTOR (USING MDC NET) 81.5 94.5 79.0
22. UNIT CAPACITY FACTOR (USING DER NET) 79.5 92.2 77.1
23. UNIT FORCED OUTAGE RATE 11.9 5.0 6.1
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

Refueling Shutdown:

March 14, 1987 to May 22, 1987 (69 days) k7 hDR DO 5